Elemental arsenic production system
By dividing the automatic processing area and the manual processing area in the elemental arsenic production system, and using automated equipment and induction control, the safety hazards of manual operation and the problem of low automation are solved, and higher safety and production efficiency are achieved.
Patent Information
- Application Number
- CN202411515901.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-29
- Publication Date
- 2024-12-20
AI Technical Summary
The existing elemental arsenic production system needs to manually enter a dangerous environment for operation during the production process, resulting in high safety hazards, low degree of automation, high labor intensity, and frequent entry and exit requires frequent purification and inconvenience to wear protective clothing.
A single arsenic production system was designed, which divided the production area into an automatic processing area and a manual processing area. Automatic equipment was used for sublimation, feeding, lifting and conveying operations, and automatic control was realized through induction equipment and center console to reduce manual contact. Risk.
It improves the degree of automation of the production system, reduces the risk of manual contact, reduces the incidence of safety accidents, reduces the inconvenience of frequent purification and wearing protective clothing, and improves the efficiency of continuous production.
Smart Images

Figure CN119162469A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of elemental arsenic production systems, and in particular relates to an elemental arsenic production system. Background Art
[0002] Arsenic trioxide is a non-metallic element that plays an important role in alloy manufacturing, pesticides and insecticides, medicines, glass manufacturing, semiconductor and laser technology. Arsenic trioxide is often produced as waste gas in metal smelting and other processes. In order to increase its utilization rate, arsenic trioxide can be used to reduce elemental arsenic. During the reduction, arsenic trioxide needs to be sublimated, so a sublimation furnace is needed. During the reduction and sublimation process, arsenic trioxide is a highly toxic compound. Its toxicity mainly comes from its chemical structure and the reaction in the human body. When arsenic trioxide sublimates, it decomposes to produce arsenic and other compounds. These products will form highly toxic gases under certain conditions, especially when encountering high heat. The gas produced by the sublimation of diarsenic is highly toxic, so the gas discharged from the sublimation furnace needs to be collected and processed by a collecting device. When the existing technology is used, the traditional production system needs to manually enter the production environment to change furnaces, add materials, etc. during the production of elemental arsenic. Although protective clothing can be worn, it is impossible to be completely immune to harm. The workers are still more or less affected by harmful gases, especially when there are omissions in protection, dangerous accidents are prone to occur, and the risk is high. At the same time, frequent entry and exit during the production process also requires frequent purification and wearing of protective clothing, which is inconvenient. In addition, when the existing technology is used, the production system has a low degree of automation, continuous production requires a high labor force, and the labor intensity of the workers is high, which is not convenient for continuous production. Summary of the invention
[0003] 1. Technical issues to be resolved
[0004] In order to overcome the shortcomings of the existing technology, a single arsenic production system is proposed to solve the problem that when the existing technology is used, the traditional production system needs to manually enter the production environment to perform operations such as furnace replacement and material addition during the single arsenic production process. Although protective clothing can be worn, it is impossible to be completely immune to harm. The staff will still be more or less affected by harmful gases. Especially when the protection is neglected, dangerous accidents are prone to occur, which is highly dangerous. At the same time, frequent entry and exit during the production process also requires frequent purification and wearing of protective clothing, which is relatively inconvenient.
[0005] Secondly, it is to solve the problem that when the existing technology is used, the production system has a low degree of automation, a high labor force required for continuous production, high labor intensity for workers, and is not convenient for continuous production.
[0006] (II) Technical solution
[0007] The present invention is implemented by the following technical solution: The present invention proposes a single substance arsenic production system, the structure of which includes an automatic processing area and a manual processing area, wherein the automatic processing area and the manual processing area are respectively located in independent rooms;
[0008] It also includes air extraction equipment, sublimation equipment, induction equipment, lifting equipment, central console, feeding equipment, conveying equipment, replacement equipment and sublimation furnace, wherein the sublimation equipment, induction equipment, lifting equipment, feeding equipment, conveying equipment and replacement equipment are all arranged in the automatic processing area, the feeding end of the feeding equipment and the processing end of the conveying equipment are located in the manual processing area, the automatic processing area and the manual processing area are both provided with air extraction equipment, and the manual processing area is also provided with a central console;
[0009] The central console is electrically connected to the air extraction equipment, the sublimation equipment, the induction equipment, the lifting equipment, the feeding equipment, the conveying equipment and the replacement equipment;
[0010] The air extraction equipment is used for purifying and extracting ambient air and air at each processing equipment;
[0011] The sublimation equipment is used for heating and sublimating raw materials in the sublimation furnace;
[0012] The lifting equipment is used for lifting and replacing the sublimation furnace at the sublimation equipment and replacement equipment;
[0013] The feeding device is located on one side of the replacement device and can be moved above the replacement device, and the feeding device is used to add raw materials to the sublimation furnace in the replacement device;
[0014] The conveying device is connected to the replacement device, and the conveying device is a circulating conveyor belt group, and the conveying device is used for automatic conveying when the sublimation furnace needs to be cleaned or maintained;
[0015] The sensing device is used for positioning each device during automatic operation.
[0016] Furthermore, the sensing device includes a first sensor, a second sensor, a third sensor, an assembly rod, a fourth sensor, a fifth sensor, a sixth sensor, a seventh sensor, an eighth sensor and a ninth sensor, the fourth sensor being assembled in the sublimation device through the assembly rod, the second sensor and the third sensor being used for docking when the feeding device is replenishing materials, the sixth sensor being assembled in the replacement device, the eighth sensor and the ninth sensor being assembled on the lifting device, the eighth sensor being used for vertical positioning of the lifting device, the ninth sensor being used for horizontal positioning of the lifting device, the first sensor being used for positioning of the lifting device when it is moving, the sixth sensor being used for positioning of the sublimation furnace in the replacement device, the fourth sensor being used for positioning of the sublimation furnace in the sublimation device, and the seventh sensor being used for positioning of items on the conveying device when they are transported to the replacement device.
[0017] Furthermore, the air extraction equipment includes a fresh air inlet pipe, an environmental exhaust pipe and an equipment exhaust pipe, the fresh air inlet pipe and the environmental exhaust pipe are used for purifying the ambient air, the fresh air inlet pipe is arranged below the side wall of the automatic treatment area and the manual treatment area, the environmental exhaust pipe is arranged above the side wall of the automatic treatment area and the manual treatment area, and the equipment exhaust pipe is used for gas extraction of each device;
[0018] It also includes a first electrically controlled valve, which is arranged at the connection between the equipment exhaust pipe and the inside of each equipment.
[0019] Furthermore, the sublimation equipment includes a heating seat, a chassis, a first electric control cover, a fixed exhaust pipe, an electric control telescopic tube, a maintenance door, a door lock, a heating furnace slot and a sublimation chamber side panel. A chassis is provided on one side of the top of the heating seat, and a heating furnace slot is provided on the other side of the top of the heating seat. The heating furnace slot is arranged between the heating seat, the chassis, the first electric control cover, the maintenance door and the sublimation chamber side panel. The first electric control cover is arranged directly above the heating furnace slot. A door lock is also provided at the assembly location of the maintenance door. The chassis is adjacent to the maintenance door side and is equipped with a fixed exhaust pipe and an electric control telescopic tube between the side panels of the sublimation chamber. Both the fixed exhaust pipe and the electric control telescopic tube are connected to the exhaust pipe of the equipment. The electric control telescopic tube can be extended and retracted from the chassis toward the maintenance door by electric control. The electric control telescopic tube is provided in the same number as the heating furnace slot and is correspondingly arranged above the heating furnace slot. The fixed exhaust pipe and the electric control telescopic tube are both located at the bottom of the first electric control cover. The number of the fourth sensors is the same as the heating furnace slot and they are assembled corresponding to the positions of the heating furnace slots.
