BIM-based building construction data processing method and system
Through the BIM-based building construction data processing method, point cloud data sets and quality evaluation indicators are used to compare construction progress and quality in real time, solving the problem of inefficiency in traditional construction management and achieving efficient and accurate construction management.
Patent Information
- Application Number
- CN202411578649.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-07
- Publication Date
- 2024-12-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional construction management collects construction information through manual inspection and data summary, resulting in slow data processing speed, high error rate, low efficiency, and even delays in construction periods.
Using BIM-based building construction data processing method, by obtaining the corrected spatial coordinates of real-time building construction scenarios, building point cloud data sets, importing BIM system, building simulation progress model and quality evaluation indicators, comparing construction progress and quality in real time, and automatically managing Construction process.
Real-time and intelligent construction management is realized, construction management efficiency is improved, error rate and the probability of construction period delay are reduced, and the construction accuracy of BIM model is improved.
Smart Images

Figure CN119067513A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of data processing, and in particular to a method and system for processing building construction data based on BIM. Background Art
[0002] Construction refers to the production activities during the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said to be the process of turning various lines on the design drawings into physical objects at designated locations.
[0003] Construction management runs through the entire life cycle of a construction project. It refers to all activities that regularly inspect, compare, and analyze the entire construction process, promptly discover deviations in the construction process, and take effective measures to adjust the construction schedule, eliminate interference, and ensure the achievement of construction period goals.
[0004] Traditional construction management collects construction information through manual inspections and data aggregation, and provides the execution status of the construction schedule in the form of text or tables. This method has slow data processing speed and high error rate, resulting in low efficiency of construction management and even delays in construction period. Summary of the invention
[0005] In view of the shortcomings of the prior art, the purpose of the present invention is to provide a BIM-based construction data processing method and system, aiming to solve the technical problems in the prior art of collecting construction information through manual inspections and data aggregation, which has slow data processing speed and high error rate, resulting in low efficiency in construction management and even causing delays in construction period.
[0006] In order to achieve the above objectives, in a first aspect, an embodiment of the present application provides a method for processing building construction data based on BIM, comprising the following steps: Acquire a number of corrected space coordinates corresponding to the real-time building construction scene, and simplify the number of corrected space coordinates to obtain a point cloud data set including point cloud coordinates of a number of stages; Importing the point cloud data set into a BIM system to obtain a BIM building model, constructing a simulation progress model based on construction plan parameters, and determining whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; Constructing several quality assessment indicators adapted to the real-time building construction scene, and acquiring indicator parameters corresponding to the quality assessment indicators based on the BIM building model; The indicator parameters are compared with preset parameters to obtain an indicator score corresponding to the quality assessment indicator, the quality score of the BIM building model is determined by the indicator score, and whether the construction quality meets the expected plan is determined based on the quality score.
[0007] Compared with the prior art, the beneficial effects of the present invention are as follows: by acquiring the point cloud data set and constructing the BIM building model based on the visualization function of the BIM system, the construction status of the real-time building construction scene can be fed back in real time, and by comparing the BIM building model with the simulation progress model constructed based on the construction plan parameters, it is possible to grasp in real time whether the current construction progress meets the expected requirements; by performing quality assessment on the BIM building model, it is possible to grasp in real time whether the current construction quality meets the expected requirements; that is, the management of construction can be completed in real time, intelligently and automatically, avoiding the low efficiency and high error caused by manual collection of construction data, improving the efficiency of construction management, and reducing the probability of construction delays; by acquiring the corrected space coordinates and performing the simplified processing, the construction accuracy of the BIM building model can be effectively improved, and the error rate of construction management can be reduced.
[0008] Furthermore, the step of obtaining a plurality of corrected space coordinates corresponding to the real-time building construction scene includes: Planning a number of measurement points in a real-time building construction scene, and scanning the measurement points by a laser scanner to obtain initial spatial coordinates of the measurement points; A deviation factor group is obtained based on the surface features of the real-time building construction scene, and the initial space coordinates are corrected by the deviation factor group to obtain a plurality of corrected space coordinates.
[0009] Furthermore, the deviation factor group includes a surface defect factor, a measurement error factor and an external influence factor, and the calculation formula of the correction space coordinate is: , in, represents the i-th correction space coordinate, represents the i-th initial space coordinate, represents the surface defect factor corresponding to the i-th initial space coordinate, represents the measurement error factor corresponding to the i-th initial space coordinate, represents the external influencing factor corresponding to the i-th initial space coordinate.
