By constructing a database and using remote sensing and ultrasonic technology to generate sludge layer prediction images, the problem of the fact that the lake sludge layer changes cannot be measured in real time before silting in the existing technology is solved, and low-cost and efficient sludge layer changes prediction and sludge plan optimization are achieved. .

CN119022892AActive Publication Date: 2024-11-26CCTEG CHONGQING ENG CO LTD
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411129538.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-26
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

The prior art cannot measure the changes in the lake silt layer in real time and accurately before silting, resulting in low silt efficiency and high cost, and the density of the silt layer increases uncertainty due to factors such as weather and wind speed.

Method used

By constructing a database to store lake historical measurement information and weather characteristics, using remote sensing to obtain geographic data and set measurement points, combining ultrasonic measurement technology to obtain real-time data, and generating future silt layer prediction images by comparing them with historical weather characteristics, optimizing the silt cleaning plan.

Benefits of technology

It realizes low-cost and accurate silt layer change prediction, improves dredging efficiency, reduces the number of measurements and model processing time, and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119022892A_ABST
    Figure CN119022892A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of underwater detection, and discloses a lake sludge automatic measurement visualization model processing method and system, and the method comprises the steps: S1, obtaining the geographic data of a target lake through remote sensing, and setting n target measurement points according to the geographic data; s2, guiding the target measurement points into a measurement device, enabling the measurement device to run to the corresponding target measurement points for measurement, and obtaining measurement data; and S3, transmitting the measurement data corresponding to each target measurement point to a data analysis end, analyzing the measurement data of each target measurement point through the data analysis end, and generating a real-time layered image of the target lake. According to the invention, the prediction layered image of the target lake in the future first time period can be obtained with low cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of underwater detection technology, and in particular to a method and system for processing a visualization model for automatic measurement of lake sludge. Background Art

[0002] Silt refers to clay soil with a natural water content greater than the liquid limit and a natural porosity greater than 1.0, which is deposited in a flowing water environment and has a particle size less than 0.03 mm. When silt accumulates for a long time, it not only affects the water quality of the lake, but also has an adverse impact on the ecological environment of the lake and its surroundings, seriously damaging the ecological environment of the area. Therefore, dredging is usually required to improve the ecological environment of the lake. Before dredging, the accumulation of silt will be measured accordingly.

[0003] In the current existing technology, measurement is performed before dredging. Measuring the accumulation of silt can only obtain the measurement results at that time. Generally, from the beginning of measurement to the end of measurement, and then to the planning and design of dredging work based on the measurement, dredging work is finally carried out. In addition, when carrying out dredging work, dredging is generally carried out step by step in each sub-area. In this way, each dredging requires a long time of operation. Since the density of the silt layer is easily affected by factors such as weather, wind speed and water flow, the density of the silt layer is a changing process. This change adds new uncertainties to the dredging work, which easily causes more and longer operation time to complete the dredging. This not only reduces the dredging efficiency, but also increases the construction cost.

[0004] To solve this problem, engineers usually place fixed measuring buoys in a designated area to obtain real-time and accurate silt layer measurement data. However, the measuring radius of the measuring buoy is small, and multiple buoys need to be deployed in a lake or reservoir to achieve a comprehensive measurement effect, which increases the measurement cost. Summary of the invention

[0005] The present invention intends to provide a first solution, which is a lake sludge automatic measurement visualization model processing method, which can obtain a predicted layered image of a target lake in a first time period in the future at a low cost.

[0006] In order to achieve the above-mentioned purpose, the following technical scheme is adopted: a method for processing a visualization model of automatic measurement of lake sludge, comprising: a database is constructed in a data analysis terminal, and the database stores historical measurement information and corresponding historical weather characteristics of each lake; S1, the geographic data of the target lake is obtained by remote sensing, and n target measurement points are set according to the geographic data; S2, the n target measurement points are imported into a measurement device, the measurement device drives to the corresponding target measurement point for measurement, and the measurement data of each target measurement point is obtained; S3, the measurement data corresponding to each target measurement point is transmitted to the data analysis terminal, and the measurement data of each target measurement point is analyzed by the data analysis terminal to generate a real-time layered image of the target lake; S4, the weather characteristics of the target lake in the first time period are obtained, the weather characteristics are compared with the historical weather characteristics stored in the database, the lake with the highest similarity is selected as the reference lake, and the historical measurement information corresponding to the historical weather characteristics of the reference lake in the first time period is used as a change parameter; S5, the real-time layered image of the target lake is adjusted according to the change parameter, and the predicted layered image of the target lake in the first time period in the future is obtained.

