Method and device for determining switch in power distribution network, storage medium, processor and program product
By acquiring and verifying the operating data of switches in the distribution network, the operating status of switches in the distribution network is accurately determined, the misjudgment problem caused by signal instability is solved, and the accuracy of data processing is improved.
Patent Information
- Application Number
- CN202411186152.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-27
- Publication Date
- 2024-12-06
AI Technical Summary
In the distribution network, there is a problem of signal instability in determining the operation status of the switch, which makes it impossible to accurately determine the operation status of the switch.
By obtaining the first running data of the branch switch to be verified and the second running data of the main switch, the data are used to verify the changed operating status of the branch switch to be verified, and its actual running status is determined, thereby accurately determining the operating status of the switch.
It realizes accurate determination of the operating status of the distribution network switch, solves the problem of misjudgment caused by signal instability, and improves data automation processing capabilities.
Smart Images

Figure CN119093345A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of power systems, and in particular to a method, device, storage medium, processor and program product for determining switches in a distribution network. Background Art
[0002] At present, in order to determine the operating status of switches in a distribution network, a collection device is usually installed on each switch, and the operating data of the auxiliary node at the switch position is directly collected through the collection device to determine the operating status of the switch node. However, the auxiliary contacts of the collection device have poor contact and jitter, which makes the signal collected by the collection device unstable, which leads to the technical problem that the operating status of the switch cannot be accurately determined.
[0003] To address the above-mentioned problems, no effective solution has been proposed yet. Summary of the invention
[0004] Embodiments of the present invention provide a method, device, storage medium, processor, and program product for determining a switch in a distribution network, so as to at least solve the technical problem that the operating status of a switch cannot be accurately determined.
[0005] According to one aspect of an embodiment of the present invention, a method for determining a switch in a distribution network is provided, the method may include: determining the operating status of at least one switch in the distribution network; determining, in the at least one switch, at least one branch switch to be verified whose operating status has changed; obtaining first operating data of the branch switch to be verified, and second operating data of the main switch in the at least one switch; using the first operating data and the second operating data, verifying the operating status of the branch switch to be verified after the change, and obtaining a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in the at least one branch switch to be verified, determining a target branch switch whose actual operating status after the change is a target operating status.
[0006] Optionally, obtaining the first operating data of the branch switch to be verified includes: before the operating state of the branch switch to be verified changes, collecting the first operating data of the branch switch to be verified, wherein the first operating data at least includes multiple first active powers and multiple first phase currents of the branch switch to be verified; obtaining the second operating data of the main switch in at least one switch includes: within a target time period, collecting the second operating data of the main switch, wherein the second operating data at least includes multiple second active powers and multiple second phase currents, and the target time period is the time period before the operating state changes.
[0007] Optionally, the first operating data and the second operating data are used to verify the operating state of the branch switch to be verified after the change, and a verification result is obtained, including: determining the first active power collected last among multiple first active powers as the first target active power of the branch switch to be verified; determining the first phase current collected last among multiple first phase currents as the first target phase current of the branch switch to be verified; determining the second active power collected last among multiple second active powers as the second target active power of the main switch; determining the second phase current collected last among multiple second phase currents as the second target phase current of the main switch; using the first target active power, the first target phase current, the second target active power and the second target phase current to verify the changed operating state and obtain a verification result.
[0008] Optionally, the changed operating state is verified using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result, including: in response to the number of branch switches to be verified being greater than a number threshold, determining the sum of multiple first target active powers of multiple branch switches to be verified, and the sum of multiple first target phase currents of multiple branch switches to be verified; using the second target active power, converting the sum of multiple first target active powers to obtain the active power to be verified, and using the second target phase current, converting the sum of multiple first target phase currents to obtain the phase current to be verified; using the power threshold to verify the active power to be verified, and using the current threshold to verify the phase current to be verified, to obtain a verification result.
[0009] Optionally, the changed operating state is verified using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result, including: in response to the number of branch switches to be verified being not greater than a quantity threshold, the first target active power is converted using the second target active power to obtain the active power to be verified, and the first target phase current is converted using the second target phase current to obtain the phase current to be verified; the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold to obtain a verification result.
[0010] Optionally, the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold, to obtain a verification result, including: in response to the active power to be verified being greater than the power threshold, and the phase current to be verified being greater than the current threshold, determining the difference between two adjacent second active powers among a plurality of second active powers; in response to the absolute value of the difference between the two second active powers satisfying a first numerical range, determining the difference between two adjacent second phase currents among a plurality of second phase currents, wherein the first numerical range is associated with the first target active power; in response to the absolute value of the difference between the two second phase currents satisfying a second numerical range, determining the verification result as a first verification result, wherein the first verification result is used to characterize that the operating state of the branch switch to be verified is changed to a target operating state, and the second numerical range is associated with the first phase current.
[0011] Optionally, the method may also include: in response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, and the number of branch switches to be verified is greater than a quantity threshold, using the second target active power to convert multiple first target active powers of multiple branch switches to be verified respectively to obtain multiple active powers to be verified, and using the second target phase current to convert multiple first target phase currents of multiple branch switches to be verified to obtain multiple phase currents to be verified.
[0012] Optionally, the method may further include: in response to the absolute value of the difference between the two second phase currents not satisfying the second numerical range, determining that the verification result is a second verification result, wherein the second verification result is used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state.
[0013] Optionally, the method may further include: using the second verification result to trigger the collection of the first operation data and the second operation data; and using the re-collected first operation data and the second operation data to verify the operation status of the branch switch to be verified.
[0014] According to another aspect of an embodiment of the present invention, a device for determining a switch in a distribution network is also provided, and the device may include: a first determination unit, used to determine the operating status of at least one switch in the distribution network; a second determination unit, used to determine at least one branch switch to be verified whose operating status has changed in at least one switch; an acquisition unit, used to acquire first operating data of the branch switch to be verified, and second operating data of the main switch in at least one switch, wherein the second operating data is associated with the opening and closing status of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the opening and closing status of the line; a verification unit, used to verify the operating status of the branch switch to be verified after the change by using the first operating data and the second operating data, and obtain a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; a third determination unit, used to determine, based on the verification result, in at least one branch switch to be verified, a target branch switch whose actual operating status after the change is the target operating status.
[0015] According to another aspect of an embodiment of the present invention, a computer-readable storage medium is further provided, which includes a stored program, wherein when the program is running, the device where the computer-readable storage medium is located is controlled to execute the method for determining switches in the distribution network of an embodiment of the present invention.
[0016] According to another aspect of an embodiment of the present invention, a processor is further provided. The processor is used to run a program. When the program is run by the processor, the method for determining a switch in a distribution network according to an embodiment of the present invention is executed.
[0017] According to another aspect of an embodiment of the present invention, a program product is further provided. The program product includes computer instructions. When the computer instructions are executed by a processor, the method for determining a switch in a distribution network according to an embodiment of the present invention is implemented.
[0018] In an embodiment of the present invention, the operating state of at least one switch in the distribution network is determined; in at least one switch, at least one branch switch to be verified whose operating state has changed is determined; first operating data of the branch switch to be verified and second operating data of the main switch in at least one switch are obtained; the operating state of the branch switch to be verified after the change is verified is verified by using the first operating data and the second operating data to obtain a verification result, wherein the verification result is used to characterize the actual operating state of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, the target branch switch whose actual operating state after the change is the target operating state is determined. That is, in an embodiment of the present invention, the operating state of at least one switch is determined, based on the operating state of at least one switch, the branch switch to be verified whose operating state has changed is determined, the first operating data of the branch switch to be verified and the second operating data of the main switch are obtained, the first operating data is verified by using the second operating data to obtain the verification result, and the actual operating state of the branch switch to be verified can be determined based on the verification result, thereby achieving the technical effect of accurately determining the operating state of the switch and solving the technical problem that the operating state of the switch cannot be accurately determined. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0020] Figure 1 is a flow chart of a method for determining a switch in a distribution network according to an embodiment of the present invention;
[0021] Figure 2 is a flow chart of a method for verifying a change in the operating state of a switch node in a low-voltage distribution network according to an embodiment of the present invention;
[0022] Figure 3 is a schematic diagram of a device for determining a switch in a distribution network according to an embodiment of the present invention;
[0023] Figure 4 is a structural block diagram of a computer terminal according to an embodiment of the present invention;
[0024] Figure 5 It is a block diagram of an electronic device for a method for determining a switch in a distribution network according to an embodiment of the present application. DETAILED DESCRIPTION
[0025] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0026] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0027] According to an embodiment of the present invention, an embodiment of a method for determining switches in a distribution network is provided, and the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and, although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0028] In this embodiment, a method for determining switches in a distribution network is proposed. The method can determine the operating status of at least one switch, determine the branch switch to be verified whose operating status has changed based on the operating status of at least one switch, obtain first operating data of the branch switch to be verified, and second operating data of the main switch, and verify the first operating data using the second operating data to obtain a verification result. Based on the verification result, the actual operating status of the branch switch to be verified can be determined, thereby achieving the technical effect of accurately determining the operating status of the switch and solving the technical problem of being unable to accurately determine the operating status of the switch.
