Large cantilever bent cap lower chord reverse supporting bracket system and construction method thereof
Through the large cantilever cover beam reverse support bracket system combined with the Beret beam, the problem of insufficient clearance under the bridge covering beam construction is solved, and rapid and economical construction is achieved, ensuring that traffic is not interrupted and traffic capacity is improved. .
Patent Information
- Application Number
- CN202411388986.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-08
- Publication Date
- 2024-11-29
AI Technical Summary
The construction of traditional overpass bridge cover beams occupies a large site, and the under-bridge space is insufficient during urban road occupation, which cannot meet the principle of "borrow one and return one" road occupation, affecting traffic guidance and increasing construction costs and construction periods.
The reverse support bracket system of the lower chord of the large cantilever cover beam is adopted, combined with the large cantilever and Bere beam, through embedded flange, steel pipe column, embossing column, sand box, distribution beam, reinforced Bere beam, load-bearing beam and keel The bottom mold assembly forms a stable structure and achieves rapid and economical cast-in-place concrete construction.
It solves the problems of small construction area and insufficient clearance under the bridge, ensures uninterrupted traffic, simplifies the construction of the bracket foundation, improves the clearance under the cantilever bracket, improves the traffic capacity, and supports the construction needs of narrow sites.
Smart Images

Figure CN119041304A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a large cantilever cap beam lower chord reverse support bracket system and a construction method thereof. Background Art
[0002] The construction of traditional viaduct cap beams usually adopts the form of full-bridge scaffolding. After the foundation is treated, a disc frame or steel pipe scaffolding is used to erect it, and the support system is composed of vertical and horizontal vertical poles, horizontal poles, diagonal rods and other rods. This type of construction plan occupies a large area and has high requirements for the bearing capacity of the foundation. In addition, due to the limitations of the construction site and insufficient clearance under the bridge, the elevated bridges in the city that occupy the road often do not have the site to erect full-bridge scaffolding, and cannot meet the "borrow one and return one" road occupation construction principle, which seriously affects traffic guidance and increases the construction cost and construction period of the guide road. Under the condition of limited site, the construction of large cantilever cap beams usually adopts the bracket method, which is divided into ground-standing brackets and rod-through-support brackets. Specifically, for the ground-type bracket structure, although its structure is relatively simple and easy to construct, and the bracket height can be adjusted with the pier height, when the pier is high, the bracket volume is huge, requiring huge investment and time-consuming and labor-intensive to install. The lower part of the cantilever end section needs to be provided with a diagonal brace. When the clearance under the bridge is insufficient and there is a need for traffic, it will affect traffic; for the through-rod support bracket, it is achieved by burying a reserved channel in the pier in advance when pouring the pier concrete, and inserting a steel rod in the channel when the bracket is erected, and the steel rod transfers the construction load to the pier. The advantage of the through-steel rod method is that the construction load is ultimately borne by the pier, and there is no problem of bracket sinking. Piers of any cross-section can be used, which is conducive to turnover. It is suitable for high pier construction and is not affected by changes in the pier height and the increase in bracket volume. The bracket form is simple and easy to erect, but its disadvantages are mainly manifested in: the reserved channel needs to be repaired after the construction is completed, which affects the appearance quality of the pier, the shear resistance of the bracket and the pier itself at the fulcrum is high, which causes damage to the pier, and it is not suitable for single-column cap beams. The present invention is proposed based on the above research background, and aims to provide a large cantilever cap beam lower chord reverse support bracket system and a construction method thereof to meet construction needs. Summary of the invention
[0003] In view of the above-mentioned deficiencies in the construction process of the lower chord of the large cantilever cap beam in the prior art, the purpose of the present invention is to provide a large cantilever cap beam lower chord reverse support bracket system and a construction method thereof. The bracket system of the present invention adopts a combination of large cantilever and Bailey beam lower chord reverse support, has reasonable force, is safe and reliable, can solve the problems of small footprint and insufficient clearance under the bridge during the construction of the large cantilever cap beam, and can quickly and economically realize the cast-in-place concrete construction of the cantilever cap beam on the bracket system.
