Mining three-blocking two-injecting hole packer and using method thereof
By setting up three capsule bags and grouting pipes in the mining three-block two-injection sealer, and using a blasting valve to divide the grouting section, the problem of slurry flowing during grouting in the existing technology is solved, and more efficient is achieved The gas extraction and sealing properties reduce construction costs.
Patent Information
- Application Number
- CN202411350200.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-26
- Publication Date
- 2024-11-26
AI Technical Summary
In the existing mining 'two blocks and one injector' process, cracks in the sealing section near the outside develop severely, resulting in the slurry that easily flows along the cracks during grouting, making it difficult to achieve complete sealing of the cracks, affecting gas extraction. efficiency.
Three plugs and two injection sealing devices for mining are used. By setting up three capsules and grouting pipes in the coal seam drilling hole, and using a blasting valve to grout to fill the outer and inner section sealing spaces under different pressure conditions, and the injection is divided. slurry section to improve sealing.
It effectively seals the cracks in the drilling holes, enhances the drilling sealing, improves the gas extraction efficiency and concentration, reduces the number of low-concentration failure drilling holes, and reduces the construction cost.
Smart Images

Figure CN119021635A_ABST
Abstract
Description
[Technical field]
[0001] The invention belongs to the technical field of mine hole sealers, and in particular relates to a mine hole sealer with three plugging and two injections and a use method thereof. [Background technology]
[0002] The "two plugging and one injection" method used in the prior art is a pressure-sealing method. The principle is to first use bags to seal the two ends of the sealing section of the coal seam borehole, and then use a grouting pipe to grout the borehole section between the two sealing sections. This method can effectively fill the cracks around the borehole and improve the efficiency of gas extraction. However, in the area where the sealing section is located near the outside, due to the more serious development of the cracks and the wide distribution range, the slurry is easy to flow along the larger cracks during the grouting process, and it is not easy to achieve complete sealing of the cracks. [Summary of the invention]
[0003] The purpose of the present invention is to provide a mining three-blocking and two-injection hole sealer and a method of using the same, so as to solve the problem that in the existing two-blocking and one-injection process, the slurry in the area where the sealing section close to the outside is located is easy to flow along the larger cracks during the grouting process, making it difficult to completely seal the cracks.
[0004] The present invention adopts the following technical scheme: a three-blocking and two-injection hole sealer for mining, comprising an assembled hole sealing pipe for being placed in a coal seam borehole to extract gas, the assembled hole sealing pipe being covered with a first bag, a second bag and a third bag; the first bag, the second bag and the third bag are respectively located at the outer end, the middle section and the inner end of the assembled hole sealing pipe;
[0005] It also includes a grouting pipe arranged in parallel with the assembled sealing pipe, the pipe body of the grouting pipe passes through the first bag, the second bag and the third bag in sequence; the inlet end of the grouting pipe is located outside the first bag, the outlet end of the grouting pipe is located inside the third bag, and the intersection of the grouting pipe with the first bag and the second bag is provided with a diversion port;
[0006] On the grouting pipe: burst valves are provided at positions between the first bladder bag and the second bladder bag, and between the second bladder bag and the third bladder bag;
[0007] Among them, the first bag, the second bag and the third bag are used to seal the drill hole through internal grouting expansion, and an outer sealing space is formed between the first bag and the second bag, and an inner sealing space is formed between the second bag and the third bag; the bursting valve is used to burst under set pressure conditions to grout and fill the outer sealing space and the inner sealing space respectively.
[0008] Furthermore, the preset pressure of the bursting valve between the first bladder bag and the second bladder bag is 1.5 MPa.
[0009] Furthermore, the preset pressure of the bursting valve between the second bladder bag and the third bladder bag is 0.8 MPa.
[0010] Furthermore, the assembled sealing pipe includes a plurality of sealing pipes connected in series, and adjacent sealing pipes are threadedly connected.
[0011] The second technical solution adopted by the present invention is a method for using a three-blocking and two-injection hole sealer for mining, which is based on the three-blocking and two-injection hole sealer for mining and includes the following contents:
[0012] The assembled sealing pipe and the grouting pipe are placed in the coal seam borehole;
[0013] injecting grout into the first bag, the second bag and the third bag through the grouting pipe;
[0014] The first bag, the second bag and the third bag are inflated and fastened to the inner wall of the coal seam borehole, thereby sealing and forming an outer section sealing space and an inner section sealing space on the assembled sealing pipe;
[0015] The grouting is continued until the pressure rises to 0.8Mp, the bursting valve between the second bag and the third bag 6 is opened, and the grouting of the inner section sealing hole space begins; after the pressure rises to 1.5Mp, the bursting valve between the first bag and the second bag is opened again, and the grouting of the outer section sealing hole space begins;
[0016] Stop grouting until the slurry fills the outer and inner sealing spaces.