[0029] Figure 1 is a flow chart of a method for determining a switch in a distribution network according to an embodiment of the present invention. Figure 1 As shown, the method may include the following steps:
[0030] Step S102, determining the operating status of at least one switch in the distribution network.
[0031] In the technical solution provided in the above step S102 of the present invention, the above distribution network can be a low-voltage distribution network, which can refer to the power transmission system from the substation or power station to the user, and can be used to distribute high-voltage electric energy to the end user after transformation, transmission, and re-transformation. The above switch can be a switch node in the distribution network, which can be a device used to control the on and off of the circuit in the distribution network, which can be manually operated or automatically controlled, and can be used to protect circuits and equipment, as well as to realize the control and automation of circuits, and can include a main switch and / or a branch switch on a branch line, for example, a low-voltage switch, an air switch, etc. It should be noted that this is only an example, and there is no specific restriction on the type of switch. The above operating state can be the real-time operating state of the switch, which can include opening and closing the turntable, or can include a gate opening or closing state. It should be noted that there is no specific restriction on the name of the operating state, and the name of the operating state can be selected and changed according to the actual situation.
[0032] Optionally, the operating status of at least one switch in the distribution network can be determined by acquiring a signal emitted by an electric meter. For example, the operating status of switch one can be determined to be an open state or a closed state by the voltage, current and other signals emitted by the electric meter installed on switch one or by the power status of the electric meter.
[0033] For example, the operating state of at least one switch can be collected by a switch state collection device to determine the operating state of each switch in the distribution network at multiple times. The switch state collection devices of different switches can be the same or different. For example, when a terminal (e.g., a gateway) receives switch position information sent by the switch state collection device, the operating state of the switch can be determined by the switch position information.
[0034] Step S104: determining, in at least one switch, at least one branch switch to be verified whose operating status has changed.
[0035] In the technical solution provided in step S104 of the present invention, the operating state of each switch in at least one switch is judged respectively, and the branch switch whose operating state has changed is determined as the branch switch to be verified, thereby obtaining at least one branch switch to be verified. The branch switch to be verified may be a branch switch whose operating state has changed, or may be a position switch.
[0036] Optionally, the operating status of at least one switch in the distribution network at multiple times is determined. If the operating status of a branch switch changes from a closed state to an open state (or can be called a tripped state), the branch switch can be determined as a branch switch to be verified, thereby obtaining at least one branch switch to be verified.
[0037] Due to the instability of the communication between the terminal and the electric meter, when the communication interruption time between the terminal and the electric meter exceeds the set value, the electric meter will be misjudged as not energized, resulting in the output of an erroneous signal that the operating state of the switch has changed to the open state, causing the switch position signal to jitter, making it impossible to accurately obtain the correct information at the position of the switch, resulting in the inability to accurately determine the operating state of the switch. Therefore, in this embodiment, the operating state of at least one switch is determined, and based on the operating state, at least one branch switch to be verified is preliminarily judged to have changed its operating state from the closed state to the open state in at least one switch, and at least one branch switch to be verified is further verified, so as to achieve the purpose of accurately determining the operating state of the branch switch. The verification method of the branch switch to be verified is further described below.
[0038] Step S106, obtaining first operating data of the branch switch to be verified and second operating data of the main switch in at least one switch, wherein the second operating data is associated with the opening and closing state of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the opening and closing state of the line.
[0039] In the technical solution provided in the above step S106 of the present invention, since there is a correlation between the second operating data of the main switch in at least one switch and the opening and closing state of the line in which the branch switch to be verified is located, the second operating data of the main switch can be used to further judge the operating state of the switch to be verified.
[0040] Optionally, the first operating data of the branch switch to be verified and the second operating data of the main switch in at least one switch are obtained. The first operating data can be used to determine the operating status of the branch switch to be verified, and can be the real-time operating data of the branch switch to be verified, and can include the voltage (P), current (I), active power (P), reactive power (Q), etc. of the verified branch switch. The second operating data can be used to determine the operating status of the main switch, and can be the real-time operating data of the main switch, and can include the voltage (P), current (I), active power (P), reactive power (Q), etc. of the verified branch switch. It should be noted that this is only an example, and there is no specific limitation on the types of the first operating data and the second operating data.
[0041] For example, the first operating data of the branch switch to be verified and the second operating data of the main switch in at least one switch can be obtained through the electric meter. For example, a collection device can be installed at the low-voltage main switch of the substation to obtain the second operating data of the main switch. The collection device can communicate with the terminal (gateway) through a broadband carrier or other communication medium, and send the real-time value of the second operating data of the main switch to the terminal (gateway) in real time. The terminal (gateway) can dynamically save the second operating data of the main switch, one point per minute, and the saving time can be the last 15 minutes; at the same time, the first operating data of each branch switch can be dynamically saved. It should be noted that this is only an example, and there is no specific restriction on the method of obtaining the first operating data and the second operating data, as well as the collection time.
[0042] Step S108, using the first operation data and the second operation data, verifying the operation status of the branch switch to be verified after the change, and obtaining a verification result, wherein the verification result is used to characterize the actual operation status of the branch switch to be verified after the change.
[0043] In the technical solution provided in the above step S108 of the present invention, after obtaining the first operation data and the second operation data, the first operation data and the second operation data can be used to further verify the operation state of the branch switch to be verified after the change, so as to obtain a verification result, and the verification result can be used to determine the actual operation state of the branch switch to be verified after the change. The above actual operation state can be used to determine whether the branch switch to be verified is in a disconnected state.
[0044] For example, when the state change information of a branch switch is obtained, it can be determined that the operating state of the branch switch has changed. Further, the first operating data of the branch switch to be verified and the second operating data of the main switch in at least one switch can be obtained. By comparing the first operating data and the second operating data, the operating state of the branch switch to be verified after the change can be verified to obtain a verification result. Based on the verification result, it can be determined whether the operating state of the branch switch to be verified has really changed, thereby achieving the purpose of accurately determining the operating state of the branch switch. It should be noted that the method of using the first operating data and the second operating data to verify the operating state of the branch switch to be verified after the change is not specifically limited. As long as it is based on the first operating data and the second operating data, the method of determining the operating state should be within the protection scope of this application.
[0045] Step S110 , based on the verification result, determining a target branch switch whose actual operating state after the change is the target operating state in at least one branch switch to be verified.
[0046] In the technical solution provided in step S110 of the present invention, based on the verification result, it can be determined that in at least one branch switch to be verified, the actual operating state after the change is the target branch switch of the target operating state. The target operating state can be the open (or disconnected) state.
[0047] In this embodiment, the change in the second operating data of the main switch (for example, active power and current) is compared and analyzed with the first operating data of the branch switch to verify the collected switch displacement information of the branch switch to be verified, and a verification result is obtained. Based on the verification result, it can be determined that the actual operating state is indeed changed to the target branch switch in the open state, thereby improving the quality of the determined low-voltage switch state information and achieving the purpose of improving the data automation processing capability, thereby solving the technical problem of being unable to accurately determine the operating state of the switch and achieving the technical effect of accurately determining the operating state of the switch.
[0048] Through the above-mentioned step S102 and step S110 of the present invention, the operating state of at least one switch in the distribution network is determined; in at least one switch, at least one branch switch to be verified whose operating state has changed is determined; the first operating data of the branch switch to be verified and the second operating data of the main switch in at least one switch are obtained; the operating state of the branch switch to be verified after the change is verified is verified by using the first operating data and the second operating data to obtain a verification result, wherein the verification result is used to characterize the actual operating state of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, the target branch switch whose actual operating state after the change is the target operating state is determined. That is, in the embodiment of the present invention, the operating state of at least one switch is determined, based on the operating state of at least one switch, the branch switch to be verified whose operating state has changed is determined, the first operating data of the branch switch to be verified and the second operating data of the main switch are obtained, the first operating data is used to verify the first operating data to obtain the verification result, and based on the verification result, the actual operating state of the branch switch to be verified can be determined, thereby achieving the technical effect of accurately determining the operating state of the switch and solving the technical problem that the operating state of the switch cannot be accurately determined.
[0049] The above method of this embodiment is further introduced below.
[0050] As an optional implementation, step S106, obtaining the first operating data of the branch switch to be verified, includes: before the operating state of the branch switch to be verified changes, collecting the first operating data of the branch switch to be verified, wherein the first operating data at least includes multiple first active powers and multiple first phase currents of the branch switch to be verified; obtaining the second operating data of the main switch in at least one switch, includes: within a target time period, collecting the second operating data of the main switch, wherein the second operating data at least includes multiple second active powers and multiple second phase currents, and the target time period is the time period before the operating state changes.
[0051] In this embodiment, before the operating state of the branch switch to be verified changes, the first operating data of the branch switch to be verified can be collected to obtain multiple first operating data corresponding to the branch switch to be verified at multiple times; within the target time period, the second operating data of the main switch can be collected to obtain multiple second operating data corresponding to multiple times in the target time period. Among them, the above-mentioned first operating data can at least include multiple first active powers and multiple first phase currents corresponding to the branch switch to be verified at multiple times. The second operating data can at least include the second active power and the second phase current corresponding to multiple times. The above-mentioned target time can be a pre-set time period, for example, it can be 15 minutes, 2 minutes, 1 minute, etc. It should be noted that there is no specific restriction on the size of the target time period here.
