Mine multi-middle-section simultaneous mining drainage system
By setting up small water tanks, sewage pipes, water discharge chambers and sedimentation tanks in the middle section of the mine, centralized treatment and multi-stage pumping of sewage are realized, and the problem of difficulty in collecting and treating sewage during simultaneous mining of multiple and medium sections is solved. Improves processing efficiency and drainage efficiency.
Patent Information
- Application Number
- CN202411544607.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2024-12-20
AI Technical Summary
During the simultaneous mining of multiple and mid-sections of the mine, the segmented production panels and vehicle washing chambers in each mid-section generate a large amount of sewage, which leads to difficulty in collecting and processing, and is costly and time-consuming.
A drainage system for mining and drainage in multiple and middle sections of mine was designed. By setting up small water tanks in the panels, drainage pipes, drainage chambers and sedimentation tanks on each section, and centralized sewage treatment is achieved by using drainage drilling and drainage ditches. The water pump room is subjected to multi-stage pumping to the surface sedimentation tank for treatment.
Improve sewage treatment efficiency, avoid blockage, increase drainage efficiency, and reduce treatment costs.
Smart Images

Figure CN119163469A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of mine drainage, and in particular to a mine multi-section simultaneous mining drainage system. Background Art
[0002] The drainage system is an important part of the eight major production systems of the mine. Whether the sewage generated in the mine is discharged efficiently and quickly has a positive impact on the production of the entire mine.
[0003] During the simultaneous mining of multiple sections in a mine, a large amount of sewage will be generated in the segmented production areas and car wash chambers of each section. It is not only difficult to collect and store, but also when processing after collection, it is necessary to clean the sewage in each section, each segment of the section, and each segmented area one by one, which is costly, time-consuming and labor-intensive. Summary of the invention
[0004] In view of the above technical problems, the present invention provides a drainage system for simultaneous mining of multiple sections in a mine, which is used to solve the problem of difficulty in collecting and treating a large amount of sewage generated during the simultaneous mining of multiple sections in a mine.
[0005] In order to achieve the above object, the technical solution of the present invention is as follows: A mine multi-section simultaneous mining drainage system, each section is composed of multiple segments, each segment is distributed with multiple production panels and car wash chambers, including a small water tank in the panel area, a sewage pipe and a drainage chamber, the small water tank in the panel area, the sewage pipe and the drainage chamber are arranged on each section in the middle section, the water inlet of the small water tank in the panel area is connected to the drainage outlet of the production panel, the sewage pipe is provided with multiple water inlets, and the multiple water inlets are respectively connected to the drainage outlets of the small water tank in the panel area and the car wash chamber, the water outlet of the sewage pipe is arranged in the drainage chamber, and the bottom of the drainage chamber is provided with Drainage boreholes are used to connect the drainage chambers in each section. Sedimentation tanks and central water tanks are provided on the horizontal plane of each middle section. The water in the drainage chamber flows into the sedimentation tank through the drainage boreholes. Drainage ditches are also provided on the horizontal plane of each middle section. The branches at one end of the drainage ditch are respectively located in the river channel and the sedimentation tank, and the other end of the drainage ditch is located in the central water tank. The central water tanks are equipped with pump houses, and drainage boreholes are provided in the central water tanks. The sewage in each central water tank is pumped from the drainage boreholes to the surface sedimentation tank in multiple stages under the action of the pump house.
[0006] A water pump is arranged in the small water tank of the pan area, and the water outlet of the water pump is connected with the water inlet of the sewage pipe.
[0007] A water pump is arranged in the car wash chamber, and the water outlet of the water pump is connected to the water inlet of the sewage pipe.
[0008] The car washing chamber is provided with a slope surface from the inside to the outside and from the bottom to the top.
[0009] The drainage chambers are provided in a plurality, preferably two.
[0010] The drainage boreholes are provided with a plurality of holes, preferably two.
[0011] The sedimentation tanks are provided with several, preferably two.
[0012] The drainage drilling holes are provided with a plurality of holes, preferably two.
