Foundation pit supporting structure and construction method thereof

By using the positioning structure of spiral steel wire and support drill rod in the SMW pile construction and combining with plastic coating, the problem of poor positioning effect of steel is solved, and the overall strength and construction efficiency of the foundation pit support structure are improved.

CN119083450APending Publication Date: 2024-12-06SINOCHEM SOUTHEAST CONSTRUCTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411341429.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-12-06

AI Technical Summary

Technical Problem

In the construction of SMW piles, the positioning effect of the steel in the cement-soil mixture is poor, which affects the overall strength and installation efficiency of the support structure.

Method used

The positioning structure including spiral steel wire and support drill rod is adopted. Through the coordination of the limiting part of the spiral steel wire and the support drill rod, the vertical positioning and guidance of the steel profile are ensured, and the surface of the steel is covered with plastic coating for easy removal.

Benefits of technology

The positioning accuracy and overall structural strength of the steel profile are improved, the installation and removal process of the steel profile is simplified, and the construction efficiency and structural strength of the supporting piles are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119083450A_ABST
    Figure CN119083450A_ABST
Patent Text Reader

Abstract

The invention discloses a foundation pit supporting structure and a construction method thereof, the foundation pit supporting structure comprises a cement pile wall and profile steel inserted in the cement pile wall, the upper end of the profile steel extends out of the top of the cement pile wall, the profile steel is sleeved with a positioning structure, the positioning structure comprises a spiral steel wire, the spiral steel wire is arranged on the profile steel in a sleeving mode, and the spiral steel wire is connected with the cement pile wall. A limiting part is arranged at the lower end of the spiral steel wire and abuts against the lower end face of the profile steel, supporting drill rods are arranged on the spiral steel wire in the length direction of the spiral steel wire at intervals, and the supporting drill rods abut against the side face of the profile steel. The two adjacent supporting drill rods are staggered by a central angle smaller than or equal to 90 degrees relative to the central line of the spiral steel wire. The positioning effect can be enhanced after the profile steel is inserted into the cement-soil mixture which is not hardened yet.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of foundation pit construction technology, and in particular to a foundation pit support structure and a construction method thereof. Background Art

[0002] SMW pile construction is one of the commonly used foundation pit support methods. The SMW method uses a multi-axis drilling and mixing machine to drill to a certain depth on site, and at the same time sprays a cement-based strengthening agent at the drill bit to repeatedly mix and stir with the foundation soil. Overlapping construction is adopted between each construction unit, and then H-shaped steel or steel plate is inserted as its stress reinforcement material before the cement-soil mixture hardens. When the cement hardens, a continuous, complete, and seamless underground wall with a certain strength and rigidity is formed.

[0003] After the steel is inserted into the cement-soil mixture that has not yet hardened, a positioning device needs to be set above the cement pile to position the steel so that the position of the steel in the cement-soil mixture remains stable. However, the positioning device set above the cement pile mainly plays a positioning role on the upper end of the steel, and the positioning effect on the overall steel is poor. Summary of the invention

[0004] In order to enhance the positioning effect of steel sections after being inserted into a cement-soil mixture that has not yet hardened, the present application provides a foundation pit support structure and a construction method thereof.

[0005] The present application provides a foundation pit support structure and a construction method thereof using the following technical solutions: A foundation pit support structure comprises a cement pile wall and a steel section inserted into the cement pile wall, wherein the upper end of the steel section extends out of the top of the cement pile wall, the steel section is sleeved with a positioning structure, the positioning structure comprises a spiral steel wire, the spiral steel wire is sleeved on the steel section, a limiting portion is provided at the lower end of the spiral steel wire, the limiting portion abuts against the lower end surface of the steel section, the spiral steel wire is provided with supporting drill rods at intervals along its own length direction, the supporting drill rods abut against the side surface of the steel section, and two adjacent supporting drill rods are staggered at a central angle of less than or 90 degrees relative to the center line of the spiral steel wire.

[0006] By adopting the above technical solution, when hoisting the steel section, the positioning structure is first installed on the steel section, and then the steel section together with the positioning structure is hoisted and inserted into the pile pit. After the steel section is installed in place, the positioning structure forms a strong positioning effect on the entire steel section, so that the center line of the steel section is kept as vertical as possible and consistent with the center line of the supporting pile, so that the overall structural strength of the supporting pile is relatively balanced, which is conducive to ensuring the supporting effect of the supporting pile. In addition, in the process of inserting the steel section into the pile pit, the spiral steel wire of the positioning structure forms a guiding effect on the process of the steel section entering the pile pit, which is conducive to reducing the adjustment work during the hoisting process of the steel section, thereby facilitating the installation efficiency of the steel section. Furthermore, after the supporting pile solidifies, the steel section is removed, and the gap in the pile body after the steel section is removed is filled with grouting. The positioning structure is left in the supporting pile, and the spiral steel wire serves as the steel reinforcement skeleton of the pile body, which is conducive to improving the structural strength of the supporting pile.

