Control method and device for offshore wind power cluster

By constructing a minimum optimization model that takes into account the actual HVDC, the problem of insufficient control accuracy of offshore wind power clusters is solved, and more efficient control and cost optimization are achieved.

CN119010011APending Publication Date: 2024-11-22GUANGDONG POWER GRID CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411307023.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The optimization control model constructed by the existing offshore wind power control optimization method does not take into account the actual situation of the HVDC sending system, resulting in insufficient control accuracy of offshore wind power clusters.

Method used

Based on the power declaration data of offshore wind power clusters, a minimum optimization model is built, including objective functions and constraints, taking into account operating costs, maintenance costs, loss costs and penalty costs. By using the minimum annual total cost of the system as the optimization goal, the optimization model is more in line with actual needs.

Benefits of technology

It improves the accuracy and accuracy of offshore wind power cluster control, while reducing the total annual cost of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119010011A_ABST
    Figure CN119010011A_ABST
Patent Text Reader

Abstract

The invention discloses a control method and device for an offshore wind power cluster, relates to the field of offshore wind power control, can solve the problem that the control precision of the offshore wind power cluster is insufficient, and comprises the steps that a minimum optimization model is constructed with the minimum annual total cost of a system as an optimization target according to power declaration data of the offshore wind power cluster to be controlled; the power declaration data comprises cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model comprises a target function and a plurality of constraints; the objective function comprises a plurality of cost functions; the plurality of cost functions comprise operation cost, maintenance cost, loss cost and penalty cost; the plurality of constraints comprise an output balance constraint and a power balance constraint; and substituting the power declaration data into the minimum optimization model for solving to obtain an output plan of each offshore wind power plant in the offshore wind power cluster, and controlling the offshore wind power cluster according to the output plan of each offshore wind power plant.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of offshore wind power control, and in particular to a control method and device for an offshore wind power cluster. Background Art

[0002] With the development of various types of renewable energy power generation, offshore wind power generation, as a member of renewable energy power generation, has also developed. At present, offshore wind power generation is mainly carried out in the form of distributed deployment to form offshore wind power clusters. This power generation method is prone to problems such as overload transmission of offshore wind power and cost surge, which has a great impact on the safe and stable operation of the power system. Therefore, it is necessary to optimize the operation control of offshore wind power clusters.

[0003] In the existing offshore wind power control optimization methods, HVDC (High Voltage DC) systems are usually used to transmit offshore wind power generation, and an optimization control model needs to be constructed to control the offshore wind power system. However, the optimization control model constructed by the existing optimization method usually only performs parameter fine-tuning in the onshore wind power model, without considering the actual use of the HVDC transmission system, resulting in uncorrectable deviations in the solution results of the optimization control model, and thus deviations in the control accuracy of the offshore wind power cluster. Therefore, how to more reasonably construct an optimization control model to improve the control accuracy of the offshore wind power cluster is an urgent problem to be solved in the existing technology. Summary of the invention

[0004] The present application provides a control method and device for an offshore wind power cluster to solve the technical problem of insufficient control accuracy of an offshore wind power cluster in the prior art.

[0005] According to a first aspect of an embodiment of the present application, a control method for an offshore wind power cluster is provided, comprising:

[0006] According to the power declaration data of the offshore wind power cluster to be controlled, a minimum optimization model is constructed with the minimum annual total cost of the system as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraint and power balance constraint;

[0007] Substituting the power declaration data into the minimum optimization model for solving, the output plan of each offshore wind farm in the offshore wind power cluster is obtained, and the offshore wind power cluster is controlled according to the output plan of each offshore wind farm.

[0008] This application first constructs a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, including cluster operation data, HVDC operation data, electricity price data and loss data, with the minimum system annual total cost as the optimization goal, and then substitutes the power declaration data into the minimum optimization model to solve the output plan of each offshore wind farm, so as to control the offshore wind power cluster according to the output plan of each offshore wind farm. Compared with the prior art, the actual operation of the cluster and the actual use of HVDC grid connection are taken into consideration, and the constructed optimization model is more in line with the actual grid connection use of the offshore wind power cluster based on HVDC, and more in line with actual needs, so that the constructed optimization model is more accurate, which can improve the control accuracy when controlling the offshore wind power cluster, and at the same time, with the minimum system annual total cost as the optimization goal, it can reduce the annual total cost of the system while controlling.