[0052] Optionally, the first operating data of the branch switch to be verified and the second operating data of the main switch can be collected in real time. The first operating data may include the first active power and the first phase current of the branch switch to be verified at multiple times. The second operating data may include the second active power and the second phase current of the main switch at multiple times.
[0053] For example, a collection device can be installed at the low-voltage main switch of the substation to obtain the second operating data of the main switch. The collection device can communicate with the terminal (gateway) through a broadband carrier or other communication medium, and send the real-time value of the second operating data of the above main switch to the terminal (gateway) in real time. Or the terminal (gateway) can dynamically save the second operating data of the main switch, one point per minute, and the target period for saving can be the last 15 minutes; at the same time, the first operating data of each branch switch to be verified can be dynamically saved.
[0054] As an optional implementation, step S108, using the first operating data and the second operating data, verifies the operating state of the branch switch to be verified after the change, and obtains a verification result, including: determining the first active power collected last among multiple first active powers as the first target active power of the branch switch to be verified; determining the first phase current collected last among multiple first phase currents as the first target phase current of the branch switch to be verified; determining the second active power collected last among multiple second active powers as the second target active power of the main switch; determining the second phase current collected last among multiple second phase currents as the second target phase current of the main switch; using the first target active power, the first target phase current, the second target active power and the second target phase current to verify the changed operating state and obtain a verification result.
[0055] In this embodiment, the first active power collected last among the multiple first active powers collected can be determined as the first target active power of the branch switch to be verified; the first phase current collected last among the multiple first phase currents can be determined as the first target phase current of the branch switch to be verified; the second active power collected last among the multiple second active powers can be determined as the second target active power of the main switch; the second phase current collected last among the multiple second phase currents can be determined as the second target phase current of the main switch; the first target active power, the first target phase current, the second target active power and the second target phase current can be used to verify the changed operating state to obtain a verification result. Among them, the second target active power can be the active power saved last by the main switch. The second target phase current can be the phase current saved last by the main switch. The first target phase current can be the last phase current collected by the switch to be verified before it is opened. The first target active power can be the last active power collected by the switch to be verified before it is opened.
[0056] For example, the operation data of the switch can be collected through the electric meter corresponding to the switch, and the first operation data corresponding to the branch switch to be verified and the second operation data corresponding to the main switch at multiple moments can be obtained respectively. Based on the first operation data, the branch switch to be verified whose operation status has changed within the same minute can be determined, and the first active power collected at the last moment before the branch switch to be verified is determined as the first target active power. The first phase current collected at the last moment before the branch switch to be verified is determined as the first target phase current. The second active power saved by the main switch at the last moment collected at the target moment can be determined as the second target active power, and the second phase current collected at the last moment can be determined as the second target phase current. Among them, the target moment can be the moment before the operation status of the branch switch to be verified changes, or it can be the moment closest to the change in the operation status of the branch switch to be verified.
[0057] As an optional implementation, the changed operating state is verified using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result, including: in response to the number of branch switches to be verified being greater than a number threshold, determining the sum of multiple first target active powers of multiple branch switches to be verified, and the sum of multiple first target phase currents of multiple branch switches to be verified; using the second target active power, converting the sum of multiple first target active powers to obtain the active power to be verified, and using the second target phase current, converting the sum of multiple first target phase currents to obtain the phase current to be verified; using the power threshold to verify the active power to be verified, and using the current threshold to verify the phase current to be verified, to obtain a verification result.
[0058] In this embodiment, the quantity threshold may be a preset number, or a number determined in advance according to experiments or tests, for example, 1, 2, etc. It should be noted that this is only an example, and the size of the quantity threshold is not specifically limited. The power threshold may be a preset value, such as 5%, 6%, etc. The current threshold may be a preset value, such as 5%, 6%, etc. It should be noted that the size of the power threshold and the current threshold is only an example, and is not specifically limited.
[0059] Optionally, determine whether the number of branch switches to be verified is greater than the number threshold. If the number of branch switches to be verified is greater than the number threshold, the sum of multiple first target active powers of multiple branch switches to be verified (which can be represented by Pt) can be further determined, that is, Pt = the sum of the first target active powers of multiple branch switches to be verified before opening, and the sum of multiple first target phase currents of multiple branch switches to be verified (which can be represented by It), that is, It = the sum of the first target phase currents of multiple branch switches to be verified before opening. Further, the sum of multiple first target active powers can be converted using the second target active power to obtain the active power to be verified, and the sum of multiple first target phase currents can be converted using the second target phase current to obtain the phase current to be verified; the active power to be verified is verified using the power threshold, and the phase current to be verified is verified using the current threshold to obtain the verification result.
[0060] Optionally, the second target active power is used to convert the sum of multiple first target active powers to obtain the active power to be verified. The active power to be verified can be obtained by the following formula:
[0061] Active power to be verified = Pt / second target active power
[0062] The phase current to be verified can be obtained by the following formula:
[0063] Active power to be verified = It / second target phase current
[0064] For example, if the number of branch switches to be verified is 3, the sum of the first target active power of branch switch 1 to be verified, branch switch 2 to be verified, and branch switch 3 to be verified before opening can be calculated to obtain Pt, and the sum of the first target phase current of branch switch 1 to be verified, branch switch 2 to be verified, and branch switch 3 to be verified before opening can be calculated to obtain It. Further, to determine the second target active power, the active power to be verified and the phase current to be verified can be calculated according to the above formula.
[0065] As an optional implementation, the changed operating state is verified using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result, including: in response to the number of branch switches to be verified being not greater than a quantity threshold, the first target active power is converted using the second target active power to obtain the active power to be verified, and the first target phase current is converted using the second target phase current to obtain the phase current to be verified; the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold to obtain a verification result.
[0066] In this embodiment, it is determined whether the number of branch switches to be verified is greater than the number threshold. If the number of branch switches to be verified is not greater than the number threshold, it can be determined that Pt=first target active power, and It=first target phase current. Further, the first target active power can be converted using the second target active power to obtain the active power to be verified, and the first target phase current can be converted using the second target phase current to obtain the phase current to be verified, and the active power to be verified is verified using the power threshold, and the phase current to be verified is verified using the current threshold to obtain a verification result.
[0067] Optionally, the active power to be verified can be obtained by the following formula:
[0068] Active power to be verified = Pt / second target active power
[0069] The phase current to be verified can be obtained by the following formula:
[0070] Phase current to be verified = It / second target phase current
[0071] In this embodiment, the number of branch switches to be verified can be determined. If the number of branch switches to be verified is greater than a pre-selected number threshold, the first target active power and the first target phase current can be determined by the first active power and the first phase current of the multiple branch switches to be verified, respectively, and the first target active power and the first target phase current are converted by the second target active power and the second target phase current to obtain the active power to be verified and the phase current to be verified. The active power to be verified and the phase current to be verified are verified to determine the actual operating status of the multiple branch switches to be verified. If the number of branch switches to be verified is not greater than the number threshold, the first target active power and the first phase current can be determined by the first active power and the first phase current of the branch switches to be verified, and the first target active power and the first target phase current are converted by the second target active power and the second target phase current to obtain the active power to be verified and the phase current to be verified. The actual operating status of a single branch switch to be verified is obtained by verifying the active power to be verified and the phase current to be verified.
[0072] For example, assume that the quantity threshold is 1. When the number of branch switches to be verified is 1, determine the first target active power among the multiple first active powers of the branch switch to be verified, and the first target phase current among the multiple first phase currents, determine Pt = first target power, It = first phase current, and use the second target active power of the main switch and the second target phase current to convert Pt and It respectively to obtain the active power to be verified and the phase current to be verified. Use the current threshold of 5% and the power threshold of 5% to judge Pt and It respectively to obtain the final verification result, and determine whether the actual operating state of the branch switch to be verified has changed based on the verification result.
[0073] When the number of branch switches to be verified is 2, the first target active power among the multiple first active powers and the first target phase current among the multiple first phase currents of each branch switch to be verified can be determined respectively, and the first target active power and the first target phase current corresponding to each branch switch to be verified can be obtained. It can be determined that Pt = the sum of the multiple first target active powers, and It = the sum of the multiple first target phase currents. Further, Pt can be converted based on the second target active power to obtain the active power to be verified, and It can be converted based on the second target phase current to obtain the phase current to be verified. The current threshold is used to judge the phase current to be verified, and the power threshold is used to judge the active power to be verified. If the phase current to be verified is greater than the current threshold, and the active power to be verified is greater than the power threshold, it can be further determined whether the absolute value of the difference between the two second active powers satisfies the first numerical range. If the absolute value of the difference between the two second active powers satisfies the first numerical range, the difference between two adjacent second phase currents among multiple second phase currents can be determined; and it is determined whether the absolute value of the difference between the two second phase currents satisfies the second numerical range. If the absolute value of the difference between the two second phase currents satisfies the second numerical range, it can be determined that the verification result is the first verification result.