[0010] Furthermore, the step of simplifying the plurality of corrected space coordinates to obtain a point cloud data set including point cloud coordinates of a plurality of stages includes: Selecting one of the correction space coordinates as a reference space coordinate, and selecting a plurality of the correction space coordinates adjacent to the reference space coordinate as a plurality of reference space coordinates; Obtaining a calculated height of the reference space coordinate based on the plurality of reference space coordinates, and comparing the calculated height of the reference space coordinate with an actual height of the reference space coordinate to determine whether the reference space coordinate is an error coordinate; If the reference space coordinate is the error coordinate, then the reference space coordinate is eliminated; If the reference space coordinate is not the error coordinate, the reference space coordinate is selected as the stage point cloud coordinate, and a plurality of the stage point cloud coordinates are combined into a point cloud data set.
[0011] Furthermore, the calculation height is obtained by the following formula: , in, represents the calculated height when the i-th correction space coordinate is the reference space coordinate, It represents the actual height when the i-th correction space coordinate is the reference space coordinate. represents the horizontal coordinate of the reference space coordinate, represents the vertical coordinate of the reference space coordinate, represents the horizontal coordinate of the jth reference space coordinate adjacent to the reference space coordinate, represents the vertical coordinate of the jth reference space coordinate adjacent to the reference space coordinate, Indicates the number of reference space coordinates adjacent to the base space coordinate. Represents a constant.
[0012] Furthermore, the step of importing the point cloud data set into the BIM system to obtain the BIM building model includes: Constructing a contour model corresponding to the real-time building construction scene according to the point cloud data set through the BIM system; Structural attributes and material attributes are assigned to the outline model to form a BIM building model.
[0013] Furthermore, the step of determining whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model includes: Comparing the BIM building model with the simulation progress model for similarity to obtain a similarity difference; It is determined whether the similarity difference is less than an error threshold. If the similarity difference is less than the error threshold, it is determined that the construction progress is in line with the expected plan.
[0014] Furthermore, the step of determining the quality score of the BIM building model by the indicator score and determining whether the construction quality meets the expected plan based on the quality score includes: Setting weight ratios of different quality assessment indicators; Determine the quality score of the BIM building model based on the weight ratio and the indicator score; It is determined whether the quality score reaches a score threshold. If the quality score reaches the score threshold, it is determined that the construction quality meets the expected plan.
[0015] In a second aspect, an embodiment of the present application provides a BIM-based construction data processing system, which is applied to the BIM-based construction data processing method as described in the first aspect above, and the system includes: An acquisition module, used to acquire a number of corrected space coordinates corresponding to the real-time building construction scene, and simplify the number of corrected space coordinates to acquire a point cloud data set including point cloud coordinates of a number of stages; A first judgment module is used to import the point cloud data set into the BIM system to obtain a BIM building model, build a simulation progress model based on the construction plan parameters, and determine whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; An evaluation module, used to construct a number of quality evaluation indicators adapted to the real-time building construction scene, and to obtain indicator parameters corresponding to the quality evaluation indicators based on the BIM building model; The second judgment module is used to compare the indicator parameters with preset parameters to obtain an indicator score corresponding to the quality assessment indicator, determine the quality score of the BIM building model through the indicator score, and determine whether the construction quality meets the expected plan based on the quality score.
[0016] In a third aspect, an embodiment of the present application provides a computer, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the BIM-based construction data processing method as described in the first aspect above is implemented.
[0017] In a fourth aspect, an embodiment of the present application provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the BIM-based construction data processing method as described in the first aspect above is implemented. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 Flow chart of a method for processing building construction data based on BIM in a first embodiment of the present invention; Figure 2 It is a structural block diagram of a BIM-based building construction data processing system in a second embodiment of the present invention; The following specific implementation manner will further illustrate the present invention in conjunction with the above-mentioned drawings. DETAILED DESCRIPTION
[0019] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. Several embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thorough and comprehensive.
[0020] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0021] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which the present invention belongs. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.
