Rapid three-dimensional linkage shield tunnel rescue operation and maintenance channel and method

By setting up evacuation corridors and vehicle-traffic passages between service tunnels and main line tunnels in complex urban road shield tunnels, the up and down linkage is achieved, and the problems of safety risks and rescue convenience of shield tunnel construction are solved, and evacuation rescue and transportation are improved Dimensional efficiency reduces the number of cross-channels.

CN119041930AActive Publication Date: 2024-11-29CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD
View PDF 12 Cites 0 Cited by

Patent Information

Application Number
CN202411155134.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-29
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

The construction safety risks of shield tunnels on complex urban roads are high, and the existing technology is difficult to achieve convenient connection between the lower pipe corridors of shield tunnels and the upper driving lanes under complex geological conditions, resulting in inconvenience in rescue and difficulty in achieving rapid rescue and transportation after reducing cross-channels. dimension.

Method used

Design a fast three-dimensional linkage shield tunnel rescue operation and maintenance channel. By setting up parallel service tunnels, upstream main line tunnels and downstream main line tunnels, the evacuation corridors and vehicle-traffic channels of the service tunnels and the main line tunnels can be used to achieve upstream and downstream linkage, cancel Pedestrian crossing passages, reduce the number of crossing passages of vehicles and improve evacuation and rescue efficiency.

Benefits of technology

The interconnection between the lane layer of the main line tunnel and the service tunnel is realized, forming an up-down linkage evacuation rescue and operation and maintenance channel, improving the efficiency of evacuation rescue and operation and maintenance convenience, reducing the number of cross-channels, especially in the evacuation state, no need to set up people Horizontal channel.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041930A_ABST
    Figure CN119041930A_ABST
Patent Text Reader

Abstract

The invention provides a fast three-dimensional linkage shield tunnel rescue operation and maintenance channel and method.The fast three-dimensional linkage shield tunnel rescue operation and maintenance channel comprises a service tunnel, an uplink main line tunnel and a downlink main line tunnel, the service tunnel, the uplink main line tunnel and the downlink main line tunnel are arranged in parallel, and the service tunnel is located between the uplink main line tunnel and the downlink main line tunnel; the main line tunnel is divided into an upper layer and a lower layer, the upper layer is a lane layer, the lower layer is a pipe gallery layer, the pipe gallery layer comprises a main line tunnel lower portion evacuation gallery, the lane layer is communicated with the main line tunnel lower portion evacuation gallery through evacuation stairs, and the lane layer is communicated with the service tunnel through a plurality of traffic transverse channels. The road surface height of the service tunnel is reduced to be equal to the road surface height of the evacuation gallery on the lower portion of the main line tunnel at the position of the working well or the dismantling cavern, and the service tunnel is communicated with the evacuation gallery on the lower portion of the main line tunnel through the lower evacuation gallery connecting transverse channel at the position of the working well or the dismantling cavern.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to complex urban road tunnels, and in particular to a rapid three-dimensionally linked shield tunnel rescue and operation maintenance channel and method. Background Art

[0002] Complex urban road shield tunnels and submarine road shield tunnels have complex geological conditions and high construction safety risks. It is necessary to make full use of the tunnel space under the shield lane as a pedestrian and vehicle evacuation corridor. Given that complex urban tunnels are generally located in soft surrounding rocks or complex ground environments, the construction of cross passages, especially vehicle cross passages, should be reduced. However, with the reduction of cross passages, how to achieve rapid rescue and provide convenience for operation and maintenance during operation is a difficult problem. In addition, the current tunnel under the shield tunnel can only be connected to the upper lane in the open-cut section, and cannot be connected in the shield section with higher risks, which also makes rescue inconvenient.

[0003] Therefore, it is necessary to design a new fast three-dimensional linkage shield tunnel rescue and operation and maintenance channel and method to overcome the above problems. Summary of the invention

[0004] The purpose of the present invention is to overcome the defects of the prior art and provide a fast three-dimensional linked shield tunnel rescue operation and maintenance channel and method. The present invention at least solves some of the problems in the prior art.