[0004] In order to achieve the above object, the present invention adopts the following technical solutions:
[0005] A reverse support bracket system for the lower chord of a large cantilever cap beam, the system comprises a cap, a steel pipe column, a holding column, a sand box, a distribution beam, a reinforced Bailey beam, a load-bearing beam, a Bailey beam reinforcement assembly and a keel bottom mold assembly, wherein at least four steel pipe columns are symmetrically installed on the embedded flange of the cap in pairs through reserved bolts; the holding column comprises a transverse channel steel and an oblique channel steel, and the two steel pipe columns in the longitudinal bridge direction are connected together by the transverse channel steel and the oblique channel steel between the two steel pipe columns in the longitudinal bridge direction; the The sand box is installed on the top of each steel pipe column, and the distribution beam is fixedly installed on the top surface of the sand box; the reinforced Bailey beam includes several groups of Bailey beams and reinforced chords, and the reinforced chords are installed on the upper and lower parts of the Bailey beams by bolts, and each group of Bailey beams is connected by a support frame; the reinforced Bailey beam is installed on the distribution beam; the load-bearing beam is fixedly installed on the lower chord and web at the lower part of the Bailey beam by a U-shaped card; the Bailey beam reinforcement assembly includes Bailey beam transverse reinforcement and Bailey beam vertical reinforcement, and the Bailey beam transverse reinforcement includes a limiter, which is welded on the distribution beam and arranged on the left and right sides of the Bailey beam. Each distribution beam is provided with 4 limiters, and a transverse connection system is arranged between each group of Bailey beams. The connection system adopts channel steel as a stable structure formed by welding cross bars and diagonal bars. The two ends of the cross bar are welded to the clamps bolted to each chord to connect the Bailey beam into one, so as to limit the left and right swing of the Bailey beam in a large span and long cantilever state; the Bailey beam vertical reinforcement includes setting Strengthen the vertical pole, and fix the strengthening vertical pole in the middle of the upper and lower chords of the Bailey beam; the keel bottom mold assembly includes a main keel and a secondary keel of the bottom mold, and the main keel of the bottom mold includes a tripod support arranged at the lower part of the cantilever end of the cap beam; the secondary keel adopts square wood arranged in a transverse direction, which is hoisted by a crane and installed symmetrically from the middle to both ends; the secondary keel is laid with multi-layer boards arranged symmetrically from the middle to both sides, and the horizontal and vertical joints are embedded with waterproof sponge strips, and the multi-layer boards and the square wood are fixedly connected with nails.
[0006] A construction method for a large cantilever cap beam lower chord reverse support bracket system, the construction method comprising the following steps:
[0007] 1) Construction preparation and measurement and layout: including the construction of the cap and measurement and layout; during the construction of the cap, a flange is embedded, and a U-shaped anchor steel bar is set at the bottom of the flange, and bolts are reserved on each embedded flange; when the flange is installed, the installation flatness is controlled to be ≤2mm, and the reserved bolts are protected with tape to prevent concrete pollution; before the measurement and layout construction, the position of the steel pipe column is determined on the cap and marked, and the design elevation of the beam bottom formwork measured on the existing cap is used, and then the height of the steel pipe column is calculated according to the erection height of the primary and secondary keels, Bailey beams, and sand boxes;
[0008] 2) Installation of steel pipe columns and holding columns: including steel pipe column assembly and holding column installation. Among them, 4 steel pipe columns are set on the cap according to the design requirements. The steel pipe columns are positioned before construction and installed according to the preset spacing in the horizontal and along the bridge direction. After the steel pipe columns are in place, they are connected with the embedded flanges with reserved bolts. During installation, pay attention to adjusting the verticality of the steel pipe. When the bottom of the pipe is uneven, the verticality of the steel pipe is controlled by reserved bolts and wedge-shaped steel plates. Finally, tighten the reserved bolts to fix the steel pipe columns. The holding columns are in the form of channel steel. After the steel pipe columns are installed, channel steel is used to set horizontal and oblique connections between the steel pipe columns in the longitudinal direction of the bridge to ensure the stability of the steel pipe columns. The steel pipe columns and the pier columns are tied into a whole by channel steel. The vertical spacing is ≤10m.