[0009] In certain embodiments of the present application, the minimum optimization model is constructed based on the power declaration data of the offshore wind power cluster to be controlled and with the minimum annual total cost of the system as the optimization goal, specifically including:

[0010] Constructing a plurality of operation models according to the power declaration data; wherein the plurality of operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model;

[0011] constructing the operating cost and the maintenance cost according to the plurality of operating models;

[0012] constructing the loss cost and the penalty cost according to the power declaration data;

[0013] The minimum optimization model is constructed by combining the operating cost, the maintenance cost, the loss cost and the penalty cost and taking the minimum annual total cost of the system as the optimization goal.

[0014] This application constructs multiple operating models based on electricity declaration data, which can provide convenience for the subsequent construction of cost functions based on the operating models, and then construct multiple cost functions of the minimum optimization model, and then take the minimum annual total cost of the system as the optimization goal to construct the minimum optimization model. This can make the minimum optimization model with the minimum annual total cost of the system as the optimization goal more in line with the actual solution, and improve the precision and accuracy of subsequent optimization and control.

[0015] In certain embodiments of the present application, the multiple operation models are constructed according to the power declaration data, specifically including:

[0016] The offshore substation operation model is specifically:

[0017] C sub_sea =0.293(S sub_sea )0.751 ;

[0018] The offshore converter station operation model is specifically as follows:

[0019] C con_sea =171.613+1.144P con_sea ;

[0020] The DC submarine cable operation model is specifically as follows:

[0021]

[0022] The onshore substation operation model is specifically:

[0023] C sub_land =-1.075+0.912(S sub_land ) 0.447 ;

[0024] The onshore converter station operation model is specifically as follows:

[0025] C con_land =123.552+0.618P con_land ;

[0026] Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; S sub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

[0027] This application constructs an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model based on the power declaration data, taking into account the different operation modes of different facilities in the offshore wind power cluster, which can make the operation model more in line with the actual setting of the offshore wind power cluster, thereby improving the subsequent construction cost and optimizing and controlling the precision and accuracy.

[0028] In certain embodiments of the present application, constructing the operating cost and the maintenance cost according to the multiple operating models specifically includes:

[0029] The operating costs are specifically:

[0030]

[0031] The maintenance costs are specifically:

[0032]

[0033] Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , α con_sea , α cab , α sub_land , α con_land They are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

[0034] This application constructs operating costs and maintenance costs based on multiple operating models, and describes the two costs generated by the long-term operation of multiple operating models from the perspective of operation and maintenance of different facilities in offshore wind power clusters, which can make the constructed operating costs and maintenance costs more in line with the actual solution, thereby improving the precision and accuracy of subsequent optimization and control.

[0035] In certain embodiments of the present application, constructing the loss cost and the penalty cost according to the power declaration data specifically includes:

[0036] The loss cost is specifically:

[0037]

[0038] Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S in is the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_lossis the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable;

[0039] The penalty costs are specifically:

[0040]

[0041] Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

[0042] This application constructs loss costs and penalty costs based on electricity declaration data, and constructs loss costs and penalty costs from the perspective of load loss and wind abandonment penalties of offshore wind power clusters, which can make the constructed loss costs and penalty costs more in line with the actual solution, thereby improving the precision and accuracy of subsequent optimization and control.

[0043] In certain embodiments of the present application, the multiple constraints specifically include:

[0044] The output balance constraint is specifically:

[0045]

[0046] The power balance constraint is specifically:

[0047]

[0048] in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

[0049] The present application can stipulate that the balance between the output plan, wind abandonment and actual output of the offshore wind farm should be maintained during model optimization through the output balance constraint, and can stipulate that the balance between the total actual output of the offshore wind farm and the total system load should be maintained during model optimization through the power balance constraint, and can maintain the accuracy of optimization, thereby improving the precision and accuracy of optimization and control.

[0050] In certain embodiments of the present application, the operation cost, the maintenance cost, the loss cost and the penalty cost are combined to minimize the total annual cost of the system as the optimization goal to construct the minimum optimization model, which specifically includes:

[0051] The minimum optimization model is specifically:

[0052]

[0053] Among them, C add is the total annual cost of the system, C inv , C pre , C loss , C drp are operating cost, maintenance cost, loss cost and penalty cost respectively, γ is the power generation discount rate of the offshore wind power cluster, T HVDC It is the service life of HVDC grid.

[0054] After determining that the optimization goal is to minimize the total annual cost of the system, this application constructs a minimum optimization model by combining multiple cost functions with multiple constraints. By solving the minimum optimization model, the minimum total annual cost of the system in the feasible domain can be obtained, thereby reducing the total annual cost of the system while controlling it.