[0007] The beneficial effect of this solution is that compared with the prior art of first measuring and then performing dredging, the difference of this embodiment is that after obtaining the measurement data through ultrasonic measurement, the weather characteristics of the target lake in a certain period of time in the future are compared with the historical weather characteristics of lakes in the same municipal area in the database to match the lake with the highest similarity. By analyzing the historical measurement information of the lake during this period, its historical measurement information is used as an analysis of the changes in the silt layer of the target lake in a certain period of time in the future. This is not only simple to calculate and low in cost, but also can accurately predict the changes in the silt layer during this time period.

[0008] Preferably, the measuring device uses ultrasonic technology to measure the lake.

[0009] Beneficial effects: Ultrasonic measurement can accurately measure the thickness of the silt layer and can adapt to different water conditions, including turbid water, and is not affected by the turbidity of the water.

[0010] Preferably, the reference lake is the target lake or other lakes in the same municipal area as the target lake.

[0011] Beneficial effects: Expand the number of reference lakes to provide more reference lakes for analysis and comparison; at the same time, limit the regional scope of reference lakes. Since the topography and climate of lakes in different regions are different, even if the weather characteristics may be relatively similar within a certain period of time, the changes in their silt layers are also affected by the terrain. If the regional scope of reference lakes is expanded, it is easy to be affected by geographical and topographical factors other than weather characteristics, and accuracy will not be achieved.

[0012] Preferably, the first time period is fourteen days.

[0013] Beneficial effects: Currently, weather forecasts within fourteen days are generally more accurate.

[0014] Preferably, the weather characteristics include wind speed and direction, precipitation, season and temperature.

[0015] Beneficial effects: The thickness of the silt layer is greatly affected by wind speed and direction, precipitation and temperature. By finding the most important influence on the thickness of the silt layer and eliminating other parameters such as humidity that have a smaller impact on the silt layer, the thickness of the silt layer can be calculated more accurately and efficiently.

[0016] Preferably, it also includes S6, the data analysis end is connected to the first model, and the dredging position and dredging amount are obtained; the dredging position and dredging amount are used as adjustment parameters, and the dredging position is used as the center point, and the first length extending outward from the center point is used as the adjustment area, the adjustment parameters and the predicted layered image are imported into the first model, the silt change situation in the adjustment area is calculated and analyzed by the first model, and the silt change situation in the adjustment area is overlaid on the corresponding area of ​​the predicted layered image to obtain the target layered image.

[0017] Beneficial effect: By taking the dredging position and dredging amount as adjustment parameters, and limiting the area within the first numerical range of the dredging position as the adjustment object, the silt layer thickness of the predicted layered image is adjusted by using the first model to obtain the target layered image, thereby eliminating the need to re-measure the changes in the silt layer in the nearby area to be dredged each time partial dredging is performed. This not only reduces multiple measurements, but also accurately predicts the changes in the silt layer, thereby improving the efficiency of dredging. Moreover, by limiting the area, the amount of model processing calculations can be reduced, the model calculation speed can be improved, and the time for the first model processing and analysis can be saved.

[0018] Preferably, the first model is a Pangu model.

[0019] Beneficial effect: It can provide stronger reasoning ability when dealing with more complex calculations of changes in silt layer thickness.

[0020] Preferably, the first length is 500 m.

[0021] Beneficial effect: By limiting the range, the amount of calculation of the model can be effectively reduced.

[0022] Preferably, the real-time layered image, the predicted layered image and the target layered image are all three-dimensional images.

[0023] Beneficial effects: The three-dimensional image can more intuitively reflect the changes in the silt layer.

[0024] The second scheme is a lake sludge automatic measurement visualization model processing system, which is used to execute the lake sludge automatic measurement visualization model processing method of the first scheme. A lake sludge automatic measurement visualization model processing system The lake sludge automatic measurement visualization model processing system includes: a target measurement point setting module, including remote sensing, which is used to obtain the geographic data of the target lake, and set n target measurement points according to the geographic data, and send the target measurement points to the measurement module; the measurement module includes a measurement device, which is used to receive the target measurement points, and measure at each target measurement point, obtain measurement data, and send the measurement data to the data analysis module; the data analysis module includes a data analysis terminal, which is used to receive the measurement data, analyze the measurement data, and generate a real-time layered image of the target lake.