[0005] The present invention is achieved in that:

[0006] The present invention provides a high-speed three-dimensional linkage shield tunnel rescue and operation channel, comprising a service tunnel, an upward main line tunnel, and a downward main line tunnel. The service tunnel, the upward main line tunnel, and the downward main line tunnel are arranged in parallel. The service tunnel is located between the upward main line tunnel and the downward main line tunnel. The service tunnel opening is directly connected to the ground. One end of the shield section of the main line tunnel is directly connected to the ground through an open-cut section. The shield section and the open-cut section are connected through a working well. The other end of the shield section of the main line tunnel is directly connected to the ground through a drilling and blasting section. The shield section and the drilling and blasting section are connected through a demolition well. The main line tunnel is connected to the dismantling cavern, the main line tunnel is divided into two layers, the upper layer is the carriageway layer, and the lower layer is the pipe gallery layer. The pipe gallery layer includes the lower evacuation corridor of the main line tunnel. The carriageway layer is connected to the lower evacuation corridor of the main line tunnel through an evacuation staircase. The carriageway layer is connected to the service tunnel through a number of vehicle cross passages. At the working shaft or the dismantling cavern, the road surface height of the service tunnel is reduced to the same as the road surface height of the lower evacuation corridor of the main line tunnel. At the working shaft or the dismantling cavern, the service tunnel is connected to the lower evacuation corridor of the main line tunnel through the lower evacuation corridor connecting cross passages.

[0007] Furthermore, at the dismantling cavern, the lower evacuation corridor connecting transverse passage is arranged in conjunction with the dismantling cavern.

[0008] Furthermore, at the working shaft, the lower evacuation corridor connecting the transverse passage is arranged in conjunction with the working shaft.

[0009] Furthermore, along the length direction of the shield tunnel, at a certain position in the middle of the shield section, the road surface height of the service tunnel is reduced to be equal to the road surface height of the lower evacuation corridor of the main line tunnel, and is connected with the lower evacuation corridor of the main line tunnel through a connecting cross passage of the lower evacuation corridor.

[0010] Furthermore, the shield section of the main line tunnel is provided with a plurality of shield vehicle cross passages, at which the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer, and the main line tunnel lane layer is connected with the service tunnel through the shield vehicle cross passages.

[0011] Furthermore, in the open-cut section, the longitudinal slope inclination of the service tunnel is greater than the longitudinal slope inclination of the main line tunnel.

[0012] Furthermore, the open-cut section of the main line tunnel is provided with an open-cut vehicle transverse passage. At the open-cut vehicle transverse passage, the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer, and the main line tunnel lane layer is connected with the service tunnel through the open-cut vehicle transverse passage.

[0013] Furthermore, in the drilling and blasting section, the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer, the drilling and blasting section of the main line tunnel is provided with a drilling and blasting vehicle transverse passage, and the main line tunnel lane layer is connected with the service tunnel through the drilling and blasting vehicle transverse passage.

[0014] The present invention also provides a rapid three-dimensionally linked shield tunnel rescue and operation method, including a rescue method and an operation method. The rescue method is: at the main line accident point, personnel enter the lower evacuation corridor of the main line tunnel through the evacuation stairs, then enter the service tunnel through the lower evacuation corridor connecting the cross passage, and then evacuate to the tunnel entrance through the service tunnel.

[0015] Furthermore, the operation and maintenance method is as follows: the operation and maintenance vehicle enters through the service tunnel, then enters the main line tunnel through the vehicle cross passage between the service tunnel and the main line tunnel, and then passes through the main line tunnel lane layer to the main line tunnel operation and maintenance point.