[0055] According to a second aspect of the implementation of the present application, there is provided a control device for an offshore wind power cluster, comprising an optimization model building module and a model solving control module;

[0056] The optimization model building module is used to build a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, with the minimum annual total cost of the system as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraint and power balance constraint;

[0057] The model solving control module is used to substitute the power declaration data into the minimum optimization model for solving, obtain the output plan of each offshore wind farm in the offshore wind power cluster, and control the offshore wind power cluster according to the output plan of each offshore wind farm.

[0058] In certain embodiments of the present application, the optimization model construction module includes an operation model construction unit, a first cost construction unit, a second cost construction unit, and an optimization model construction unit;

[0059] The operation model building unit is used to build multiple operation models according to the power declaration data; wherein the multiple operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model;

[0060] The first cost construction unit is used to construct the operation cost and the maintenance cost according to the multiple operation models;

[0061] The second cost construction unit is used to construct the loss cost and the penalty cost according to the power declaration data;

[0062] The optimization model building unit is used to combine the operating cost, the maintenance cost, the loss cost and the penalty cost, and take the minimization of the total annual cost of the system as the optimization goal to build the minimum optimization model.

[0063] In certain embodiments of the present application, when the operation model building unit is used to build multiple operation models according to the power declaration data, specifically:

[0064] The offshore substation operation model is specifically:

[0065] C sub_sea =0.293(S sub_sea ) 0.751 ;

[0066] The offshore converter station operation model is specifically as follows:

[0067] C con_sea =171.613+1.144P con_sea ;

[0068] The DC submarine cable operation model is specifically as follows:

[0069]

[0070] The onshore substation operation model is specifically:

[0071] C sub_land =-1.075+0.912(S sub_land ) 0.447 ;

[0072] The onshore converter station operation model is specifically as follows:

[0073] C con_land =123.552+0.618P con_land ;

[0074] Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; S sub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

[0075] In certain embodiments of the present application, when the first cost construction unit is used to construct the operating cost and the maintenance cost according to the multiple operating models, specifically:

[0076] The operating costs are specifically:

[0077]

[0078] The maintenance costs are specifically:

[0079]

[0080] Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , α con_sea , α cab , α sub_land , α con_land They are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

[0081] In certain embodiments of the present application, when the second cost construction unit is used to construct the loss cost and the penalty cost according to the power declaration data, specifically:

[0082] The loss cost is specifically:

[0083]

[0084] Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S in is the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_loss is the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable;

[0085] The penalty costs are specifically:

[0086]

[0087] Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

[0088] In certain embodiments of the present application, the multiple constraints are specifically:

[0089] The output balance constraint is specifically:

[0090]

[0091] The power balance constraint is specifically:

[0092]

[0093] in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

[0094] In certain embodiments of the present application, the optimization model construction unit is used to combine the operating cost, the maintenance cost, the loss cost and the penalty cost, and take the minimum annual total cost of the system as the optimization goal to construct the minimum optimization model, specifically:

[0095] The minimum optimization model is specifically:

[0096]

[0097] Among them, C add is the total annual cost of the system, C inv , C pre , C loss , C drp are operating cost, maintenance cost, loss cost and penalty cost respectively, γ is the power generation discount rate of the offshore wind power cluster, T HVDC It is the service life of HVDC grid.

[0098] This application first constructs a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, including cluster operation data, HVDC operation data, electricity price data and loss data, with the minimum system annual total cost as the optimization goal, and then substitutes the power declaration data into the minimum optimization model to solve the output plan of each offshore wind farm, so as to control the offshore wind power cluster according to the output plan of each offshore wind farm. Compared with the prior art, the actual operation of the cluster and the actual use of HVDC grid connection are taken into consideration, and the constructed optimization model is more in line with the actual grid connection use of the offshore wind power cluster based on HVDC, and more in line with actual needs, so that the constructed optimization model is more accurate, which can improve the control accuracy when controlling the offshore wind power cluster, and at the same time, with the minimum system annual total cost as the optimization goal, it can reduce the annual total cost of the system while controlling. BRIEF DESCRIPTION OF THE DRAWINGS

[0099] Figure 1 : A flow chart of a control method for an offshore wind power cluster shown in certain embodiments of the present application;

[0100] Figure 2 : A module structure diagram of a control device for an offshore wind power cluster shown in certain embodiments of the present application. DETAILED DESCRIPTION

[0101] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals represent the same or similar elements or elements having the same or similar functions from beginning to end. The embodiments described below in conjunction with the accompanying drawings are exemplary and are only used to explain some embodiments of the present application, and should not be construed as limitations on the embodiments of the present application. Based on the embodiments shown in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.