[0025] Beneficial effects: Compared with the use of fixed buoys or drones for measurement, this embodiment provides a lake silt automatic measurement visualization model processing system. By using a measuring device for measurement, it is not only highly flexible, but also less likely to be affected by the open airflow of the lake than when measuring with a drone. It can accurately measure at the measurement point to improve the accuracy of the measurement results such as the distribution and thickness of the silt. At the same time, the measuring device can automatically drive to the measurement point for measurement, and the measurement efficiency is higher. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 It is a structural diagram of embodiment 1 of the present invention. DETAILED DESCRIPTION

[0027] The following embodiments of the technical solution of the present invention are described in detail in conjunction with the accompanying drawings. The following embodiments are only used to more clearly illustrate the technical solution of the present invention, and are therefore only used as examples, and cannot be used to limit the protection scope of the present invention.

[0028] Embodiment 1

[0029] like Figure 1 As shown, a lake silt automatic measurement visualization model processing method includes:

[0030] S1, obtaining geographic data of a target lake through remote sensing, and setting n target measurement points according to the geographic data.

[0031] Specifically, the geographic data of the target lake can be imported into the GIS system to more efficiently determine the measurement points. The measurement points can be determined based on the selection of measurement accuracy.

[0032] S2, import the n target measurement points into the measurement device, the measurement device drives to the corresponding target measurement point for measurement, and obtains the measurement data of each target measurement point. The measurement accuracy can be: 1m, 2m, 3m, 4m, 5m, 6m, 7m, 8m, 9m, 10m, 11m, 12m, 13m, 14m, 15m, etc., with 1m as the tolerance, for selection. If the measurement point uses a measurement accuracy of 1m, that is, according to the shape of the lake, with 1m as the distance between two measurement points, the coastline of the lake is covered, and according to the size of the lake, every 1m from the coastline of the lake to the center of the lake is used as a measurement point.

[0033] S3, transmitting the measurement data corresponding to each target measurement point to the data analysis terminal, analyzing the measurement data of each target measurement point through the data analysis terminal, and generating a real-time layered image of the target lake.

[0034] Specifically, in this embodiment, the measuring device is an unmanned measuring device. The measuring device automatically moves to the measuring point according to the selected measuring point. The measuring device measures the lake by using ultrasound to obtain measurement data. In this embodiment, the measurement accuracy is based on 5m as the range between the two target measurement points. After obtaining the measurement data of each target measurement point, the measurement data includes the depth of the clear water layer and the silt layer. And the measurement data is summarized to form a real-time layered image of the target lake. In the real-time layered image, the clear water layer, the silt layer and the bottom solid layer are included from high to low.

[0035] From the natural sedimentation process of solid matter, it is known that the sediment at the bottom will be stratified and clearly divided into two layers. A silt layer appears above the bottom solid layer. In other words, the entire lake can be divided into: clear water layer, silt layer and bottom solid layer. Since the density of the silt layer is a changing process, the density change process is closely related to the weather and climate. Through the difference in the propagation speed of ultrasound in the silt layer and seawater, the thickness of the clear water layer and the silt layer at the measurement point can be measured.

[0036] A database is built in the data analysis end, which stores the historical measurement information of each lake and the corresponding historical weather characteristics. Weather characteristics include wind speed and direction, precipitation, season and temperature.

[0037] S4, obtaining the weather characteristics of the target lake in the first time period, comparing the weather characteristics with the historical weather characteristics stored in the database, selecting the lake with the highest similarity as the reference lake, and using the historical measurement information corresponding to the historical weather characteristics of the reference lake in the first time period as the change parameter.

[0038] Specifically, since the thickness of the silt layer is a changing process and is greatly affected by the weather, predicting the changes in the silt layer through the weather requires considering the impact of future wind speed, direction, precipitation, and temperature on the silt layer. If accurate changes in the thickness of the silt layer are required, a very large amount of data is required to support it, which is too costly.