[0007] Optionally, the support drill rod gradually extends downwardly in a direction away from the spiral steel wire, and an arc-shaped guide section is provided at one end of the support drill rod away from the spiral steel wire, and the arc-shaped guide section abuts against the side surface of the steel section.

[0008] By adopting the above technical solution, the support drill rod of the positioning structure abuts against the side of the steel section, and the positioning structure is maintained on the steel section by the friction damping between the support drill rod and the steel section. In the process of hoisting the steel section into the pile pit, when the concave and convex obstacles on the inner wall of the pile pit touch the spiral steel wire, the spiral steel wire squeezes the support drill rod, causing the support drill rod to deform, thereby causing the spiral steel wire to deform to avoid the obstacle on the inner wall of the pile pit. An arc-shaped guide section is provided at the end of the support drill rod away from the spiral steel wire, so that the end of the support drill rod away from the spiral steel wire can slide relatively easily relative to the steel section.

[0009] Optionally, the supporting drill rod includes two rows of transverse drill rods and two rows of longitudinal drill rods, the two rows of transverse drill rods are symmetrical along the center line of the spiral steel wire, and the two rows of longitudinal drill rods are symmetrical along the center of the spiral steel wire; the transverse drill rod is connected to a first vertical drill rod, and the longitudinal drill rod is connected to a second vertical drill rod.

[0010] By adopting the above technical solution, two rows of transverse drill rods and two rows of longitudinal drill rods jointly press against the outer surface of the column steel section, so that the distribution of the interaction force between the steel section and the spiral steel wire is more balanced.

[0011] Optionally, the surface of the steel section is provided with a coating, which wraps the outer surface of the steel section along the circumferential direction, and the upper edge of the coating is higher than the top of the cement pile wall. The coating includes an outer coating layer and an inner coating layer, and the lower end of the inner coating layer is bonded and sealed to the surface of the steel section, and the lower end of the outer coating layer is bonded and sealed to the lower end of the inner coating layer.

[0012] By adopting the above technical solution, when the cement of the support pile solidifies and the steel section is removed and recovered, the coating separates the cement of the support pile from the outer surface of the steel section, so that the cement is not easy to form adhesion to the surface of the steel section, so that the steel section is easier to be removed from the support pile. The outer coating layer of the coating is separated from the surface of the steel section, and in the process of removing the steel section, the steel section is not easy to scratch the outer coating layer, so that the outer coating layer is easier to maintain a high integrity, so that the outer coating layer can be peeled off from the cement pile wall from which the steel section has been pulled out, and the inner coating layer can be taken out at the same time when the outer coating layer is peeled off.

[0013] Optionally, four plastic separation strips are provided on the surface of the outer film layer, two of which are used to separate the transverse drill rod and the film, and the other two are used to separate the longitudinal drill rod and the film.

[0014] By adopting the above technical solution, the plastic dividing strip separates the supporting drill rod and the coating layer. When the supporting drill rod slides relative to the surface of the steel section, the plastic dividing strip can protect the coating layer and reduce the friction and cracking of the coating layer surface.

[0015] Optionally, the surface of the plastic dividing strip is provided with two mutually parallel limiting tapes, the limiting tapes are extended along the length direction of the plastic dividing strip, the limiting tapes are bonded to the plastic dividing strip and the coating at the same time, and the two limiting tapes and the surface of the plastic dividing strip form a sliding area for the supporting drill rod to slide.

[0016] By adopting the above technical solution, when the support drill rod slides along the surface of the plastic dividing strip, the two limiting tapes can guide and limit the support drill rod, so that the end of the support drill rod is not easy to leave the surface of the plastic dividing strip.

[0017] Optionally, the inner coating layer is bonded to the outer surface of the steel section via patchy glue dots at intervals, and the outer coating layer is bonded to the inner coating layer via patchy glue dots at intervals.

[0018] By adopting the above technical solution, the inner coating layer and the surface of the steel section are bonded by patchy glue spots, which can reduce the resistance when the steel section surface and the coating layer are separated.