[0016] The present invention has the following beneficial effects:

[0017] 1. The present invention realizes the interconnection of the lane layer of the main line tunnel, the evacuation corridor under the main line tunnel and the service tunnel through the ingenious arrangement of the evacuation corridor under the main line tunnel, the service tunnel and the vehicle cross passage, forming an evacuation and rescue as well as daily operation and maintenance channel with vertical linkage and three-dimensional connection, which greatly improves the evacuation and rescue efficiency and the convenience of daily operation and maintenance.

[0018] 2. The present invention can eliminate pedestrian crosswalks, and the number of vehicle crosswalks can be reduced compared to the standard.

[0019] 3. In the evacuation state, the evacuees can enter the evacuation corridor at the bottom of the main tunnel through the evacuation stairs and achieve rapid evacuation through rescue vehicles, etc. Due to the high efficiency of personnel evacuation, the shield section does not need to be equipped with a pedestrian cross passage. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0021] Figure 1 A schematic diagram of a tunnel longitudinal section provided by an embodiment of the present invention;

[0022] Figure 2 The embodiment of the present invention provides Figure 1 The left side enlarged image of ;

[0023] Figure 3 The embodiment of the present invention provides Figure 1 A magnified view of the middle part;

[0024] Figure 4 The embodiment of the present invention provides Figure 1 The right side enlarged image of ;

[0025] Figure 5 A schematic diagram of a cross-section of a tunnel shield section provided by an embodiment of the present invention;

[0026] Figure 6 The embodiment of the present invention provides Figure 5 The left side enlarged image of ;

[0027] Figure 7 The embodiment of the present invention provides Figure 5 The right side enlarged image of ;

[0028] Figure 8 A cross-sectional view of the dismantling of the cavern bottom gallery and the service tunnel connection provided by an embodiment of the present invention;

[0029] Fig. 9 The embodiment of the present invention provides Figure 8 The left side enlarged image of ;

[0030] Fig.10 The embodiment of the present invention provides Figure 8The right side enlarged image of ;

[0031] Fig.11 A schematic diagram of lane layer interconnection provided by an embodiment of the present invention;

[0032] Fig.12 The embodiment of the present invention provides Fig.11 The left side enlarged image of ;

[0033] Fig.13 The embodiment of the present invention provides Fig.11 The right side enlarged image of ;

[0034] Fig.14 A schematic diagram of interconnection of lower evacuation corridor layers provided by an embodiment of the present invention;

[0035] Fig.15 The embodiment of the present invention provides Fig.14 The left side enlarged image of ;

[0036] Fig.16 The embodiment of the present invention provides Fig.14 The right side enlarged image of ;

[0037] Fig.17 A schematic diagram of the operation and maintenance and evacuation routes provided by an embodiment of the present invention;

[0038] Fig.18 The embodiment of the present invention provides Fig.17 The left side enlarged image of ;

[0039] Fig.19 The embodiment of the present invention provides Fig.17 Enlarged image on the right.