[0013] Compared with the prior art, the present invention has the following beneficial effects: the small water tanks in the pan area on each segment are used to collect secondary muddy sewage and fissure seepage during the operation of the equipment in the production process of the production pan area, the car wash chamber collects sewage after the equipment is cleaned, and then the water collected in the small water tanks in the pan area and the car wash chamber is sent to the drainage chamber through the sewage pipe, the water in the drainage chamber flows into the sedimentation tank on the middle section through the drainage borehole for sedimentation, and then flows into the central water tank in the middle section through the sewage ditch, the water in the central water tank of each middle section is pumped in multiple stages under the action of the water pump, and the sewage is sent to the surface sedimentation tank through the drainage borehole for centralized treatment, thereby improving the treatment efficiency; The car washing chamber is designed to have a certain depression angle. The front half of the chamber is used to wash various equipment. The sewage from the washing equipment is collected in the rear half of the chamber along the inclined slope. The rear half is similar to a slightly larger water tank, and then sent to the drainage chamber through the sewage pipe. The car wash chamber, drainage chamber, drainage borehole, sedimentation tank, and drainage borehole can be used in one and one as a spare, or in multiple and multiple as a spare, to avoid blockage and increase drainage efficiency when the water volume is large. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 It is a schematic diagram of the process of the present invention; Figure 2 It is a structural schematic diagram of the present invention; In the figure: 1. Middle section; 101. Sedimentation tank; 102. Central water tank; 103. Drainage ditch; 104. River channel; 105. Pump house; 106. Drainage borehole; 2. Segmentation; 201. Production panel area; 202. Car wash chamber; 203. Small water tank in the panel area; 204. Sewage pipe; 205. Drainage chamber; 206. Drainage borehole. DETAILED DESCRIPTION
[0015] In order to make the purpose, technical scheme and advantages of the present invention clearer, the present invention is further described in detail below in conjunction with specific embodiments and with reference to the accompanying drawings. It should be understood that these descriptions are only exemplary and are not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concept of the present invention.
[0016] The distance between each middle section 1 in the mine is 150m, and the distance between each subsection 2 on the middle section is 24m.
[0017] Embodiment 1, Taking the 934m section in the middle section of 850m as an example, the 934m section is divided into two parts, east and west, according to the direction of the ore body, hereinafter referred to as the 934m section east part and the 934m section west part respectively. The east and west parts of the 934m section are each designed with a drainage chamber 205, and each production panel 201 of the 934m section is designed with a panel small water tank 203. The panel small water tank 203 in the production panel 201 is mainly used to store fissure water and wastewater generated during the drilling process of the drilling rig. The sewage is transported to the nearest drainage chamber 205 through the sewage pipe 204 through the water pump in the panel small water tank 203 of the production panel 201. The general design specifications of the drainage chamber 205 are: 30m×4.6m×4.3m (length×width×height). The 934m section is equipped with three car wash chambers 202, which are mainly used to centrally wash large trackless equipment that have completed the work on duty. The washing equipment will produce a large amount of sewage mixed with oil. The sewage generated by the washing equipment is discharged to the sewage pool in the back half of the chamber through the inclined slope of the car wash chamber 202. A water pump is placed in the sewage pool in the back half of the chamber, and the water pump is connected to the drainage chamber 205 through the sewage pipe 204. This process basically realizes the concentration of a large amount of sewage in the mining field to the drainage chamber 205 corresponding to the 934m section.
[0018] The sewage in the drainage chamber 205 in the east and west of the 934m section of the middle section of 850m is discharged to the sedimentation tank 101 in the middle section of 850m through the drainage borehole 206 of 934m-850m under the action of its own weight. The drainage borehole 206 of 934m-850m also undertakes the sewage treatment task of the 910m section and the 886m section at this stage. So far, the sewage of the 934m section, the 910m section and the 886m section are all collected to the sedimentation tank 101 in the middle section of 850m by the drainage borehole 206 under the action of their own weight. There is a water outlet reserved on the sedimentation, which is connected to the drainage ditches 103 in the middle section of 850m. The sewage generated by production and life in the middle section of 850m also enters the drainage ditch 103. The sewage is finally collected in the central water tank 102 in the middle section of 850m through the drainage ditch 103 in the middle section of 850m.
