Novel power system power supply guarantee consumption method based on section power limiting classification
By optimizing the calculation and division of sections based on cross-sectional power limit classification in large-scale power grids, intermittent problems of renewable energy such as wind and light are solved, the stability of power supply and efficient utilization of resources are achieved, and the phenomenon of power abandonment is reduced .
Patent Information
- Application Number
- CN202411271838.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The prior art has failed to effectively solve the intermittent, volatility and randomness of renewable energy such as wind and light in large-scale power grids, and has not taken into account the characteristics and types of cross-sections, resulting in insufficient power supply and serious power abandonment.
Using a new power system method based on cross-sectional power limit classification, by establishing a constraint model, optimized calculations to maximize the total power generation of power in the section, divide limited and non-limited power sections, and optimize for different sections to maximize channels Utilization and minimize residual load fluctuations.
Effectively absorb clean water, wind, and light energy in large-scale power grids, improve the stability of power supply and resource utilization efficiency, and reduce the phenomenon of power abandonment.
Smart Images

Figure CN119093360A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of complementary operation of multiple power sources in multi-type sections of a large-scale power grid, and in particular to a novel method for ensuring power supply and consumption of power in a power system based on section power restriction classification. Background Art
[0002] Renewable energy sources such as wind and solar are highly intermittent, volatile, and random, making them difficult to absorb and causing serious power abandonment. Bundling wind, solar, and hydropower and establishing a multi-energy complementary system is an important way to reduce the impact of new energy grid connection and improve the efficiency of basin resource utilization. At present, there are many methods for water, wind, and solar complementarity in basins. These methods mainly focus on how to complement each other on the power generation side, but there are few complementary methods for large-scale power grids, and they do not involve the characteristics and types of sections in large-scale power grids. In addition, all existing methods use the same optimization strategy. Summary of the invention
[0003] In view of the above-mentioned deficiencies in the prior art, the present invention provides a new method for ensuring power supply and consumption in a power system based on section power restriction classification.
[0004] In order to achieve the above-mentioned object of the invention, the technical solution adopted by the present invention is:
[0005] A new method for ensuring power supply and consumption of power system based on section power restriction classification includes the following steps:
[0006] S1. Establish a constraint model for a new power system. Based on the constraint model of the new power system, perform optimization calculations with the goal of maximizing the total power generation of all power sources in the section to obtain optimization calculation results for the new power system.
[0007] S2. According to the optimization calculation results of the new power system, the sections in the new power system are divided into restricted power sections and non-restricted power sections;
[0008] S3. Optimize the restricted power sections with the goal of maximizing channel utilization, and optimize the non-restricted power sections with the goal of minimizing the residual load fluctuation after the combined regulation of hydro, wind and solar power sources, so as to obtain the power supply and consumption results of the new power system.
[0009] Furthermore, in step S1, a constraint model of a new power system is established, including the following steps:
[0010] A1. Establish the section transmission capacity constraint model as follows:
[0011]
[0012] in: is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d;
[0013] A2. Establish the operation constraint model of the hydropower station;
[0014] A3. Establish output constraint model of wind and solar power stations;
[0015] A4. Combine the section transmission capacity constraint model, the hydropower station operation constraint model and the wind and solar power station output constraint model to establish a constraint model for a new power system.
[0016] Further, step A2 includes the following steps:
[0017] A21. Construct a reservoir capacity constraint model for hydropower stations with daily or higher water storage and regulation capabilities:
[0018] |V i,end -V i,begin |=V i,allow if rc i =1
[0019] Where: V i,begin 、V i,end are the reservoir capacities at the beginning and end of the day of the i-th hydropower station, V i,allow is the daily regulating storage capacity of the i-th reservoir power station, rc i is the regulation capacity of the power station, with a value of 1 for daily regulation and above, and 0 otherwise;
[0020] A22. Build the operation constraint model of all hydropower stations;
[0021] A23. Combine the regulation reservoir capacity constraint model of hydropower stations with daily or higher water storage regulation capacity and the operation constraint models of all hydropower stations to establish the operation constraint model of the hydropower stations.
[0022] Furthermore, in step A22, the operation constraint models of all hydropower stations include a hydropower output constraint model, a reservoir water level constraint model, a reservoir water level daily fluctuation constraint model, a discharge flow constraint model, a power generation flow constraint model, a time dimension water balance constraint model, a space dimension water balance constraint model and a flow relationship constraint model.