[0019] Optionally, the outer surface of the outer covering layer is coated with a concrete release agent layer.

[0020] By adopting the above technical solution, after the steel section is pulled out from the supporting pile, the coating layer is continuously peeled off from the supporting pile. By coating a concrete release agent on the outer surface of the outer coating layer, the resistance of the coating layer to be peeled off from the concrete of the supporting pile can be reduced.

[0021] Optionally, the coating layer is provided with a winding tape, and a winding wire is provided between the winding tape and the coating layer, and the winding wire extends to the top of the steel section.

[0022] By adopting the above technical solution, after the steel section is pulled out and recovered from the cement pile wall, the coating can be more easily peeled off from the cement pile wall from which the steel section has been pulled out by pulling the wrapping tape and using the wrapping tape to pull the coating. Furthermore, by pulling and stretching the wrapping wire, the wrapping wire is straightened to cut the bonding surface between the outer coating layer and the inner surface of the cement pile wall, so that the outer coating layer is more easily peeled off from the inner surface of the cement pile wall.

[0023] A construction method for a foundation pit support structure comprises the following steps: stakeout, staking out the position of a positioning steel section with the pile position coordinates and marking it; excavating a guide groove along the center line of the supporting pile by using an excavator; putting the pile driver in place to perform a mixing and sinking operation on the supporting pile; after the mixing is completed and the drill rod is pulled out, the pile driver moves horizontally to the next pile position to leave a working surface for inserting the steel section; vertically arranging the spiral steel wire of the positioning structure above the cement pile, raising the bottom of the positioning structure, and temporarily positioning the spiral steel wire; hoisting the steel section and slowly inserting it into the spiral steel wire so that the supporting drill rod is pressed against the surface of the steel section; when the lower end of the steel section abuts against the limiting part at the lower end of the spiral steel wire, removing the raising component, hoisting the steel section together with the spiral steel wire into the pile hole; slowly inserting the steel section together with the positioning structure into the pile hole.

[0024] By adopting the above technical scheme, before lifting the steel section, the spiral steel wire is directly raised by the raising component and placed above the cement pile. After the steel section is inserted into the inside of the spiral steel wire, it can be directly and continuously lifted downward in the vertical direction and inserted into the cement pile, which is beneficial to ensure the continuity of the steel section lifting action.

[0025] In summary, the present application includes at least one of the following beneficial technical effects: 1. After the steel is installed in place, the positioning structure has a strong positioning effect on the steel as a whole, so that the center line of the steel is kept as vertical as possible, so that the overall structural strength of the support pile is relatively balanced, which is conducive to ensuring the support effect of the support pile. After the support pile solidifies, the positioning structure remains in the support pile, and the spiral steel wire serves as the steel skeleton of the pile body, which is conducive to improving the structural strength of the support pile.

[0026] 2. When the cement of the supporting pile solidifies and the steel section is removed and recovered, the coating separates the cement of the supporting pile from the outer surface of the steel section, making it difficult for the cement to form adhesion to the surface of the steel section, making it easier to remove the steel section from the supporting pile.

[0027] 3. The plastic dividing strip separates the supporting drill rod and the coating layer. When the supporting drill rod slides relative to the surface of the steel section, the plastic dividing strip can protect the coating layer and reduce the friction and cracking of the coating layer surface. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a schematic diagram of the foundation pit supporting structure of this embodiment.

[0029] Figure 2 It is a schematic diagram of the present embodiment for illustrating the positional relationship between the positioning structure and the steel section.

[0030] Figure 3 Schematic diagram of the cross section of the steel section of this embodiment.

[0031] Figure 4 It is a schematic diagram of the present embodiment for illustrating the positional relationship between the wrapping tape and the plastic separating tape.

[0032] Figure 5 It is a flow chart of the construction method of the foundation pit support structure of this embodiment.

[0033] Description of reference numerals: 1. Cement pile wall; 2. Steel section; 3. Positioning structure; 31. Spiral steel wire; 311. Limiting part; 32. Support drill rod; 321. Arc-shaped guide section; 3201. Horizontal drill rod; 3202. Longitudinal drill rod; 33. First vertical drill rod; 34. Second vertical drill rod; 4. Coating; 41. Outer coating layer; 42. Inner coating layer; 43. Wrapping tape; 44. Wrapping silk thread; 45. Plastic dividing tape; 46. Limiting tape; 461. Guide section. DETAILED DESCRIPTION

[0034] The following is combined with Figure 1-5 This application is described in further detail.