[0009] 3) Installation of sand box and distribution beam: including installation of sand box and distribution beam, in which the sand box is installed on the top of the steel pipe column, and the height of the sand box can be adjusted to 40-50cm; the sand box is placed in the center during installation, and the sand box and the steel pipe column are connected as a whole with bolts after positioning. Each steel pipe column is equipped with a sand box, and the top elevation of the sand box = the top elevation of the pier column - the thickness of the template - the thickness of the secondary keel - the thickness of the main keel - the thickness of the Bailey beam - the thickness of the distribution beam; the distribution beam adopts double-jointed 45b I-beams, which are welded into one on the ground, and then placed on the sand box by a car crane in cooperation with manual labor, and fixedly connected with the top surface of the sand box by spot welding;
[0010] 4) Installation of reinforced Bailey beam: The main beam adopts reinforced Bailey beam, which is first assembled as a whole on the ground. After the Bailey beam is assembled, reinforced chords are set at the upper and lower parts, connected to the Bailey beam by bolts. A group of Bailey beams are assembled each time, and the Bailey beams are connected with support frames. When all Bailey beams are assembled, they are installed on the distribution beam by a car crane. Symmetrical construction is adopted during installation to ensure the stability of the entire structural system. In order to ensure that the load-bearing beam can be smoothly inserted, the position of the Bailey beam is fine-tuned to align it, and the crossbeam pad on the lower chord is removed before the Bailey beam is installed;
[0011] 5) Installation of load-bearing beam: The load-bearing beam is made of I-beam, which is horizontally arranged on the top surface of the lower chord close to the vertical poles of each node. It is hoisted to one side of the main beam by a crane. The load-bearing beam is passed through the gap between the lower chord and the web of the Bailey beam by manual labor and automobile crane, and is connected and fixed to the Bailey beam with a U-shaped clamp;
[0012] 6) Bailey beam reinforcement, including transverse reinforcement of Bailey beam and vertical reinforcement of Bailey beam. In transverse reinforcement of Bailey beam, the limiter is processed by channel steel, welded on the distribution beam, and set on the left and right sides of the Bailey beam. Four limiters are set on each distribution beam. A transverse connection system is set between each group of Bailey beams. The connection system uses channel steel as a cross bar and a diagonal bar to form a stable structure. The two ends of the cross bar are welded to the clamping plate bolted to each chord to connect the Bailey beam into one body, so as to limit the left and right swing of the Bailey beam in the state of large span and long cantilever. In vertical reinforcement of Bailey beam, a strengthening pole is set at the fulcrum position to increase the shear resistance of the Bailey beam. The strengthening pole is made of channel steel and installed between the upper and lower chords of the Bailey beam. The horizontal direction is connected as a whole by steel bars to ensure the overall stability of the strengthening pole;
[0013] 7) Install the main keel and secondary keel of the bottom formwork: including the installation of the main keel, secondary keel and bottom formwork. The main keel is supported by a tripod, and a tripod support is set at the lower part of the cantilever end of the cap beam. The tripod is made of channel steel, and a vertical rib is set in the middle. To facilitate the operation of construction personnel, a working platform is set on the outside of the cap beam structure, and the tripod support is connected horizontally with steel pipe fasteners; the secondary keel is made of square wood arranged in the horizontal direction of the bridge, which is hoisted by a crane and installed symmetrically from the middle to both ends; multi-layer boards arranged symmetrically from the middle to both sides are laid on the secondary keel, and the horizontal and vertical joints are embedded with waterproof sponge strips to ensure that the joints are tight. The multi-layer boards are fixed and connected to the square wood with nails. The elevation of the multi-layer boards is adjusted by hanging lines and re-measured to ensure the accuracy of the template elevation;
[0014] 8) After the pouring and tensioning of the cap beam concrete is completed, remove the sand box, dismantle the main keel, secondary keel, Bailey beam and steel pipe column of the bottom formwork to complete the construction.