[0039] In this embodiment, a database is constructed, which stores historical measurement information and corresponding historical weather characteristics of the target lake, as well as historical measurement information and corresponding weather conditions of other lakes located in the municipal area together with the target lake. When it is necessary to predict the change of the silt layer of the target lake in a certain period of time in the future, the weather characteristics of the target lake in the first time period in the future are obtained. In this embodiment, the first time period is fourteen days. The weather characteristics of the target lake in the first time period in the future are compared with the historical weather characteristics stored in the database.

[0040] The weather characteristics are compared with the historical weather characteristics stored in the database, and the comparison content specifically includes whether the seasons to which the two belong are consistent. If one belongs to summer and the other belongs to winter, the comparison is unsuccessful. Because there are obvious differences between different silt layers, the changes in the density of their silt layers are difficult to use as a reference standard. Secondly, if the wind direction is consistent, the comparison is successful. In addition, the minimum and maximum wind speeds of the two must not differ by 3 wind speed levels. The total precipitation of the two in the first time period differs by less than 5 mm. The average temperature of the two in the first time period differs by less than 3°C. After the above conditions are met, the smaller the difference value, the higher the similarity. The lake with the highest similarity is used as the reference lake.

[0041] The historical measurement information corresponding to the historical weather characteristics of the reference lake in the first time period is obtained from the database as a change parameter. Specifically, the first time period in which the reference lake has the highest similarity with the target lake in the first time period is determined. The beginning and last historical measurement information of the reference lake in the first time period is obtained. If the first time period is fourteen days, the historical measurement information of the reference lake on the first day and the fourteenth day in the first time period is obtained. From the first day to the fourteenth day of the reference lake, according to its historical measurement information, the average change thickness of its silt layer is used as the change parameter.

[0042] For example, when it is necessary to predict the thickness of the silt layer of Reservoir A in Region A within the next fourteen days, the weather conditions of Reservoir A within the next fourteen days are obtained. The precipitation conditions of the lakes in Region A within fourteen days are searched in the database, and when the precipitation conditions of the lakes in Region A within fourteen days are most consistent with the weather conditions of Reservoir A within the next fourteen days, the lake that is consistent with the weather conditions of Reservoir A within the next fourteen days is set as Lake B, and the average thickness change of the silt layer of Lake B within fourteen days is calculated, and the thickness change of the silt layer of Lake B within fourteen days is used as the thickness change of the silt layer of Reservoir A within the next fourteen days, thereby obtaining the thickness of the silt layer of Reservoir A in Region A within the next fourteen days. Region A refers to the city-level area.

[0043] Since the thickness of the silt layer in a lake is predicted by the weather conditions of the lake, the calculation is large, the calculation is complex, the calculation time is long and the cost is high in order to accurately measure the thickness of the silt layer. By building a database, other lakes in the same area with a high degree of consistency with the weather conditions of the lake to be predicted in a certain period of time in the future are found. The changes in the thickness of the silt layer of other lakes in the same area in the corresponding period are used to analyze the changes in the thickness of the silt layer of the lake to be predicted in the future. In this way, not only the calculation amount is small and simple, but also the calculation time is short and the cost is low, and the thickness of the silt layer can be accurately measured.

[0044] S5, adjusting the real-time layered image of the target lake according to the change parameters, and obtaining a predicted layered image of the target lake within a first time period in the future.

[0045] Specifically, the real-time layered image is to process the measurement data of each measurement point to obtain a 3D model of the lake, in which the bottom solid layer of the lake is the lowest point and the water level of the lake is the highest point. The measurement data of each measurement point in the lake are connected into lines, and the silt layer is connected with the data of the clear water layer and the bottom solid layer into lines respectively. After corresponding processing, a 3D model of the entire lake is formed, thereby forming a visual processing image of the lake. The thickness of the silt layer of the target lake is modified accordingly by changing the parameters, so as to obtain the predicted layered image of the target lake in the first time period in the future.

[0046] It should be noted that lakes include lakes and reservoirs. The water level changes of the target lake can be obtained through remote sensing satellites, so as to analyze the water level changes of the target lake in the future, and analyze the thickness of the clear water layer in combination with the water level changes of the target lake. In this embodiment, the measuring device can be a survey ship. The measurement data includes more of the position of the silt layer, the thickness corresponding to different positions, the height of the silt layer from the water surface, and the depth of the lake.

