Gas turbine MARK VIe control architecture

Through hardwired connection of DI, DO, AI and AO terminals, the connection problem between the LCI and excitation system of GE 9F gas engine unit and the MARK VIe control system is solved, and the domestic transformation is realized, which improves the reliability and independent control capabilities of the system. , reduce maintenance costs.

CN119163507AActive Publication Date: 2024-12-20GUANGZHOU DEV ELECTRIC POWER TECH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411207124.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-12-20
Estimated Expiration
2044-08-30

AI Technical Summary

Technical Problem

The LCI and excitation systems of GE 9F gas engine units cannot be connected with the original GE company's MARK VIe control system during the domestic transformation, resulting in equipment aging and high procurement costs, affecting the maintenance and safe operation of the power plant.

Method used

Use DI, DO, AI and AO terminals for hard wiring to replace the original EGD communication method, so that signal interconnection between the LCI system, excitation system and the MARK VIe control system can be achieved through the newly added terminal card board and communication switch. Signal transmission.

Benefits of technology

The localized transformation of LCI and excitation systems has been realized, which reduces maintenance costs, improves the reliability and independent control capabilities of the system, reduces dependence on original manufacturers, and ensures the stability and security of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119163507A_ABST
    Figure CN119163507A_ABST
Patent Text Reader

Abstract

The invention discloses a gas turbine MARK VIe control framework which comprises a gas turbine MARK VIe control system, an excitation system, an LCI system and a gas turbine MARK VIe communication switch. The DI card port, the DO card port, the AI card port and the AO card port of the gas turbine MARK VIe control system are respectively connected with the DI card port, the DO card port, the AI card port and the AO card port of the excitation system, and the DI card port, the DO card port, the AI card port and the AO card port of the gas turbine MARK VIe control system are connected with the DI card port, the DO card port, the AI card port and the AO card port of the LCI system. According to the invention, various LCI system and various excitation system control signals can replace original EGD point communication signals, and the control logic of the MARK VIe control system is kept unchanged.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of gas engine control, and in particular to a gas engine MARK VIe control architecture. Background Art

[0002] In recent years, the LCI system equipment of the GE 9F gas turbine units put into operation in my country has been in operation for more than ten years. The gas turbine units are basically operated in a daily start-stop mode in the power grid dispatching. The LCI system has begun to show defects such as equipment aging and high failure rate, which seriously affects the safe operation of the gas turbine units. In addition, the gas turbine LCI and excitation system equipment are all imported equipment from GE. The purchase price of spare parts and equipment upgrades is high, and the supply cycle is long. Key technologies are blocked and not open, which is not conducive to the daily maintenance of gas turbine power plants and the safe operation requirements of units.

[0003] GE 9F gas turbine unit LCI, excitation system operation, control signals and MARK VIe control system all use the embedded EGD communication protocol (ethernet global data) (Ethernet Global Data Protocol) communication system connection method, which supports information sharing between multiple nodes based on the UPD / IP standard protocol. It is a non-international standard communication system protocol (as shown above Figure 1 As shown in the figure). Due to the lack of GE's support and technology in the communication system during the localization process, the domestic equipment cannot be connected to the original equipment's EGD-based communication system, and the localization transformation of the LCI system equipment cannot achieve signal connection with GE's MARK VIe control system. The localization transformation of the excitation system also has this problem. If the localization transformation of LCI and the excitation system is to be realized, the technical barrier must be broken. Summary of the invention

[0004] An embodiment of the present invention provides a MARK VIe control architecture for a gas turbine, wherein the MARK VIe control system, the excitation system and the LCI system of the gas turbine are hard wired through DI, DO, AI and AO terminals, replacing the EGD-based communication method.

