Method for stoping gently inclined end part of steeply inclined ore body

By adopting a mining method with quasi-ramping and optimizing medium-deep hole layout at the gently tilted end of the lead-zinc mine, the problem of poverty alleviation rate and waste rock increase caused by conventional mining methods is solved, and the more Efficient ore recycling and economic benefits.

CN119021696APending Publication Date: 2024-11-26GANSU CHANGBA NONFERROUS METALS CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411151370.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the mining process of the gently inclined ends of the lead-zinc mine, conventional mining methods have led to a sharp increase in the depletion rate and mining and cutting project volume, resulting in a large amount of waste rock, reducing the ore output grade and economic benefits.

Method used

The quasi-mining ramp and optimized medium-deep hole rock drilling parameters are used to change the bottom structure mining cutting project and medium-deep hole layout, and the ore is recovered through slightly differential blasting between holes to form compensation space, reduce the amount of waste stone and improve ore recovery efficiency.

Benefits of technology

The amount of waste stone is reduced, the ore output grade is improved, the income per unit of ore is increased, and the economic benefits of the mine are significantly improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021696A_ABST
    Figure CN119021696A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of mine stoping, and aims to provide a stoping method for a gently inclined end part of a steeply inclined ore body. The method is mainly characterized in that in the stoping process of the gently inclined end of the steeply inclined ore body, when a bottom structure is arranged in a stoping layer in the trend for mining, a conventional bottom structure mining and cutting project and a medium-length hole rock drilling parameter stoping method are not used; according to the stoping method, a mining preparation slope ramp and optimized medium-length hole arrangement are creatively used for the gently inclined end of a steeply inclined ore body, and more reasonable engineering arrangement and ore recovery sequence are adopted; the problem that the mixing amount of surrounding rock is too large due to the fact that a conventional bottom structure mining and cutting project and a medium-length hole arrangement stoping method are adopted for the gently-inclined end of the steeply-inclined ore body is solved, the purpose of low dilution of stoping of the gently-inclined end of the ore body is achieved, the ore removal grade is improved, the income of unit ore is increased, and economic benefits are remarkable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of mine recovery, and in particular relates to a recovery method for a gently inclined end portion of a steeply inclined ore body. Background Art

[0002] In the mining process of the gently inclined end of a steeply inclined ore body in a lead-zinc mine, the surrounding rocks of the ore are relatively stable and firm. The mining method of segmented empty field followed by filling is adopted. Due to the gently inclined pinch-out at the end of the ore body in the segment, the dilution rate and the amount of mining and cutting engineering will increase sharply according to the conventional mining method. Therefore, a mining method for the gently inclined end of a steeply inclined ore body is invented. This invention changes the bottom structure mining and cutting engineering and medium-deep hole drilling parameters of the original mining method, creatively uses the mining ramp and optimized medium-deep hole drilling parameters, and reduces the dilution rate and the amount of mining and cutting engineering compared with the original mining method.

[0003] In the mining process of the gently inclined end of the steeply inclined ore body of the lead-zinc mine, the segmented open-pit and subsequent filling mining method is usually used for mining. When the bottom structure mining is arranged in the mining layer along the strike, the rock drilling tunnel is generally excavated to the corresponding position of the upper layer cutting groove, and then the cutting tunnel is excavated vertically in the rock drilling tunnel. The skylight and the cutting groove are arranged between the boundary of the upper layer and the upper layer ore body in the cutting tunnel to form a cutting groove, which provides a blasting free surface for the normal mining of the subsequent rock drilling tunnel. In order to maximize the recovery of the retained ore in the upper layer, the vein tunnel is arranged at a position more than 10m away from the rock drilling tunnel, and the mining tunnel is arranged every 10m. However, when the above method is used for mining at the gently inclined end of the steeply inclined ore body, the amount of waste rock generated will increase significantly, resulting in a large amount of waste rock, causing the ore grade to drop sharply when recovering the retained ore in the upper layer, and the depletion rate will increase sharply, thereby reducing the economic benefits of room mining. Summary of the invention

[0004] The object of the present invention is to provide a method for recovering a steeply inclined ore body at a gently inclined end, so as to solve the problems raised in the above-mentioned background technology.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is:

[0006] A method for recovering a steeply inclined ore body at a gently inclined end, comprising the following steps:

[0007] S1: Excavate the mining ramp to the upper stratified ore storage position, that is, the corresponding position of the cutting groove and the cutting shaft, and determine the reasonable slope and length of the mining ramp according to the requirements of the mining design specifications, so as to determine the starting position of the mining ramp;

[0008] S2: After the construction of the mining ramp, the inclined row and normal row of medium and deep holes are constructed according to the designed different machine positions;

[0009] S3: After the construction of the inclined row of medium and deep holes is completed, the normal row of medium and deep holes will be constructed. After all the preparation for mining construction is completed, the above-layered goaf and the mining ramp are used as the compensation space to recover the inclined row of medium and deep holes in batches by using micro-difference blasting between holes. Then, the goaf formed by the inclined row of medium and deep holes is used as the compensation space to recover the normal row of medium and deep holes in batches by using micro-difference blasting between holes, and finally the mining work is completed.