[0023] Furthermore, in step A3, the output constraint model of the wind-solar power station includes a calculated output constraint model of the wind-solar power station and an actual absorbed output constraint model of the wind-solar power station.
[0024] Furthermore, in step S1, an optimization calculation is performed with the goal of maximizing the total power generation of all power sources in the section, and the optimization calculation result of the new power system is obtained as follows:
[0025]
[0026] Where: d is the section identifier, t is the time period identifier, in is within the section, E d is the grid-connected power of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
[0027] Further, step S2 includes the following steps:
[0028] S21. Construct the conditional model of the restricted power section as follows:
[0029]
[0030] Where: t is the time period identifier, T is the number of calculation time periods, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d, is the abandoned power output of section d during period t, which is obtained by superimposing the abandoned hydropower output, abandoned wind power output, and abandoned solar power output. This is the time period when the output of section d is the largest;
[0031] S22. According to the optimization calculation results of the new power system, determine whether the section in the new power system meets the conditional model of the restricted power section; if so, classify it as a restricted power section, otherwise classify it as a non-restricted power section.
[0032] Furthermore, in step S3, the restricted electrical section is optimized with the goal of maximizing channel utilization, as follows:
[0033]
[0034] Where: d is the section identifier, t is the time period identifier, in is within the section, u d is the transmission channel utilization rate of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, TC d is the transmission capacity of section d, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
[0035] Further, in step S3, the non-restricted power section is optimized with the goal of minimizing the residual load fluctuation after the combined regulation of the hydropower, wind power and solar power sources, as follows:
[0036]
[0037] Where: f is the residual load fluctuation within the calculation period, R t is the residual load value in period t, is the average value of the residual load during the calculation period, L t is the load level of the power grid during period t, ain is the inter-provincial input identifier, N ain,t is the inter-provincial input power in period t, D is the total transmission section, j=w,s,h is the power source category identifier, w represents wind farm, s represents photovoltaic farm, h represents hydropower farm, out is the out-of-section identifier, is the power output of the i-th power station of the j-th type power source outside the section in the t-th period, n j is the number of power stations of the jth type of power supply.
[0038] The beneficial effects of the present invention are:
[0039] The present invention establishes a constraint model of the new power system, and based on the constraint model of the new power system, performs optimization calculation with the goal of maximizing the total power generation of all power sources in the section to obtain the optimization calculation result of the new power system, and then divides the sections in the new power system into restricted power sections and non-restricted power sections according to the optimization calculation result of the new power system. Finally, the restricted power sections are optimized with the goal of maximizing channel utilization, and the non-restricted power sections are optimized with the goal of minimizing the residual load fluctuation after the joint regulation of water, wind and solar power sources to obtain the power supply and consumption results of the new power system. This process takes into account the large-scale power grid in hydropower-rich areas, when transmitting electricity at different power-restricted sections, divides sections into different types, and optimizes each section progressively for different types of sections, so that the power supply and consumption results of the new power system obtained can consume the clean energy of water, wind and solar power in each section. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 The figure is a flow chart of a new method for ensuring power supply and consumption in a power system based on section power restriction classification. DETAILED DESCRIPTION
[0041] The specific implementation modes of the present invention are described below so that those skilled in the art can understand the present invention. However, it should be clear that the present invention is not limited to the scope of the specific implementation modes. For those of ordinary skill in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the attached claims, these changes are obvious, and all inventions and creations utilizing the concept of the present invention are protected.
[0042] like Figure 1 As shown, a new method for ensuring power supply and consumption of power system based on section power restriction classification includes steps S1-S3, which are as follows:
[0043] S1. Establish a constraint model for the new power system. Based on the constraint model of the new power system, perform optimization calculations with the goal of maximizing the total power generation of all power sources in the section to obtain the optimization calculation results of the new power system.
[0044] In an optional embodiment of the present invention, the present invention establishes a constraint model of a new power system, comprising the following steps:
[0045] A1. Establish the section transmission capacity constraint model as follows:
[0046]
[0047] in: is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d.
[0048] A2. Establish an operation constraint model for the hydropower station.