[0047] The beneficial effects of this embodiment

[0048] Compared with the prior art, either measurement is performed again to adjust the original real-time layered image, or a fixed measuring buoy is set on the lake. The difference of this embodiment is that after obtaining the real-time layered image through ultrasonic measurement, the weather characteristics of the target lake in a certain period of time in the future are compared with the historical weather characteristics of lakes in the same municipal area in the database, and the lake with the highest similarity is matched. By analyzing the historical measurement information of the reference lake during this period, its historical measurement information is used as the analysis of the silt layer changes of the target lake in a certain period of time in the future, so as to obtain the predicted layered image of the target lake in the first time period in the future, so that there is no need to spend money to fix the measuring buoy on the lake.

[0049] Secondly, compared with the use of various algorithms and models to calculate and predict the predicted layered image of the target lake in a certain period of time in the future, not only is the calculation complicated, but the accuracy is not necessarily guaranteed. In this embodiment, the weather characteristics are compared with the historical weather characteristics stored in the database, and the comparison content specifically includes whether the seasons to which the two belong are consistent. If one belongs to summer and the other belongs to winter, the comparison is unsuccessful. Because there are obvious differences between different silt layers, it is difficult to use the change in the density of the silt layer as a reference standard. Secondly, if the wind direction is consistent, the comparison is successful. In addition, the minimum wind speed and the maximum wind speed of the two shall not differ by 3 wind speed levels. The total precipitation of the two in the first time period differs by less than 5 mm. The average temperature of the two in the first time period differs by less than 3 ° C. After meeting the above conditions, the smaller the difference value, the higher the similarity. The lake with the highest similarity is used as the reference lake. By comparing to obtain the predicted layered image in a certain period of time in the future, not only is the calculation simple, but also the change of the silt layer in this time period can be accurately predicted.

[0050] Embodiment 2

[0051] Different from the first embodiment, a method for processing a visualization model for automatic measurement of lake silt also includes S6, where the data analysis end is connected to the first model, and the location and amount of silt removal are obtained. The location and amount of silt removal can be selected by the worker, and the location and amount of silt removal are used as adjustment parameters, and the location of silt removal is used as the center point, and a first length extending outward from the center point is used as the adjustment area. The adjustment parameters and the predicted layered image are imported into the first model, and the silt changes in the adjustment area are calculated and analyzed by the first model, and the silt changes in the adjustment area are covered to the corresponding area of ​​the predicted layered image to obtain the target layered image.

[0052] Specifically, when the staff is dredging an area in a lake, the flowing water drives the silt near the area into the area, causing the thickness of the silt nearby to decrease. At the same time, since the dredging work has been carried out for a period of time, the thickness of the silt layer in other areas is also changing due to weather reasons and the large-scale dredging of nearby silt. Other silt layers will flow to the dredged areas, resulting in the thickness of the silt layer constantly changing. This will make the silt layer thickness measured previously inaccurate, and at the same time, judging the thickness of other silt layers according to the method of the aforementioned embodiment one is also inaccurate.

[0053] In order to improve the efficiency of dredging, when dredging other areas of the lake, it is necessary to measure the thickness of the silt layer in other areas several times according to the progress of the dredging work to ensure the smooth and efficient progress of the dredging work. However, the multiple measurements of the relevant positions and thickness of the silt layer require the arrangement of corresponding staff to carry out the measurements, which not only increases the cost, but also requires the measurement before dredging work in other areas can be carried out, which reduces the work efficiency.

[0054] After dredging a certain area, the staff will import the dredging location and dredging amount into the data analysis end. The data analysis end is connected to the Pangu model, and the dredging location and dredging amount are input into the Pangu model as adjustment parameters, and the area with the dredging location as the center point and a radius of 500 meters is used as the adjustment area. Through the analysis of the Pangu model, the thickness of the silt layer and the distribution of the silt layer in the adjustment area are calculated, and the adjustment area is covered on the corresponding position of the original predicted layered image to obtain the target layered image. The corresponding position refers to the area with the dredging location as the center point and a radius of 500 meters. In this embodiment, the predicted layered image refers to the image at the beginning of the construction phase, and the real-time layered image of Example 1 refers to the image during the measurement phase.