[0005] To achieve the above-mentioned purpose, the embodiment of the present application provides a gas turbine MARK VIe control architecture, including: a gas turbine MARK VIe control system, an excitation system, an LCI system and a gas turbine MARK VIe communication switch;

[0006] The DI card port of the gas engine MARK VIe control system is connected to the DI card port of the excitation system, and the DI card port of the gas engine MARK VIe control system is connected to the DI card port of the LCI system; the DO card port of the gas engine MARK VIe control system is connected to the DO card port of the excitation system, and the DO card port of the gas engine MARK VIe control system is connected to the DO card port of the LCI system; the AI ​​card port of the gas engine MARK VIe control system is connected to the AI ​​card port of the excitation system, and the AI ​​card port of the gas engine MARK VIe control system is connected to the AI ​​card port of the LCI system; the AO card port of the gas engine MARK VIe control system is connected to the AO card port of the excitation system, and the AO card port of the gas engine MARK VIe control system is connected to the AO card port of the LCI system;

[0007] The communication end of the gas turbine MARK VIe control system is connected to the first communication end of the gas turbine MARK VIe communication switch; the gas turbine MARK VIe communication switch is connected to the external MARK VIe communication system through the second communication end.

[0008] In a possible implementation, the gas engine MARK VIe control system includes a gas engine MARK VIe controller and a gas engine MARK VIe signal terminal board; the gas engine MARK VIe controller is communicatively connected to the gas engine MARK VIe signal terminal board;

[0009] The DI card port of the gas turbine MARK VIe signal terminal board is connected to the DI card port of the excitation system, and the DI card port of the gas turbine MARK VIe signal terminal board is connected to the DI card port of the LCI system; the DO card port of the gas turbine MARK VIe signal terminal board is connected to the DO card port of the excitation system, and the DO card port of the gas turbine MARK VIe signal terminal board is connected to the DO card port of the LCI system; the AI ​​card port of the gas turbine MARK VIe signal terminal board is connected to the AI ​​card port of the excitation system, and the AI ​​card port of the gas turbine MARK VIe signal terminal board is connected to the AI ​​card port of the LCI system; the AO card port of the gas turbine MARK VIe signal terminal board is connected to the AO card port of the excitation system, and the AO card port of the gas turbine MARK VIe signal terminal board is connected to the AO card port of the LCI system;

[0010] The communication end of the gas engine MARK VIe controller is connected to the first communication end of the gas engine MARK VIe communication switch.

[0011] In a possible implementation, the excitation system includes an excitation system controller and an excitation system control signal baseboard; the excitation system controller is communicatively connected to the excitation system control signal baseboard;

[0012] The DI card port of the excitation system control signal baseboard is connected to the DI card port of the gas turbine MARK VIe control system, and the DI card port of the excitation system control signal baseboard is connected to the DI card port of the LCI system; the DO card port of the excitation system control signal baseboard is connected to the DO card port of the gas turbine MARK VIe control system, and the DO card port of the excitation system control signal baseboard is connected to the DO card port of the LCI system; the AI ​​card port of the excitation system control signal baseboard is connected to the AI ​​card port of the gas turbine MARK VIe control system, and the AI ​​card port of the excitation system control signal baseboard is connected to the AI ​​card port of the LCI system; the AO card port of the excitation system control signal baseboard is connected to the AO card port of the gas turbine MARK VIe control system, and the AO card port of the excitation system control signal baseboard is connected to the AO card port of the LCI system.

[0013] In a possible implementation, the LCI system includes an LCI system controller and an LCI system control signal backplane; the LCI system controller is communicatively connected to the LCI system control signal backplane;

[0014] The DI card port of the LCI system control signal baseboard is connected to the DI card port of the gas turbine MARK VIe control system, and the DI card port of the LCI system control signal baseboard is connected to the DI card port of the excitation system; the DO card port of the LCI system control signal baseboard is connected to the DO card port of the gas turbine MARK VIe control system, and the DO card port of the LCI system control signal baseboard is connected to the DO card port of the excitation system; the AI ​​card port of the LCI system control signal baseboard is connected to the AI ​​card port of the gas turbine MARK VIe control system, and the AI ​​card port of the LCI system control signal baseboard is connected to the AI ​​card port of the excitation system; the AO card port of the LCI system control signal baseboard is connected to the AO card port of the gas turbine MARK VIe control system, and the AO card port of the LCI system control signal baseboard is connected to the AO card port of the excitation system.

[0015] In a possible implementation, the LCI system sends a first DI input signal to the DI card port of the gas turbine MARK VIe control system through the DI card port of the LCI system control signal backplane, and the first DI input signal includes LCI system availability information and system service information after configuration modification.