[0035] The present application embodiment discloses a foundation pit support structure. Figure 1 and Figure 2 The foundation pit support structure includes a cement pile wall 1 and a steel section 2 inserted in the cement pile wall 1. The steel section 2 in this embodiment is specifically selected from H-shaped steel 2. The upper end of the steel section 2 extends out of the top of the cement pile wall 1. The steel section 2 is sleeved with a positioning structure 3. The positioning structure 3 includes a spiral steel wire 31. The wire diameter of the spiral steel wire 31 is 3-5mm. The spiral steel wire 31 is sleeved on the steel section 2. The lower end of the spiral steel wire 31 is provided with a limiting portion 311. The limiting portion 311 abuts against the lower end surface of the steel section 2. The spiral steel wire 31 is spaced apart along its own length direction. The supporting drill rod 32 is a steel drill. The wire diameter of the supporting drill rod 32 is consistent with that of the spiral steel wire 31, and the supporting drill rod 32 abuts against the side of the steel section 2.

[0036] When the cement pile wall 1 has not yet solidified, the positioning structure 3 can keep the center line of the steel section 2 consistent with the center line of the cement pile wall 1 as much as possible, which is beneficial to ensure the strength of the supporting structure after solidification.

[0037] Reference Figure 2 The two adjacent supporting drill rods 32 are staggered at an angle of 90 degrees relative to the center line of the spiral steel wire 31. The supporting drill rods 32 include two rows of transverse drill rods 3201 and two rows of longitudinal drill rods 3202. The two rows of transverse drill rods 3201 are symmetrical along the center line of the spiral steel wire 31, and the two rows of longitudinal drill rods 3202 are symmetrical along the center of the spiral steel wire 31; the transverse drill rod 3201 is connected to the first vertical drill rod 33, and the longitudinal drill rod 3202 is connected to the second vertical drill rod 34.

[0038] Reference Figure 2 The support drill rod 32 gradually extends downward in a direction away from the spiral steel wire 31 . An arc-shaped guide section 321 is provided at one end of the support drill rod 32 away from the spiral steel wire 31 . The arc-shaped guide section 321 abuts against the side surface of the section steel 2 .

[0039] During the process of hoisting and installing the steel section 2 , the support drill rod 32 abuts against the surface of the steel section 2 through the arc-shaped guide section 321 , which can reduce the resistance of the steel section 2 inserted into the inner side of the spiral steel wire 31 .

[0040] Reference Figure 3 The surface of the steel 2 is provided with a coating 4, which wraps the outer surface of the steel 2 in the circumferential direction, and the upper edge of the coating 4 is higher than the top of the cement pile wall 1. The coating 4 includes an outer coating layer 41 and an inner coating layer 42, both of which are plastic films. The inner coating layer 42 is bonded to the outer surface of the steel 2 at intervals by patchy glue dots, and the lower end of the inner coating layer 42 is bonded and sealed to the surface of the steel 2; the outer coating layer 41 and the inner coating layer 42 are bonded at intervals by patchy glue dots, and the lower end of the outer coating layer 41 is bonded and sealed to the lower end of the inner coating layer 42. The outer surface of the outer coating layer 41 is coated with a concrete release agent layer.

[0041] When the cement of the support pile solidifies and the steel 2 is removed and recovered, the coating 4 separates the cement of the support pile from the outer surface of the steel 2, so that the cement is not easy to form adhesion to the surface of the steel 2, so that the steel 2 is easier to be removed from the support pile. After the steel 2 is removed, the coating 4 is continuously peeled off from the cement pile wall 1 from which the steel 2 is removed. The outer coating layer 41 of the coating 4 is separated from the surface of the steel 2. In the process of removing the steel 2, the outer coating layer 41 is not easy to be scratched by the steel 2, so that the outer coating layer 41 is easier to maintain a high integrity, so as to facilitate the peeling of the outer coating layer 41 from the cement pile wall 1 from which the steel 2 is removed.

[0042] Reference Figure 4In order to make the coating 4 easier to peel off from the cement pile wall 1 after the steel section 2 is removed, a wrapping tape 43 is provided on the coating 4 layer, and a wrapping wire 44 is provided between the wrapping tape 43 and the coating 4 layer, and the wrapping wire 44 extends to the top of the steel section 2. In the process of peeling off the coating 4, the wrapping wire 44 is pulled and stretched, so that the wrapping wire 44 is straightened and cuts the bonding surface between the outer coating layer 41 and the cement pile wall 1, so that the outer coating layer 41 is easier to peel off from the cement pile wall 1.