[0015] The large cantilever cap beam lower chord reverse support bracket system and the construction method thereof of the present invention have the following beneficial effects:
[0016] The present invention fully considers the difficulties of small clearance size under the main line bridge, multiple roads crossed, and narrow construction site in actual construction projects. After multiple process comparisons and repeated scheme demonstrations, a reverse support formwork system and construction method for the lower chord of a large cantilever cap beam in a confined space are designed, which solves the problem that conventional full-bridge supports cannot achieve the goal of not interrupting traffic; the bridge's own pedestal is used as the support foundation, which simplifies the process and solves the support foundation treatment and foundation construction; the steel pipe column is assembled in place on the ground at one time, and after the automobile crane is hoisted into place, it is connected to the flange pre-buried in the pedestal foundation, and channel steel is used to set column holding measures to hold the steel pipe The columns and piers are tied together to form a stable structure, which ensures the overall stability of the supporting structure. Reinforced Bailey beams are used as the main beams, and transverse connections and vertical reinforcing poles are set to strengthen the Bailey beams, so as to improve the strength, rigidity and stability of the Bailey beams and meet the construction requirements of large cantilever cap beams. The main keel is arranged on the top surface of the lower chord of the Bailey beam, which effectively increases the clearance height under the cantilever bracket and improves the vehicle traffic capacity under the cantilever bracket. The main Bailey beam is divided into sections by bolts and can be assembled and disassembled on site, which solves the problems of narrow site, limited assembly and transportation. Sand boxes are set on the steel pipe columns to facilitate the removal of the bottom formwork and bracket at a later stage.
[0017] The innovative technical points of the large cantilever cap beam lower chord reverse support bracket system of the present invention are mainly:
[0018] 1. The large cantilever cap beam lower chord reverse support formwork system is adopted to solve the problem that the conventional full-floor support cannot achieve the function of not interrupting traffic.
[0019] 2. The main keel is arranged on the top surface of the lower chord of the Bailey beam, which effectively increases the clearance height under the cantilever bracket and improves the vehicle traffic capacity under the cantilever bracket.
[0020] 3. The Bailey beam is reinforced by setting up transverse connections and vertical reinforcing poles to improve the strength, rigidity and stability of the Bailey beam and meet the requirements of large cantilever cap beam construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Attached Figure 1 It is a structural schematic diagram of a reverse support bracket system for the lower chord of a large cantilever cap beam of the present invention.
[0022] Attached Figure 2 The present invention is a flow chart of a construction method of a large cantilever cap beam lower chord reverse support bracket system.
[0023] Attached Figure 3 It is a structural design drawing of the steel pipe column of the present invention, wherein (a) is a vertical view of the steel pipe column, (b) is a cross-sectional view of the steel pipe column, and (c) is a plan view of the steel pipe column.
[0024] Attached Figure 4The present invention provides a design drawing of a steel pipe column, wherein (a) is a vertical view of the column, (b) is a cross-sectional view of the column, and (c) is a plan view of the column.
[0025] Attached Figure 5 The following are the design drawings for Bailey beam installation according to the present invention, wherein (a) is the elevation view of Bailey beam installation, (b) is the cross-sectional view of Bailey beam installation, and (c) is the plan view of Bailey beam installation.
[0026] Attached Figure 6 It is the design drawing of the installation of the load-bearing beam of the present invention, wherein (a) is the elevation drawing of the installation of the load-bearing beam, (b) is the cross-sectional drawing of the installation of the load-bearing beam, and (c) is the plan drawing of the installation of the load-bearing beam.
[0027] Attached Figure 7 The following are the design drawings of the transverse reinforcement of the Bailey beam of the present invention, wherein (a) is the elevation view of the transverse connection of the Bailey beam; (b) is the schematic diagram of the 1-1 section; and (c) is the schematic diagram of the 2-2 section.
[0028] Attached Figure 8 It is a design drawing of the vertical reinforcement of the Bailey beam of the present invention, wherein (a) is a vertical elevation view of the vertical reinforcement pole, and (b) is a cross-sectional view of the vertical reinforcement pole.