[0019] The central water tank 102 in the middle section of 850m is designed with a matching pump house 105. The pump house 105 has pumping equipment. Various water pumps in the pump house 105 are directly connected to the central water tank 102. The pumps directly pump the sewage in the 850m water tank to the central water tank 102 in the middle section of 1000m through the drainage borehole 106 between 850m and 1000m. The pumps in the pump house 105 in the 1000m central water tank 102 use the drainage borehole 106 between 1000m and 1150m to pump the sewage to the central water tank 102. The water borehole 106 pumps the sewage from the central water tank 102 at the middle section of 850m and 1000m to the central water tank 102 at the middle section of 1150m. The pump in the water pump room 105 at the central water tank 102 at the middle section of 1150m pumps the sewage from the central water tank 102 at the middle section of 850m, 1000m and 1150m to the surface through the drainage borehole 106 at the middle section of 1150m. So far, the sewage from each middle section of the well has been discharged from the well to the surface through the multi-stage relay drainage system.
[0020] Embodiment 2, Taking the 814m section in the middle section of 700m as an example, similar to the 934m section in the middle section of 850m mentioned above, the 814m section in the middle section of 700m is divided into east and west according to the direction of the ore body, and a drainage chamber 205 is designed in the east and west of the 814m section, which are respectively called the 814m east drainage chamber 205 and the 814m west drainage chamber 205.
[0021] A small water tank 203 is designed in each production panel 201 of the 814m section. The small water tank 203 in the production panel 201 is mainly used to store fissure water and waste water generated during the drilling process of the drilling rig. A water pump is placed in the small water tank 203 of the production panel 201. The water pump is connected to the sewage pipe 204. The sewage pipe 204 runs from the mining field through the layered connecting road and the segmented road to the drainage chamber 205 in the east and west of the 814m section. The general design specifications of the drainage chamber 205 are: 30m×4.6m×4.3m (length×width×height). The 814m section is equipped with two car wash chambers 202. The sewage generated by washing the trackless equipment is discharged to the sewage pool in the rear part of the chamber through the drainage ditch 103 of the car wash chamber 202. A water pump is placed in the sewage pool in the rear part of the chamber, and the water pump is connected to the drainage chamber 205 through the sewage pipe 204. This process basically realizes the concentration of a large amount of sewage in the mining field to the drainage chamber 205 corresponding to the 814m section.
[0022] The sewage in the drainage chamber 205 in the east and west of the 814m section of the middle section of 700m is discharged to the east and west sedimentation tank 101 in the middle section of 700m through the drainage borehole 206 of 814m-700m under the action of its own weight. The sewage in the sedimentation tank 101 settles under the action of its own weight to form upper "clear liquid" and lower "thin mud". The upper "clear liquid" is discharged into the central water tank 102 in the middle section of 700m through the sewage pump, and then pumped to the central water tank 102 in the middle section of 850m by the central water tank 102. At this point, all the sewage in the middle section of 700m is collected in the central water tank 102 in the middle section of 850m, and the lower "thin mud" is transported to the middle section of 1150m through the 700m horizontal vacuum pump. The "thin mud" is then relayed to the surface for treatment in the form of "water carrying mud" through the vacuum pumps in the middle sections of 1150m and 1350m.
[0023] Embodiment 3, Taking the 1018m section in the middle section of 1000m as an example, similar to the 934m section in the middle section of 850m and the 814m section in the middle section of 700m, the 1018m section in the middle section of 1000m is divided into the east and west according to the direction of the ore body, and a drainage chamber 205 is designed in the east and west of the 1018m section.
[0024] A small water tank 203 is designed in each production panel 201 of the 1018m section. The small water tank 203 in the production panel 201 is mainly used to store fissure water and waste water generated during the drilling process of the drilling rig. A water pump is placed in the small water tank 203 of the production panel 201. The water pump is connected to the sewage pipe 204. The sewage pipe 204 runs from the mining area through the layered connecting road and the segmented road to the drainage chamber 205 in the east and west of the 814m section. The general design specifications of the drainage chamber 205 are: 30m×4.6m×4.3m (length×width×height). There are 4 car wash chambers 202 in the 1018m section. The sewage generated by washing the trackless equipment is discharged to the sewage pool in the rear part of the chamber through the drainage ditch 103 of the car wash chamber 202. A water pump is placed in the sewage pool in the rear part of the chamber, and the water pump is connected to the drainage chamber 205 through the sewage pipe 204. This process basically realizes the concentration of a large amount of sewage in the mining field to the drainage chamber 205 corresponding to the 1018m section.