[0074] As an optional implementation, the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold, to obtain a verification result, including: in response to the active power to be verified being greater than the power threshold, and the phase current to be verified being greater than the current threshold, determining the difference between two adjacent second active powers among a plurality of second active powers; in response to the absolute value of the difference between the two second active powers satisfying a first numerical range, determining the difference between two adjacent second phase currents among a plurality of second phase currents, wherein the first numerical range is associated with the first target active power; in response to the absolute value of the difference between the two second phase currents satisfying a second numerical range, determining the verification result as a first verification result, wherein the first verification result is used to characterize that the operating state of the branch switch to be verified is changed to a target operating state, and the second numerical range is associated with the first phase current.
[0075] In this embodiment, the first numerical range is associated with the first target active power, for example, it can be within the range of plus or minus 10% of the first target active power. The second numerical range is associated with the first phase current, for example, it can be within the range of plus or minus 10% of the first phase current. It should be noted that the size of the above numbers is only for example, and there is no specific limitation on the size of the numbers here.
[0076] Optionally, the first target phase current and the second target active power are converted respectively to obtain the active power to be verified and the phase current to be verified, and the active power to be verified and the phase current to be verified are verified using the current threshold and the power threshold respectively. If the active power to be verified is greater than the power threshold, and the phase current to be verified is greater than the current threshold, the difference between two adjacent second active powers among the multiple second active powers can be determined; it can be further determined whether the absolute value of the difference between the two second active powers satisfies the first numerical range. If the absolute value of the difference between the two second active powers satisfies the first numerical range, the difference between two adjacent second phase currents among the multiple second phase currents can be determined; and it is determined whether the absolute value of the difference between the two second phase currents satisfies the second numerical range. If the absolute value of the difference between the two second phase currents satisfies the second numerical range, the verification result can be determined to be the first verification result. The first verification result can be used to characterize that the operating state of the branch switch to be verified is changed to the target operating state.
[0077] Optionally, if the absolute value of the difference between the two second active powers satisfies the first numerical range, but the absolute value of the difference between the two second phase currents does not satisfy the second numerical range, it can be determined that the operating state of the branch switch to be verified has not changed, and the actual operating state of the branch switch to be verified can still be a closed state. Further, in order to improve the accuracy of the verification of the actual operating state of the branch switch to be verified, the first operating data of the branch switch to be verified and the second operating data of the main switch can be re-collected according to the above judgment steps, and the first operating data can be further judged by using the second operating data, so as to achieve the purpose of improving the accuracy of the judgment of the operating data of the switch to be verified.
[0078] As an optional implementation, the method may also include: in response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, and the number of branch switches to be verified is greater than the number threshold, respectively using the second target active power to convert multiple first target active powers of multiple branch switches to be verified to obtain multiple active powers to be verified, and using the second target phase current to convert multiple first target phase currents of multiple branch switches to be verified to obtain multiple phase currents to be verified; using the power threshold to verify the active power to be verified, and using the current threshold to verify the phase current to be verified to obtain the verification result of the branch switch to be verified.
[0079] In this embodiment, if the absolute value of the difference between the two second active powers does not satisfy the first numerical range, the number of multiple branch switches to be verified can be further determined to determine whether the number of branch switches to be verified is greater than the number threshold. If the number of branch switches to be verified is greater than the number threshold, the second target active power can be used to convert the multiple first target active powers of the multiple branch switches to be verified to obtain multiple active powers to be verified, and the second target phase current can be used to convert the multiple first target phase currents of the multiple branch switches to be verified to obtain multiple phase currents to be verified; the power threshold is used to verify the active power to be verified, and the current threshold is used to verify the phase current to be verified to obtain the verification result of the branch switch to be verified. The above verification result can be used to characterize the actual operating state of the branch switch to be verified, which can include a closed state and an open state. Different verification results represent different meanings.
[0080] Optionally, if the absolute value of the difference between the two second active powers does not satisfy the first numerical range, the number of multiple branch switches to be verified can be further determined to determine whether the number of branch switches to be verified is greater than the number threshold. If the number of branch switches to be verified is greater than the number threshold, multiple branch switches to be verified can be verified in sequence, and the first active power collected at the last moment before the branch switch to be verified is determined as the first target active power, and the first phase current collected at the last moment before the branch switch is opened is determined as the first target phase current. Further, the active power to be verified can be determined by the following steps:
[0081] Active power to be verified = Pt / second target active power
[0082] The phase current to be verified can be obtained by the following formula:
[0083] Phase current to be verified = It / second target phase current
[0084] For example, the number of branch switches to be verified can be determined. When the number of branch switches to be verified is 2, the first target active power among the multiple first active powers and the first target phase current among the multiple first phase currents of each branch switch to be verified can be determined respectively, and the first target active power and the first target phase current corresponding to each branch switch to be verified can be obtained. It can be determined that Pt = the sum of the multiple first target active powers, and It = the sum of the multiple first target phase currents. Further, Pt can be converted based on the second target active power to obtain the active power to be verified, and It can be converted based on the second target phase current to obtain the phase current to be verified. The current threshold is used to judge the phase current to be verified, and the power threshold is used to judge the active power to be verified. If the phase current to be verified is greater than the current threshold, and the active power to be verified is greater than the power threshold, it can be further determined whether the absolute value of the difference between the two second active powers satisfies the first numerical range. If the absolute value of the difference between the two second active powers does not satisfy the first numerical range, the number of branch switches to be verified can be further confirmed. If the number of branch switches to be verified is greater than 1, the branch switches to be verified can be verified in turn to determine the actual operating status of each branch switch to be verified.
[0085] Optionally, separately verifying multiple branch switches to be verified may include the following steps: Pt and It corresponding to each branch switch to be verified may be determined in turn. Pt and It are converted respectively to obtain the active power to be verified and the phase current to be verified. The active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold. Further, the operating state of the switch to be verified may be further judged based on the multiple second active powers of the main switch, and the operating state may be judged by the difference between two adjacent second phase currents of the multiple second phase currents of the main switch to obtain the final verification result of the switch to be verified. It should be noted that the above verification steps are for illustrative purposes only and are not specifically limited here.
[0086] As an optional implementation, the method may further include: in response to the absolute value of the difference between the two second phase currents not satisfying the second numerical range, determining that the verification result is a second verification result, wherein the second verification result is used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state.
[0087] In this embodiment, if the absolute value of the difference between the two second phase currents does not satisfy the second numerical range, the verification result can be determined to be the second verification result, wherein the second verification result can be used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state, that is, the second verification result may be that the branch switch to be verified has not passed the verification, which can be used to indicate that the actual operating state of the branch switch to be verified has not changed and is still in a closed state.
[0088] As an optional implementation, the method may further include: in response to the verification result being the second verification result, re-collecting the first operation data and the second operation data; and verifying the operation status of the branch switch to be verified using the re-collected first operation data and the second operation data.
[0089] In this embodiment, if the verification result is the second verification result, in order to ensure the accuracy of the verification, the first operating data and the second operating data at multiple times can be re-collected; the operating status of the branch switch to be verified is verified using the re-collected first operating data and the second operating data, so as to achieve the purpose of further verifying the actual operating status of the branch switch to be verified.
[0090] In an embodiment of the present invention, the operating status of at least one switch is determined, and based on the operating status of at least one switch, a branch switch to be verified whose operating status has changed is determined, first operating data of the branch switch to be verified and second operating data of the main switch are obtained, and the first operating data is verified using the second operating data to obtain a verification result. Based on the verification result, the actual operating status of the branch switch to be verified can be determined, thereby achieving a technical effect of accurately determining the operating status of the switch and solving the technical problem of being unable to accurately determine the operating status of the switch.
[0091] The technical solution of the embodiment of the present invention is illustrated below in conjunction with preferred implementation modes.
[0092] At present, in order to determine the operating status of switches in low-voltage distribution networks, a collection device is usually installed on each switch, and the operating data of the auxiliary nodes of the switch position are directly collected through the collection device to determine the operating status of the switch. However, the auxiliary contacts of the collection device may jitter due to poor contact, thereby making the collected signal unstable, which in turn leads to a technical problem that the operating status of the switch cannot be accurately determined.
[0093] In the related art, the real-time operating status of the low-voltage switch can be judged by the energized state of the meter and the topological relationship of the low-voltage power grid. However, due to the instability of the communication between the terminal (for example, the gateway) and the meter, when the communication interruption time between the terminal and the meter exceeds the set value, the meter will be misjudged as not energized, resulting in an erroneous signal of the switch position being opened, causing the signal at the switch position to jitter, thereby making it impossible to accurately obtain the correct information at the switch position, making it impossible to accurately determine the operating status of the switch, and thus interfering with the operation and maintenance of the low-voltage power grid.
[0094] To solve the above problem, in this embodiment, a method for verifying the change of the operating status of a switch node in a low-voltage distribution network is proposed. The method verifies the collected switch displacement information by comparing and analyzing the change in the active power and current of the main switch with the active power and current of the disconnecting switch to obtain a verification result. Based on the verification result, the low-voltage real-time data acquisition terminal in the substation (for example, a gateway) can filter the received switch erroneous disconnection information to improve the quality of the determined low-voltage switch status information, thereby achieving the purpose of improving the data automation processing capability, thereby solving the technical problem of being unable to accurately determine the operating status of the switch, and achieving the technical effect of being able to accurately determine the operating status of the switch.