[0020] Furthermore, the replacement equipment includes a second electric control cover, a replacement bin plate, an electric control cover lock and a furnace placement slot. The replacement bin plate is a sealing frame plate. The top of the replacement bin plate is equipped with a second electric control cover, and the opening of the second electric control cover is equipped with an electric control cover lock. A furnace placement slot is provided on one side within the range of the replacement bin plate. The number of the furnace placement slots is greater than or equal to the heating furnace slots. The setting direction of the multiple furnace placement slots is consistent with the setting direction of the multiple heating furnace slots. One side of the conveying equipment is arranged in the replacement bin plate and is parallel to the setting direction of the multiple furnace placement slots. The number of the sixth sensors is twice the number of the furnace placement slots, and every 2 sixth sensors are correspondingly arranged on both sides of each of the furnace placement slots.
[0021] Furthermore, the lifting device includes a mobile assembly rod, a mobile assembly beam, a first mobile seat, a connector, a first electrically controlled lifting component and a second mobile seat. The mobile assembly beam is fixed above the side wall of the automatic processing area room. The first mobile seat is fixed at both ends of the mobile assembly rod. The first mobile seat is assembled on the mobile assembly beam and can move by electric control. The second mobile seat is assembled on the mobile assembly rod and can move by electric control. The bottom of the second mobile seat is connected to a connector through the first electrically controlled lifting component. The connector is used for assembling and fixing the sublimation furnace during lifting. The mobile assembly rod is parallel to the arrangement direction of the multiple heating furnace slots. The first sensor is assembled on the wall of the automatic processing area room and has the same height as the second mobile seat. The first sensor is located above the sublimation equipment. The first sensor and the number are the same as the number of furnace slots and are assembled corresponding to the positions where the furnace slots are placed. The second mobile seat is equipped with a ninth sensor adjacent to the first sensor side. The ninth sensor determines the position by identifying with the first sensor. The bottom of the second mobile seat is equipped with an eighth sensor adjacent to the first sensor side. The eighth sensor determines the position by identifying with the sixth sensor and the third sensor.
[0022] Furthermore, the feeding equipment includes a hoist, a second electrically-controlled valve, an electrically-controlled movable frame, a track, a feed joint, a storage hopper, a screw conveyor, a second electrically-controlled lifting component, a hose and a discharge docking ring. The inlet side of the hoist is arranged in a manual processing area, and the outlet side of the hoist is arranged in an automatic processing area. The track is arranged on both sides of the replacement bin plate. The electrically-controlled movable frame is assembled on the track and can move on the track. The storage hopper is equipped with a screw conveyor at the bottom of the storage hopper. The discharge port of the screw conveyor is equipped with a hose. A discharge docking ring is fixed to the bottom of the hose. A feed joint is arranged at the top of the storage hopper. The top of the discharge docking ring is connected to the screw conveyor through the second electrically-controlled lifting component. The fifth sensor is arranged on the discharge docking ring adjacent to the sixth sensor. When the storage hopper is fed, the feed joint is located below the discharge port of the hoist. After the discharge docking ring moves, it can be located directly above the furnace slot. A second sensor is arranged at the side end of the discharge port of the hoist, and a third sensor is arranged at the side end of the feed joint.
[0023] Furthermore, the conveying equipment includes a cleaning conveyor belt, a conveyor belt guard, an exhaust joint, a rotary conveyor belt, a gravity sensing base and an induction conveyor belt. The cleaning conveyor belt is arranged in the manual processing area, the gravity sensing base is arranged in the range of replacing the warehouse plate, an induction conveyor belt is installed above the gravity sensing base, the assembly direction of the induction conveyor belt is parallel to the furnace trough, the rotary conveyor belt is used to connect the cleaning conveyor belt and the induction conveyor belt, a conveyor belt guard is provided at the assembly place of the rotary conveyor belt, an exhaust joint is provided on the top of the conveyor belt guard, and the exhaust joint can be connected to the exhaust pipe of the equipment.
[0024] Furthermore, the sublimation furnace includes an upper furnace body and a lower furnace body, the upper furnace body is placed and assembled on the lower furnace body, an upper lifting ring is fixed to the side end of the upper furnace body, and a lower lifting ring is assembled to the side end of the lower furnace body, and the connecting head lifts the upper furnace body and the lower furnace body through the upper lifting ring and the lower lifting ring, and the seventh sensor is arranged on the side end of the replacement warehouse plate, and the seventh sensor is used to identify and determine the position of the upper furnace body.
[0025] Furthermore, a method for operating an elemental arsenic production system comprises the following steps:
[0026] First, the lower furnace body is placed in the furnace slot, and the upper furnace body is placed on the induction conveyor belt and recorded through the central console;
[0027] Second, during automatic feeding, the central console controls the second electric control cover to open, and then controls the electric control moving frame to drive the storage hopper to move to the specified position. During the movement, the fifth sensor determines the corresponding furnace slot position through identification induction with the corresponding sixth sensor;
[0028] Third, after the fifth sensor recognizes the corresponding sixth sensor, the central console controls the electric control moving frame to stop moving and controls the second electric control lifting assembly to lower the discharge docking ring. After the discharge docking ring is lowered, the central console controls the screw conveyor to add material to the lower furnace body. After adding one lower furnace body, it automatically moves to the next lower furnace body to add material until the feeding is completed;
[0029] Fourth, after the feeding is completed, the central console controls the electric control moving frame to move to the bottom of the elevator discharge port through the identification of the second sensor and the third sensor, and then the central console controls the lifting equipment to move to the top of the replacement equipment, and locates the upper furnace body on the induction conveyor belt through the identification of the ninth sensor and the first sensor, combined with the eighth sensor and the sixth sensor adjacent to the induction conveyor belt, and then controls the first electric control lifting component to lower the connecting head to clamp the upper furnace body, and then lifts the first electric control lifting component to a certain distance for horizontal movement, and locates and places the furnace slot through the identification of the eighth sensor and the sixth sensor far away from the induction conveyor belt, and finally lowers the connecting head to combine the upper furnace body and the lower furnace body;
[0030] Fifth, during sublimation, the central console controls the first electric control cover to open, and then controls the lifting device to move above the replacement device, and lowers the connection head to clamp the upper furnace body and the lower furnace body by identifying the corresponding furnace slot, and then raises the connection head and locates the heating furnace slot according to the identification of the ninth sensor and the first sensor, and moves it by combining the identification of the eighth sensor and the third sensor, and then lowers the upper furnace body and the lower furnace body and places them in the heating furnace slot, and then raises the connection head and covers the first electric control cover, and finally the electric control telescopic tube extends to exhaust the sublimation and start the heating seat to sublimate;
[0031] Sixth, another group of sublimation furnaces can be arranged at the furnace slot for automatic feeding. After the feeding is completed, the second electric control cover is closed as a preparation. After the sublimation furnace of the sublimation equipment is completed, the lifting device can alternately replace the preparation sublimation furnace with the sublimation furnace that has completed sublimation;
[0032] Seventh, the sublimation furnace after sublimation can be cooled in the furnace tank. After cooling, the upper furnace body can be positioned and lifted by the lifting equipment to the induction conveyor belt, and then transported to the cleaning conveyor belt through the induction conveyor belt and the rotary conveyor belt to pick up the materials. After picking up the materials, they can be transported back to the induction conveyor belt through the rotary conveyor belt to prepare for capping after adding materials. When transporting back to the induction conveyor belt, it is positioned by the seventh sensor. When necessary, the lower furnace body can also be lifted and placed on the induction conveyor belt to be transported to the cleaning conveyor belt for maintenance;
[0033] Eighth, when refilling the storage hopper, the elevator is started after the second sensor and the third sensor identify, and the second electric control valve is opened at the same time, and then the storage hopper is refilled by adding material at the feed inlet of the elevator;
[0034] Ninth, when the above steps are running, the air extraction equipment can automatically open and close the fresh air inlet pipes, environmental exhaust pipes and equipment exhaust pipes according to needs.