[0102] In the description of this application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, unless otherwise clearly and specifically defined, "multiple" and "several" mean two or more.

[0103] The optimization control model constructed in the existing offshore wind power control optimization method usually only fine-tunes the parameters without considering the actual use of the HVDC transmission system, resulting in uncorrectable deviations in the solution results of the optimization control model, and thus deviations in the control accuracy of the offshore wind power cluster. Therefore, how to more reasonably construct an optimization control model to improve the control accuracy of the offshore wind power cluster is an urgent problem to be solved in the existing technology.

[0104] Based on the above technical background, please refer to Figure 1 The embodiment of the present application provides a control method for an offshore wind power cluster, including steps S101 to S102, each of which is as follows:

[0105] Step S101: According to the power declaration data of the offshore wind power cluster to be controlled, a minimum optimization model is constructed with the minimum annual total system cost as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraints and power balance constraints.

[0106] In certain embodiments of the present application, the minimum optimization model is constructed based on the power declaration data of the offshore wind power cluster to be controlled and with the minimum annual total cost of the system as the optimization goal, specifically including:

[0107] Constructing a plurality of operation models according to the power declaration data; wherein the plurality of operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model;

[0108] constructing the operating cost and the maintenance cost according to the plurality of operating models;

[0109] constructing the loss cost and the penalty cost according to the power declaration data;

[0110] The minimum optimization model is constructed by combining the operating cost, the maintenance cost, the loss cost and the penalty cost and taking the minimum annual total cost of the system as the optimization goal.

[0111] This application constructs multiple operating models based on electricity declaration data, which can provide convenience for the subsequent construction of cost functions based on the operating models, and then construct multiple cost functions of the minimum optimization model, and then take the minimum annual total cost of the system as the optimization goal to construct the minimum optimization model. This can make the minimum optimization model with the minimum annual total cost of the system as the optimization goal more in line with the actual solution, and improve the precision and accuracy of subsequent optimization and control.

[0112] In certain embodiments of the present application, the multiple operation models are constructed according to the power declaration data, specifically including:

[0113] The offshore substation operation model is specifically:

[0114] C sub_sea =0.293(S sub_sea ) 0.75 1;

[0115] The offshore converter station operation model is specifically as follows:

[0116] C con_sea =171.613+1.144P con_sea ;

[0117] The DC submarine cable operation model is specifically as follows:

[0118]

[0119] The onshore substation operation model is specifically:

[0120] C sub_land =-1.075+0.912(S sub_land ) 0.447 ;

[0121] The onshore converter station operation model is specifically as follows:

[0122] C con_land =123.552+0.618P con_land ;

[0123] Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; S sub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

[0124] This application constructs an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model based on the power declaration data, taking into account the different operation modes of different facilities in the offshore wind power cluster, which can make the operation model more in line with the actual setting of the offshore wind power cluster, thereby improving the subsequent construction cost and optimizing and controlling the precision and accuracy.

[0125] In certain embodiments of the present application, constructing the operating cost and the maintenance cost according to the multiple operating models specifically includes:

[0126] The operating costs are specifically:

[0127]

[0128] The maintenance costs are specifically:

[0129]

[0130] Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , α con_sea , α cab , α sub_land , α con_landThey are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

[0131] The reason for considering setting operating costs and maintenance costs according to multiple operating models is that the construction and power generation operation models of different facilities in the offshore wind power cluster are different, but the commonality between different facilities is that there is a correlation between the operation and maintenance of the facilities. The corresponding operating costs and maintenance costs can be constructed based on the operating models of the current facilities. By setting the operating costs and maintenance costs separately, the system's annual total cost can also be made more in line with the actual annual total cost of the offshore wind power cluster.

[0132] This application constructs operating costs and maintenance costs based on multiple operating models, and describes the two costs generated by the long-term operation of multiple operating models from the perspective of operation and maintenance of different facilities in offshore wind power clusters, which can make the constructed operating costs and maintenance costs more in line with the actual solution, thereby improving the precision and accuracy of subsequent optimization and control.