[0016] In one possible implementation, the gas turbine MARK VIe control system sends a DO output signal to the DO card port of the LCI system through the DO card port of the gas turbine MARK VIe signal terminal board, and the DO output signal includes power-on request information, start selection information, LCI service confirmation information after configuration modification, remote signal reset information and unit start information.

[0017] In a possible implementation, the gas turbine MARK VIe control system sends an AO output signal to the AO card port of the LCI system through the AO card port of the gas turbine MARK VIe signal terminal board, and the AO output signal includes LCT speed reference information.

[0018] In a possible implementation, the excitation system sends a second DI input signal to a DI card port of the gas engine MARK VIe control system through a DI card port of the excitation system control signal baseboard.

[0019] In a possible implementation, before sending the first DI input signal, the sub-signals in the first DI input signal are renamed according to a preset rule.

[0020] In a possible implementation, before sending the second DI input signal, the sub-signals in the second DI input signal are renamed according to a preset rule.

[0021] Compared with the prior art, the MARK VIe control architecture of a gas turbine provided in an embodiment of the present invention adopts DI (digital input), DO (digital output), AI (analog input), and AO (analog output) terminals for hard wiring connection to replace the original EGD communication mode: the LCI system and the excitation system input the input signal to the MARK VIe control system through the newly added DI and AI terminal cards to participate in the control. The output signal output by the MARK VIe control system is sent to the LCI system and the excitation system through the DO and AO terminal output cards to realize the control of the equipment.

[0022] Without using EDG communication mode, the MARK VIe control system is given logical assignment, and the LCI system and excitation system can be correctly interconnected and control technology can be maintained while keeping the original MARK VIe control LCI and excitation system logic unchanged. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 It is a structural schematic diagram of a MARK VIe control architecture of a gas turbine provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0025] To solve the above problems, see Figure 1 An embodiment of the present invention provides a gas turbine MARK VIe control architecture, including: a gas turbine MARK VIe control system 1, an excitation system 2, an LCI system 3 and a gas turbine MARK VIe communication switch 4.

[0026] The DI card port of the gas engine MARK VIe control system 1 is connected to the DI card port of the excitation system 2, and the DI card port of the gas engine MARK VIe control system 1 is connected to the DI card port of the LCI system 3; the DO card port of the gas engine MARK VIe control system 1 is connected to the DO card port of the excitation system 2, and the DO card port of the gas engine MARK VIe control system 1 is connected to the DO card port of the LCI system 3; the AI ​​card port of the gas engine MARK VIe control system 1 is connected to the AI ​​card port of the excitation system 2, and the AI ​​card port of the gas engine MARK VIe control system 1 is connected to the AI ​​card port of the LCI system 3; the AO card port of the gas engine MARK VIe control system 1 is connected to the AO card port of the excitation system 2, and the AO card port of the gas engine MARK VIe control system 1 is connected to the AO card port of the LCI system 3.

[0027] The communication end of the gas engine MARK VIe control system 1 is connected to the first communication end of the gas engine MARK VIe communication switch 4; the gas engine MARK VIe communication switch 4 is connected to the external MARK VIe communication system through the second communication end.

[0028] The above architecture uses DI (digital input), DO (digital output), AI (analog input), and AO (analog output) terminals for hard wiring connection, replacing the original EGD communication method (in the prior art, GE's LCI system 3 controls the EGD point signal and the two redundant communication switches of the MARK VIe control system, and GE's excitation system 2 controls the two network twisted pair cables for communication between the EGD point signal and the MARK VIe control system).

[0029] LCI system 3 and excitation system 2 participate in control by inputting input signals to the MARK VIe control system through the newly added DI and AI terminal cards. The technical barrier problem of the original EGD communication method is solved by hard wiring connection, making the localization transformation of LCI system 3 and excitation system 2 possible. Without adopting the EGD communication method, the original MARK VIe control logic of LCI and excitation system 2 can still be maintained through hard wiring connection, ensuring the stability and reliability of the system.

[0030] Wired connections are generally more reliable than EDG communication connections, especially in industrial environments. In addition, hard-wired connections are easier to troubleshoot and maintain, reducing maintenance costs. The use of hard-wired connections reduces dependence on original manufacturer support and technology blockades, and improves autonomous control capabilities.