[0095] The following will be combined with the accompanying drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments; the size of the numbers in the embodiments is only for illustration and is not specifically limited here. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention and are not specifically limited here.
[0096] Figure 2 is a flow chart of a method for verifying a change in the operating state of a switch node in a low-voltage distribution network according to an embodiment of the present invention. Figure 2 As shown, the method may include the following steps:
[0097] Step S201, determining the operating status of at least one switch.
[0098] In this embodiment, a collection device can be installed at the low-voltage main switch of the substation to obtain the second operating data of the main switch. The collection device can communicate with the terminal (gateway) via a broadband carrier or other communication medium, and send the real-time value of the second operating data of the above-mentioned main switch to the terminal (gateway) in real time. The terminal (gateway) can dynamically save the second operating data of the main switch, one point per minute, and the saving time can be the last 15 minutes; at the same time, the first operating data of each branch switch can be dynamically saved. It should be noted that this is only an example, and there is no specific restriction on the method of obtaining the first operating data and the second operating data, as well as the collection time.
[0099] Optionally, the terminal can obtain switch position information sent by the switch status collection device, and based on the switch position information, it can determine whether the operating status of the switch has changed, or the terminal can judge the operating status of the switch according to the power-on status of the meter.
[0100] Optionally, when it is determined that the operating state of the switch has changed, step S202 may be executed.
[0101] Step S202: determine whether the number of branch switches to be verified is greater than 1.
[0102] In this embodiment, when it is determined that the operating state of a branch switch has changed from a closed state to an open state (or can be called a closed state), the branch switch whose operating state has changed can be determined as a branch switch to be verified, and it can be determined whether the number of branch switches to be verified is greater than 1.
[0103] Optionally, if the number of branch switches to be verified is greater than 1, step S203 may be executed, and if the number of branch switches to be verified is not greater than 1, step S204 may be executed.
[0104] For example, it can be determined whether the number of branch switches to be verified in the data collected within one minute is greater than 1.
[0105] Step S203, calculating Pt and It corresponding to a plurality of branch switches to be verified.
[0106] In this embodiment, if the number of branch switches to be verified is greater than 1, the sum of multiple first target active powers of multiple branch switches to be verified can be further determined, that is, Pt = the sum of the first target active powers of multiple branch switches to be verified before opening, and the sum of multiple first target phase currents of multiple branch switches to be verified, that is, It = the sum of the first target phase currents of multiple branch switches to be verified before opening.
[0107] For example, if the number of branch switches to be verified is 3, the sum of the first target active powers of branch switches 1 to be verified, 2 to be verified and 3 to be verified before opening can be calculated to obtain Pt, and the sum of the first target phase currents of branch switches 1 to be verified, 2 to be verified and 3 to be verified before opening can be calculated to obtain It.
[0108] Step S204, calculating Pt and It corresponding to a branch switch to be verified.
[0109] In this embodiment, if the number of branch switches to be verified is not greater than 1, it can be further determined that Pt = the first target active power (that is, the first active power collected by the changing switch before opening), and It = the first target phase power (that is, the first phase current collected by the changing switch before opening).
[0110] Step S205, judging the active power to be verified and the phase current to be verified respectively.
[0111] In this embodiment, Pt and It are calculated, and the active power to be verified and the phase current to be verified can be determined based on Pt and It, respectively.
[0112] Optionally, the active power to be verified can be obtained by the following formula:
[0113] Active power to be verified = Pt / second target active power
[0114] The phase current to be verified can be obtained by the following formula:
[0115] Phase current to be verified=It / second target phase current.
[0116] Optionally, after the active power to be verified and the phase current to be verified are calculated, a judgment may be made on the active power to be verified and the phase current to be verified.
[0117] Optionally, the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold, that is, it is determined whether the active power to be verified is greater than the power threshold, and whether the phase current to be verified is greater than the current threshold. If yes, step S206 is executed, if not, step S209 is executed.
[0118] Step S206: further determine the operating state of the switch to be verified based on the multiple second active powers of the main switch.
[0119] In this embodiment, the active power to be verified is verified using a power threshold. If the active power to be verified is greater than the power threshold, and the current threshold is greater than the phase current to be verified, the operating state of the switch to be verified can be further judged based on the multiple second active powers of the main switch. For example, it can be checked whether the absolute value of the difference between two adjacent second active powers within 15 minutes saved by the main switch is within the range of plus or minus 10% of the first target active power. If so, step S207 can be executed, otherwise, step S208 can be executed. It should be noted that the size of the above numbers is only for example and is not specifically limited here.
[0120] Step S207: further judging the operating state of the switch to be verified based on the multiple second-phase currents of the main switch.
[0121] In this embodiment, the operating state of the switch to be verified is further judged based on the multiple second active powers of the main switch. If the absolute value of the difference between two adjacent second active powers satisfies the first numerical range, the difference between two adjacent second phase currents in the multiple second phase currents can be further determined. If the absolute value of the difference between the two second phase currents satisfies the second numerical range, step S209 can be executed, otherwise, step S210 can be executed. The second numerical range can be within the range of plus or minus 10% of the first target phase current. It should be noted that this is only an example, and the size of the second numerical range is not specifically limited here.
[0122] For example, it can be checked whether the absolute value of the difference between two adjacent second-phase currents in the multiple second-phase currents within 15 minutes saved by the main switch is within the range of plus or minus 10% of the first-phase current. If yes, step S209 can be executed, otherwise, step S210 can be executed. It should be noted that the size of the above numbers is only for example and is not specifically limited here.
[0123] Step S208: determine whether the number of branch switches to be verified is greater than 1.
[0124] In this embodiment, in response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, it can be further determined whether the number of branch switches to be verified is greater than 1. If the number of branch switches to be verified is greater than 1, step S211 can be executed, otherwise step S210 can be executed.
[0125] Step S209: determine the target branch switch.
[0126] In this embodiment, the operating state of the switch to be verified is further judged based on the multiple second active powers of the main switch. If the absolute value of the difference between two adjacent second active powers satisfies the first numerical range, the difference between two adjacent second phase currents in the multiple second phase currents can be further determined. If the absolute value of the difference between the two second phase currents satisfies the second numerical range, the branch switch to be verified can be determined to be the target branch switch. Alternatively, it is determined whether the active power to be verified is greater than the power threshold, and whether the phase current to be verified is greater than the current threshold. If the active power to be verified is not greater than the power threshold and / or the phase current to be verified is not greater than the current threshold, it can be determined that the actual operating states of the branch switches to be verified are all target operating states. Therefore, it can be determined that the branch switches to be verified are all target branch switches.
[0127] Step S210, denying the received branch switch displacement information.
[0128] In this embodiment, it can be determined that the operating state of the branch switch to be verified has not changed, and the received displacement information of the branch switch can be denied and not adopted.
[0129] Step S211, sorting a plurality of branch switches to be verified.
[0130] In this embodiment, within one minute, a plurality of branch switches to be verified in at least one switch are determined, and the plurality of branch switches to be verified are sorted.
[0131] Optionally, multiple branch switches to be verified are sorted, and the record pointer is set at the top.
[0132] Step S212, calculating Pt and It corresponding to a plurality of branch switches to be verified.
[0133] In this embodiment, Pt and It corresponding to each branch switch to be verified may be determined in sequence.
[0134] Optionally, in this embodiment, the first target active power of the branch switch to be verified may be determined as Pt, and the first target phase current of the branch switch to be verified may be determined as It.
[0135] Alternatively, Pt and It can be determined by the following formula:
[0136] Pt=First target active power
[0137] It=First target phase current
[0138] Step S213, verifying the active power to be verified and the phase current to be verified.
[0139] In this embodiment, Pt and It may be converted respectively to obtain the active power to be verified and the phase current to be verified, and the active power to be verified and the phase current to be verified are verified.
[0140] Optionally, the active power to be verified can be obtained by the following formula:
[0141] Active power to be verified = Pt / second target active power
[0142] The phase current to be verified can be obtained by the following formula:
[0143] Phase current to be verified=It / second target phase current.
[0144] Optionally, after the active power to be verified and the phase current to be verified are calculated, a judgment may be made on the active power to be verified and the phase current to be verified.
[0145] Optionally, the active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold, that is, it is determined whether the active power to be verified is greater than the power threshold, and whether the phase current to be verified is greater than the current threshold. If yes, execute step S214, if not, execute step S209.
[0146] Step S214: further determine the operating state of the switch to be verified based on the multiple second active powers of the main switch.
[0147] In this embodiment, the active power to be verified is verified using a power threshold. If the active power to be verified is greater than the power threshold, and the current threshold is greater than the phase current to be verified, the operating state of the switch to be verified can be further judged based on the multiple second active powers of the main switch. For example, it can be checked whether the absolute value of the difference between two adjacent second active powers within 15 minutes saved by the main switch is within the range of plus or minus 10% of the first target active power. If so, step S216 can be executed, otherwise, step S215 can be executed. It should be noted that the size of the above numbers is only for example and is not specifically limited here.