[0043] Reference Figure 3 and Figure 4 The surface of the outer film layer 41 is provided with four plastic separation strips 45, of which two plastic separation strips 45 are used to separate the transverse drill rod 3201 and the film 4, and the other two plastic separation strips 45 are used to separate the longitudinal drill rod 3202 and the film 4. The surface of the plastic separation strip 45 is provided with two mutually parallel limiting tapes 46, which extend along the length direction of the plastic separation strip 45, and the limiting tapes 46 are bonded to the plastic separation strip 45 and the film 4 at the same time. The two limiting tapes 46 and the surface of the plastic separation strip 45 form a sliding area for supporting the drill rod 32 to slide. The lower end of the limiting tape 46 is provided with a guide section 461, and the guide sections 461 of the two limiting tapes 46 gradually move away from each other from bottom to top.

[0044] During the process of inserting the steel section 2 into the spiral steel wire 31 , the guide section 461 of the limiting tape 46 guides the support drill rod 32 into the sliding area, and the support drill rod 32 slides along the surface of the plastic dividing strip 45 , which can reduce the situation where the support drill rod 32 scratches the coating 4 .

[0045] The implementation principle of a foundation pit support structure of the embodiment of the present application is as follows: during the construction of the foundation pit support structure, when the steel section 2 is hoisted and inserted into the cement mixture that has not yet hardened, the positioning structure 3 forms a strong positioning effect on the steel section 2 as a whole, so that the center line of the steel section 2 is kept as vertical as possible and consistent with the center line of the support pile, so that the overall structural strength of the support pile is relatively balanced, which is conducive to ensuring the support effect of the support pile. In addition, during the insertion of the steel section 2 into the pile pit, the spiral steel wire 31 of the positioning structure 3 forms a guiding effect on the process of the steel section 2 entering the pile pit, which is conducive to reducing the adjustment work during the hoisting process of the steel section 2, thereby facilitating the improvement of the installation efficiency of the steel section 2. Furthermore, after the support pile solidifies, the steel section 2 is removed, and the pile body gap after the steel section 2 is removed is filled with grouting. The positioning structure 3 is left in the support pile, and the spiral steel wire 31 serves as the steel reinforcement skeleton of the pile body, which is conducive to improving the structural strength of the support pile.

[0046] This embodiment also discloses a construction method of a foundation pit support structure, comprising the following steps: Step 1, according to the pile position coordinates, use a total station or GPS surveying instrument to carry out pile position setting, use the pile position coordinates to release the position of the positioning steel 2 outwards, and mark it; Step 2: Use an excavator to level the site and ensure that the walking path is within the operating range of the pile driver and that conditions for traffic and construction are met; Step 3: Use an excavator to dig a guide groove along the center line of the support pile and remove underground obstacles. The width of both sides of the center line should be 0.6m and the depth should be 0.5-0.7m. Step 4: After the pile driver is in place and the cement slurry can be supplied normally, the mixing and sinking operation of the supporting piles is started; spraying, mixing and lifting are carried out: after the deep mixer sinks to the designed depth, the mortar pump is turned on, and the slurry reaches the spraying port, and then the deep mixer is lifted while spraying at the lifting speed determined by the design; repeated mixing and sinking, repeated mixing and lifting: after the first spraying and mixing is lifted to the designed elevation of the pile top, the repeated mixing and sinking and repeated mixing and lifting are carried out once, and the spraying is carried out according to the designed cement content requirements; after the mixing is completed and the drill rod is pulled out, the machine moves horizontally to the next pile position, leaving the plug-in steel 2 working surface; Step 5, vertically erect the spiral steel wire 31 of the positioning structure 3 above the cement pile, and raise the bottom of the positioning structure 3 with a raising component, which is a wooden beam or a channel steel, to temporarily position the spiral steel wire 31; use the lifting equipment to lift the steel section 2, and slowly put it into the spiral steel wire 31, so that the support drill rod 32 is pressed against the surface of the steel section 2; when the lower end of the steel section 2 abuts against the limiting part 311 at the lower end of the spiral steel wire 31, remove the raising component, and lift the steel section 2 together with the spiral steel wire 31 and insert it into the cement pile wall 1 that has not yet solidified; Step 6, grouting is performed to fill the void in the pile body after the steel section 2 is removed; parameters such as grouting material, grouting pressure and grouting amount are determined according to design requirements.