[0133] In certain embodiments of the present application, constructing the loss cost and the penalty cost according to the power declaration data specifically includes:

[0134] The loss cost is specifically:

[0135]

[0136] Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S in is the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_loss is the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable;

[0137] The penalty costs are specifically:

[0138]

[0139] Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

[0140] The reason for considering setting loss costs is that in the process of continuous operation of the offshore wind power cluster, unrepairable facility losses will occur accordingly, and these losses cannot be attributed to the operating costs used for construction and power generation or the maintenance costs for maintaining facilities. It is necessary to additionally consider the impact of loss costs on the annual total cost of the system; the reason for considering setting penalty costs is that in the offshore wind power cluster, due to the changeable weather, each offshore wind farm will produce wind speed fluctuations. Taking into account the daily power generation and wind abandonment of the offshore wind farm, setting a wind abandonment penalty cost based on wind abandonment can make the annual total cost of the system more in line with the actual annual total cost of the offshore wind power cluster.

[0141] This application constructs loss costs and penalty costs based on electricity declaration data, and constructs loss costs and penalty costs from the perspective of load loss and wind abandonment penalties of offshore wind power clusters, which can make the constructed loss costs and penalty costs more in line with the actual solution, thereby improving the precision and accuracy of subsequent optimization and control.

[0142] In certain embodiments of the present application, the multiple constraints specifically include:

[0143] The output balance constraint is specifically:

[0144]

[0145] The power balance constraint is specifically:

[0146]

[0147] in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

[0148] The present application can stipulate that the balance between the output plan, wind abandonment and actual output of the offshore wind farm should be maintained during model optimization through the output balance constraint, and can stipulate that the balance between the total actual output of the offshore wind farm and the total system load should be maintained during model optimization through the power balance constraint, and can maintain the accuracy of optimization, thereby improving the precision and accuracy of optimization and control.

[0149] In certain embodiments of the present application, the operation cost, the maintenance cost, the loss cost and the penalty cost are combined to minimize the total annual cost of the system as the optimization goal to construct the minimum optimization model, which specifically includes:

[0150] The minimum optimization model is specifically:

[0151]

[0152] Among them, C add is the total annual cost of the system, C inv , C pre , C loss , C drp are operating cost, maintenance cost, loss cost and penalty cost respectively, γ is the power generation discount rate of the offshore wind power cluster, T HVDC It is the service life of HVDC grid.

[0153] The reason for considering the introduction of HVDC's grid-connected service life is that the operation of the offshore wind power cluster depends on the HVDC grid-connected system to transmit the offshore wind power generation. With the continuous operation of the offshore wind power cluster and HVDC, the operating cost of the offshore wind power cluster will also change with the grid-connected service life of HVDC. By considering the grid-connected service life of HVDC, the system's annual total cost can be made more in line with the actual annual total cost of the offshore wind power cluster using the HVDC transmission system.

[0154] After determining that the optimization goal is to minimize the total annual cost of the system, this application constructs a minimum optimization model by combining multiple cost functions with multiple constraints. By solving the minimum optimization model, the minimum total annual cost of the system in the feasible domain can be obtained, thereby reducing the total annual cost of the system while controlling it.

[0155] Step S102: Substitute the power declaration data into the minimum optimization model for solution to obtain the output plan of each offshore wind farm in the offshore wind power cluster, and control the offshore wind power cluster according to the output plan of each offshore wind farm.

[0156] Compared with the prior art, this application first constructs a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, including cluster operation data, HVDC operation data, electricity price data and loss data, with the minimum system annual total cost as the optimization goal, and then substitutes the power declaration data into the minimum optimization model to solve the output plan of each offshore wind farm, so as to control the offshore wind power cluster according to the output plan of each offshore wind farm. Compared with the prior art, the actual operation of the cluster and the actual use of HVDC grid connection are taken into consideration, and the constructed optimization model is more in line with the actual use of the offshore wind power cluster based on HVDC grid connection, and more in line with actual needs, so that the constructed optimization model is more accurate, which can improve the control accuracy when controlling the offshore wind power cluster, and at the same time, with the minimum system annual total cost as the optimization goal, it can reduce the annual total cost of the system while controlling.

[0157] Corresponding to the previous method, see Figure 2 , the embodiment of the present application provides a control device for an offshore wind power cluster, including an optimization model building module 210 and a model solving control module 220;

[0158] The optimization model building module 210 is used to build a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, with the minimum annual total cost of the system as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraint and power balance constraint;

[0159] The model solving control module 220 is used to substitute the power declaration data into the minimum optimization model for solving, obtain the output plan of each offshore wind farm in the offshore wind power cluster, and control the offshore wind power cluster according to the output plan of each offshore wind farm.