[0035] (III) Beneficial effects
[0036] One of the above technical solutions has the following advantages or beneficial effects:
[0037] In order to solve the problem that when the existing technology is used, the traditional production system needs to manually enter the production environment to perform operations such as furnace replacement and material addition during the production of elemental arsenic. Although protective clothing can be worn, it is impossible to be completely immune to harm. The workers are still more or less affected by harmful gases. Especially when protection is neglected, dangerous accidents are prone to occur, which is very dangerous. At the same time, frequent entry and exit during the production process also requires frequent purification and wearing of protective clothing, which is relatively inconvenient. In addition, when the existing technology is used, the production system has a low degree of automation, continuous production requires a high labor force, the labor intensity of the workers is high, and it is not convenient for continuous production. The production area is divided into an automatic area and a manual area, and the automatic area is equipped with automatic feeding, sublimation, cooling preparation, lifting and conveying equipment. The sublimation equipment and the sublimation furnace in the cooling replacement equipment are automatically switched through the lifting equipment, and the sublimation processing and cooling placement can be automatically performed, and the cooled furnace body can be automatically transported to the manual area for material collection. The furnace body after material collection can be automatically transported back to the placement place and automatically lifted and placed by the lifting equipment, and can be automatically prepared for feeding through the feeding equipment. The high degree of automation can greatly reduce manual contact during production and reduce production risks, thereby reducing the inconvenience of frequent entry and exit purification and wearing protective clothing. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings:
[0039] Figure 1 This is a schematic diagram of the partitioning of a system for producing elemental arsenic according to the present invention;
[0040] Figure 2 It is a schematic diagram of the structure of the device of the present invention when it is not unfolded;
[0041] Figure 3 It is a schematic diagram of the structure of the device of the present invention after being unfolded;
[0042] Figure 4 It is a schematic diagram of the structure of the sublimation equipment of the present invention after being unfolded;
[0043] Figure 5 It is a cross-sectional structural schematic diagram of the side view of the assembly of the feeding device and the replacement device of the present invention;
[0044] Figure 6 It is a cross-sectional structural schematic diagram of a top view of a replacement device of the present invention;
[0045] Figure 7 This is a schematic diagram of the structure of Embodiment 2 of the present invention;
[0046] Figure 8 It is a schematic cross-sectional structure diagram of a side view after combining the fourth embodiment with the sixth embodiment of the present invention;
[0047] Fig. 9 It is a schematic cross-sectional structure diagram of a side view of Embodiment 6 of the present invention;
[0048] Fig.10 It is a schematic cross-sectional structure diagram of a side view of Embodiment 3 of the present invention;
[0049] In the figure: automatic processing area -1, manual processing area -2, air extraction equipment -3, sublimation equipment -4, induction equipment -5, lifting equipment -6, central control panel -7, feeding equipment -8, conveying equipment -9, replacement equipment -10 and sublimation furnace -11, fresh air inlet pipe -3a, environmental exhaust pipe -3b, equipment exhaust pipe -3c, heating seat -4a, chassis -4b, first electric control cover -4c, fixed exhaust pipe -4d, electric control telescopic pipe -4e, maintenance door -4f, door lock -4g, heating furnace slot -4h, sublimation chamber side panel - 4i, first sensor - 5a, second sensor - 5b, third sensor - 5c, assembly rod - 5d, fourth sensor - 5e, fifth sensor - 5f, sixth sensor - 5g, seventh sensor - 5h, eighth sensor - 5i, ninth sensor - 5j, mobile assembly rod - 6a, mobile assembly beam - 6b, first mobile seat - 6c, connector - 6d, first electric control lifting component - 6e, second mobile seat - 6f, lifting assembly ring - 6d1, electric push rod - 6d2, push rod assembly plate - 6d3, fixed connecting rod -6d4, motor -6e1, rope reel -6e2, encoder -6e3, telescopic bracket -6e4, rope -6e5, hoist -8a, second electric control valve -8b, electric control moving frame -8c, track -8d, feed connector -8e, storage hopper -8f, screw conveyor -8g, second electric control lifting component -8h, hose -8i, discharge docking ring -8j, cleaning conveyor belt -9a, conveyor belt cover -9b, exhaust connector -9c, rotary conveyor belt -9d, gravity sensing base -9e, sensing conveyor belt -9f , second electric control cover - 10a, replacement of warehouse plate - 10b, electric control cover lock - 10c, furnace placement slot - 10d, upper furnace body - 11a, lower furnace body - 11b, upper lifting ring - 11a1, upper clamping slot - 11a2, crystallization plate - 11a3, hanging rod - 11a4, filling slot - 11a5, bottom ring - 11a6, ring groove - 11a7, lower lifting ring - 11b1, lower clamping slot - 11b2, docking furnace head - 11b3, assembly slot - 11b4, clamping rod - 11b5, compression spring - 11b6, screw - 11b7. DETAILED DESCRIPTION
[0050] The present invention is further described in detail below in conjunction with examples, but the embodiments of the present invention are not limited thereto.
[0051] Embodiment 1:
[0052] The present invention provides a single substance arsenic production system: its structure comprises an automatic processing area 1 and a manual processing area 2, wherein the automatic processing area 1 and the manual processing area 2 are respectively located in independent rooms;
[0053] It also includes an air extraction device 3, a sublimation device 4, a sensing device 5, a lifting device 6, a central console 7, a feeding device 8, a conveying device 9, a replacement device 10 and a sublimation furnace 11. The sublimation device 4, the sensing device 5, the lifting device 6, the feeding device 8, the conveying device 9 and the replacement device 10 are all arranged in the automatic processing area 1. The feeding end of the feeding device 8 and the processing end of the conveying device 9 are located in the manual processing area 2. The air extraction device 3 is provided in both the automatic processing area 1 and the manual processing area 2. The central console 7 is also provided in the manual processing area 2.