[0049] Step A2 includes the following steps:
[0050] A21. Construct a reservoir capacity constraint model for hydropower stations with daily or higher water storage and regulation capabilities:
[0051] |V i,end -V i,begin |=V i,allow if rc i =1
[0052] Where: V i,begin 、V i,end are the reservoir capacities at the beginning and end of the day of the i-th hydropower station, V i,allow is the daily regulating storage capacity of the i-th reservoir power station, rc iIt is the regulation capacity of the power station. The value is 1 for daily regulation and above, otherwise it is 0.
[0053] A22. Construct operation constraint models for all hydropower stations.
[0054] The operation constraint models of all hydropower stations include hydropower output constraint model, reservoir water level constraint model, reservoir water level daily fluctuation constraint model, discharge flow constraint model, power generation flow constraint model, time dimension water balance constraint model, space dimension water balance constraint model and flow relationship constraint model.
[0055] The present invention constructs a hydropower output constraint model as follows:
[0056]
[0057] in: are the minimum and maximum output and power generation flow allowed for the ith power station in the tth period, δ i is the water consumption rate of the ith hydropower station, λ is the conversion coefficient of electricity units, λ=3600.
[0058] The present invention constructs a reservoir water level constraint model as follows:
[0059]
[0060] Where: Z i,t is the water level of the ith hydropower station at the end of the tth period, are the upper and lower limits of the water level of the ith hydropower station at the end of the tth period, respectively.
[0061] The present invention constructs a reservoir water level daily fluctuation constraint model as follows:
[0062] |Z i,end -Z i,begin |≤Z i,allow
[0063] Where: Z i,begin , Z i,end are the water levels at the beginning and end of the day of the i-th reservoir, Z i,allow is the daily water level variation allowed for the ith reservoir. Generally, earth-rock dams are equipped with daily water level variation constraints.
[0064] The present invention constructs a downstream flow constraint model as follows:
[0065]
[0066] Where: Q i,t is the discharge flow of the i-th hydropower station in the t-th period, are the maximum and minimum discharge flows of the ith hydropower station in period t, respectively.
[0067] The present invention constructs a power generation flow constraint model as follows:
[0068]
[0069] in: and are the maximum and minimum power generation flows of the ith hydropower station in the tth period, respectively.
[0070] The present invention constructs a time dimension water balance constraint model, which is:
[0071] V i,t =V i,t-1 +[R i,t -Q i,t ]·Δts
[0072] Where: V i,t-1 、V i,t are the initial and final storage capacities of the ith hydropower station at the tth period, R i,t is the inflow of the ith hydropower station in the tth period, and Δts is the number of seconds in each period.
[0073] The present invention constructs a spatial dimension water balance constraint model, which is:
[0074]
[0075] Where: R d,t is the inflow of the downstream hydropower station in the tth period, I d,t is the interval flow of the downstream hydropower station in the tth period, τ u,d It is the time taken for the outflow from the upstream power station u to reach the reservoir of the downstream power station d.
[0076] The present invention constructs a flow relationship constraint model as follows:
[0077]
[0078] Where: S i,t is the water discharge of the i-th hydropower station in the t-th period.
[0079] A23. Combine the regulation reservoir capacity constraint model of hydropower stations with daily or higher water storage regulation capacity and the operation constraint models of all hydropower stations to establish the operation constraint model of the hydropower stations.
[0080] A3. Establish output constraint model of wind and solar power stations.
[0081] The output constraint model of the wind-solar power station includes the calculated output constraint model of the wind-solar power station and the actual output constraint model of the wind-solar power station.
[0082] The present invention constructs a calculation output constraint model for a wind and solar power station, which is:
[0083]
[0084] in: is the calculated output of the i-th wind power station in the t-th period, is the calculated output of the ith PV power station in the tth period, g i,t is the output coefficient of the i-th wind power station in period t, f i,t is the output coefficient of the ith photovoltaic power station in period t, IC w,i is the installed capacity of the i-th wind power station, IC s,i is the installed capacity of the i-th photovoltaic power station.
[0085] The present invention constructs the actual consumption output constraint model of the wind and solar power station, which is:
[0086]
[0087] Where: N wi,t is the calculated output of the i-th wind power station in the t-th period, N si,t is the calculated output of the ith PV power station in the tth period.