[0040] In the figure: drilling and blasting section 1, dismantling cavern 2, shield section 3, working shaft 4, open-cut section 5, drilling and blasting pedestrian cross passage 6, drilling and blasting vehicle cross passage 7, shield vehicle cross passage 8, open-cut vehicle cross passage 9, main line tunnel 10, service tunnel 11, road elevation 12, main line tunnel lower evacuation corridor 13, evacuation stairs 14, lower evacuation corridor liaison cross passage combined with dismantling cavern 15, lower evacuation corridor liaison cross passage 16, lower evacuation corridor liaison cross passage combined with working shaft 17 , main line driving direction 18, main line accident point 19, personnel enter the lower evacuation corridor of the main line tunnel through the evacuation stairs 20, enter the service tunnel through the lower evacuation corridor connecting the cross passage set at the working shaft 21, evacuate to the tunnel entrance through the service tunnel 22, operation and maintenance vehicles enter through the service tunnel 23, then enter the main line tunnel through the shield vehicle cross passage between the service tunnel and the main line tunnel 24, through the main line tunnel lane layer to the main line tunnel operation and maintenance point 25, main line tunnel operation and maintenance point 26. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] like Figure 1-Figure 19 The first embodiment of the present invention provides a fast three-dimensionally linked shield tunnel rescue and operation channel, including a service tunnel 11, an upward main line tunnel 10, and a downward main line tunnel 10. The service tunnel 11, the upward main line tunnel 10, and the downward main line tunnel 10 are arranged in parallel. The service tunnel 11 is located between the upward main line tunnel 10 and the downward main line tunnel 10. The opening of the service tunnel 11 is directly connected to the ground. One end of the shield section 3 of the main line tunnel is directly connected to the ground through the open-cut section 5. The shield section 3 and the open-cut section 5 are connected through a working well 4. The other end of the shield section 3 of the main line tunnel is directly connected to the ground through the drilling and blasting section 1. The shield section 3 and the drilling and blasting section 5 are connected. Section 1 is connected through the dismantling cavern 2, the main line tunnel 10 is divided into two layers, the upper layer is the carriageway layer, and the lower layer is the pipe gallery layer. The pipe gallery layer includes the lower evacuation corridor 13 of the main line tunnel. The carriageway layer is connected with the lower evacuation corridor 13 of the main line tunnel through an evacuation staircase 14. The carriageway layer is connected with the service tunnel 11 through a number of vehicle transverse passages. At the working shaft 4 or the dismantling cavern 2, the road surface height of the service tunnel 11 is reduced to the same as the road surface height of the lower evacuation corridor 13 of the main line tunnel. At the working shaft 4 or the dismantling cavern 2, the service tunnel 11 is connected with the lower evacuation corridor 13 of the main line tunnel through the lower evacuation corridor liaison transverse passage 16. Preferably, at the dismantling cavern 2, the lower evacuation corridor liaison transverse passage 16 is set in combination with the dismantling cavern 2. At the working shaft 4, the lower evacuation corridor liaison transverse passage 16 is set in combination with the working shaft 4.

[0043] If necessary, preferably, along the length direction of the shield tunnel, at a certain position in the middle of the shield section 3, the road surface height of the service tunnel 11 is lowered to be equal to the road surface height of the lower evacuation corridor 13 of the main line tunnel, and is connected with the lower evacuation corridor 13 of the main line tunnel through the lower evacuation corridor connecting transverse passage 16, so that the lower evacuation corridor 13 of the main line tunnel can be directly connected to the ground as soon as possible.

[0044] The shield section 3 of the main line tunnel 10 is provided with a plurality of shield vehicle cross passages 8. At the shield vehicle cross passages 8, the road surface height of the service tunnel 11 is equal to the road surface height of the main line tunnel lane layer. The main line tunnel lane layer is connected with the service tunnel 11 through the shield vehicle cross passages 8.

[0045] In the open cut section 5, the longitudinal slope inclination of the service tunnel 11 is greater than that of the main line tunnel 10. The service tunnel 11 drives out of the tunnel entrance through the longitudinal slope and directly reaches the ground, realizing early exit from the ground through the service tunnel 11. The open cut section 5 of the main line tunnel 10 is provided with an open cut vehicle transverse passage 9. At the open cut vehicle transverse passage 9, the road surface height of the service tunnel 11 is equal to the road surface height of the main line tunnel lane layer. The main line tunnel lane layer is connected to the service tunnel 11 through the open cut vehicle transverse passage 9.

[0046] In the drilling and blasting section 1, the road surface height of the service tunnel 11 is equal to the road surface height of the main line tunnel lane layer. The drilling and blasting section 1 of the main line tunnel 10 is provided with a drilling and blasting vehicle transverse passage 7, and the main line tunnel lane layer is connected with the service tunnel 11 through the drilling and blasting vehicle transverse passage 7.