[0054] The central console 7 is electrically connected to the air extraction device 3, the sublimation device 4, the induction device 5, the lifting device 6, the feeding device 8, the conveying device 9 and the replacement device 10;
[0055] The air extraction equipment 3 is used for purifying and extracting ambient air and air at each processing equipment;
[0056] The sublimation equipment 4 is used for heating and sublimating the raw materials in the sublimation furnace 11;
[0057] The lifting device 6 is used for lifting and replacing the sublimation furnace 11 at the sublimation device 4 and the replacement device 10;
[0058] The feeding device 8 is located on one side of the replacement device 10 and can be moved above the replacement device 10. The feeding device 8 is used to add raw materials to the sublimation furnace 11 in the replacement device 10;
[0059] The conveying device 9 is connected to the replacement device 10. The conveying device 9 is a circulating conveyor belt group. The conveying device 9 is used for automatic conveying when the sublimation furnace 11 needs to be cleaned or maintained;
[0060] The sensing device 5 is used for positioning each device when it is automatically running.
[0061] Further, the sensing device 5 includes a first sensor 5a, a second sensor 5b, a third sensor 5c, an assembly rod 5d, a fourth sensor 5e, a fifth sensor 5f, a sixth sensor 5g, a seventh sensor 5h, an eighth sensor 5i and a ninth sensor 5j, the fourth sensor 5e is assembled in the sublimation device 4 through the assembly rod 5d, the second sensor 5b and the third sensor 5c are used for docking when the feeding device 8 replenishes materials, the sixth sensor 5g is assembled in the replacement device 10, the eighth sensor 5i and the ninth sensor 5j are assembled on the lifting device 6, the eighth sensor 5i is used for positioning the lifting device 6 in the vertical direction, the ninth sensor 5j is used for positioning the lifting device 6 in the horizontal direction, the first sensor 5a is used for positioning the lifting device 6 when it moves, the sixth sensor 5g is used for positioning the sublimation furnace 11 in the replacement device 10, the fourth sensor 5e is used for positioning the sublimation furnace 11 in the sublimation device 4, and the seventh sensor 5h is used for positioning the items on the conveying device 9 when they are transported to the replacement device 10.
[0062] Further, the air exhaust device 3 includes a fresh air inlet pipe 3a, an environmental exhaust pipe 3b and an equipment exhaust pipe 3c, the environmental exhaust pipe 3b and the equipment exhaust pipe 3c are both connected to the exhaust gas treatment equipment, the fresh air inlet pipe 3a is arranged below the side wall of the room of the automatic treatment area 1 and the manual treatment area 2, the environmental exhaust pipe 3b is arranged above the side wall of the room of the automatic treatment area 1 and the manual treatment area 2, and the equipment exhaust pipe 3c is used for gas extraction of each device;
[0063] It also includes a first electrically controlled valve 3d, which is arranged at the connection between the equipment exhaust pipe 3c and the inside of each equipment.
[0064] Further, the sublimation equipment 4 includes a heating seat 4a, a chassis 4b, a first electric control cover 4c, a fixed exhaust pipe 4d, an electric control telescopic pipe 4e, a maintenance door 4f, a door lock 4g, a heating furnace slot 4h and a sublimation chamber side plate 4i. The heating seat 4a is provided with a chassis 4b on one side of the top, and a heating furnace slot 4h is provided on the other side of the top of the heating seat 4a. The heating furnace slot 4h is arranged between the heating seat 4a, the chassis 4b, the first electric control cover 4c, the maintenance door 4f and the sublimation chamber side plate 4i. The first electric control cover 4c is arranged directly above the heating furnace slot 4h. The maintenance door 4f is also provided with a door lock 4g. The chassis 4b is adjacent to the heating seat 4a. A fixed exhaust pipe 4d and an electrically controlled telescopic pipe 4e are installed near the maintenance door 4f and between the sublimation chamber side panels 4i. The fixed exhaust pipe 4d and the electrically controlled telescopic pipe 4e are both connected to the equipment exhaust pipe 3c. The electrically controlled telescopic pipe 4e can be extended and retracted from the chassis 4b toward the maintenance door 4f by electric control. The electrically controlled telescopic pipes 4e are provided in the same number as the heating furnace slots 4h and are correspondingly arranged above the heating furnace slots 4h. The fixed exhaust pipe 4d and the electrically controlled telescopic pipe 4e are both located at the bottom of the first electrically controlled cover 4c. The number of the fourth sensors 5e is the same as that of the heating furnace slots 4h and are installed corresponding to the positions of the heating furnace slots 4h.
[0065] Furthermore, the replacement device 10 includes a second electric control cover 10a, a replacement bin plate 10b, an electric control cover lock 10c and a furnace placement slot 10d. The replacement bin plate 10b is a sealing frame plate. The second electric control cover 10a is installed on the top of the replacement bin plate 10b. The opening of the second electric control cover 10a is equipped with an electric control cover lock 10c. A furnace placement slot 10d is provided on one side within the range of the replacement bin plate 10b. The number of the furnace placement slots 10d is greater than or equal to the heating furnace slots 4h. The setting direction of the multiple furnace placement slots 10d is consistent with the setting direction of the multiple heating furnace slots 4h. One side of the conveying device 9 is arranged in the replacement bin plate 10b and is parallel to the setting direction of the multiple furnace placement slots 10d. The number of the sixth sensors 5g is twice the number of the furnace placement slots 10d, and every 2 sixth sensors 5g are correspondingly arranged on both sides of each of the furnace placement slots 10d.
[0066] Furthermore, the lifting device 6 includes a mobile assembly rod 6a, a mobile assembly beam 6b, a first mobile seat 6c, a connector 6d, a first electrically controlled lifting component 6e and a second mobile seat 6f. The mobile assembly beam 6b is fixed above the side wall of the room in the automatic processing area 1. The first mobile seat 6c is fixed at both ends of the mobile assembly rod 6a. The first mobile seat 6c is assembled on the mobile assembly beam 6b and can be moved by electric control. The second mobile seat 6f is assembled on the mobile assembly rod 6a and can be moved by electric control. The bottom of the second mobile seat 6f is connected to a connector 6d through the first electrically controlled lifting component 6e. The connector 6d is used for assembling and fixing the sublimation furnace 11 during lifting. The mobile assembly rod 6a is connected to a plurality of the The arrangement direction of the heating furnace slots 4h is parallel, the first sensor 5a is installed on the wall of the room of the automatic processing area 1 and has the same height as the second movable seat 6f, the first sensor 5a is located above the sublimation equipment 4, the first sensor 5a and the number are the same as the number of the furnace slots 10d and are installed corresponding to the positions where the furnace slots 10d are placed, the second movable seat 6f is equipped with a ninth sensor 5j on the side adjacent to the first sensor 5a, and the ninth sensor 5j determines the position by identifying with the first sensor 5a, and the eighth sensor 5i is equipped with the bottom of the second movable seat 6f adjacent to the first sensor 5a, and the eighth sensor 5i determines the position by identifying with the sixth sensor 5g and the third sensor 5c.