[0025] The sewage in the drainage chambers 205 in the east and west of the 1018m section of the middle section of 1000m is discharged to the water tanks in the west and east of the middle section of 1000m through the drainage boreholes 206 of 1018m-1000m under the action of its own weight. Since the designed size of the water tank in the east of the 1018m section is larger, the water tank in the east of 1000m is also used as the central water tank 102 of the middle section of 1000m. The sewage in the water tank in the west of the middle section of 1000m is transported to the central water tank 102 of the middle section of 1000m through a sewage pump, and the sewage in the middle section of 1000m is then pumped to the central water tank 102 of the middle section of 1150m through the drainage boreholes 106 of 1150m-1000m.
[0026] Finally, all kinds of sewage generated in the middle sections of 700m, 850m and 1000m underground are collected in the central water tank 102 in the middle section of 1150m through the middle section collection and step-by-step relay method, and then pumped to the surface sedimentation tank 101 for sewage treatment.
[0027] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A mine multi-section simultaneous mining and drainage system, wherein each section (1) is composed of a plurality of subsections (2), and each subsection (2) is provided with a plurality of production panels (201) and a car wash chamber (202), characterized in that: The utility model comprises a small water tank (203) in the panel area, a sewage pipe (204) and a drainage chamber (205). The small water tank (203) in the panel area, the sewage pipe (204) and the drainage chamber (205) are arranged on each segment (2) in the middle segment (1). The water inlet of the small water tank (203) in the panel area is connected to the drainage outlet of the production panel area (201). The sewage pipe (204) is provided with a plurality of water inlets, which are respectively connected to the drainage outlets of the small water tank (203) in the panel area and the car wash chamber (202). The water outlet of the sewage pipe (204) is arranged in the drainage chamber (205). A drainage borehole (206) is provided at the bottom of the drainage chamber (205). The drainage chambers (205) in each segment (2) are connected to each other through the drainage borehole (206). A sedimentation tank (101) and a central water tank (102) are provided on the horizontal surface of each section (1). Water in a drainage chamber (205) flows into the sedimentation tank (101) through a drainage borehole (206). A drainage ditch (103) is also provided on the horizontal surface of each middle section (1). Branches at one end of the drainage ditch (103) are respectively located in a river channel (104) and a sedimentation tank (101). The other end of the drainage ditch (103) is located in the central water tank (102). Each central water tank (102) is equipped with a pump house (105). Each central water tank (102) is provided with a drainage borehole (106). Under the action of the pump house (105), sewage in each central water tank (102) is pumped from the drainage borehole (106) to the surface sedimentation tank (101) through multiple stages.
2. A mine multi-section simultaneous mining and drainage system according to claim 1, characterized in that: A water pump is provided in the small water tank (203) of the pan area, and the water outlet of the water pump is connected to the water inlet of the sewage pipe (204).
3. A mine multi-section simultaneous mining and drainage system according to claim 2, characterized in that: A water pump is provided in the car washing chamber (202), and a water outlet of the water pump is connected to a water inlet of a sewage pipe (204).
4. A mine multi-section simultaneous mining and drainage system according to claim 3, characterized in that: The car washing chamber (202) is provided with a slope surface from the inside to the outside and from the bottom to the top.
5. A mine multi-section simultaneous mining and drainage system according to claim 4, characterized in that: The drainage chambers (205) are provided in a plurality, preferably two.
6. A mine multi-section simultaneous mining and drainage system according to claim 5, characterized in that: The drainage boreholes (206) are provided in a plurality, preferably two.
7. A mine multi-section simultaneous mining and drainage system according to claim 6, characterized in that: The sedimentation tanks (101) are provided in a plurality, preferably two.
8. A mine multi-section simultaneous mining and drainage system according to any one of claims 1 to 7, characterized in that: The drainage drilling holes (106) are provided in a plurality, preferably two.