[0047] The complex urban shield tunnel adopts a three-tunnel parallel arrangement, in which the main line tunnel shield section 3 adopts an upper and lower double-layer arrangement, with the upper layer being the lane layer and the lower layer being the pipe gallery layer. The lower evacuation corridor 13 of the main line tunnel is set in the middle of the pipe gallery, and an evacuation staircase 14 is set on one side to realize pedestrian connection between the upper lane layer and the lower evacuation corridor 13 of the main line tunnel. A service tunnel 11 is set between the up and down shield tunnels, and the entrance of the service tunnel 11 is directly connected to the ground.

[0048] The shield section 3 of the main line tunnel can directly reach the ground through the open-cut section 5, and the shield section 3 and the open-cut section 5 are connected through the working shaft 4. The shield section 3 of the main line tunnel can also directly reach the ground through the drilling and blasting section 1, and the shield section 3 and the drilling and blasting section 1 are connected through the dismantling cavern 2. At the working shaft 4 or the dismantling cavern 2, the road surface elevation of the service tunnel 11 is equal to the elevation of the evacuation corridor 13 at the bottom of the main line tunnel to achieve the connection between the service tunnel 11 and the evacuation corridor 13 at the bottom of the main line tunnel. According to the needs of evacuation and operation and maintenance, the elevation of the service tunnel 11 can be partially lowered in the middle of the shield section 3 to achieve the same elevation of the road surface elevation of the service tunnel 11 and the evacuation corridor 13 at the bottom of the main line tunnel.

[0049] According to the needs of comprehensive disaster prevention and operation and maintenance of the shield section and the hydrogeological conditions, vehicle cross passages are set at certain intervals, and most sections of the road surface of the service tunnel 11 are at the same elevation as the lane level of the main tunnel 10. In principle, the vehicle cross passage also takes into account the function of the pedestrian cross passage. In the open-cut section 5, the longitudinal slope of the service tunnel 11 is greater than the longitudinal slope of the main tunnel 10 to achieve rapid ground exit, and an open-cut vehicle cross passage 9 is set at the same elevation of the road surface of the open-cut section 5 to achieve the connection between the service tunnel 11 and the lane level of the main tunnel 10. In the drilling and blasting section, the service tunnel 11 and the main tunnel 10 are at the same elevation, and a drilling and blasting vehicle cross passage 7 is set to achieve the interconnection between the service tunnel 11 and the lane level of the main tunnel 10.

[0050] Figure 1-Figure 4It is a schematic diagram of the longitudinal section of the tunnel, with the tunnel shield section 3 in the middle, the drilling and blasting section 1 on the left, and the open-cut section 5 on the right. The shield section 3 and the drilling and blasting section 1 are connected through the dismantling cavern 2, and the shield section 3 and the open-cut section 5 are connected through the working shaft 4. Overall, the service tunnel 11 and the main line tunnel 10 have the same elevation as the road surface elevation (e.g. Figure 5-Figure 7 ), near the dismantling cavern 2 and the working shaft 4 and, if necessary, at the same elevation of the road surface of the service tunnel 11 in the middle of the shield tunnel and the road surface of the evacuation corridor 13 at the lower part of the shield section (e.g. Figure 8-Figure 10 ).

[0051] Figure 5-Figure 7 It is a cross-sectional view of the shield tunnel. The service tunnel 11 is located in the middle of the up and down main line tunnels 10. The main line tunnel 10 is divided into two layers, the upper layer is the carriageway layer, and the lower layer is the pipe gallery layer. The middle of the pipe gallery layer is the lower evacuation corridor 13 of the main line tunnel. The carriageway layer of the main line tunnel 10 is connected to the lower evacuation corridor 13 of the main line tunnel through the evacuation stairs 14. When evacuation is required, personnel enter the lower evacuation corridor 13 of the main line tunnel through the evacuation stairs 14 and quickly leave the tunnel through the evacuation vehicles.

[0052] Figure 8-Figure 10 To dismantle the location of the cavern 2, a cross-sectional view of the main line tunnel lower evacuation corridor 13 connected to the service tunnel 11 is provided. Here, the road surface elevation 12 of the local service tunnel is lowered to be basically flush with the road surface of the main line tunnel lower evacuation corridor 13.