[0160] In certain embodiments of the present application, the optimization model construction module 210 includes an operation model construction unit 211, a first cost construction unit 212, a second cost construction unit 213, and an optimization model construction unit 214;

[0161] The operation model building unit 211 is used to build multiple operation models according to the power declaration data; wherein the multiple operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model;

[0162] The first cost construction unit 212 is used to construct the operation cost and the maintenance cost according to the multiple operation models;

[0163] The second cost construction unit 213 is used to construct the loss cost and the penalty cost according to the power declaration data;

[0164] The optimization model building unit 214 is used to combine the operation cost, the maintenance cost, the loss cost and the penalty cost, and take the minimum annual total cost of the system as the optimization goal to build the minimum optimization model.

[0165] In some embodiments of the present application, the operation model building unit 211 is used to build multiple operation models according to the power declaration data, specifically:

[0166] The offshore substation operation model is specifically:

[0167] C sub_sea =0.293(S sub_sea ) 0.751 ;

[0168] The offshore converter station operation model is specifically as follows:

[0169] C con_sea =171.613+1.144P con_sea ;

[0170] The DC submarine cable operation model is specifically as follows:

[0171]

[0172] The onshore substation operation model is specifically:

[0173] C sub_land =-1.075+0.912(S sub_land ) 0.447 ;

[0174] The onshore converter station operation model is specifically as follows:

[0175] C con_land =123.552+0.618P con_land ;

[0176] Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; Ssub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

[0177] In some embodiments of the present application, when the first cost construction unit 212 is used to construct the operation cost and the maintenance cost according to the multiple operation models, specifically:

[0178] The operating costs are specifically:

[0179]

[0180] The maintenance costs are specifically:

[0181]

[0182] Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , α con_sea , α cab , α sub_land , α con_land They are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

[0183] In some embodiments of the present application, when the second cost construction unit 213 is used to construct the loss cost and the penalty cost according to the power declaration data, specifically:

[0184] The loss cost is specifically:

[0185]

[0186] Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S inis the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_loss is the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable;

[0187] The penalty costs are specifically:

[0188]

[0189] Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

[0190] In certain embodiments of the present application, the multiple constraints are specifically:

[0191] The output balance constraint is specifically:

[0192]

[0193] The power balance constraint is specifically:

[0194]

[0195] in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

[0196] In certain embodiments of the present application, the optimization model construction unit 214 is used to combine the operating cost, the maintenance cost, the loss cost and the penalty cost, and take the minimum annual total cost of the system as the optimization goal to construct the minimum optimization model, specifically:

[0197] The minimum optimization model is specifically:

[0198]

[0199] Among them, C add is the total annual cost of the system, C inv , C pre , C loss , C drp are operating cost, maintenance cost, loss cost and penalty cost respectively, γ is the power generation discount rate of the offshore wind power cluster, T HVDC It is the service life of HVDC grid.

[0200] This application first constructs a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, including cluster operation data, HVDC operation data, electricity price data and loss data, with the minimum system annual total cost as the optimization goal, and then substitutes the power declaration data into the minimum optimization model to solve the output plan of each offshore wind farm, so as to control the offshore wind power cluster according to the output plan of each offshore wind farm. Compared with the prior art, the actual operation of the cluster and the actual use of HVDC grid connection are taken into consideration, and the constructed optimization model is more in line with the actual grid connection use of the offshore wind power cluster based on HVDC, and more in line with actual needs, so that the constructed optimization model is more accurate, which can improve the control accuracy when controlling the offshore wind power cluster, and at the same time, with the minimum system annual total cost as the optimization goal, it can reduce the annual total cost of the system while controlling.

[0201] It should be understood that the device provided in the embodiment of the present application corresponds to the aforementioned method, and a control device for an offshore wind power cluster provided in the embodiment of the present application can implement a control method for an offshore wind power cluster provided in any embodiment of the present application.

[0202] Adaptively, the embodiments of the present application also provide a computer device and a computer-readable storage medium.

[0203] The computer device comprises: a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor;

[0204] Wherein, when the processor executes the computer program, a control method for an offshore wind power cluster of the present application is implemented.

[0205] The computer-readable storage medium stores a plurality of instructions, and the instructions are suitable for being loaded by a processor to execute a control method for an offshore wind power cluster of the present application.