[0067] Furthermore, the feeding device 8 includes an elevator 8a, a second electrically-controlled valve 8b, an electrically-controlled movable frame 8c, a track 8d, a feed connector 8e, a storage hopper 8f, a screw conveyor 8g, a second electrically-controlled lifting assembly 8h, a hose 8i and a discharge docking ring 8j. The inlet side of the elevator 8a is arranged in the manual processing area 2, and the outlet side of the elevator 8a is arranged in the automatic processing area 1. The track 8d is arranged on both sides of the replacement bin plate 10b. The electrically-controlled movable frame 8c is mounted on the track 8d and can walk on the track 8d. The electrically-controlled movable frame 8c is equipped with a storage hopper 8f, and the bottom of the storage hopper 8f is equipped with a screw conveyor 8g. The discharge port of the rotary conveyor 8g is equipped with a hose 8i, a discharge docking ring 8j is fixed at the bottom of the hose 8i, a feed connector 8e is provided at the top of the storage hopper 8f, and the top of the discharge docking ring 8j is connected to the screw conveyor 8g through the second electrically-controlled lifting component 8h. The fifth sensor 5f is arranged on the side of the discharge docking ring 8j adjacent to the sixth sensor 5g. When the storage hopper 8f is added, the feed connector 8e is located below the discharge port of the elevator 8a. After moving, the discharge docking ring 8j can be located directly above the furnace trough 10d. The side end of the discharge port of the elevator 8a is provided with a second sensor 5b, and the side end of the feed connector 8e is provided with a third sensor 5c.
[0068] Furthermore, the conveying equipment 9 includes a cleaning conveyor belt 9a, a conveyor belt guard 9b, an exhaust joint 9c, a rotary conveyor belt 9d, a gravity sensing base 9e and an induction conveyor belt 9f. The cleaning conveyor belt 9a is arranged in the manual processing area 2, and the gravity sensing base 9e is arranged within the range of the replacement bin plate 10b. The induction conveyor belt 9f is installed above the gravity sensing base 9e. The assembly direction of the induction conveyor belt 9f is parallel to the furnace trough 10d. The rotary conveyor belt 9d is used to connect the cleaning conveyor belt 9a and the induction conveyor belt 9f. The assembly place of the rotary conveyor belt 9d is provided with a conveyor belt guard 9b, and the top of the conveyor belt guard 9b is provided with an exhaust joint 9c, and the exhaust joint 9c can be connected to the equipment exhaust pipe 3c.
[0069] Furthermore, the sublimation furnace 11 includes an upper furnace body 11a and a lower furnace body 11b, the upper furnace body 11a is placed and assembled on the lower furnace body 11b, an upper lifting ring 11a1 is fixed to the side end of the upper furnace body 11a, and a lower lifting ring 11b1 is assembled to the side end of the lower furnace body 11b, the connecting head 6d lifts the upper furnace body 11a and the lower furnace body 11b through the upper lifting ring 11a1 and the lower lifting ring 11b1, and the seventh sensor 5h is arranged on the side end of the replacement warehouse plate 10b, and the seventh sensor 5h is used to identify and determine the position of the upper furnace body 11a.
[0070] Furthermore, a method for operating an elemental arsenic production system comprises the following steps:
[0071] First, the lower furnace body 11b is placed in the furnace placement slot 10d, and the upper furnace body 11a is placed on the induction conveyor belt 9f and recorded by the central console 7;
[0072] Second, during automatic feeding, the central control console 7 controls the second electric control cover 10a to open, and then controls the electric control moving frame 8c to drive the storage hopper 8f to move to the specified position. During the movement, the fifth sensor 5f determines the position of the corresponding furnace slot 10d through identification induction with the corresponding sixth sensor 5g;
[0073] Third, after the fifth sensor 5f recognizes the corresponding sixth sensor 5g, the central console 7 controls the electric control moving frame 8c to stop moving and controls the second electric control lifting assembly 8h to lower the discharge docking ring 8j. After the discharge docking ring 8j is lowered, the central console 7 controls the screw conveyor 8g to add material to the lower furnace body 11b. After adding one lower furnace body 11b, it automatically moves to the next lower furnace body 11b to add material until the feeding is completed;
[0074] Fourth, after the feeding is completed, the central console 7 controls the electric control moving frame 8c to move to the bottom of the discharge port of the elevator 8a through the identification of the second sensor 5b and the third sensor 5c, and the central console 7 controls the lifting device 6 to move to the top of the replacement device 10, and locates the upper furnace body 11a on the induction conveyor belt 9f through the identification of the ninth sensor 5j and the first sensor 5a, combined with the eighth sensor 5i and the sixth sensor 5g adjacent to the induction conveyor belt 9f, and then controls the first electric control lifting component 6e to lower the connector 6d to clamp the upper furnace body 11a, and then lifts it a certain distance through the first electric control lifting component 6e to move horizontally, and locates and places the furnace slot 10d through the identification of the eighth sensor 5i and the sixth sensor 5g far away from the induction conveyor belt 9f, and finally lowers the connector 6d to combine the upper furnace body 11a and the lower furnace body 11b;
[0075] Fifth, during sublimation, the central console 7 controls the first electric control cover 4c to open, and then controls the lifting device 6 to move above the replacement device 10, and lowers the connector 6d to clamp the upper furnace body 11a and the lower furnace body 11b by identifying the corresponding furnace slot 10d, and then raises the connector 6d and locates the heating furnace slot 4h according to the identification of the ninth sensor 5j and the first sensor 5a, and combines the identification of the eighth sensor 5i and the third sensor 5c to move, and then lowers the upper furnace body 11a and the lower furnace body 11b to be placed in the heating furnace slot 4h, and then raises the connector 6d and covers the first electric control cover 4c, and finally the electric control telescopic tube 4e extends to exhaust the sublimation and start the heating seat 4a to sublimate;
[0076] Sixth, another group of sublimation furnaces 11 can be arranged at the furnace slot 10d for automatic feeding. After the feeding is completed, the second electric control cover 10a is closed as a preparation. After the sublimation furnace 11 of the sublimation equipment 4 is completed, the lifting device 6 can alternately replace the preparation sublimation furnace 11 with the sublimation furnace 11 that has completed sublimation;
[0077] Seventh, the sublimation furnace 11 after sublimation can be cooled in the furnace slot 10d. After cooling, the upper furnace body 11a can be positioned and lifted by the lifting device 6 to the induction conveyor belt 9f, and transported to the cleaning conveyor belt 9a through the induction conveyor belt 9f and the rotary conveyor belt 9d to take the material. After taking the material, it can be transported back to the induction conveyor belt 9f through the rotary conveyor belt 9d to prepare for the capping after adding the material. When transported back to the induction conveyor belt 9f, it is positioned by the seventh sensor 5h. When necessary, the lower furnace body 11b can also be lifted and placed on the induction conveyor belt 9f and transported to the cleaning conveyor belt 9a for maintenance;
[0078] Eighth, when the storage hopper 8f is replenished, the elevator 8a is started after the second sensor 5b and the third sensor 5c identify each other, and the second electric control valve 8b is opened, and then the storage hopper 8f is replenished by adding material at the inlet of the elevator 8a;
[0079] Ninth, when the above steps are executed, the air extraction device 3 can automatically open and close the fresh air inlet pipe 3a, the environment exhaust pipe 3b and the equipment exhaust pipe 3c according to the demand;
[0080] The production area is divided into an automatic area 1 and a manual area 2, and automatic feeding, sublimation, cooling preparation, lifting and transportation equipment are provided in the automatic area 1. The sublimation equipment 4 and the sublimation furnace 11 in the cooling replacement equipment 10 are automatically switched through the lifting equipment 6, and sublimation processing and cooling placement can be automatically performed, and the cooled furnace body can be automatically transported to the manual area 2 for material collection. The furnace body after material collection can be automatically transported back to the placement place and automatically lifted and placed by the lifting equipment 6, and can be automatically prepared for feeding through the feeding equipment 8. The high degree of automation can greatly reduce manual contact during production, reduce production risks, and thus reduce the inconvenience of frequent entry and exit purification and wearing protective clothing.