[0022] See also Figure 1 The first embodiment of the present invention provides a method for processing construction data based on BIM, comprising the following steps: S10: acquiring a number of corrected space coordinates corresponding to the real-time building construction scene, and performing simplification processing on the number of corrected space coordinates to acquire a point cloud data set including point cloud coordinates of a number of stages; Generally speaking, although the BIM model can realize the acquisition of building information, it can only display some static information of the building in a two-dimensional form. In this embodiment, by acquiring the point cloud data set, a three-dimensional BIM building model can be constructed to achieve a true restoration of the real-time construction scene.
[0023] The step S10 comprises: S110: planning a plurality of measurement points in a real-time construction scene, and scanning the measurement points by a laser scanner to obtain initial spatial coordinates of the measurement points; That is, the real-time construction scene is scanned by the laser scanner to obtain the initial spatial coordinates of the measuring point.
[0024] The formula for obtaining the initial space coordinates is: , in, , , Represents the three-axis coordinate values of the initial spatial coordinates of the i-th measurement point in the spatial rectangular coordinate system, represents the distance between the laser scanner and the i-th measurement point, represents the lateral scanning angle of the laser emitted by the laser scanner, Indicates the longitudinal scanning angle of the laser emitted by the laser scanner.
[0025] It can be understood that the ith measurement point is the ith initial space coordinate. In this embodiment, the distance between the laser scanner and the measurement point is obtained by a phase difference method, which has been widely used and will not be described in detail here.
[0026] S120: acquiring a deviation factor group based on the surface features of the real-time building construction scene, and correcting the initial space coordinates by using the deviation factor group to obtain a plurality of corrected space coordinates; During the laser scanning process, the initial spatial coordinates obtained by the laser scanner will be affected by factors such as reflections from the building surface, resulting in certain errors in the obtained initial spatial coordinates. In order to truly restore the real-time construction scene, some of the initial spatial coordinates need to be corrected.
[0027] The deviation factor group includes surface defect factors, measurement error factors and external influence factors. The calculation formula of the correction space coordinates is: , in, represents the i-th correction space coordinate, represents the i-th initial space coordinate, represents the surface defect factor corresponding to the i-th initial space coordinate, represents the measurement error factor corresponding to the i-th initial space coordinate, It represents the external influencing factor corresponding to the ith initial spatial coordinate. It can be understood that the ith initial spatial coordinate is the data of the ith corrected spatial coordinate before correction, and both represent the same measurement point.
[0028] S130: selecting one of the correction space coordinates as a reference space coordinate, and selecting a plurality of the correction space coordinates adjacent to the reference space coordinate as a plurality of reference space coordinates; After the correction is completed, there may still be non-real scanning data, which affects the three-dimensional reconstruction of the building. Therefore, it is necessary to further eliminate errors in the correction space coordinates.
[0029] S140: obtaining a calculated height of the reference space coordinate based on the plurality of reference space coordinates, and comparing the calculated height of the reference space coordinate with an actual height of the reference space coordinate to determine whether the reference space coordinate is an error coordinate; The calculation height is obtained by the following formula: , in, represents the calculated height when the i-th correction space coordinate is the reference space coordinate, It represents the actual height when the i-th correction space coordinate is the reference space coordinate. represents the horizontal coordinate of the reference space coordinate, represents the vertical coordinate of the reference space coordinate, represents the horizontal coordinate of the jth reference space coordinate adjacent to the reference space coordinate, represents the vertical coordinate of the jth reference space coordinate adjacent to the reference space coordinate, Indicates the number of reference space coordinates adjacent to the base space coordinate. The actual height can be obtained when setting the measuring point.
[0030] S150: If the reference space coordinate is the error coordinate, remove the reference space coordinate; S160: If the reference space coordinate is not the error coordinate, the reference space coordinate is selected as a stage point cloud coordinate, and a plurality of the stage point cloud coordinates are combined into a point cloud data set.
[0031] In some embodiments, the point cloud data set is acquired by a plurality of laser scanners. Preferably, after step S10, step S50 is further included: The coordinates of the point clouds in the several stages are unified.
[0032] Specifically, several spatial rectangular coordinate systems corresponding to different laser scanners are obtained, and a certain spatial rectangular coordinate system is used as a reference coordinate system. The translation parameters and rotation parameters between the other spatial rectangular coordinate systems and the reference coordinate system are obtained, and the stage point cloud coordinates corresponding to the other spatial rectangular coordinate systems are adjusted through the translation parameters and the rotation parameters to complete coordinate unification.