[0029] Attached Fig. 9 This is the installation design drawing of the main keel and secondary keel of the present invention. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-9 A large cantilever cap beam lower chord reverse support bracket system and a construction method thereof are described in detail in the present invention.
[0031] A reverse support bracket system for the lower chord of a large cantilever cap beam, the system comprises a cap, a steel pipe column, a holding column, a sand box, a distribution beam, a reinforced Bailey beam, a load-bearing beam, a Bailey beam reinforcement assembly and a keel bottom mold assembly, wherein at least four steel pipe columns are symmetrically installed on the embedded flange of the cap in pairs through reserved bolts; the holding column comprises a transverse channel steel and an oblique channel steel, and the two steel pipe columns in the longitudinal bridge direction are connected together by the transverse channel steel and the oblique channel steel between the two steel pipe columns in the longitudinal bridge direction; the The sand box is installed on the top of each steel pipe column, and the distribution beam is fixedly installed on the top surface of the sand box; the reinforced Bailey beam includes several groups of Bailey beams and reinforced chords, and the reinforced chords are installed on the upper and lower parts of the Bailey beams by bolts, and each group of Bailey beams is connected by a support frame; the reinforced Bailey beam is installed on the distribution beam; the load-bearing beam is fixedly installed on the lower chord and web at the lower part of the Bailey beam by a U-shaped card; the Bailey beam reinforcement assembly includes Bailey beam transverse reinforcement and Bailey beam vertical reinforcement, and the Bailey beam transverse reinforcement includes a limiter, which is welded on the distribution beam and arranged on the left and right sides of the Bailey beam. Each distribution beam is provided with 4 limiters, and a transverse connection system is arranged between each group of Bailey beams. The connection system adopts channel steel as a stable structure formed by welding cross bars and diagonal bars. The two ends of the cross bar are welded to the clamps bolted to each chord to connect the Bailey beam into one, so as to limit the left and right swing of the Bailey beam in a large span and long cantilever state; the Bailey beam vertical reinforcement includes setting Strengthen the vertical pole, and fix the strengthening vertical pole in the middle of the upper and lower chords of the Bailey beam; the keel bottom mold assembly includes a main keel and a secondary keel of the bottom mold, and the main keel of the bottom mold includes a tripod support arranged at the lower part of the cantilever end of the cap beam; the secondary keel adopts square wood arranged in a transverse direction, which is hoisted by a crane and installed symmetrically from the middle to both ends; the secondary keel is laid with multi-layer boards arranged symmetrically from the middle to both sides, and the horizontal and vertical joints are embedded with waterproof sponge strips, and the multi-layer boards and the square wood are fixedly connected with nails.
[0032] The construction method of the above-mentioned large cantilever cap beam lower chord reverse support bracket system comprises the following steps:
[0033] 1) Construction preparation and measurement and layout: including the construction of the cap and measurement and layout; during the construction of the cap, a flange is embedded, and a U-shaped anchor steel bar is set at the bottom of the flange, and bolts are reserved on each embedded flange; when the flange is installed, the installation flatness is controlled to be ≤2mm, and the reserved bolts are protected with tape to prevent concrete pollution; before the measurement and layout construction, the position of the steel pipe column is determined on the cap and marked, and the design elevation of the beam bottom formwork measured on the existing cap is used, and then the height of the steel pipe column is calculated according to the erection height of the primary and secondary keels, Bailey beams, and sand boxes;
[0034] 2) Installation of steel pipe columns and holding columns: including steel pipe column assembly and holding column installation. Among them, 4 steel pipe columns are set on the cap according to the design requirements. The steel pipe columns are positioned before construction and installed according to the preset spacing in the horizontal and along the bridge direction. After the steel pipe columns are in place, they are connected with the embedded flanges with reserved bolts. During installation, pay attention to adjusting the verticality of the steel pipe. When the bottom of the pipe is uneven, the verticality of the steel pipe is controlled by reserved bolts and wedge-shaped steel plates. Finally, tighten the reserved bolts to fix the steel pipe columns. The holding columns are in the form of channel steel. After the steel pipe columns are installed, channel steel is used to set horizontal and oblique connections between the steel pipe columns in the longitudinal direction of the bridge to ensure the stability of the steel pipe columns. The steel pipe columns and the pier columns are tied into a whole by channel steel. The vertical spacing is ≤10m.