[0010] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0011] The present invention mainly does not use a conventional bottom structure mining and cutting engineering and a medium-deep hole rock drilling parameter mining method when arranging bottom structure mining in the mining layer along the strike during the mining process of the gently inclined end of the steeply inclined ore body, but uses an innovative mining method using a mining ramp and optimized medium-deep hole rock drilling parameters, thereby reducing the amount of waste rock, improving the ore grade, and increasing the unit ore income, with significant economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a plan view of conventional bottom structure cutting works and layout of medium and deep holes.

[0013] Figure 2 It is a cross-sectional schematic diagram of the conventional bottom structure cutting project and the layout of medium and deep holes.

[0014] Figure 3 This is a schematic plan view of the ramp and optimized layout of medium and deep holes in the present invention.

[0015] Figure 4 This is a cross-sectional schematic diagram of the invention for selecting the ramp and optimizing the layout of the medium and deep holes.

[0016] Serial numbers and names of the attached drawings: rock drilling tunnel 1, mine exit tunnel 2, off-vein tunnel 3, cutting tunnel 4, cutting shaft 5, cutting groove 6, medium and deep hole arrangement in the cutting groove 7, medium and deep hole arrangement in the positive row 8, ore-rock boundary line 9, and mining ramp 10. DETAILED DESCRIPTION

[0017] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0018] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] Example

[0020] 1. If Figure 3 In order to recover the ore in the upper layer to the maximum extent, the mining ramp needs to be excavated to the location of the ore in the upper layer, that is, the corresponding location of the cutting groove and the cutting well. According to the requirements of the mining design specifications, the reasonable slope and length of the mining ramp are determined to determine the starting position of the mining ramp. The determination of the starting position and the position of the connection with the upper layer is crucial, and it has a decisive influence on the detailed design of the subsequent medium and deep holes, so it must be considered carefully.

[0021] 2. After the construction of the mining ramp 10, the inclined row and normal row of medium-deep holes 8 are constructed according to the designed different machine positions. The inclined row and normal row of medium-deep holes are designed in the ore body according to the ore body and rock boundaries, which changes the previous unfavorable situation of regular design of the row but high dilution caused by mixed mining of ore and rock. Figure 2 and Figure 4 By comparison, it is obvious that the new solution will not mix with the surrounding rock.

[0022] 3. After the construction of the inclined row of medium and deep holes is completed, the normal row of medium and deep holes will be constructed. After all the preparation for mining construction is completed, the above-layered goaf and the mining ramp are used as the compensation space to recover the inclined row of medium and deep holes in batches by adopting micro-difference blasting between holes. Then, the goaf formed by the inclined row of medium and deep holes is used as the compensation space to recover the normal row of medium and deep holes in batches by adopting micro-difference blasting between holes, and finally the mining work is completed.

[0023] 4. According to the implementation of the above steps, although the construction is slower than the original method Figure 2 It increases the difficulty of construction organization, but can effectively change the phenomenon of high ore dilution caused by fixed regular row mining in the original method, and increase economic benefits.

[0024] 5. The relevant parameters such as the bottom distance of the medium and deep holes and the row spacing required for the row face design need to be combined with the surrounding rock on site and the selected equipment in different mines, and are designed and implemented in accordance with relevant specifications and design manuals, and will not be described in detail in this invention;

[0025] 6. The present invention breaks the traditional design thinking, creatively uses the mining ramp and optimized medium-deep hole layout for the gently inclined end of the steeply inclined ore body, adopts a more reasonable engineering layout and ore recovery sequence, and solves the problem of excessive mixing of surrounding rock caused by the conventional bottom structure mining and cutting engineering and medium-deep hole layout mining method at the gently inclined end of the steeply inclined ore body. The purpose of low-depletion mining at the gently inclined end of the ore body is achieved, the ore grade is improved, the unit ore revenue is increased, and the economic benefits are significant.

Claims

1. A method for recovering a steeply inclined ore body at a gently inclined end, characterized in that: The following steps are involved: S1: Excavate the mining ramp to the upper stratified ore storage position, that is, the corresponding position of the cutting groove and the cutting shaft, and determine the reasonable slope and length of the mining ramp according to the requirements of the mining design specifications, so as to determine the starting position of the mining ramp; S2: After the construction of the mining ramp, the inclined row and normal row of medium and deep holes are constructed according to the designed different machine positions; S3: After the construction of the inclined row of medium and deep holes is completed, the normal row of medium and deep holes will be constructed. After all the preparation for mining construction is completed, the above-layered goaf and the mining ramp are used as the compensation space to recover the inclined row of medium and deep holes in batches by using micro-difference blasting between holes. Then, the goaf formed by the inclined row of medium and deep holes is used as the compensation space to recover the normal row of medium and deep holes in batches by using micro-difference blasting between holes, and finally the mining work is completed.