[0031] The output signal of the gas turbine MARK VIe control system 1 can be sent to the LCI system 3 and the excitation system 2 through the DO and AO terminal output card boards, thereby realizing the control of the equipment.

[0032] By adopting the hard-wired connection method, the technical barriers of the original EGD communication method are effectively solved, while keeping the original control logic unchanged, improving the reliability and maintainability of the system. This is of great significance for the localization transformation and helps to improve the operating efficiency and safety of gas turbine power plants.

[0033] Exemplarily, the gas engine MARK VIe control system 1 includes a gas engine MARK VIe controller 10 and a gas engine MARK VIe signal terminal board 11 ; the gas engine MARK VIe controller 10 is communicatively connected with the gas engine MARK VIe signal terminal board 11 .

[0034] The DI card port of the gas turbine MARK VIe signal terminal board 11 is connected to the DI card port of the excitation system 2, and the DI card port of the gas turbine MARK VIe signal terminal board 11 is connected to the DI card port of the LCI system 3; the DO card port of the gas turbine MARK VIe signal terminal board 11 is connected to the DO card port of the excitation system 2, and the DO card port of the gas turbine MARK VIe signal terminal board 11 is connected to the DO card port of the LCI system 3; the AI ​​card port of the gas turbine MARK VIe signal terminal board 11 is connected to the AI ​​card port of the excitation system 2, and the AI ​​card port of the gas turbine MARK VIe signal terminal board 11 is connected to the AI ​​card port of the LCI system 3; the AO card port of the gas turbine MARK VIe signal terminal board 11 is connected to the AO card port of the excitation system 2, and the AO card port of the gas turbine MARK VIe signal terminal board 11 is connected to the AO card port of the LCI system 3;

[0035] The communication end of the gas engine MARK VIe controller 10 is connected to the first communication end of the gas engine MARK VIe communication switch 4 .

[0036] Exemplarily, the excitation system 2 includes an excitation system controller 20 and an excitation system 2 control signal baseboard; the excitation system controller 20 is communicatively connected with the excitation system control signal baseboard 21;

[0037] The DI card port of the excitation system control signal baseboard 21 is connected to the DI card port of the gas turbine MARK VIe control system 1, and the DI card port of the excitation system control signal baseboard 21 is connected to the DI card port of the LCI system 3; the DO card port of the excitation system control signal baseboard 21 is connected to the DO card port of the gas turbine MARK VIe control system 1, and the DO card port of the excitation system control signal baseboard 21 is connected to the DO card port of the LCI system 3; the AI ​​card port of the excitation system control signal baseboard 21 is connected to the AI ​​card port of the gas turbine MARK VIe control system 1, and the AI ​​card port of the excitation system control signal baseboard 21 is connected to the AI ​​card port of the LCI system 3; the AO card port of the excitation system control signal baseboard 21 is connected to the AO card port of the gas turbine MARK VIe control system 1, and the AO card port of the excitation system control signal baseboard 21 is connected to the AO card port of the LCI system 3.

[0038] Exemplarily, the LCI system 3 includes an LCI system controller 30 and an LCI system 3 control signal backplane; the LCI system controller 30 is communicatively connected with the LCI system control signal backplane 31;

[0039] The DI card port of the LCI system control signal baseboard 31 is connected to the DI card port of the gas turbine MARK VIe control system 1, and the DI card port of the LCI system control signal baseboard 31 is connected to the DI card port of the excitation system 2; the DO card port of the LCI system control signal baseboard 31 is connected to the DO card port of the gas turbine MARK VIe control system 1, and the DO card port of the LCI system control signal baseboard 31 is connected to the DO card port of the excitation system 2; the AI ​​card port of the LCI system control signal baseboard 31 is connected to the AI ​​card port of the gas turbine MARK VIe control system 1, and the AI ​​card port of the LCI system control signal baseboard 31 is connected to the AI ​​card port of the excitation system 2; the AO card port of the LCI system control signal baseboard 31 is connected to the AO card port of the gas turbine MARK VIe control system 1, and the AO card port of the LCI system control signal baseboard 31 is connected to the AO card port of the excitation system 2.