[0053] Figure 11-13 This is a plan view of the interconnection between the main line tunnel 10 lane level and the service tunnel 11.

[0054] Figure 14-16 It is a plan view of the interconnection between the lower evacuation corridor 13 of the main line tunnel and the service tunnel 11. Near the dismantling cavern 2 and the working shaft 4 and, when necessary, in the middle of the shield tunnel, the road surface elevation of the service tunnel 11 is the same as the road surface elevation of the lower evacuation corridor 13 of the shield section. The lower evacuation corridor 13 of the main line tunnel for both up and down directions is connected with the service tunnel 11 through the lower evacuation corridor connecting transverse passage 16.

[0055] At the dismantling cavern 2, a lower evacuation corridor connecting transverse passage is set in combination with the dismantling cavern 15, and at the working shaft 4, a lower evacuation corridor connecting transverse passage is set in combination with the working shaft 17.

[0056] By adjusting the longitudinal section of the service tunnel (adjusting the longitudinal road surface height of the service tunnel), the lane layer of the up and down main line tunnel 10 and the service tunnel 11 are interconnected through the vehicle cross passage (drilling and blasting vehicle cross passage 7, shield vehicle cross passage 8, open-cut vehicle cross passage 9) ( Figure 11-13), the lower evacuation corridor 13 of the up and down main line tunnels and the service tunnel 11 are interconnected through the lower evacuation corridor connecting transverse passage 16, thereby realizing the functions of rapid evacuation and rescue as well as daily operation and maintenance.

[0057] Embodiment 2 of the present invention provides a rapid three-dimensionally linked shield tunnel rescue and operation method, the rescue method being: at the main line accident point, personnel enter the lower evacuation corridor of the main line tunnel through the evacuation stairs, then enter the service tunnel through the lower evacuation corridor connecting the horizontal passage, and then evacuate to the tunnel entrance through the service tunnel; the operation and maintenance method is: the operation and maintenance vehicle enters through the service tunnel, then enters the main line tunnel through the vehicle horizontal passage between the service tunnel and the main line tunnel, and then passes through the main line tunnel lane layer to the main line tunnel operation and maintenance point.

[0058] Figure 17-Figure 19 This is a schematic diagram of the operation and maintenance and evacuation route, which illustrates the route for personnel to quickly evacuate to the tunnel entrance through the service tunnel 11 in the event of an accident in the main line tunnel 10; for example, at the main line accident point 19 in the figure, personnel enter the lower evacuation corridor 20 of the main line tunnel through the evacuation stairs, and then enter the service tunnel 21 through the lower evacuation corridor connecting the cross passage set at the working shaft, and then evacuate to the tunnel entrance 22 through the service tunnel.

[0059] Figure 17-Figure 19 It also shows that the mainline tunnel requires an operation and maintenance point, and the route for the operation and maintenance vehicle to enter the mainline tunnel 10 through the service tunnel 11; as shown in the figure, the operation and maintenance vehicle enters 23 through the service tunnel, then enters the mainline tunnel 24 through the shield vehicle cross passage between the service tunnel and the mainline tunnel, and then passes through the mainline tunnel lane layer to the mainline tunnel operation and maintenance point 25.