[0033] S20: importing the point cloud data set into a BIM system to obtain a BIM building model, constructing a simulation progress model based on construction plan parameters, and determining whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; The step S20 comprises: S210: constructing a contour model corresponding to the real-time building construction scene according to the point cloud data set based on the BIM system; S220: Assigning structural attributes and material attributes to the outline model to form a BIM building model.
[0034] Through the structural attributes, the connection relationship between the point cloud coordinates of different stages and the selection of the connection module can be determined, and the corresponding material can be assigned to the connection module through the material attributes. It can be understood that the structural attributes and the material attributes are obtained based on the construction parameters stored in the construction plan in the BIM system.
[0035] S230: performing a similarity comparison between the BIM building model and the simulation progress model to obtain a similarity difference; S240: Determine whether the similarity difference is less than an error threshold. If the similarity difference is less than the error threshold, determine that the construction progress meets the expected plan. It can be understood that by obtaining the construction plan parameters, the simulation construction of the building scene can be completed according to the preset construction plan, which is a standard model under the standard progress. If the similarity difference is greater than the error threshold, it is determined that the construction progress does not meet the expected plan, and the preset construction plan needs to be adjusted according to the similarity difference.
[0036] S30: constructing a number of quality assessment indicators adapted to the real-time building construction scene, and acquiring indicator parameters corresponding to the quality assessment indicators based on the BIM building model; In this embodiment, the several quality assessment indicators are damage assessment indicators, crack assessment indicators, earthquake resistance assessment indicators and deformation assessment indicators. By truly restoring the BIM building model of the real-time building construction scene, the indicator parameters corresponding to the several quality assessment indicators can be obtained by testing the BIM building model and simulating mechanical experiments.
[0037] S40: comparing the indicator parameter with a preset parameter to obtain an indicator score corresponding to the quality assessment indicator, determining a quality score of the BIM building model according to the indicator score, and determining whether the construction quality meets the expected plan based on the quality score; Taking the damage assessment index as an example, the index parameters include the area of a single damaged region and the number of damaged areas. The preset parameters are a single damaged area threshold and a damage number threshold. Two sub-scores are obtained by comparing them respectively, and then the two sub-scores are weighted to obtain the index score.
[0038] The step S40 comprises: S410: Setting weight ratios of different quality assessment indicators; In this embodiment, the weight proportions of the different quality assessment indicators can be determined by construction experience. In some embodiments, the weight proportions can also be determined by using a hierarchy analysis method.
[0039] S420: Determine the quality score of the BIM building model based on the weight ratio and the indicator score; S430: Determine whether the quality score reaches a score threshold. If the quality score reaches the score threshold, determine that the construction quality meets the expected plan.
[0040] By acquiring the point cloud data set and constructing the BIM building model based on the visualization function of the BIM system, the construction status of the real-time construction scene can be fed back in real time. By comparing the BIM building model with the simulation progress model constructed based on the construction plan parameters, it is possible to understand in real time whether the current construction progress meets the expected requirements; by performing quality assessment on the BIM building model, it is possible to understand in real time whether the current construction quality meets the expected requirements; that is, the construction management can be completed in real time, intelligently, and automatically, avoiding the low efficiency and high errors caused by manual collection of construction data, improving the efficiency of construction management, and reducing the probability of construction delays; by acquiring the corrected space coordinates and performing the simplified processing, the construction accuracy of the BIM building model can be effectively improved, and the error rate of construction management can be reduced.
[0041] See also Figure 2 The second embodiment of the present invention provides a BIM-based construction data processing system, which is applied to the BIM-based construction data processing method described in the above embodiment, and will not be repeated here. As used below, the terms "module", "unit", "sub-unit", etc. can be a combination of software and / or hardware that implements a predetermined function. Although the device described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.