[0148] Step S215, determining that the received branch switch position change information is wrong.
[0149] In this embodiment, it is determined that the operating state of the branch switch to be verified has not changed, and the received displacement information of the branch switch can be denied, and it is determined that the received displacement information of the branch switch is wrong, that is, it can be determined that the operating state of the branch switch has not changed, and the branch switch is still in a closed state.
[0150] Step S216: further determine the operating state of the switch to be verified based on the multiple second-phase currents of the main switch.
[0151] In this embodiment, the operating state of the switch to be verified is further judged based on the multiple second active powers of the main switch. If the absolute value of the difference between two adjacent second active powers satisfies the first numerical range, the difference between two adjacent second phase currents in the multiple second phase currents can be further determined. If the absolute value of the difference between the two second phase currents satisfies the second numerical range, step S217 can be executed, otherwise, step S215 can be executed. The second numerical range can be within the range of plus or minus 10% of the first target phase current. It should be noted that this is only an example, and the size of the second numerical range is not specifically limited here.
[0152] Step S217: determining a target branch switch among the plurality of branch switches to be verified.
[0153] In this embodiment, if the branch switch passes the verification, the actual operating state of the branch switch to be verified may be determined as a target branch switch in a target operating state.
[0154] In this embodiment, the above method is used to verify a plurality of branch switches to be verified, so as to confirm a target branch switch among the plurality of branch switches to be verified.
[0155] For example, multiple branch switches to be verified can be verified simultaneously through steps S212 to S217, or the multiple branch switches to be verified can be sorted and verified in sequence through steps S212 to S217 to obtain the verification result of each branch switch to be verified, thereby determining the target branch switch among the multiple branch switches to be verified.
[0156] For another example, if multiple branch switches to be verified are sorted and verified in sequence, the following steps may be included: first, multiple branch switches to be verified are photographed, and the record pointer is set to the top. Then, steps S212 to S217 are executed in sequence to determine whether the verified branch switch record is the bottom one to be verified. If so, it means that the verification of the sorted branch switches to be verified is completed. If not, the pointer can be jumped to the next change switch record, and steps S212 to S217 are repeated for the next change switch until the verification is the bottom one to be verified. The verification is completed. Otherwise, steps S212 to S217 are continued to be repeated. In the above manner, the target branch switch among the multiple branch switches to be verified is determined.
[0157] In an embodiment of the present invention, the operating status of at least one switch is determined, and based on the operating status of at least one switch, a branch switch to be verified whose operating status has changed is determined, first operating data of the branch switch to be verified and second operating data of the main switch are obtained, and the first operating data is verified using the second operating data to obtain a verification result. Based on the verification result, the actual operating status of the branch switch to be verified can be determined, thereby achieving a technical effect of accurately determining the operating status of the switch and solving the technical problem of being unable to accurately determine the operating status of the switch.
[0158] According to an embodiment of the present invention, a device for determining switches in a distribution network is also provided. It should be noted that the device for determining switches in a distribution network of this embodiment can be used to execute the method for determining switches in a distribution network of embodiment 1 of the present invention.
[0159] Figure 3 is a schematic diagram of a device for determining a switch in a distribution network according to an embodiment of the present invention. Figure 3 As shown, the device 30 for determining a switch in a power distribution network may include: a first determining unit 302 , a second determining unit 304 , an acquiring unit 306 , a verifying unit 308 and a third determining unit 310 .
[0160] The first determining unit 302 is configured to determine the operating state of at least one switch in the distribution network.
[0161] The second determining unit 304 is configured to determine, among at least one switch, at least one branch switch to be verified whose operating state has changed.
[0162] The acquisition unit 306 is used to acquire the first operating data of the branch switch to be verified and the second operating data of the main switch in at least one switch, wherein the second operating data is associated with the opening and closing state of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the opening and closing state of the line.
[0163] The verification unit 308 is used to verify the operation status of the branch switch to be verified after the change by using the first operation data and the second operation data to obtain a verification result, wherein the verification result is used to represent the actual operation status of the branch switch to be verified after the change.
[0164] The third determining unit 310 is configured to determine, based on the verification result, a target branch switch whose actual operating state after the change is the target operating state in at least one branch switch to be verified.
[0165] The device for determining switches in the distribution network of this embodiment determines the operating state of at least one switch in the distribution network through a first determining unit; determines at least one branch switch to be verified whose operating state has changed in at least one switch through a second determining unit; obtains first operating data of the branch switch to be verified and second operating data of the main switch in at least one switch through an acquiring unit, wherein the second operating data is associated with the opening and closing state of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the opening and closing state of the line; verifies the operating state of the branch switch to be verified after the change by using the first operating data and the second operating data through a verifying unit, and obtains a verification result, wherein the verification result is used to characterize the actual operating state of the branch switch to be verified after the change; determines the target branch switch whose actual operating state after the change is the target operating state in at least one branch switch to be verified based on the verification result through a third determining unit, thereby achieving the technical effect of accurately determining the operating state of the switch and solving the technical problem that the operating state of the switch cannot be accurately determined.
[0166] The embodiment of the present invention can provide a computer terminal, which can be any computer terminal device in a computer terminal group. Optionally, in this embodiment, the computer terminal can also be replaced by a terminal device such as a mobile terminal.
[0167] Optionally, in this embodiment, the computer terminal may be located in at least one network device among a plurality of network devices of the computer network.
[0168] In this embodiment, the above-mentioned computer terminal can execute the program code of the following steps in the method for determining switches in the distribution network: determining the operating status of at least one switch in the distribution network; in at least one switch, determining at least one branch switch to be verified whose operating status has changed; obtaining the first operating data of the branch switch to be verified, and the second operating data of the main switch in at least one switch; using the first operating data and the second operating data, verifying the operating status of the branch switch to be verified after the change, and obtaining a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, determining the target branch switch whose actual operating status after the change is the target operating status.
[0169] Optionally, Figure 4 is a structural block diagram of a computer terminal according to an embodiment of the present invention. Figure 4 As shown, the computer terminal 408 may include: one or more (only one is shown in the figure) processors 402 , a memory 404 and a transmission device 406 .
[0170] Among them, the memory can be used to store software programs and modules, such as the program instructions / modules corresponding to the method and device for determining switches in the distribution network in the embodiment of the present invention. The processor executes various functional applications and data processing by running the software programs and modules stored in the memory, that is, the above-mentioned method for determining switches in the distribution network is realized. The memory may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some examples, the memory may further include a memory remotely arranged relative to the processor, and these remote memories can be connected to the computer terminal 408 via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0171] The processor can call the information and application stored in the memory through the transmission device to perform the following steps: determine the operating status of at least one switch in the distribution network; in at least one switch, determine at least one branch switch to be verified whose operating status has changed; obtain the first operating data of the branch switch to be verified, and the second operating data of the main switch in at least one switch; use the first operating data and the second operating data to verify the operating status of the branch switch to be verified after the change, and obtain a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, determine the target branch switch whose actual operating status after the change is the target operating status.
[0172] It can be understood by those skilled in the art that Figure 4The structure shown is for illustration only, and the computer terminal 408 may also be a smart phone (such as an Android phone, an iOS phone, etc.), a tablet computer, a PDA, a mobile Internet device (MID for short), a PAD, or other terminal devices. Figure 4 The structure of the computer terminal 408 is not limited. For example, the computer terminal 408 may also include Figure 4 More or fewer components (such as network interfaces, display devices, etc.) shown in, or having Figure 4 Different configurations are shown.
[0173] A person of ordinary skill in the art can understand that all or part of the steps in the various methods of the above embodiments can be completed by instructing the hardware related to the terminal device through a program, and the program can be stored in a computer-readable storage medium, and the storage medium may include: a flash drive, a read-only memory (ROM), a random access memory (RAM), a disk or an optical disk, etc.
[0174] According to an embodiment of the present invention, a computer-readable storage medium is further provided. The computer-readable storage medium includes a stored program, wherein the program executes the method for determining a switch in a distribution network in Embodiment 1.
[0175] Optionally, in this embodiment, the computer-readable storage medium may be located in any one of the computer terminals in a computer terminal group in a computer network, or in any one of the mobile terminals in a mobile terminal group.
[0176] Optionally, in this embodiment, the computer-readable storage medium is configured to store program codes for executing the following steps: determining the operating status of at least one switch in the distribution network; in at least one switch, determining at least one branch switch to be verified whose operating status has changed; obtaining first operating data of the branch switch to be verified, and second operating data of the main switch in at least one switch; using the first operating data and the second operating data, verifying the operating status of the branch switch to be verified after the change, and obtaining a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, determining the target branch switch whose actual operating status after the change is the target operating status.
[0177] Optionally, in this embodiment, the computer-readable storage medium is configured to store program codes for executing the following steps: before the operating state of the branch switch to be verified changes, collecting first operating data of the branch switch to be verified, wherein the first operating data at least includes multiple first active powers and multiple first phase currents of the branch switch to be verified; within a target time period, collecting second operating data of the main switch, wherein the second operating data at least includes multiple second active powers and multiple second phase currents, and the target time period is the time period before the operating state changes.