[0017] The beneficial effect of the present invention is that by setting three bags, the grouting section is divided into two sections, an inner sealing space and an outer sealing space; in the area where the outer sealing space is located, due to the more serious development of cracks and a wide distribution range, the slurry is easy to flow along the larger cracks during the grouting process, and it is not easy to achieve complete sealing of the cracks. Therefore, the outer section mainly plays the role of filling the borehole, and the cracks in the inner section space are relatively small, which is convenient for high-pressure grouting sealing, can better achieve effective sealing of the cracks, and can enhance the sealing of the borehole, thereby achieving the purpose of improving the gas extraction effect.
Brief Description of the Drawings
[0018] Figure 1 It is a structural schematic diagram of the three-blocking and two-injection hole sealer for mining of the present invention;
[0019] Figure 2 for Figure 1 The enlarged view of point A in the middle;
[0020] Figure 3 It is a schematic diagram of the use status of the three-blocking and two-injection hole sealer for mining of the present invention.
[0021] Among them, 1. sealing tube, 2. grouting tube, 21. inlet end, 22. outlet end, 23. diversion port, 24. tube body, 3. bursting valve, 4. first bag, 5. second bag, 6. third bag. [Specific implementation method]
[0022] The present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0023] The present invention provides a three-blocking and two-injection hole sealing device for mining, such as Figure 1 As shown, it includes an assembled sealing pipe placed in a borehole to extract gas, and the assembled sealing pipe is covered with a first bag 4, a second bag 5 and a third bag 6; the first bag 4, the second bag 5 and the third bag 6 are respectively located at the outer end, the middle section and the inner end of the assembled sealing pipe.
[0024] It also includes a grouting pipe 2 arranged in parallel with the assembly sealing pipe, the pipe body of the grouting pipe 2 passes through the first bag 4, the second bag 5 and the third bag 6 in sequence; the inlet end 21 of the grouting pipe 2 is located outside the first bag 4, the outlet end 22 of the grouting pipe 2 is located inside the third bag 6, and the intersection of the grouting pipe 2 and the first bag 4 and the second bag 5 is provided with a diversion port 23. Figure 2 As shown, the diversion port 23 is an opening provided on the grouting pipe 2, which is used to divert the slurry into the bag. The grouting pipe 2 is used to inject grout into the first bag 4 and the second bag 5 through the two diversion ports 23 thereon, and is also used to inject grout into the third bag 6 through its outlet end 22; the first bag 4, the second bag 5 and the third bag 6 are used to achieve the plugging of the borehole by their own expansion.
[0025] The grouting pipe 2 is provided with burst valves 3 at positions between the first bag 4 and the second bag 5 , and between the second bag 5 and the third bag 6 .
[0026] The first bag 4, the second bag 5 and the third bag 6 are used to seal the borehole by internal grouting expansion. The expanded bags can effectively support the borehole, forming a high stress area around the borehole sealing section, and avoiding continuous cracks after sealing to form a leakage channel.
[0027] An outer sealing space is formed between the first bag 4 and the second bag 5, and an inner sealing space is formed between the second bag 5 and the third bag 6. The outer sealing space mainly serves to fill the borehole, and the cracks in the inner sealing space are relatively small, which is convenient for high-pressure grouting sealing, can better achieve effective plugging of the cracks, and can enhance the sealing of the borehole, thereby achieving the purpose of improving the gas extraction effect.
[0028] The bursting valve 3 is used to burst under set pressure conditions to inject grout into the outer section sealing space and the inner section sealing space respectively.
[0029] In some embodiments, the preset pressure of the bursting valve 3 between the first bladder 4 and the second bladder 5 is 1.5 MPa.
[0030] In some embodiments, the bursting valve 3 between the second bladder 5 and the third bladder 6 is preset at 0.8 MPa.
[0031] In some embodiments, the assembled sealing pipe comprises a plurality of sealing pipes 1 connected in series, and adjacent sealing pipes 1 are threadedly connected. The length of the assembled sealing pipe can be adjusted according to the actual drilling conditions downhole.