[0042] The system comprises: An acquisition module 10 is used to acquire a number of corrected space coordinates corresponding to the real-time building construction scene, and simplify the number of corrected space coordinates to acquire a point cloud data set including point cloud coordinates of a number of stages; The acquisition module 10 includes: The first unit is used to plan a number of measurement points in a real-time building construction scene, and scan the measurement points by a laser scanner to obtain initial spatial coordinates of the measurement points; The second unit is used to obtain a deviation factor group based on the surface features of the real-time building construction scene, and correct the initial space coordinates by the deviation factor group to obtain a plurality of corrected space coordinates; A third unit is used for selecting one of the correction space coordinates as a reference space coordinate, and selecting a plurality of the correction space coordinates adjacent to the reference space coordinate as a plurality of reference space coordinates; a fourth unit, configured to obtain a calculated height of the reference space coordinate based on the plurality of reference space coordinates, and compare the calculated height of the reference space coordinate with an actual height of the reference space coordinate to determine whether the reference space coordinate is an error coordinate; A fifth unit, configured to remove the reference space coordinate if the reference space coordinate is the error coordinate; A sixth unit is used for selecting the reference space coordinate as the stage point cloud coordinate if the reference space coordinate is not the error coordinate, and combining a plurality of the stage point cloud coordinates into a point cloud data set; A first judgment module 20 is used to import the point cloud data set into the BIM system to obtain a BIM building model, build a simulation progress model based on the construction plan parameters, and determine whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; The first determination module 20 includes: A seventh unit is used to construct a contour model corresponding to a real-time building construction scene according to the point cloud data set based on a BIM system; An eighth unit is used to assign structural attributes and material attributes to the contour model to form a BIM building model; The ninth unit is used to compare the similarity between the BIM building model and the simulation progress model to obtain a similarity difference; The tenth unit is used to determine whether the similarity difference is less than an error threshold. If the similarity difference is less than the error threshold, it is determined that the construction progress meets the expected plan; An evaluation module 30 is used to construct a number of quality evaluation indicators adapted to the real-time building construction scene, and obtain indicator parameters corresponding to the quality evaluation indicators based on the BIM building model; A second judgment module 40 is used to compare the indicator parameter with a preset parameter to obtain an indicator score corresponding to the quality assessment indicator, determine the quality score of the BIM building model according to the indicator score, and determine whether the construction quality meets the expected plan based on the quality score; The second determination module 40 includes: The eleventh unit is used to set the weight ratios of different quality assessment indicators; A twelfth unit is used to determine the quality score of the BIM building model based on the weight ratio and the indicator score; The thirteenth unit is used to determine whether the quality score reaches a score threshold. If the quality score reaches the score threshold, it is determined that the construction quality meets the expected plan.
[0043] The present invention also provides a computer, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the BIM-based construction data processing method as described in the above technical solution is implemented.
[0044] The present invention also provides a storage medium on which a computer program is stored. When the computer program is executed by a processor, the BIM-based construction data processing method as described in the above technical solution is implemented.
[0045] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0046] The above-mentioned embodiments only express several implementation methods of the present invention, and the description thereof is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be subject to the attached claims.
Claims
1. A method for processing building construction data based on BIM, characterized in that: The following steps are involved: Acquire a number of corrected space coordinates corresponding to the real-time building construction scene, and simplify the number of corrected space coordinates to obtain a point cloud data set including point cloud coordinates of a number of stages; Importing the point cloud data set into a BIM system to obtain a BIM building model, constructing a simulation progress model based on construction plan parameters, and determining whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; Constructing several quality assessment indicators adapted to the real-time building construction scene, and acquiring indicator parameters corresponding to the quality assessment indicators based on the BIM building model; The indicator parameters are compared with preset parameters to obtain an indicator score corresponding to the quality assessment indicator, the quality score of the BIM building model is determined by the indicator score, and whether the construction quality meets the expected plan is determined based on the quality score.
2. The method for processing building construction data based on BIM according to claim 1, characterized in that: The step of obtaining a plurality of corrected space coordinates corresponding to the real-time building construction scene comprises: Planning a number of measurement points in a real-time building construction scene, and scanning the measurement points by a laser scanner to obtain initial spatial coordinates of the measurement points; A deviation factor group is obtained based on the surface features of the real-time building construction scene, and the initial space coordinates are corrected by the deviation factor group to obtain a plurality of corrected space coordinates.
3. The method for processing building construction data based on BIM according to claim 2, characterized in that: The deviation factor group includes surface defect factors, measurement error factors and external influence factors. The calculation formula of the correction space coordinates is: , in, represents the i-th correction space coordinate, represents the i-th initial space coordinate, represents the surface defect factor corresponding to the i-th initial space coordinate, represents the measurement error factor corresponding to the i-th initial space coordinate, represents the external influencing factor corresponding to the i-th initial space coordinate.