[0178] Optionally, in this embodiment, the computer-readable storage medium is configured to store program codes for executing the following steps: determining the first active power collected last among multiple first active powers as the first target active power of the branch switch to be verified; determining the first phase current collected last among multiple first phase currents as the first target phase current of the branch switch to be verified; determining the second active power collected last among multiple second active powers as the second target active power of the main switch; determining the second phase current collected last among multiple second phase currents as the second target phase current of the main switch; and verifying the changed operating state using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result.
[0179] Optionally, in this embodiment, the computer-readable storage medium is configured to store program code for performing the following steps: in response to the number of branch switches to be verified being greater than a number threshold, determining the sum of multiple first target active powers of multiple branch switches to be verified, and the sum of multiple first target phase currents of multiple branch switches to be verified; using the second target active power, converting the sum of multiple first target active powers to obtain the active power to be verified, and using the second target phase current, converting the sum of multiple first target phase currents to obtain the phase current to be verified; verifying the active power to be verified using a power threshold, and verifying the phase current to be verified using a current threshold, to obtain a verification result.
[0180] Optionally, in this embodiment, the computer-readable storage medium is configured to store program codes for performing the following steps: in response to the number of branch switches to be verified being not greater than a number threshold, converting the first target active power using the second target active power to obtain the active power to be verified, and converting the first target phase current using the second target phase current to obtain the phase current to be verified; verifying the active power to be verified using the power threshold, and verifying the phase current to be verified using the current threshold to obtain a verification result.
[0181] Optionally, in this embodiment, the computer-readable storage medium is configured to store program code for performing the following steps: in response to the active power to be verified being greater than a power threshold and the phase current to be verified being greater than a current threshold, determining the difference between two adjacent second active powers among a plurality of second active powers; in response to the absolute value of the difference between the two second active powers satisfying a first numerical range, determining the difference between two adjacent second phase currents among a plurality of second phase currents, wherein the first numerical range is associated with a first target active power; in response to the absolute value of the difference between the two second phase currents satisfying a second numerical range, determining the verification result to be a first verification result, wherein the first verification result is used to characterize that the operating state of the branch switch to be verified is changed to a target operating state, and the second numerical range is associated with the first phase current.
[0182] Optionally, in this embodiment, the computer-readable storage medium is configured to store program code for executing the following steps: in response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, and the number of branch switches to be verified is greater than a quantity threshold, using the second target active power, respectively converting multiple first target active powers of multiple branch switches to be verified to obtain multiple active powers to be verified, and using the second target phase current, converting multiple first target phase currents of multiple branch switches to be verified to obtain multiple phase currents to be verified.
[0183] Optionally, in this embodiment, the computer-readable storage medium is configured to store program code for performing the following steps: in response to the absolute value of the difference between the two second phase currents not satisfying the second numerical range, determining that the verification result is a second verification result, wherein the second verification result is used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state.
[0184] Optionally, in this embodiment, the computer-readable storage medium is configured to store program code for executing the following steps: using the second verification result to trigger the collection of first operating data and second operating data; using the re-collected first operating data and second operating data to verify the operating status of the branch switch to be verified.
[0185] In this embodiment, the operating status of at least one switch is determined, and based on the operating status of at least one switch, the branch switch to be verified whose operating status has changed is determined, the first operating data of the branch switch to be verified and the second operating data of the main switch are obtained, and the first operating data is verified using the second operating data to obtain a verification result. Based on the verification result, the actual operating status of the branch switch to be verified can be determined, thereby achieving the technical effect of accurately determining the operating status of the switch and solving the technical problem of being unable to accurately determine the operating status of the switch.
[0186] According to an embodiment of the present invention, a processor is further provided. The processor is used to run a program. When the program is run by the processor, the method for determining a switch in a distribution network in Embodiment 1 is executed.
[0187] Optionally, in this embodiment, the computer terminal may be located in at least one network device among a plurality of network devices of the computer network.
[0188] In this embodiment, the above-mentioned computer terminal can execute the program code of the following steps in the multi-language translation method: determining the operating status of at least one switch in the distribution network; in at least one switch, determining at least one branch switch to be verified whose operating status has changed; obtaining the first operating data of the branch switch to be verified, and the second operating data of the main switch in at least one switch; using the first operating data and the second operating data, verifying the operating status of the branch switch to be verified after the change, and obtaining a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, determining the target branch switch whose actual operating status after the change is the target operating status.
[0189] Wherein, the memory can be used to store software programs and modules, such as the program instructions / modules corresponding to the multilingual translation method and device in the embodiment of the present invention, and the processor executes various functional applications and data processing by running the software programs and modules stored in the memory, that is, realizing the above-mentioned multilingual translation method. The memory may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some instances, the memory may further include a memory remotely arranged relative to the processor, and these remote memories may be connected to the computer terminal via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.
[0190] The processor can call the information and application stored in the memory through the transmission device to perform the following steps: determine the operating status of at least one switch in the distribution network; in at least one switch, determine at least one branch switch to be verified whose operating status has changed; obtain the first operating data of the branch switch to be verified, and the second operating data of the main switch in at least one switch; use the first operating data and the second operating data to verify the operating status of the branch switch to be verified after the change, and obtain a verification result, wherein the verification result is used to characterize the actual operating status of the branch switch to be verified after the change; based on the verification result, in at least one branch switch to be verified, determine the target branch switch whose actual operating status after the change is the target operating status.
[0191] Optionally, the processor may also execute the program code of the following steps: before the operating state of the branch switch to be verified changes, collecting the first operating data of the branch switch to be verified, wherein the first operating data at least includes multiple first active powers and multiple first phase currents of the branch switch to be verified; obtaining the second operating data of the main switch in at least one switch, including: within a target time period, collecting the second operating data of the main switch, wherein the second operating data at least includes multiple second active powers and multiple second phase currents, and the target time period is the time period before the operating state changes.
[0192] Optionally, the processor may also execute the program code of the following steps: determining the first active power collected last among multiple first active powers as the first target active power of the branch switch to be verified; determining the first phase current collected last among multiple first phase currents as the first target phase current of the branch switch to be verified; determining the second active power collected last among multiple second active powers as the second target active power of the main switch; determining the second phase current collected last among multiple second phase currents as the second target phase current of the main switch; and verifying the changed operating state using the first target active power, the first target phase current, the second target active power and the second target phase current to obtain a verification result.
[0193] Optionally, the processor may also execute the program code of the following steps: in response to the number of branch switches to be verified being greater than a number threshold, determining the sum of multiple first target active powers of multiple branch switches to be verified, and the sum of multiple first target phase currents of multiple branch switches to be verified; using the second target active power, converting the sum of multiple first target active powers to obtain the active power to be verified, and using the second target phase current, converting the sum of multiple first target phase currents to obtain the phase current to be verified; using the power threshold to verify the active power to be verified, and using the current threshold to verify the phase current to be verified, to obtain a verification result.
[0194] Optionally, the processor may also execute the program code of the following steps: in response to the number of branch switches to be verified being not greater than a number threshold, the first target active power is converted using the second target active power to obtain the active power to be verified, and the first target phase current is converted using the second target phase current to obtain the phase current to be verified; the active power to be verified is verified using the power threshold, and the phase current to be verified is verified using the current threshold to obtain a verification result.
[0195] Optionally, the processor may also execute program code for the following steps: in response to the active power to be verified being greater than a power threshold and the phase current to be verified being greater than a current threshold, determining the difference between two adjacent second active powers among a plurality of second active powers; in response to the absolute value of the difference between the two second active powers satisfying a first numerical range, determining the difference between two adjacent second phase currents among a plurality of second phase currents, wherein the first numerical range is associated with a first target active power; in response to the absolute value of the difference between the two second phase currents satisfying a second numerical range, determining the verification result to be a first verification result, wherein the first verification result is used to characterize that the operating state of the branch switch to be verified is changed to a target operating state, and the second numerical range is associated with the first phase current.
[0196] Optionally, the processor may also execute the program code of the following steps: in response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, and the number of branch switches to be verified is greater than a quantity threshold, using the second target active power, respectively converting multiple first target active powers of multiple branch switches to be verified to obtain multiple active powers to be verified, and using the second target phase current, converting multiple first target phase currents of multiple branch switches to be verified to obtain multiple phase currents to be verified.
[0197] Optionally, the processor may also execute the program code of the following steps: in response to the absolute value of the difference between the two second phase currents not satisfying the second numerical range, determining that the verification result is a second verification result, wherein the second verification result is used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state.
[0198] Optionally, the processor may also execute program codes of the following steps: using the second verification result to trigger the collection of the first operation data and the second operation data; and using the re-collected first operation data and the second operation data to verify the operation status of the branch switch to be verified.
[0199] By adopting the embodiment of the present invention, the operating status of at least one switch is determined, and based on the operating status of at least one switch, the branch switch to be verified whose operating status has changed is determined, the first operating data of the branch switch to be verified and the second operating data of the main switch are obtained, and the first operating data is verified using the second operating data to obtain a verification result. Based on the verification result, the actual operating status of the branch switch to be verified can be determined, thereby achieving the technical effect of accurately determining the operating status of the switch and solving the technical problem that the operating status of the switch cannot be accurately determined.