[0055] Using the historical measurement information and corresponding historical weather characteristics of each lake stored in the database, as well as how each dredging volume affects the silt changes in the nearby area, the staff has trained the corresponding silt layer analysis model in the existing Pangu model. It only needs to import the dredging location, dredging volume and adjustment area into the Pangu model for analysis. Dredging refers to the removal of silt. The dredging volume refers to the volume of silt and bottom mud removed.

[0056] The beneficial effects of this embodiment

[0057] The current existing technology is to dredge a certain area of ​​the lake, then measure the silt thickness in the surrounding area again to obtain the accurate silt thickness, and then carry out the dredging work. This takes a long time for the overall dredging work.

[0058] The present embodiment uses the dredging location and dredging amount as adjustment parameters, and limits the area within 500 meters of the dredging location as the adjustment object. By using the Pangu large model to analyze and adjust the predicted layered image, a target layered image is obtained. This eliminates the need to re-measure the changes in the silt layer in the nearby area to be dredged each time partial dredging is performed. This not only reduces multiple measurements, but also can accurately predict the changes in the silt layer, thereby improving the efficiency of dredging. In addition, by limiting the area, the amount of model processing calculations can be reduced, the model calculation speed can be increased, and the time for Pangu large model processing and analysis can be saved.

[0059] The second embodiment of the present invention provides a method for automatically measuring and visualizing a model for processing lake sludge. For the sake of brief description, for matters not mentioned in the embodiment part, reference may be made to the corresponding contents in the aforementioned first embodiment.

[0060] Embodiment 3

[0061] At present, in order to ensure the accuracy of the measurement, most of the silt measurements are made by fixed buoys in the lakes. However, this method can only measure a single area and has low flexibility. There are also methods of measuring silt by drones, but because the lakes are relatively open and the wind and waves are relatively strong, drones are prone to shaking, causing the measuring instruments they are equipped with to fail to accurately obtain relevant measurement data. At the same time, affected by the open airflow of the lake, it is difficult for drones to align with the measurement points when they fly to the measurement points for measurement, resulting in large errors. After multiple measurements, the measured data will be summarized and analyzed, and the errors will be even greater. Therefore, the measurement results of the distribution and thickness of the silt will be inaccurate.

[0062] This embodiment provides a lake silt automatic measurement visualization model processing system, which specifically includes:

[0063] A target measurement point module is set, including remote sensing, for acquiring geographic data of a target lake, and n target measurement points are set according to the geographic data, and the target measurement points are sent to a measurement module.

[0064] Specifically, the geographic data of the target lake is obtained through remote sensing, and the geographic data includes the shape and size of the lake. In order to conveniently and efficiently set the target measurement point, the geographic data can be imported into the GIS system, and the measurement accuracy can be set using the GIS system to set the target measurement point.

[0065] The measurement module includes a measurement device, which is used to receive target measurement points, perform measurement at each target measurement point, obtain measurement data, and send the measurement data to the data analysis module.

[0066] Specifically, the measuring device is equipped with radar, GPS, ultrasonic measuring instrument and wireless transceiver components. The measuring device receives relevant information of the target measuring point through the wireless transceiver component, and then uses GPS and radar to drive to the target measuring point by itself. The measuring device measures the lake through ultrasonic technology, obtains measurement data through the ultrasonic measuring instrument, and then sends the measurement data to the data analysis end through the wireless transceiver component.

[0067] The data analysis module includes a data analysis terminal for receiving the measurement data, analyzing the measurement data, and generating a real-time layered image of the target lake.

[0068] Specifically, the data analysis end can generally be located on a computer processor in the work area of ​​the staff along the lake shore, or it can be a cloud platform. At the same time, the data analysis end on the computer processor in the work area along the lake shore can generate a real-time layered image of the target lake. If it is to obtain a predicted layered image or a target layered image of the target lake in the first time period in the future, the cloud platform can perform corresponding processing and analysis due to the limited processing capacity of the computer processing device in the temporary work area set up along the lake shore.

[0069] Beneficial effects of this embodiment:

[0070] Compared with the use of fixed buoys or drones for measurement, this embodiment provides a lake silt automatic measurement visualization model processing system. By using a measuring device for measurement, it is not only highly flexible, but also less likely to be affected by the open airflow of the lake than when measuring with a drone. It can accurately measure at the measurement point to improve the accuracy of the measurement results such as the distribution and thickness of the silt. At the same time, the measuring device can automatically drive to the measurement point for measurement, which has higher measurement efficiency.