[0088] A4. Combine the section transmission capacity constraint model, the hydropower station operation constraint model and the wind and solar power station output constraint model to establish a constraint model for a new power system.
[0089] The present invention performs optimization calculation with the goal of maximizing the total power generation of all power sources in the section, and obtains the optimization calculation results of the new power system, which are:
[0090]
[0091] Where: d is the section identifier, t is the time period identifier, in is within the section, E d is the grid-connected power of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
[0092] S2. According to the optimization calculation results of the new power system, the sections in the new power system are divided into restricted power sections and non-restricted power sections.
[0093] In an optional embodiment of the present invention, step S2 includes the following steps:
[0094] S21. Construct the conditional model of the restricted power section as follows:
[0095]
[0096] Where: t is the time period identifier, T is the number of calculation time periods, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d, is the abandoned power output of section d during period t, which is obtained by superimposing the abandoned hydropower output, abandoned wind power output, and abandoned solar power output. This is the period when the online output of section d is the largest.
[0097] S22. According to the optimization calculation results of the new power system, determine whether the section in the new power system meets the conditional model of the restricted power section; if so, classify it as a restricted power section, otherwise classify it as a non-restricted power section.
[0098] S3. Optimize the restricted power sections with the goal of maximizing channel utilization, and optimize the non-restricted power sections with the goal of minimizing the residual load fluctuation after the combined regulation of hydro, wind and solar power sources, so as to obtain the power supply and consumption results of the new power system.
[0099] In an optional embodiment of the present invention, the present invention optimizes the restricted electrical section with the goal of maximizing channel utilization, as follows:
[0100]
[0101] Where: d is the section identifier, t is the time period identifier, in is within the section, u d is the transmission channel utilization rate of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, TC d is the transmission capacity of section d, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
[0102] The present invention optimizes the non-restricted power section with the goal of minimizing the residual load fluctuation after the combined regulation of water, wind and solar power sources, as follows:
[0103]
[0104] Where: f is the residual load fluctuation within the calculation period, R t is the residual load value in period t, is the average value of the residual load during the calculation period, L t is the load level of the power grid during period t, ain is the inter-provincial input identifier, N ain,t is the inter-provincial input power in period t, D is the total transmission section, j=w,s,h is the power source category identifier, w represents wind farm, s represents photovoltaic farm, h represents hydropower farm, out is the out-of-section identifier, is the power output of the i-th power station of the j-th type power source outside the section in the t-th period, n j is the number of power stations of the jth type of power supply.
[0105] The present invention is based on the constraint model of the new power system and optimizes the restricted power sections and non-restricted power sections in the above-mentioned way. It takes into account the large-scale power grid in the hydropower-rich area to transmit electricity in different restricted power sections, divides the sections into different types, and optimizes each section in a progressive manner for different types of sections to obtain the power supply and consumption results of the new power system, which can consume the clean energy of water, wind and light in each section.
[0106] Those skilled in the art will appreciate that the embodiments described herein are intended to help readers understand the principles of the present invention, and should be understood that the protection scope of the present invention is not limited to such specific statements and embodiments. Those skilled in the art can make various other specific variations and combinations that do not deviate from the essence of the present invention based on the technical revelations disclosed by the present invention, and these variations and combinations are still within the protection scope of the present invention.
Claims
1. A new method for ensuring power supply and consumption of power system based on section power restriction classification, characterized in that: The following steps are involved: S1. Establish a constraint model for a new power system. Based on the constraint model of the new power system, perform optimization calculations with the goal of maximizing the total power generation of all power sources in the section to obtain optimization calculation results for the new power system. S2. According to the optimization calculation results of the new power system, the sections in the new power system are divided into restricted power sections and non-restricted power sections; S3. Optimize the restricted power sections with the goal of maximizing channel utilization, and optimize the non-restricted power sections with the goal of minimizing the residual load fluctuation after the combined regulation of hydro, wind and solar power sources, so as to obtain the power supply and consumption results of the new power system.
2. According to the new power system power supply and consumption method based on section power restriction classification according to claim 1, it is characterized in that: In step S1, a constraint model of a new power system is established, including the following steps: A1. Establish the section transmission capacity constraint model as follows: in: is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d; A2. Establish the operation constraint model of the hydropower station; A3. Establish output constraint model of wind and solar power stations; A4. Combine the section transmission capacity constraint model, the hydropower station operation constraint model and the wind and solar power station output constraint model to establish a constraint model for a new power system.