[0081] Embodiment 2:
[0082] Based on the first embodiment, Figure 7 As shown, the first electric-controlled lifting component 6e can be composed of a motor 6e1, a rope reel 6e2, an encoder 6e3, a telescopic bracket 6e4 and a rope 6e5. The rope reel 6e2 is fixed on the second moving seat 6f. The motor 6e1 is used to drive the rope reel 6e2 to rotate. The encoder 6e3 is used to calculate the number of rotations of the rope reel 6e2. The telescopic bracket 6e4 is used to connect the top of the connector 6d and the bottom of the second moving seat 6f. One end of the rope 6e5 is connected to the rope reel 6e2, and the other end of the rope 6e5 is connected to the top of the connector 6d.
[0083] Furthermore, the structure of the second electrically controlled lifting assembly 8h may be the same as that of the first electrically controlled lifting assembly 6e;
[0084] While ensuring the stability of lifting, the component structure is made simpler and clearer, which is convenient for maintenance and replacement. At the same time, it is convenient to calculate the lifting height through the encoder to further strengthen the judgment of the lifting height and facilitate the adjustment of the lifting rate.
[0085] Embodiment three:
[0086] Based on the second embodiment, Fig.10 As shown, the first electrically controlled lifting component 6e may be a hydraulic scissor frame for a lifting platform;
[0087] Compared with the second embodiment, the height judgment is omitted, and the stability of the structure is enhanced.
[0088] Embodiment 4:
[0089] Based on the first embodiment, Figure 8As shown, the connector 6d may be composed of a lifting assembly ring 6d1, an electric push rod 6d2, a push rod assembly plate 6d3 and a fixed connecting rod 6d4, two lifting assembly rings 6d1 are provided, and the two lifting assembly rings 6d1 are connected by a fixed connecting rod 6d4, and the distance between the two lifting assembly rings 6d1 is consistent with the distance between the upper lifting ring 11a1 and the lower lifting ring 11b1, and a plurality of push rod assembly plates 6d3 are evenly arranged at the bottom of the lifting assembly ring 6d1, and an electric push rod 6d2 is assembled in the push rod assembly plate 6d3, and the telescopic rod of the electric push rod 6d2 is assembled toward the middle of the lifting assembly ring 6d1;
[0090] The lifting assembly ring 6d1 is sleeved on the outside of the sublimation furnace 11, and the multi-electric push rod 6d2 is extended to clamp the upper and lower parts of the sublimation furnace 11, so that the sublimation furnace 11 is more stable during the lifting process to prevent shaking and tipping.
[0091] Embodiment five:
[0092] Based on the fourth embodiment, the connector 6d may also adopt a structure not shown in the mechanical claw diagram.
[0093] Embodiment six:
[0094] Based on the first embodiment, Fig. 9 As shown, the upper furnace body 11a also includes an upper clamping groove 11a2, a crystallization plate 11a3, a hanging rod 11a4, a filling groove 11a5, a bottom ring 11a6 and an annular groove 11a7, and the lower furnace body 11b also includes a lower clamping groove 11b2, a docking furnace head 11b3, an assembly groove 11b4, a clamping rod 11b5, a compression spring 11b6 and a screw 11b7. The filling groove 11a5 is arranged in the side wall of the upper furnace body 11a, and the upper clamping groove 11a2 is arranged in a wave shape at the bottom of the upper lifting ring 11a1. The side end of the crystallization plate 11a3 is hung in the upper furnace body 11a through the hanging rod 11a4. The bottom end of the upper furnace body 11a is fixed with a bottom ring 11a6, and the bottom of the bottom ring 11a6 is provided with an annular groove 11a7 The lower card groove 11b2 is arranged in a wave shape at the bottom of the lower lifting ring 11b1, and a docking furnace head 11b3 is integrated with the top of the lower furnace body 11b. A mounting groove 11b4 is arranged in the middle of the top of the docking furnace head 11b3, and the mounting groove 11b4 is larger than or equal to the bottom ring 11a6. A clamping rod 11b5 is inlaid at the top of the docking furnace head 11b3 corresponding to the ring groove 11a7. The diameter of the clamping rod 11b5 is larger than that of the screw 11b7. The top of the screw 11b7 passes through the docking furnace head 11b3 and is fixedly connected to the clamping rod 11b5. The bottom of the screw 11b7 is locked to the lower lifting ring 11b1, and a compression spring 11b6 is also arranged between the lower lifting ring 11b1 and the docking furnace head 11b3;
[0095] Further, such as Figure 8As shown, based on the fourth embodiment, the upper concave parts of the upper clamping groove 11a2 and the lower clamping groove 11b2 are greater than or equal to the extension rod diameter of the electric push rod 6d2;
[0096] Furthermore, the clamping rod 11b5 can enter the annular groove 11a7;
[0097] Through the structure that the lower lifting ring 11b1 can move up and down, combined with the structure that the lower lifting ring 11b1 can drive the clamping rod 11b5 to enter the ring groove 11a7 of the upper furnace body 11a after rising, the upper furnace body 11a of the sublimation furnace 11 can be conveniently separated from the lower furnace body 11b. At the same time, during the lifting process of the sublimation furnace 11, the double-layer latch limiter of the bottom ring 11a6 and the assembly groove 11b4, and the clamping rod 11b5 and the ring groove 11a7 can be used to prevent the upper furnace body 11a from easily tipping over due to shaking.
[0098] In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "up", "down", "left", "right", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0099] The wiring diagram of the power element of the present invention and the provision of power supply are common knowledge in the field. The mobile wiring adopts the mobile wiring method commonly used in the field, and the present invention is mainly used to protect mechanical devices, so the present invention will no longer explain the wiring arrangement in detail.
[0100] The above shows and describes the basic principles and main features of the present invention and the advantages of the present invention. It is obvious to those skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and the present invention can be implemented in other specific forms without departing from the spirit or basic features of the present invention. Therefore, no matter from which point of view, the embodiments should be regarded as exemplary and non-restrictive. The scope of the present invention is defined by the attached claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention. Any figure mark in the claims should not be regarded as limiting the claims involved.