[0071] The third embodiment of the present invention provides a lake sludge automatic measurement visualization model processing system. For the sake of brief description, for matters not mentioned in the embodiment part, please refer to the corresponding content in the aforementioned first embodiment.

[0072] In this specification, a lot of specific details are described. However, it is understood that embodiments of the present invention can be put into practice without these specific details. In some examples, known methods, systems and techniques are not shown in detail so as not to obscure the understanding of this specification. In the description of this specification, the description of reference terms "one embodiment", "some embodiments", "example", "specific example" or "some examples" etc. means that the specific features, methods, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of this specification.

[0073] In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, systems, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art can combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples without contradiction.

[0074] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, several modifications and improvements can be made without departing from the technical solution of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

[0075] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. These modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.

Claims

1. A visual model processing method for automatic measurement of lake silt, It is characterized in that include: A database is built in the data analysis end, which stores the historical measurement information of each lake and the corresponding historical weather characteristics; S1, obtaining geographic data of a target lake through remote sensing, and setting n target measurement points according to the geographic data; S2, importing the n target measurement points into a measurement device, driving the measurement device to the corresponding target measurement points for measurement, and acquiring measurement data of each target measurement point; S3, transmitting the measurement data corresponding to each target measurement point to the data analysis terminal, analyzing the measurement data of each target measurement point through the data analysis terminal, and generating a real-time layered image of the target lake; S4, obtaining weather characteristics of the target lake in a first time period, comparing the weather characteristics with historical weather characteristics stored in a database, selecting the lake with the highest similarity as a reference lake, and using historical measurement information corresponding to the historical weather characteristics of the reference lake in the first time period as a change parameter; S5, adjusting the real-time layered image of the target lake according to the change parameters, and obtaining a predicted layered image of the target lake within a first time period in the future.

2. A visual measurement processing method for hydrological detection according to claim 1, It is characterized in that The measuring device uses ultrasonic technology to measure the lake.

3. A visual measurement processing method for hydrological detection according to claim 1, It is characterized in that The reference lake is the target lake or other lakes in the same municipal area as the target lake.

4. A visual measurement processing method for hydrological detection according to claim 1, It is characterized in that The first time period is fourteen days.

5. A visual measurement processing method for hydrological detection according to claim 1, It is characterized in that The weather characteristics include wind speed and direction, precipitation, season and temperature.

6. A visual measurement processing method for hydrological detection according to claim 1, It is characterized in that It also includes S6, the data analysis end is connected to the first model, and the dredging position and dredging amount are obtained; the dredging position and dredging amount are used as adjustment parameters, and the dredging position is used as the center point, and a first length is extended outward from the center point as the adjustment area, and the adjustment parameters and the predicted layered image are imported into the first model, and the silt change situation in the adjustment area is calculated and analyzed by the first model, and the silt change situation in the adjustment area is covered to the corresponding area of ​​the predicted layered image to obtain the target layered image.

7. A visual measurement processing method for hydrological detection according to claim 6, It is characterized in that The first model is the Pangu model.

8. A visual measurement processing method for hydrological detection according to claim 6, It is characterized in that The first length is 500m.

9. A visual measurement processing method for hydrological detection according to claim 6, It is characterized in that The real-time layered image, the predicted layered image and the target layered image are all three-dimensional images.

10. A lake silt automatic measurement visualization model processing system, It is characterized in that A visual measurement processing method for hydrological detection implemented in any one of claims 1-9; The lake silt automatic measurement visualization model processing system comprises: Setting a target measurement point module, including remote sensing, for obtaining geographic data of a target lake, and setting n target measurement points according to the geographic data, and sending the target measurement points to a measurement module; The measurement module includes a measurement device for receiving target measurement points, performing measurement at each target measurement point, acquiring measurement data, and sending the measurement data to the data analysis module; The data analysis module includes a data analysis terminal for receiving the measurement data, analyzing the measurement data, and generating a real-time layered image of the target lake.

Citation Information

Patent Citations

  • Lake water level forecasting method based on multi-factor similarity analysis

    CN113762618A

  • Lake sediment deposition amount monitoring method and device, electronic equipment and storage medium

    CN114972483A

  • AU2020103889A4