[0206] The above are some implementation methods of the present application, and the purpose, technical scheme and beneficial effects of the present application are further described in detail. It should be clear that the above-mentioned partial implementation methods of the present application cannot be understood as limiting the present application. It is particularly pointed out that for those skilled in the art, any changes, modifications, equivalent substitutions and variations made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A control method for an offshore wind power cluster, characterized in that: include: According to the power declaration data of the offshore wind power cluster to be controlled, a minimum optimization model is constructed with the minimum annual total cost of the system as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraint and power balance constraint; Substituting the power declaration data into the minimum optimization model for solving, the output plan of each offshore wind farm in the offshore wind power cluster is obtained, and the offshore wind power cluster is controlled according to the output plan of each offshore wind farm.

2. A control method for an offshore wind power cluster according to claim 1, characterized in that: According to the power declaration data of the offshore wind power cluster to be controlled, the minimum total annual cost of the system is taken as the optimization goal to construct a minimum optimization model, which specifically includes: Constructing a plurality of operation models according to the power declaration data; wherein the plurality of operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model; constructing the operating cost and the maintenance cost according to the plurality of operating models; constructing the loss cost and the penalty cost according to the power declaration data; The minimum optimization model is constructed by combining the operating cost, the maintenance cost, the loss cost and the penalty cost and taking the minimum annual total cost of the system as the optimization goal.

3. A control method for an offshore wind power cluster according to claim 2, characterized in that: The constructing of multiple operation models according to the power declaration data specifically includes: The offshore substation operation model is specifically: C sub_sea =0.293(S sub_sea ) 0.751 ; The offshore converter station operation model is specifically as follows: C con_sea =171.613+1.144P con_sea ; The DC submarine cable operation model is specifically as follows: The onshore substation operation model is specifically as follows: C sub_land =-1.075+0.912(S sub_land ) 0.447 ; The onshore converter station operation model is specifically as follows: C con_land =123.552+0.618P con_land ; Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; S sub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

4. A control method for an offshore wind power cluster according to claim 3, characterized in that: The constructing the operation cost and the maintenance cost according to the multiple operation models specifically includes: The operating costs are specifically: The maintenance costs are specifically: Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , α con_sea , α cab , α sub_land , α con_land They are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

5. The control method of an offshore wind power cluster according to claim 2, characterized in that: The constructing the loss cost and the penalty cost according to the power declaration data specifically includes: The loss cost is specifically: Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S in is the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_loss is the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable; The penalty costs are specifically: Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

6. A control method for an offshore wind power cluster according to claim 2, characterized in that: The multiple constraints specifically include: The output balance constraint is specifically: The power balance constraint is specifically: in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

7. A control method for an offshore wind power cluster according to claim 2, characterized in that: The minimum optimization model is constructed by combining the operation cost, the maintenance cost, the loss cost and the penalty cost with the minimum annual total cost of the system as the optimization goal, and specifically includes: The minimum optimization model is specifically: Among them, is the total annual cost of the system, which includes operation cost, maintenance cost, loss cost and penalty cost, is the power generation discount rate of the offshore wind power cluster, and is the grid-connected service life of HVDC.

8. A control device for an offshore wind power cluster, characterized in that: It includes an optimization model building module and a model solving control module; The optimization model building module is used to build a minimum optimization model based on the power declaration data of the offshore wind power cluster to be controlled, with the minimum annual total cost of the system as the optimization goal; wherein the power declaration data includes cluster operation data, HVDC operation data, electricity price data and loss data; the minimum optimization model includes an objective function and multiple constraints; the objective function includes multiple cost functions; the multiple cost functions include operation cost, maintenance cost, loss cost and penalty cost; the multiple constraints include output balance constraint and power balance constraint; The model solving control module is used to substitute the power declaration data into the minimum optimization model for solving, obtain the output plan of each offshore wind farm in the offshore wind power cluster, and control the offshore wind power cluster according to the output plan of each offshore wind farm.

9. A control device for an offshore wind power cluster according to claim 8, characterized in that: The optimization model construction module includes an operation model construction unit, a first cost construction unit, a second cost construction unit and an optimization model construction unit; The operation model building unit is used to build multiple operation models according to the power declaration data; wherein the multiple operation models include an offshore substation operation model, an offshore converter station operation model, a DC submarine cable operation model, an onshore substation operation model and an onshore converter station operation model; The first cost construction unit is used to construct the operation cost and the maintenance cost according to the multiple operation models; The second cost construction unit is used to construct the loss cost and the penalty cost according to the power declaration data; The optimization model building unit is used to combine the operating cost, the maintenance cost, the loss cost and the penalty cost, and take the minimization of the total annual cost of the system as the optimization goal to build the minimum optimization model.