[0060] The key technical points of the present invention are as follows: (1) Setting up a service tunnel: In order to improve the convenience of disaster prevention, rescue and operation and maintenance of complex urban tunnels, a service tunnel is generally set up between the up and down main line tunnels, and the service tunnel 11 has an opening directly connected to the ground. (2) The service tunnel is connected to the lower evacuation corridor of the shield: Taking advantage of the fact that the opening of the service tunnel 11 is directly connected to the ground, the elevation of the service tunnel pavement at the working shaft 4 or the dismantling cavern 2 is equivalent to the elevation of the pavement of the lower evacuation corridor 13 of the main line tunnel, and the lower evacuation corridor 13 of the main line tunnel is directly connected to the ground. According to the length of the shield tunnel, the needs of evacuation and operation and maintenance, the elevation of the service tunnel 11 pavement can be partially lowered in the middle of the shield section to achieve the same elevation as that of the service tunnel 11 and the lower evacuation corridor 13 of the main line tunnel, so as to achieve the direct connection of the lower evacuation corridor 13 of the main line tunnel with the ground as soon as possible. In the evacuation state, the evacuees can enter the lower evacuation corridor 13 of the main line tunnel through the evacuation stairs 14, and achieve rapid evacuation through rescue vehicles and other means. Due to the high efficiency of personnel evacuation, the shield section can be provided with no pedestrian cross passage in principle. (3) Use the vehicle cross passage to connect the service tunnel and the main line tunnel driving lane layer: The shield section 3 can be provided with a shield vehicle cross passage 8 appropriately. At the location of the vehicle cross passage, the elevation of the main line tunnel pavement is basically the same as that of the service tunnel pavement. The lane layer of the main line tunnel 10 is connected with the service tunnel 11. In this way, small operation and maintenance vehicles can directly enter the main line tunnel 10 through the service tunnel 11, thereby improving the timeliness of evacuation or daily operation and maintenance. (4) A cross passage for vehicles is set up in the open-cut section 5 and the drill-and-blast section 1: the service tunnel 11 of the open-cut section adopts a larger longitudinal slope than the main line tunnel 10 to get out of the ground in advance, and a cross passage for vehicles 9 is set up at the same elevation to connect the service tunnel 11 with the lane level of the main line tunnel of the open-cut section; the service tunnel 11 of the drill-and-blast section is at the same elevation as the lane level of the main line tunnel 10, and the main line tunnel 10 is connected to the service tunnel 11 through the drill-and-blast cross passage 7, thereby realizing a rapid evacuation or daily maintenance channel at the lane level of the entire tunnel.

[0061] Overall tunnel design: determine the horizontal and vertical sections of the tunnel based on its functional positioning and traffic diversion, determine the cross-section of the tunnel based on the exchange flow, etc., and determine the segmented construction method based on the hydrogeological conditions of the tunnel.

[0062] Tunnel disaster prevention, evacuation and operation and maintenance strategies: Determine whether to set up an intermediate service tunnel 11 based on the functional positioning of the tunnel, fire rescue timeliness, and convenience of operation and maintenance. Consider the rescue timeliness and hydrogeological conditions to determine the spacing of the shield vehicle cross passage 8 in the shield section. Determine whether to lower the elevation of the service tunnel and the elevation of the evacuation corridor 13 in the lower part of the main line tunnel in the middle of the shield section 3 based on the length of the shield section 3 and the hydrogeological conditions.

[0063] Tunnel disaster prevention, evacuation and operation and maintenance plan: The tunnel adopts a three-tunnel parallel layout plan, with a service tunnel 11 in the middle. The pavement elevation of the service tunnel 11 at the working shaft 4 and the dismantling cavern 2 and the middle of the shield section 3 is equal to the pavement elevation of the evacuation corridor 13 at the bottom of the main line tunnel. The pavement elevation of the service tunnel 11 at the shield section vehicle cross passage 8, the drilling and blasting section vehicle cross passage 7 and the open-cut section vehicle cross passage 9 is equal to the pavement elevation of the main line tunnel 10 lane layer. The service tunnel 11 is connected in series to form the evacuation corridor 13 at the bottom of the main line tunnel and the three-dimensional interconnected disaster prevention and evacuation channel and operation and maintenance channel at the lane layer, which directly leads to the ground through the service tunnel 11 or the main line tunnel 10 hole.

