The present application relates to the technical field of
tunnel construction, and particularly relates to a tunnel portal and tunnel body
pipe shed construction method, step S1, portal side slope and portal
drainage ditch construction is carried out, step S2, concrete arch is constructed in open
cut section and buried section, step S3,
step method is used for tunnel excavation, first, upper step arc-shaped guide pit is excavated, step S4, lower step excavation is carried out in staggered manner at a certain distance from the
lag upper step working face, step S5, invert and tunnel bottom filling are poured at a certain distance from the
lag lower step working face, and secondary lining construction is carried out after initial support, invert and tunnel bottom filling convergence; step S6, steps S4-S5 are repeated until
tunnel construction is completed. The concrete arch is set, the concrete arch is used as a guide wall, the arch uses the existing soil layer as a formwork, so that the formwork setting difficulty is reduced, and the construction efficiency is improved.