[0047] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A foundation pit support structure, Features: The invention comprises a cement pile wall (1) and a steel section (2) inserted into the cement pile wall (1), wherein the upper end of the steel section (2) extends out of the top of the cement pile wall (1), the steel section (2) is sleeved with a positioning structure (3), the positioning structure (3) comprises a spiral steel wire (31), the spiral steel wire (31) is sleeved on the steel section (2), a limiting portion (311) is provided at the lower end of the spiral steel wire (31), the limiting portion (311) abuts against the lower end surface of the steel section (2), the spiral steel wire (31) is provided with supporting drill rods (32) at intervals along its length direction, the supporting drill rods (32) abut against the side surface of the steel section (2), and two adjacent supporting drill rods (32) are staggered at a central angle of less than or equal to 90 degrees relative to the central line of the spiral steel wire (31).

2. A foundation pit support structure according to claim 1, Features: The support drill rod (32) gradually extends downwardly at an angle in a direction away from the spiral steel wire (31); an arc-shaped guide section (321) is provided at one end of the support drill rod (32) away from the spiral steel wire (31); the arc-shaped guide section (321) abuts against a side surface of the section steel (2).

3. A foundation pit support structure according to claim 1, Features: The supporting drill rods (32) comprise two rows of transverse drill rods (3201) and two rows of longitudinal drill rods (3202); the two rows of transverse drill rods (3201) are symmetrical along the center line of the spiral steel wire (31); and the two rows of longitudinal drill rods (3202) are symmetrical along the center of the spiral steel wire (31); the transverse drill rods (3201) are connected to the first vertical drill rods (33), and the longitudinal drill rods (3202) are connected to the second vertical drill rods (34).

4. A foundation pit support structure according to claim 3, Features: The surface of the steel section (2) is provided with a coating (4), the coating (4) wrapping the outer surface of the steel section (2) in the circumferential direction, the upper edge of the coating (4) being higher than the top of the cement pile wall (1), the coating (4) comprising an outer coating layer (41) and an inner coating layer (42), the lower end of the inner coating layer (42) being bonded and sealed to the surface of the steel section (2), and the lower end of the outer coating layer (41) being bonded and sealed to the lower end of the inner coating layer (42).

5. A foundation pit support structure according to claim 4, Features: The surface of the outer film layer (41) is provided with four plastic separation strips (45), two of which are used to separate the transverse drill rod (3201) and the film (4), and the other two are used to separate the longitudinal drill rod (3202) and the film (4).

6. A foundation pit support structure according to claim 5, Features: The surface of the plastic dividing strip (45) is provided with two mutually parallel limiting tapes (46), the limiting tapes (46) extending along the length direction of the plastic dividing strip (45), the limiting tapes (46) simultaneously bonding the plastic dividing strip (45) and the coating (4), the two limiting tapes (46) and the surface of the plastic dividing strip (45) forming a sliding area for the supporting drill rod (32) to slide.

7. A foundation pit support structure according to claim 4, Features: The inner coating layer (42) is bonded to the outer surface of the steel section (2) at intervals by means of patchy glue dots, and the outer coating layer (41) is bonded to the inner coating layer (42) at intervals by means of patchy glue dots.

8. A foundation pit support structure according to claim 4, Features: The outer surface of the outer coating layer (41) is coated with a concrete release agent layer.

9. A foundation pit support structure according to claim 4, Features: The coating (4) layer is provided with a winding tape (43), and a winding wire (44) is provided between the winding tape (43) and the coating (4) layer, and the winding wire (44) extends to the top of the steel section (2).

10. A construction method for a foundation pit support structure according to any one of claims 1 to 9, It is characterized in that The steps include: Stake out the pile position, lay out the position of the positioning steel (2) outwards according to the pile position coordinates, and mark them; Along the center line of the support piles, use an excavator to dig the guide trench; The pile driver is in place to mix and sink the supporting piles. After the mixing is completed and the drill rod is pulled out, the pile driver moves horizontally to the next pile position, leaving a working surface for the steel insert (2). The spiral steel wire (31) of the positioning structure (3) is vertically erected above the cement pile, the bottom of the positioning structure (3) is padded, and the spiral steel wire (31) is temporarily positioned; the steel section (2) is hoisted and slowly placed into the spiral steel wire (31), so that the supporting drill rod (32) is pressed against the surface of the steel section (2); when the lower end of the steel section (2) abuts against the limiting portion (311) at the lower end of the spiral steel wire (31), the padded component is removed, and the steel section (2) and the spiral steel wire (31) are hoisted and placed into the pile hole; Slowly insert the steel section (2) together with the positioning structure (3) into the pile hole.