10. A control device for an offshore wind power cluster according to claim 9, characterized in that: When the operation model building unit is used to build a plurality of operation models according to the power declaration data, specifically: The offshore substation operation model is specifically: C sub_sea =0.293(S sub_sea ) 0.751 ; The offshore converter station operation model is specifically as follows: C con_sea =171.613+1.144P con_sea ; The DC submarine cable operation model is specifically: The onshore substation operation model is specifically as follows: C sub_land =-1.075+0.912(S sub_land ) 0.447 ; The onshore converter station operation model is specifically as follows: C con_land =123.552+0.618P con_land ; Among them, C sub_sea , C con_sea , C cab , C sub_land , C con_land They are the operating cost of offshore substation, offshore converter station, DC submarine cable, onshore substation and onshore converter station respectively; S sub_sea is the daily transmitted apparent power of the offshore substation; P con_sea is the daily transmitted active power of the offshore converter station; P cab , M cab are the actual capacity and laying cost of DC submarine cables, n DC , l cab are the number and length of DC submarine cables, respectively; a, b, c are the selection parameters of DC submarine cables; S sub_land is the daily transmission apparent power of the onshore substation; P con_land It is the daily transmitted active power of the onshore converter station.

11. A control device for an offshore wind power cluster according to claim 10, characterized in that: When the first cost construction unit is used to construct the operation cost and the maintenance cost according to the multiple operation models, specifically: The operating costs are specifically: The maintenance costs are specifically: Among them, C inv , C pre are the operating cost and maintenance cost respectively, d represents the dth day of the year, α sub_sea , a con_sea , α cab , α sub_land , α con_land They are the annual maintenance rates for offshore substations, offshore converter stations, DC submarine cables, onshore substations and onshore converter stations respectively.

12. The control device for an offshore wind power cluster according to claim 9, characterized in that: When the second cost construction unit is used to construct the loss cost and the penalty cost according to the power declaration data, specifically: The loss cost is specifically: Among them, C loss For loss cost; is the total daily loss of offshore substation and onshore substation, S sub_N is the rated apparent power of the offshore substation, P sub_0 is the no-load loss of the offshore substation, P sub_L is the daily load loss of the offshore substation, S in is the daily input capacity of the offshore substation; p sa is the offshore wind power price; P con_loss =P con_in α con_loss is the total daily loss of the offshore converter station and the onshore converter station, P con_in is the daily input power of the offshore converter station, α con_loss is the fixed loss rate for offshore converter stations; is the daily loss of the DC submarine cable, r ab is the resistance per unit length of the DC submarine cable, P cab_in is the actual daily transmission power of the DC submarine cable, U cab_N is the rated voltage of the DC submarine cable; The penalty costs are specifically: Among them, C drp is the penalty cost, d is the dth day of the year, N i is the number of offshore wind farms; is the penalty factor for unit wind curtailment of the i-th offshore wind farm on the d-th day, ρ d is the offshore wind power price on day d, is the output plan of the i-th offshore wind farm on the d-th day, P d is the total system load on day d, is the maximum system load on day d; is the amount of wind abandoned by the i-th offshore wind farm on the d-th day.

13. The control device for an offshore wind power cluster according to claim 9, characterized in that: The multiple constraints are specifically: The output balance constraint is specifically: The power balance constraint is specifically: in, is the output plan of the i-th offshore wind farm on the d-th day, is the wind curtailment of the ith offshore wind farm on the dth day, is the actual output of the ith offshore wind farm on day d, N i is the number of offshore wind farms, P d is the total system load on day d.

14. The control device for an offshore wind power cluster according to claim 9, characterized in that: The optimization model construction unit is used to combine the operating cost, the maintenance cost, the loss cost and the penalty cost, and take the minimum annual total cost of the system as the optimization goal to construct the minimum optimization model, specifically: The minimum optimization model is specifically: Among them, C add is the total annual cost of the system, C inv , C pre , C loss , C drp are operating cost, maintenance cost, loss cost and penalty cost respectively, γ is the power generation discount rate of the offshore wind power cluster, T HVDC It is the service life of HVDC grid.