3. The new power system power supply and consumption method based on section power restriction classification according to claim 2 is characterized in that: Step A2 includes the following steps: A21. Construct a reservoir capacity constraint model for hydropower stations with daily or higher water storage and regulation capabilities: |V i,end -V i,begin |=V i,allow if rc i =1 Where: V i,begin 、V i,end are the reservoir capacities at the beginning and end of the day of the i-th hydropower station, V i,allow is the daily regulating storage capacity of the i-th reservoir power station, rc i is the regulation capacity of the power station, with a value of 1 for daily regulation and above, and 0 otherwise; A22. Build the operation constraint model of all hydropower stations; A23. Combine the regulation reservoir capacity constraint model of hydropower stations with daily or higher water storage regulation capacity and the operation constraint models of all hydropower stations to establish the operation constraint model of the hydropower stations.
4. The new power system power supply and consumption method based on section power restriction classification according to claim 3 is characterized in that: In step A22, the operation constraint models of all hydropower stations include hydropower output constraint model, reservoir water level constraint model, reservoir water level daily fluctuation constraint model, discharge flow constraint model, power generation flow constraint model, time dimension water balance constraint model, space dimension water balance constraint model and flow relationship constraint model.
5. The new power system power supply and consumption method based on section power restriction classification according to claim 2 is characterized in that: In step A3, the output constraint model of the wind-solar power station includes a calculated output constraint model of the wind-solar power station and an actual absorbed output constraint model of the wind-solar power station.
6. The new power system power supply and consumption method based on section power restriction classification according to claim 1 is characterized in that: In step S1, an optimization calculation is performed with the goal of maximizing the total power generation of all power sources in the section, and the optimization calculation result of the new power system is obtained as follows: Where: d is the section identifier, t is the time period identifier, in is within the section, E d is the online power of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
7. The new power system power supply and consumption method based on section power restriction classification according to claim 1 is characterized in that: Step S2 includes the following steps: S21. Construct the conditional model of the restricted power section as follows: Where: t is the time period identifier, T is the number of calculation time periods, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, is the inter-provincial power transmission of section d in period t, aout is the inter-provincial power transmission identifier, TC d is the transmission capacity of section d, is the abandoned power output of section d during period t, which is obtained by superimposing the abandoned hydropower output, abandoned wind power output, and abandoned solar power output. This is the time period when the output of section d is the largest; S22. According to the optimization calculation results of the new power system, determine whether the section in the new power system meets the conditional model of the restricted power section; if so, classify it as a restricted power section, otherwise classify it as a non-restricted power section.
8. The new power system power supply and consumption method based on section power restriction classification according to claim 1 is characterized in that: In step S3, the restricted electrical section is optimized with the goal of maximizing channel utilization, as follows: Where: d is the section identifier, t is the time period identifier, in is within the section, u d is the transmission channel utilization rate of section d, is the total power generation output of hydropower, wind power and solar power in section d during period t, is the power load in section d during period t, TC d is the transmission capacity of section d, T is the number of calculation periods, Δt is the number of hours in each calculation period, aout is the identifier for the inter-provincial transmission of electricity, is the inter-provincial power transmission of section d in period t.
9. The new power system power supply and consumption method based on section power restriction classification according to claim 1 is characterized in that: In step S3, the non-restricted power section is optimized with the goal of minimizing the residual load fluctuation after the combined regulation of the hydropower, wind power and solar power sources, as follows: Where: f is the residual load fluctuation within the calculation period, R t is the residual load value in period t, is the average value of the residual load during the calculation period, L t is the load level of the power grid during period t, ain is the inter-provincial input identifier, N ain,t is the inter-provincial input power in period t, D is the total transmission section, j=w,s,h is the power source category identifier, w represents wind farm, s represents photovoltaic farm, h represents hydropower farm, out is the out-of-section identifier, is the power output of the i-th power station of the j-th type power source outside the section in the t-th period, n j is the number of power stations of the jth type of power supply.
Citation Information
Patent Citations
Source and storage collaborative optimization operation method for improvement of section conveying capacity
CN115967085A
Probabilistic capacity planning in a power system
US20240162710A1