[0101] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A system for producing elemental arsenic, comprising an automatic processing area (1) and a manual processing area (2), wherein the automatic processing area (1) and the manual processing area (2) are respectively located in separate rooms; Its characteristics are: It also includes an air extraction device (3), a sublimation device (4), a sensing device (5), a lifting device (6), a central console (7), a feeding device (8), a conveying device (9), a replacement device (10) and a sublimation furnace (11), wherein the sublimation device (4), the sensing device (5), the lifting device (6), the feeding device (8), the conveying device (9) and the replacement device (10) are all arranged in the automatic processing area (1), the feeding end of the feeding device (8) and the processing end of the conveying device (9) are located in the manual processing area (2), the air extraction device (3) is provided in both the automatic processing area (1) and the manual processing area (2), and the central console (7) is also provided in the manual processing area (2); The central console (7) is electrically connected to the air extraction device (3), the sublimation device (4), the sensing device (5), the lifting device (6), the feeding device (8), the conveying device (9) and the replacement device (10); The air extraction equipment (3) is used for purifying and extracting ambient air and air at each processing equipment; The sublimation equipment (4) is used for heating and sublimating raw materials in the sublimation furnace (11); The lifting device (6) is used for lifting and replacing the sublimation furnace (11) at the sublimation device (4) and the replacement device (10); The feeding device (8) is located on one side of the replacement device (10) and can be moved above the replacement device (10), and the feeding device (8) is used to add raw materials to the sublimation furnace (11) in the replacement device (10); The conveying device (9) is connected to the replacement device (10), and the conveying device (9) is a circulating conveyor belt group. The conveying device (9) is used for automatic conveying when the sublimation furnace (11) needs to be cleaned or maintained; The sensing device (5) is used for positioning each device during automatic operation.
2. The elemental arsenic production system according to claim 1, characterized in that: The sensing device (5) includes a first sensor (5a), a second sensor (5b), a third sensor (5c), an assembly rod (5d), a fourth sensor (5e), a fifth sensor (5f), a sixth sensor (5g), a seventh sensor (5h), an eighth sensor (5i) and a ninth sensor (5j).
3. The elemental arsenic production system according to claim 2, characterized in that: The air extraction device (3) comprises a fresh air inlet pipe (3a), an environmental exhaust pipe (3b) and an equipment exhaust pipe (3c); the fresh air inlet pipe (3a) and the environmental exhaust pipe (3b) are used for purifying the environmental air, and the equipment exhaust pipe (3c) is used for extracting gas from various equipment; It also includes a first electrically controlled valve (3d), which is arranged at the connection between the equipment exhaust pipe (3c) and the interior of each equipment.
4. The elemental arsenic production system according to claim 3, characterized in that: The sublimation equipment (4) comprises a heating seat (4a), a chassis (4b), a first electric control cover (4c), a fixed exhaust pipe (4d), an electric control telescopic pipe (4e), a maintenance door (4f), a door lock (4g), a heating furnace slot (4h) and a sublimation chamber side plate (4i). The heating seat (4a) is provided with a chassis (4b) on one side of its top, and a heating furnace slot (4h) is provided on the other side of its top. The heating furnace slot (4h) is provided between the heating seat (4a), the chassis (4b), the first electric control cover (4c), the maintenance door (4f) and the sublimation chamber side plate (4i). The first electric control cover (4c) is provided directly above the heating furnace slot (4h). The maintenance door (4f) is also provided with a door lock (4g). The chassis (4 b) A fixed exhaust pipe (4d) and an electrically controlled telescopic pipe (4e) are installed adjacent to the maintenance door (4f) and between the sublimation chamber side panels (4i). The fixed exhaust pipe (4d) and the electrically controlled telescopic pipe (4e) are both connected to the equipment exhaust pipe (3c). The electrically controlled telescopic pipe (4e) can be extended and retracted from the chassis (4b) toward the maintenance door (4f) through electric control. The number of electrically controlled telescopic pipes (4e) is equal to the number of heating furnace slots (4h) and is correspondingly arranged above the heating furnace slots (4h). The fixed exhaust pipe (4d) and the electrically controlled telescopic pipe (4e) are both located at the bottom of the first electrically controlled cover (4c). The number of the fourth sensors (5e) is equal to the number of heating furnace slots (4h) and is installed corresponding to the position of the heating furnace slots (4h).
5. The elemental arsenic production system according to claim 4, characterized in that: The replacement device (10) comprises a second electric control cover (10a), a replacement compartment plate (10b), an electric control cover lock (10c) and a furnace placement slot (10d); the replacement compartment plate (10b) is a sealing frame plate; the second electric control cover (10a) is mounted on the top of the replacement compartment plate (10b); the electric control cover lock (10c) is mounted at the opening of the second electric control cover (10a); a furnace placement slot (10d) is provided on one side within the range of the replacement compartment plate (10b); the furnace placement slot (10d) The number of the plurality of furnace placement slots (10d) is greater than or equal to the heating furnace slots (4h), the setting direction of the plurality of furnace placement slots (10d) is consistent with the setting direction of the plurality of heating furnace slots (4h), one side of the conveying device (9) is arranged in the replacement bin plate (10b) and is parallel to the setting direction of the plurality of furnace placement slots (10d), the number of the sixth sensors (5g) is twice the number of the furnace placement slots (10d), and every two sixth sensors (5g) are correspondingly arranged on both sides of each furnace placement slot (10d).
6. The elemental arsenic production system according to claim 5, characterized in that: The lifting device (6) comprises a mobile assembly rod (6a), a mobile assembly beam (6b), a first mobile seat (6c), a connector (6d), a first electrically controlled lifting assembly (6e) and a second mobile seat (6f); the mobile assembly beam (6b) is fixed above the side wall of the automatic processing area (1); the first mobile seat (6c) is fixed at both ends of the mobile assembly rod (6a); the first mobile seat (6c) is assembled on the mobile assembly beam (6b) and can move by electric control; the second mobile seat (6f) is assembled on the mobile assembly rod (6a) and can move by electric control; the bottom of the second mobile seat (6f) is connected to the connector (6d) via the first electrically controlled lifting assembly (6e); the connector (6d) ) is used for assembling and fixing the sublimation furnace (11) during lifting, the movable assembly rod (6a) is parallel to the arrangement direction of the plurality of heating furnace slots (4h), the first sensor (5a) is assembled on the wall of the automatic processing area (1) room and has the same height as the second movable seat (6f), the first sensor (5a) is located above the sublimation equipment (4), the first sensor (5a) and the number of the first sensors (5a) are the same as the number of furnace slots (10d) and are assembled corresponding to the positions where the furnace slots (10d) are placed, the ninth sensor (5j) determines the position by identifying with the first sensor (5a), and the eighth sensor (5i) determines the position by identifying with the sixth sensor (5g) and the third sensor (5c).