[0035] 3) Installation of sand box and distribution beam: including installation of sand box and distribution beam, in which the sand box is installed on the top of the steel pipe column, and the height of the sand box can be adjusted to 40-50cm; the sand box is placed in the center during installation, and the sand box and the steel pipe column are connected as a whole with bolts after positioning. Each steel pipe column is equipped with a sand box, and the top elevation of the sand box = the top elevation of the pier column - the thickness of the template - the thickness of the secondary keel - the thickness of the main keel - the thickness of the Bailey beam - the thickness of the distribution beam; the distribution beam adopts double-jointed 45b I-beams, which are welded into one on the ground, and then placed on the sand box by a car crane in cooperation with manual labor, and fixedly connected with the top surface of the sand box by spot welding;
[0036] 4) Installation of reinforced Bailey beam: The main beam adopts reinforced Bailey beam, which is first assembled as a whole on the ground. After the Bailey beam is assembled, reinforced chords are set at the upper and lower parts, connected to the Bailey beam by bolts. A group of Bailey beams are assembled each time, and the Bailey beams are connected with support frames. When all Bailey beams are assembled, they are installed on the distribution beam by a car crane. Symmetrical construction is adopted during installation to ensure the stability of the entire structural system. In order to ensure that the load-bearing beam can be smoothly inserted, the position of the Bailey beam is fine-tuned to align it, and the crossbeam pad on the lower chord is removed before the Bailey beam is installed;
[0037] 5) Installation of load-bearing beam: The load-bearing beam is made of I-beam, which is horizontally arranged on the top surface of the lower chord close to the vertical poles of each node. It is hoisted to one side of the main beam by a crane. The load-bearing beam is passed through the gap between the lower chord and the web of the Bailey beam by manual labor and automobile crane, and is connected and fixed to the Bailey beam with a U-shaped clamp;
[0038] 6) Bailey beam reinforcement, including transverse reinforcement of Bailey beam and vertical reinforcement of Bailey beam. In transverse reinforcement of Bailey beam, the limiter is processed by channel steel, welded on the distribution beam, and set on the left and right sides of the Bailey beam. Four limiters are set on each distribution beam. A transverse connection system is set between each group of Bailey beams. The connection system uses channel steel as a cross bar and a diagonal bar to form a stable structure. The two ends of the cross bar are welded to the clamping plate bolted to each chord to connect the Bailey beam into one body, so as to limit the left and right swing of the Bailey beam in the state of large span and long cantilever. In vertical reinforcement of Bailey beam, a strengthening pole is set at the fulcrum position to increase the shear resistance of the Bailey beam. The strengthening pole is made of channel steel and installed between the upper and lower chords of the Bailey beam. The horizontal direction is connected as a whole by steel bars to ensure the overall stability of the strengthening pole;
[0039] 7) Install the main keel and secondary keel of the bottom formwork: including the installation of the main keel, secondary keel and bottom formwork. The main keel is supported by a tripod, and a tripod support is set at the lower part of the cantilever end of the cap beam. The tripod is made of channel steel, and a vertical rib is set in the middle. To facilitate the operation of construction personnel, a working platform is set on the outside of the cap beam structure, and the tripod support is connected horizontally with steel pipe fasteners; the secondary keel is made of square wood arranged in the horizontal direction of the bridge, which is hoisted by a crane and installed symmetrically from the middle to both ends; multi-layer boards arranged symmetrically from the middle to both sides are laid on the secondary keel, and the horizontal and vertical joints are embedded with waterproof sponge strips to ensure that the joints are tight. The multi-layer boards are fixed and connected to the square wood with nails. The elevation of the multi-layer boards is adjusted by hanging lines and re-measured to ensure the accuracy of the template elevation;
[0040] 8) After the pouring and tensioning of the cap beam concrete is completed, remove the sand box, dismantle the main keel, secondary keel, Bailey beam and steel pipe column of the bottom formwork to complete the construction.