[0064] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

[0065] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A fast three-dimensional linkage shield tunnel rescue operation and maintenance channel, characterized by: It includes a service tunnel, an upward main line tunnel, and a downward main line tunnel. The service tunnel, the upward main line tunnel, and the downward main line tunnel are arranged in parallel. The service tunnel is located between the upward main line tunnel and the downward main line tunnel. The service tunnel opening is directly connected to the ground. One end of the shield section of the main line tunnel is directly connected to the ground through an open-cut section. The shield section and the open-cut section are connected through a working well. The other end of the shield section of the main line tunnel is directly connected to the ground through a drilling and blasting section. The shield section and the drilling and blasting section are connected through a dismantling cavern. It is divided into two layers, the upper layer is the carriageway layer, and the lower layer is the pipe gallery layer. The pipe gallery layer includes the lower evacuation corridor of the main line tunnel. The carriageway layer is connected with the lower evacuation corridor of the main line tunnel through an evacuation staircase. The carriageway layer is connected with the service tunnel through a number of vehicle cross passages. At the working shaft or dismantling cavern position, the road surface height of the service tunnel is reduced to the same as the road surface height of the lower evacuation corridor of the main line tunnel. At the working shaft or dismantling cavern position, the service tunnel is connected with the lower evacuation corridor of the main line tunnel through the lower evacuation corridor connecting cross passages.

2. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1 is characterized by: At the dismantling cavern, the lower evacuation corridor connecting transverse passage is arranged in conjunction with the dismantling cavern.

3. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1 is characterized by: At the working shaft, the lower evacuation corridor connecting the horizontal passage is set in conjunction with the working shaft.

4. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1 is characterized by: Along the length direction of the shield tunnel, at a certain position in the middle of the shield section, the road surface height of the service tunnel is reduced to the same level as the road surface height of the lower evacuation corridor of the main line tunnel, and is connected to the lower evacuation corridor of the main line tunnel through a connecting cross passage of the lower evacuation corridor.

5. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1 is characterized by: The shield section of the main line tunnel is provided with a plurality of shield vehicle cross passages. At the shield vehicle cross passages, the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer. The main line tunnel lane layer is connected with the service tunnel through the shield vehicle cross passages.

6. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1, characterized in that: In the open-cut section, the longitudinal slope inclination of the service tunnel is greater than the longitudinal slope inclination of the main line tunnel.

7. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1 is characterized by: The open-cut section of the main line tunnel is provided with an open-cut vehicle transverse passage. At the open-cut vehicle transverse passage, the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer. The main line tunnel lane layer is connected to the service tunnel through the open-cut vehicle transverse passage.

8. The fast three-dimensional linkage shield tunnel rescue and operation channel according to claim 1, characterized in that: In the drilling and blasting section, the road surface height of the service tunnel is equal to the road surface height of the main line tunnel lane layer. The drilling and blasting section of the main line tunnel is provided with a drilling and blasting vehicle transverse passage, and the main line tunnel lane layer is connected with the service tunnel through the drilling and blasting vehicle transverse passage.

9. A fast three-dimensional linkage shield tunnel rescue operation and maintenance method, characterized by: It includes a rescue method and an operation and maintenance method. The rescue method is: at the main line accident point, personnel enter the lower evacuation corridor of the main line tunnel through the evacuation stairs, then enter the service tunnel through the lower evacuation corridor connecting the cross passage, and then evacuate to the tunnel entrance through the service tunnel.

10. The rapid three-dimensional linkage shield tunnel rescue operation and maintenance method according to claim 9, characterized in that: The operation and maintenance method is as follows: the operation and maintenance vehicle enters through the service tunnel, then enters the main line tunnel through the vehicle cross passage between the service tunnel and the main line tunnel, and then passes through the main line tunnel lane layer to the main line tunnel operation and maintenance point.

Citation Information

Patent Citations

  • Five-hole and four-path railway underwater tunnel and construction method thereof

    CN101892845A

  • Layered railway tunnel structure

    CN107218058A

  • Highway double-layer shield tunnel section structure

    CN110566222A

  • Three-hole parallel magnetic levitation vacuum tunnel structure

    CN110985039A

  • Evacuation and rescue longitudinal channel for connecting ground and lower-layer space of shield tunnel

    CN113914924A