[0200] According to an embodiment of the present invention, a computer program product is further provided. The computer program product includes computer instructions. When the computer instructions are executed by a processor, the method for determining switches in a distribution network in Embodiment 1 is implemented.
[0201] An embodiment of the present application may provide an electronic device, which may include a memory and a processor.
[0202] Figure 5 It is a block diagram of an electronic device for determining a switch in a distribution network according to an embodiment of the present application. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workbenches, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device may also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present application described and / or required herein.
[0203] like Figure 5 As shown, the device 500 includes a computing unit 501, which can perform various appropriate actions and processes according to a computer program stored in a read-only memory (ROM) 502 or a computer program loaded from a storage unit 508 to a random access memory (RAM) 503. In the RAM 503, various programs and data required for the operation of the device 500 can also be stored. The computing unit 501, the ROM 502, and the RAM 503 are connected to each other via a bus 504. An input / output (I / O) interface 505 is also connected to the bus 504.
[0204] A number of components in the device 500 are connected to the I / O interface 505, including: an input unit 506, such as a keyboard, a mouse, etc.; an output unit 504, such as various types of displays, speakers, etc.; a storage unit 508, such as a disk, an optical disk, etc.; and a communication unit 509, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 509 allows the device 500 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0205] The computing unit 501 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 501 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various computing units running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The computing unit 501 performs the various methods and processes described above, such as a verification method for data. For example, in some embodiments, the verification method for data may be implemented as a computer software program, which is tangibly included in a machine-readable medium, such as a storage unit 508. In some embodiments, part or all of the computer program may be loaded and / or installed on the device 500 via the ROM 502 and / or the communication unit 509. When the computer program is loaded into the RAM 503 and executed by the computing unit 501, one or more steps of the verification method for data described above may be executed. Alternatively, in other embodiments, the computing unit 501 may be configured to execute the data verification method in any other appropriate manner (for example, by means of firmware).
[0206] According to an embodiment of the present application, a method for determining switches in a distribution network is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0207] Various embodiments of the systems and techniques described above herein may be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on a chip (SOCs), complex programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various embodiments may include: being implemented in one or more computer programs that may be executed and / or interpreted on a programmable system including at least one programmable processor that may be a dedicated or general purpose programmable processor that may receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0208] The program code for implementing the method of the present application can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0209] In the context of the present application, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or equipment, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0210] To provide interaction with a user, the systems and techniques described herein may be implemented on a computer having: a display device (e.g., a CRT (cathode ray tube) or an LCD (liquid crystal display, monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or a path ball) through which the user can provide input to the computer. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0211] The systems and techniques described herein may be implemented in a computing system that includes back-end components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes front-end components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such back-end components, middleware components, or front-end components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a Local Area Network (LAN), a Wide Area Network (WAN), and the Internet.
[0212] A computer system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship with each other. The server may be a cloud server, a server of a distributed system, or a server combined with a blockchain.
[0213] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0214] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0215] In the several embodiments provided by the present invention, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic, for example, the division of units can be a logical function division, and there can be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point, the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0216] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed over multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.
[0217] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0218] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including a number of instructions for a computer device (which can be a personal computer, a server or a network device, etc.) to perform all or part of the steps of the methods of each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, magnetic disk or optical disk and other media that can store program codes.
[0219] The above are only preferred embodiments of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for determining a switch in a distribution network, characterized in that: include: determining an operating state of at least one switch in a power distribution network; Among the at least one switch, determining at least one branch switch to be verified whose operating state has changed; Acquire the first operation data of the branch switch to be verified and the second operation data of the main switch in the at least one switch, wherein the second operation data is associated with the on-off state of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the on-off state of the line; Using the first operation data and the second operation data, verify the operation state of the branch switch to be verified after the change, and obtain a verification result, wherein the verification result is used to characterize the actual operation state of the branch switch to be verified after the change; Based on the verification result, in at least one of the branch switches to be verified, a target branch switch whose actual operating state after change is a target operating state is determined.
2. The method according to claim 1, characterized in that The obtaining of the first operation data of the branch switch to be verified includes: Before the operation state of the branch switch to be verified changes, collecting the first operation data of the branch switch to be verified, wherein the first operation data at least includes a plurality of first active powers and a plurality of first phase currents of the branch switch to be verified; Obtaining the second operating data of the main switch in the at least one switch includes: collecting the second operating data of the main switch within a target time period, wherein the second operating data includes at least multiple second active powers and multiple second phase currents, and the target time period is the time period before the operating state changes.
3. The method according to claim 2, characterized in that The using the first operation data and the second operation data to verify the operation state of the branch switch to be verified after the change to obtain a verification result includes: Determine the first active power collected last among the plurality of the first active powers as the first target active power of the branch switch to be verified; Determine the first phase current collected last among the plurality of first phase currents as the first target phase current of the branch switch to be verified; Determining the second active power collected last among the plurality of the second active powers as the second target active power of the main switch; Determining the second phase current collected last among the plurality of second phase currents as the second target phase current of the main switch; The changed operating state is verified using the first target active power, the first target phase current, the second target active power, and the second target phase current to obtain the verification result.
4. The method according to claim 3, characterized in that The using the first target active power, the first target phase current, the second target active power and the second target phase current to verify the changed operating state to obtain the verification result includes: In response to the number of the branch switches to be verified being greater than a number threshold, determining a sum of a plurality of the first target active powers of a plurality of the branch switches to be verified and a sum of a plurality of the first target phase currents of a plurality of the branch switches to be verified; Using the second target active power, converting the sum of the plurality of the first target active powers to obtain an active power to be verified, and using the second target phase current, converting the sum of the plurality of the first target phase currents to obtain a phase current to be verified; The active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold to obtain the verification result.
5. The method according to claim 3, characterized in that: The using the first target active power, the first target phase current, the second target active power and the second target phase current to verify the changed operating state to obtain the verification result includes: In response to the number of the branch switches to be verified being not greater than the number threshold, using the second target active power to convert the first target active power to obtain the active power to be verified, and using the second target phase current to convert the first target phase current to obtain the phase current to be verified; The active power to be verified is verified using a power threshold, and the phase current to be verified is verified using a current threshold to obtain the verification result.
6. The method according to claim 4 or 5, characterized in that: The method of verifying the active power to be verified by using the power threshold and verifying the phase current to be verified by using the current threshold to obtain the verification result includes: In response to the active power to be verified being greater than the power threshold and the phase current to be verified being greater than the current threshold, determining a difference between two adjacent second active powers among a plurality of the second active powers; determining a difference between two adjacent second phase currents of a plurality of second phase currents in response to an absolute value of a difference between two of the second active powers satisfying a first value range, wherein the first target range is associated with the first target active power; In response to the absolute value of the difference between the two second-phase currents satisfying a second numerical range, the verification result is determined to be a first verification result, wherein the first verification result is used to characterize that the operating state of the branch switch to be verified is changed to the target operating state, and the second target range is associated with the first phase current.
7. The method according to claim 6, characterized in that The method further comprises: In response to the absolute value of the difference between the two second active powers not satisfying the first numerical range, and the number of the branch switches to be verified is greater than the number threshold, the second target active power is used to convert the multiple first target active powers of the multiple branch switches to be verified respectively to obtain multiple active powers to be verified, and the second target phase current is used to convert the multiple first target phase currents of the multiple branch switches to be verified to obtain multiple phase currents to be verified.
8. The method according to claim 6, characterized in that The method further comprises: In response to the absolute value of the difference between the two second-phase currents not satisfying the second numerical range, the verification result is determined to be a second verification result, wherein the second verification result is used to characterize that the operating state of the branch switch to be verified has not changed to the target operating state.
9. The method according to claim 8, characterized in that The method further comprises: Using the second verification result, triggering the collection of the first operation data and the second operation data; The operating state of the branch switch to be verified is verified by using the re-collected first operating data and the second operating data.
10. A device for determining a switch in a distribution network, characterized in that: include: A first determining unit, configured to determine an operating state of at least one switch in the distribution network; A second determining unit is used to determine, among the at least one switch, at least one branch switch to be verified whose operating state has changed; an acquisition unit, configured to acquire first operation data of the branch switch to be verified and second operation data of the main switch in the at least one switch, wherein the second operation data is associated with the on / off state of the line where the branch switch to be verified is located, and the branch switch to be verified is used to control the on / off state of the line; A verification unit, used to verify the operation state of the branch switch to be verified after the change by using the first operation data and the second operation data, and obtain a verification result, wherein the verification result is used to characterize the actual operation state of the branch switch to be verified after the change; The third determining unit is configured to determine, based on the verification result, a target branch switch in which the actual operating state after the change is a target operating state in at least one of the branch switches to be verified.
11. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute the method according to any one of claims 1 to 9.
12. A processor, characterized in that: The processor is used to run a program, wherein the program executes the method according to any one of claims 1 to 9 when being run by the processor.
13. A computer program product, characterized in that The method comprises computer instructions, which, when executed by a processor, implement the method according to any one of claims 1 to 9.