[0041] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0042] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A large cantilever cap beam lower chord reverse support bracket system, characterized in that: The system includes a cap, a steel pipe column, a holding column, a sand box, a distribution beam, a reinforced Bailey beam, a load-bearing beam, a Bailey beam reinforcement assembly and a keel bottom mold assembly, wherein at least four steel pipe columns are symmetrically installed on the embedded flange of the cap in pairs by reserved bolts; the holding column includes a transverse channel steel and an oblique channel steel, and between the two steel pipe columns in the longitudinal bridge direction, the two steel pipe columns in the longitudinal bridge direction are connected together by the transverse channel steel and the oblique channel steel; the sand box is installed on the top of each steel pipe column, and the distribution beam is fixedly installed on the top surface of the sand box; the reinforced Bailey beam includes several groups of Bailey beams and reinforced chord rods, and the reinforced chord rods are installed on the upper and lower parts of the Bailey beams by bolts, and each group of Bailey beams is connected by a support frame; the reinforced Bailey beam is installed on the distribution beam; the load-bearing beam is fixedly installed on the lower chord rod and the web rod at the lower part of the Bailey beam by a U-shaped clamp; the Bailey beam reinforcement assembly includes Bailey beam transverse reinforcement and Bailey beam vertical reinforcement, and the Bailey beam transverse reinforcement It includes a limiter, which is welded on the distribution beam and arranged on the left and right sides of the Bailey beam. Four limiters are arranged on each distribution beam. A transverse connection system is arranged between each group of Bailey beams. The connection system adopts channel steel as a cross bar and a diagonal bar to form a stable structure. The two ends of the cross bar are welded to the clamping plates bolted to each chord to connect the Bailey beam into one body, so as to limit the left and right swing of the Bailey beam in a large span and long cantilever state; the vertical reinforcement of the Bailey beam includes the arrangement of a reinforcing vertical pole, and the reinforcing vertical pole is fixedly installed in the middle of the upper and lower chords of the Bailey beam; the keel bottom mold assembly includes a main keel and a secondary keel of the bottom mold, and the main keel of the bottom mold includes a tripod support arranged at the lower part of the cantilever end of the cap beam; the secondary keel adopts square wood arranged in a transverse direction of the bridge, which is hoisted by a crane and installed symmetrically from the middle to both ends; the secondary keel is laid with multi-layer boards arranged symmetrically from the middle to both sides, and the horizontal and vertical joints are embedded with waterproof sponge rubber strips, and the multi-layer boards and the square wood are fixedly connected with nails.
2. The construction method of the large cantilever cap beam lower chord reverse support bracket system according to claim 1 is characterized in that: The construction method comprises the following steps: 1) Construction preparation and measurement and layout: including the construction of the cap and measurement and layout; during the construction of the cap, a flange is embedded, and a U-shaped anchor steel bar is set at the bottom of the flange, and bolts are reserved on each embedded flange; when the flange is installed, the installation flatness is controlled to be ≤2mm, and the reserved bolts are protected with tape to prevent concrete pollution; before the measurement and layout construction, the position of the steel pipe column is determined on the cap and marked, and the design elevation of the beam bottom formwork measured on the existing cap is used, and then the height of the steel pipe column is calculated according to the erection height of the primary and secondary keels, Bailey beams, and sand boxes; 2) Installation of steel pipe columns and holding columns: including steel pipe column assembly and holding column installation. Among them, 4 steel pipe columns are set on the cap according to the design requirements. The steel pipe columns are positioned before construction and installed according to the preset spacing in the horizontal and along the bridge direction. After the steel pipe columns are in place, they are connected with the embedded flanges with reserved bolts. During installation, pay attention to adjusting the verticality of the steel pipe. When the bottom of the pipe is uneven, the verticality of the steel pipe is controlled by reserved bolts and wedge-shaped steel plates. Finally, tighten the reserved bolts to fix the steel pipe columns. The holding columns are in the form of channel steel. After the steel pipe columns are installed, channel steel is used to set horizontal and oblique connections between