7. The elemental arsenic production system according to claim 5, characterized in that: The feeding device (8) includes an elevator (8a), a second electrically controlled valve (8b), an electrically controlled movable frame (8c), a track (8d), a feed connector (8e), a storage hopper (8f), a screw conveyor (8g), a second electrically controlled lifting assembly (8h), a hose (8i) and a discharge docking ring (8j). The inlet side of the elevator (8a) is located in the manual processing area (2), and the outlet side of the elevator (8a) is located in the automatic processing area (1). The track (8d) is located on both sides of the replacement bin plate (10b). The electrically controlled movable frame (8c) is mounted on the track (8d) and can move on the track (8d). The electrically controlled movable frame (8c) is equipped with a storage hopper (8f). The bottom of the storage hopper (8f) is equipped with a screw conveyor (8g). The discharge port of the rotary conveyor (8g) is equipped with a hose (8i), a discharge docking ring (8j) is fixed at the bottom of the hose (8i), a feed connector (8e) is provided at the top of the storage hopper (8f), the top of the discharge docking ring (8j) is connected to the screw conveyor (8g) through a second electrically controlled lifting component (8h), the fifth sensor (5f) is provided on the side of the discharge docking ring (8j) adjacent to the sixth sensor (5g), when the storage hopper (8f) is being fed, the feed connector (8e) is located below the discharge port of the elevator (8a), and the discharge docking ring (8j) can be located directly above the furnace trough (10d) after movement, a second sensor (5b) is provided at the side end of the discharge port of the elevator (8a), and a third sensor (5c) is provided at the side end of the feed connector (8e).
8. The elemental arsenic production system according to claim 6, characterized in that: The conveying device (9) comprises a cleaning conveyor belt (9a), a conveyor belt shield (9b), an exhaust connector (9c), a rotary conveyor belt (9d), a gravity sensing base (9e) and an induction conveyor belt (9f). The cleaning conveyor belt (9a) is arranged in the manual processing area (2). The gravity sensing base (9e) is arranged within the range of the replacement warehouse plate (10b). The induction conveyor belt (9f) is installed above the gravity sensing base (9e). The installation direction of the induction conveyor belt (9f) is parallel to the furnace slot (10d). The rotary conveyor belt (9d) is used to connect the cleaning conveyor belt (9a) and the induction conveyor belt (9f). The assembly position of the rotary conveyor belt (9d) is provided with a conveyor belt shield (9b). The top of the conveyor belt shield (9b) is provided with an exhaust connector (9c). The exhaust connector (9c) can be connected to the equipment exhaust pipe (3c).
9. The elemental arsenic production system according to claim 8, characterized in that: The sublimation furnace (11) includes an upper furnace body (11a) and a lower furnace body (11b), wherein the upper furnace body (11a) is placed and assembled on the lower furnace body (11b), an upper lifting ring (11a1) is fixed to the side end of the upper furnace body (11a), and a lower lifting ring (11b1) is assembled to the side end of the lower furnace body (11b), and the connecting head (6d) lifts the upper furnace body (11a) and the lower furnace body (11b) through the upper lifting ring (11a1) and the lower lifting ring (11b1), and the seventh sensor (5h) is arranged on the side end of the replacement warehouse plate (10b), and the seventh sensor (5h) is used to identify and determine the position of the upper furnace body (11a).
10. A method for operating an elemental arsenic production system, characterized in that: The following steps are involved: First, the lower furnace body (11b) is placed in the furnace placement slot (10d), and the upper furnace body (11a) is placed on the induction conveyor belt (9f) and recorded through the central console (7); Second, during automatic feeding, the central control console (7) controls the second electric control cover (10a) to open, and then controls the electric control moving frame (8c) to drive the storage hopper (8f) to move to a designated position. During the movement, the fifth sensor (5f) determines the position of the corresponding furnace slot (10d) through identification and induction with the corresponding sixth sensor (5g); Third, after the fifth sensor (5f) identifies the corresponding sixth sensor (5g), the central console (7) controls the electric-controlled moving frame (8c) to stop moving and controls the second electric-controlled lifting component (8h) to lower the discharge docking ring (8j). After the discharge docking ring (8j) is lowered, the central console (7) controls the screw conveyor (8g) to add material to the lower furnace body (11b). After adding one lower furnace body (11b), the central console (7) automatically moves to the next lower furnace body (11b) to add material until the addition is completed. Fourth, after the feeding is completed, the central control console (7) controls the electric control moving frame (8c) to move to the bottom of the discharge port of the elevator (8a) through the identification of the second sensor (5b) and the third sensor (5c), and the central control console (7) then controls the lifting device (6) to move to the top of the replacement device (10), and locates the sensor through the identification of the ninth sensor (5j) and the first sensor (5a), combined with the identification of the eighth sensor (5i) and the sixth sensor (5g) of the adjacent induction conveyor belt (9f). The upper furnace body (11a) on the conveyor belt (9f) is then controlled to lower the connecting head (6d) to clamp the upper furnace body (11a), and then the first electrically controlled lifting component (6e) is raised a certain distance to move horizontally, and the furnace slot (10d) is positioned and placed through the eighth sensor (5i) and the sixth sensor (5g) away from the induction conveyor belt (9f) for identification, and finally the connecting head (6d) is lowered to combine the upper furnace body (11a) and the lower furnace body (11b); Fifth, during sublimation, the central control console (7) controls the first electric control cover (4c) to open, and then controls the lifting device (6) to move to the top of the replacement device (10), and by identifying the corresponding furnace slot (10d), lowers the connecting head (6d) to clamp the upper furnace body (11a) and the lower furnace body (11b), and then raises the connecting head (6d) and locates the heating furnace slot (4h) according to the identification of the ninth sensor (5j) and the first sensor (5a), combined with the identification of the eighth sensor (5i) and the third sensor (5c) to move, and then lowers the upper furnace body (11a) and the lower furnace body (11b) to place them in the heating furnace slot (4h), and then raises the connecting head (6d) and covers the first electric control cover (4c), and finally the electric control telescopic tube (4e) extends to perform sublimation exhaust and starts the heating seat (4a) to perform sublimation; Sixth, another set of sublimation furnaces (11) can be arranged at the furnace slot (10d) for automatic feeding. After the feeding is completed, the second electric control cover (10a) is closed as a preparation. After the sublimation furnace (11) of the sublimation equipment (4) is sublimated, the lifting device (6) can be used to alternately replace the sublimation furnace (11) in preparation with the sublimation furnace (11) that has completed sublimation. Seventh, the sublimation furnace (11) after sublimation can be cooled in the furnace trough (10d). After cooling, the upper furnace body (11a) can be positioned and lifted onto the induction conveyor belt (9f) by the lifting device (6), and then transported to the cleaning conveyor belt (9a) for material collection via the induction conveyor belt (9f) and the rotary conveyor belt (9d). After the material collection is completed, it can be transported back to the induction conveyor belt (9f) via the rotary conveyor belt (9d) for preparation of sealing after adding materials. When transported back to the induction conveyor belt (9f), it is positioned by the seventh sensor (5h). When necessary, the lower furnace body (11b) can also be lifted and placed on the induction conveyor belt (9f) and transported to the cleaning conveyor belt (9a) for maintenance. Eighth, when refilling the storage hopper (8f), the elevator (8a) is started after the second sensor (5b) and the third sensor (5c) are identified, and the second electric control valve (8b) is opened at the same time, and then the storage hopper (8f) is refilled by adding material at the inlet of the elevator (8a); Ninth, when the above steps are executed, the air extraction device (3) can automatically open and close each fresh air inlet pipe (3a), environmental exhaust pipe (3b) and equipment exhaust pipe (3c) according to demand.