[0032] The use method of the three-blocking and two-injection hole sealer for mining of the present invention is as follows:
[0033] The assembled sealing pipe and the grouting pipe 2 are placed in the coal seam borehole;
[0034] The grouting pipe 2 is connected to the grouting pump, and the slurry quickly enters the first bag 4, the second bag 5 and the third bag 6 due to the grouting pressure;
[0035] like Figure 3 As shown, the three bags expand rapidly, and their outer wall surfaces are fastened to the inner wall of the coal seam borehole, and their inner wall surfaces are fastened to the outer surface of the assembled sealing pipe, thereby sealing and forming an outer section sealing space and an inner section sealing space on the assembled sealing pipe;
[0036] After the three bags are filled to support the borehole to form two grouting spaces, the outer sealing space and the inner sealing space, grouting is continued and the pressure slowly increases to 0.8Mp. First, the bursting valve between the second bag 5 and the third bag 6 is opened, and grouting of the inner sealing space begins. After the inner sealing space is filled, the pressure continues to increase to 1.5Mp, and then the bursting valve between the first bag 4 and the second bag 5 is opened again, and grouting of the outer sealing space begins. The slurry fills the outer sealing space and the inner sealing space. After the grouting is completely solidified, gas extraction is carried out by assembling the sealing pipe.
[0037] Through comparative analysis of 50 sets of drilling test data, the average gas extraction concentration of a single hole using the "three-blocking and two-injection" sealing device within 15 days was increased by 39.14% compared with the "two-blocking and one-injection" sealing device. After 75 days of extraction, the average gas concentration of the "three-blocking and two-injection" drilling holes was 58.87% higher than that of the "two-blocking and one-injection" drilling holes. On average, 50 drilling holes can reduce more than one low-concentration failed drilling hole. At present, the mine has fully promoted the use of the "three-blocking and two-injection" sealing technology. According to the calculation based on 8,500 drilling holes constructed throughout the year, 170 failed drilling holes can be reduced throughout the year. The total labor and material cost of a single hole of through-layer drilling is about 8,000 yuan, which can reduce the waste of funds by more than 1.36 million yuan on average throughout the year.
Claims
1. The three-blocking and two-injection hole sealer for mining is characterized by: The invention comprises an assembled sealing pipe for being placed in a coal seam borehole to extract gas, wherein the assembled sealing pipe is covered with a first bag (4), a second bag (5) and a third bag (6); the first bag (4), the second bag (5) and the third bag (6) are respectively located at the outer end, the middle section and the inner end of the assembled sealing pipe; It also comprises a grouting pipe (2) arranged in parallel with the assembled sealing pipe, the pipe body of the grouting pipe (2) passes through the first bag (4), the second bag (5) and the third bag (6) in sequence; the inlet end (21) of the grouting pipe (2) is located outside the first bag (4), the outlet end (22) of the grouting pipe (2) is located inside the third bag (6), and the intersection of the grouting pipe (2) with the first bag (4) and the second bag (5) is provided with a diversion port (23); On the grouting pipe (2), burst valves (3) are provided at positions between the first bag (4) and the second bag (5), and between the second bag (5) and the third bag (6); The first bag (4), the second bag (5) and the third bag (6) are used to seal the borehole by internal grouting expansion, and to form an outer sealing space between the first bag (4) and the second bag (5), and an inner sealing space between the second bag (5) and the third bag (6); the bursting valve (3) is used to burst under set pressure conditions to inject grout into the outer sealing space and the inner sealing space respectively.
2. The three-blocking and two-injection hole sealer for mining as claimed in claim 1 is characterized in that: The preset pressure of the burst valve (3) between the first bladder bag (4) and the second bladder bag (5) is 1.5 MPa.
3. The three-blocking and two-injection hole sealer for mining as claimed in claim 1 is characterized in that: The preset pressure of the burst valve (3) between the second bladder (5) and the third bladder (6) is 0.8 MPa.
4. The three-blocking and two-injection hole sealer for mining as claimed in claim 1 or 2, characterized in that: The assembled sealing pipe comprises a plurality of sealing pipes (1) connected in series, and adjacent sealing pipes (1) are threadedly connected.
5. The method of using the three-blocking and two-injection hole sealer for mining is characterized in that: The three-blocking and two-injection hole sealer for mining according to any one of claims 1 to 4 includes the following contents: Placing the assembled sealing pipe and the grouting pipe (2) in the coal seam borehole; Injecting grout into the first bag (4), the second bag (5) and the third bag (6) through a grouting pipe (2); The first bag (4), the second bag (5) and the third bag (6) are expanded and fastened to the inner wall of the coal seam borehole, thereby sealing and forming an outer section sealing space and an inner section sealing space on the assembled sealing pipe; The grouting is continued until the pressure rises to 0.8 Mp, the bursting valve between the second bag (5) and the third bag 6 is opened, and the grouting of the inner section sealing hole space begins; after the pressure rises to 1.5 Mp, the bursting valve between the first bag (4) and the second bag (5) is opened again, and the grouting of the outer section sealing hole space begins; Stop grouting until the slurry fills the outer and inner sealing spaces.