the steel pipe columns in the longitudinal direction of the bridge to ensure the stability of the steel pipe columns. The steel pipe columns and the pier columns are tied into a whole by channel steel. The vertical spacing is ≤10m. 3) Installation of sand box and distribution beam: including installation of sand box and distribution beam, in which the sand box is installed on the top of the steel pipe column, and the height of the sand box can be adjusted to 40-50cm; the sand box is placed in the center during installation, and the sand box and the steel pipe column are connected as a whole with bolts after positioning. Each steel pipe column is equipped with a sand box, and the top elevation of the sand box = the top elevation of the pier column - the thickness of the template - the thickness of the secondary keel - the thickness of the main keel - the thickness of the Bailey beam - the thickness of the distribution beam; the distribution beam adopts double-jointed 45b I-beams, which are welded into one on the ground, and then placed on the sand box by a car crane in cooperation with manual labor, and fixedly connected with the top surface of the sand box by spot welding; 4) Installation of reinforced Bailey beam: The main beam adopts reinforced Bailey beam, which is first assembled as a whole on the ground. After the Bailey beam is assembled, reinforced chords are set at the upper and lower parts, connected to the Bailey beam by bolts. A group of Bailey beams are assembled each time, and the Bailey beams are connected with support frames. When all Bailey beams are assembled, they are installed on the distribution beam by a car crane. Symmetrical construction is adopted during installation to ensure the stability of the entire structural system. In order to ensure that the load-bearing beam can be smoothly inserted, the position of the Bailey beam is fine-tuned to align it, and the crossbeam pad on the lower chord is removed before the Bailey beam is installed; 5) Installation of load-bearing beam: The load-bearing beam is made of I-beam, which is horizontally arranged on the top surface of the lower chord close to the vertical poles of each node. It is hoisted to one side of the main beam by a crane. The load-bearing beam is passed through the gap between the lower chord and the web of the Bailey beam by manual labor and automobile crane, and is connected and fixed to the Bailey beam with a U-shaped clamp; 6) Bailey beam reinforcement, including transverse reinforcement of Bailey beam and vertical reinforcement of Bailey beam. In transverse reinforcement of Bailey beam, the limiter is processed by channel steel, welded on the distribution beam, and set on the left and right sides of the Bailey beam. Four limiters are set on each distribution beam. A transverse connection system is set between each group of Bailey beams. The connection system uses channel steel as a cross bar and a diagonal bar to form a stable structure. The two ends of the cross bar are welded to the clamping plate bolted to each chord to connect the Bailey beam into one body, so as to limit the left and right swing of the Bailey beam in the state of large span and long cantilever. In vertical reinforcement of Bailey beam, a strengthening pole is set at the fulcrum position to increase the shear resistance of the Bailey beam. The strengthening pole is made of channel steel and installed between the upper and lower chords of the Bailey beam. The horizontal direction is connected as a whole by steel bars to ensure the overall stability of the strengthening pole; 7) Install the main keel and secondary keel of the bottom formwork: including the installation of the main keel, secondary keel and bottom formwork. The main keel is supported by a tripod, and a tripod support is set at the lower part of the cantilever end of the cap beam. The tripod is made of channel steel, and a vertical rib is set in the middle. To facilitate the operation of construction personnel, a working platform is set on the outside of the cap beam structure, and the tripod support is connected horizontally with steel pipe fasteners; the secondary keel is made of square wood arranged in the horizontal direction of the bridge, which is hoisted by a crane and installed symmetrically from the middle to both ends; multi-layer boards arranged symmetrically from the middle to both sides are laid on the secondary keel, and the horizontal and vertical joints are embedded with waterproof sponge strips to ensure that the joints are tight. The multi-layer boards are fixed and connected to the square wood with nails. The elevation of the multi-layer boards is adjusted by hanging lines and re-measured to ensure the accuracy of the template elevation; 8) After the pouring and tensioning of the cap beam concrete is completed, remove the sand box, dismantle the main keel, secondary keel, Bailey beam and steel pipe column of the bottom formwork to complete the construction.
Citation Information
Cited By
Large-span cast-in-place bent cap construction method based on limited space
CN120967813A