4. The method for processing building construction data based on BIM according to claim 1, characterized in that: The step of simplifying the plurality of corrected space coordinates to obtain a point cloud data set including point cloud coordinates of a plurality of stages comprises: Selecting one of the correction space coordinates as a reference space coordinate, and selecting a plurality of the correction space coordinates adjacent to the reference space coordinate as a plurality of reference space coordinates; Obtaining a calculated height of the reference space coordinate based on the plurality of reference space coordinates, and comparing the calculated height of the reference space coordinate with an actual height of the reference space coordinate to determine whether the reference space coordinate is an error coordinate; If the reference space coordinate is the error coordinate, then the reference space coordinate is eliminated; If the reference space coordinate is not the error coordinate, the reference space coordinate is selected as the stage point cloud coordinate, and a plurality of the stage point cloud coordinates are combined into a point cloud data set.
5. The method for processing building construction data based on BIM according to claim 4, characterized in that: The calculation height is obtained by the following formula: , in, represents the calculated height when the i-th correction space coordinate is the reference space coordinate, It represents the actual height when the i-th correction space coordinate is the reference space coordinate. represents the horizontal coordinate of the reference space coordinate, represents the vertical coordinate of the reference space coordinate, represents the horizontal coordinate of the jth reference space coordinate adjacent to the reference space coordinate, represents the vertical coordinate of the jth reference space coordinate adjacent to the reference space coordinate, Indicates the number of reference space coordinates adjacent to the base space coordinate. Represents a constant.
6. The method for processing building construction data based on BIM according to claim 1, characterized in that: The step of importing the point cloud data set into the BIM system to obtain the BIM building model comprises: Based on the BIM system, construct a contour model corresponding to the real-time building construction scene according to the point cloud data set; Structural attributes and material attributes are assigned to the outline model to form a BIM building model.
7. The method for processing building construction data based on BIM according to claim 1, characterized in that: The step of determining whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model includes: Comparing the BIM building model with the simulation progress model for similarity to obtain a similarity difference; It is determined whether the similarity difference is less than an error threshold. If the similarity difference is less than the error threshold, it is determined that the construction progress is in line with the expected plan.
8. The method for processing building construction data based on BIM according to claim 1, characterized in that: The steps of determining the quality score of the BIM building model by the indicator score and determining whether the construction quality meets the expected plan based on the quality score include: Setting weight ratios of different quality assessment indicators; Determine the quality score of the BIM building model based on the weight ratio and the indicator score; It is determined whether the quality score reaches a score threshold. If the quality score reaches the score threshold, it is determined that the construction quality meets the expected plan.
9. A BIM-based construction data processing system, applied to the BIM-based construction data processing method according to any one of claims 1 to 8, characterized in that: The system comprises: An acquisition module, used to acquire a number of corrected space coordinates corresponding to the real-time building construction scene, and simplify the number of corrected space coordinates to acquire a point cloud data set including point cloud coordinates of a number of stages; A first judgment module is used to import the point cloud data set into the BIM system to obtain a BIM building model, build a simulation progress model based on the construction plan parameters, and determine whether the construction progress meets the expected plan based on the BIM building model and the simulation progress model; An evaluation module, used to construct a number of quality evaluation indicators adapted to the real-time building construction scene, and to obtain indicator parameters corresponding to the quality evaluation indicators based on the BIM building model; The second judgment module is used to compare the indicator parameters with preset parameters to obtain an indicator score corresponding to the quality assessment indicator, determine the quality score of the BIM building model through the indicator score, and determine whether the construction quality meets the expected plan based on the quality score.
10. A computer comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the BIM-based construction data processing method according to any one of claims 1 to 8 is implemented.
Citation Information
Patent Citations
Building construction progress management method
CN111898990A
Point cloud data screening method, and vehicle control method and device
CN113064179A
Building construction pre-assembly method based on BIM technology
CN113112601A
Power transmission equipment safety early warning method
CN114092273A
Object shape measurement method, device and equipment and storage medium
CN114581361A
Cited By
Building construction quality evaluation processing method and system based on BIM data analysis
CN119720362A
A building construction quality assessment and processing method and system based on BIM data analysis
CN119720362B
Building supervision quality management detection method and system
CN120163496A
Water stop construction control method and system for overflow gate reinforcement project
CN120471522A
BIM modeling method and system of building model
CN121120937A