[0040] The existing LCI system 3 and excitation system 2 send the MARK VIe control system EGD point control signal prefix generally starts with L1(E1).G1.X (X represents the suffix signal point name), L1(E1).X (X represents the suffix signal point name), etc. plus the signal point name. The original GE company's LCI2 system sends the MARK VIe control system EGD point control signal prefix L2(E2).G2.X (X represents the suffix signal point name), L2(E2).X (X represents the suffix signal point name), etc. plus the signal point name. This is a unique technical communication signal method of EGD protocol communication. The modified LCI and excitation system 2 control signal points are changed to prefix L1(E1)_G1_X, L1_X (excitation system 2LCI1) or L2(E2)_G2_X, L2_X (excitation system 2LCI2) etc. with point names (Note: This format is used to distinguish the original EGD control signal points. The original EGD control signal points use L1(2) to indicate that the signal comes from the LCI1(2) control system, and E1(2) to indicate that the signal comes from the #1(2) excitation control system. The prefix L1(E1)_G1_ is mainly used to distinguish the original EGD signal point "L1(E1).G1."; X represents the suffix signal point name which is the same as the original EGD signal point name, mainly to facilitate the subsequent replacement of the original EGD signal without error, duplication, or missing signal points, and to distinguish it from the existing EGD control signal points, and to replace the EGD control signal points used by the original GE company with the new control signals of the localized transformation of the LCI system 3 and the excitation system 2 using the newly invented assignment method.

[0041] Exemplarily, referring to Table 1, the LCI system 3 sends a first DI input signal to the DI card port of the gas turbine MARK VIe control system 1 through the DI card port of the LCI system control signal baseboard 31, and the first DI input signal includes the LCI system 3 availability information and the system service information after the configuration is modified.

[0042]

[0043]

[0044] Table 1 DI point table of the first DI input signal

[0045] In this way, the LCI system can report its current status and service information to the MARK VIe control system 1 in a timely manner, thereby ensuring that the control system can make correct decisions based on the actual status of the LCI system 3. This method improves the reliability and maintainability of the structure, helps to keep the original control logic unchanged, and solves the technical barrier problem of the original EGD communication method.

[0046] Exemplarily, please refer to Table 2, the gas turbine MARK VIe control system 1 sends a DO output signal to the DO card port of the LCI system 3 through the DO card port of the gas turbine MARK VIe signal terminal board 11, and the DO output signal includes power-on request information, start selection information, LCI service confirmation information after configuration modification, remote signal reset information and unit start information.

[0047] Signal name after transformation Original signal name Explanation L1_lss_pwr (Static starter AC power up to LCI1) Power-on request 1 G1.l4ssrun G1.l4ssrun (Static Start Master Control Signal) Run command 1 G1.L4SSTORQ G1.l4sstorq (Static Start Make Torque Command) Output torque request 1 L1_LCI_SEL (LCI Start Select Command 1) Start Select Command 1 L1_LSS_SELECT G1.LSS_SELECT (LS2100 1Selected to Start G1)LCI Service G1 Confirmed LCI1_RESET (LCI1 RESET) Remote signal reset 1 L1START_LCI1 G1.L1START_CPB Master start signal to LCI1 Start (Master start signal to LCI1 Start)

[0048] Table 2 DO point table of DO output signal

[0049] In this way, the MARK VIe control system 1 of the gas turbine can send necessary control instructions and service information to the LCI system 3 in a timely manner, thereby ensuring that the LCI system 3 can operate according to the predetermined logic and requirements. This method improves the reliability and maintainability of the system, helps to keep the original control logic unchanged, and solves the technical barrier problem of the original EGD communication method.

[0050] Exemplarily, referring to Table 3, the gas turbine MARK VIe control system 1 sends an AO output signal to the AO card port of the LCI system 3 through the AO card port of the gas turbine MARK VIe signal terminal board 11, and the AO output signal includes LCT speed reference information.

[0051]

[0052] Table 3 AO point table of AO output signal

[0053] In this way, the MARK VIe control system of the gas turbine can send the necessary speed reference information to the LCI system in a timely manner, thereby ensuring that the LCI system can control the speed of the LCT according to the predetermined logic and requirements. This method improves the reliability and maintainability of the system, helps to keep the original control logic unchanged, and solves the technical barriers of the original EGD communication method.

[0054] Exemplarily, referring to Table 4, the excitation system 2 sends a second DI input signal to the DI card port of the gas engine MARK VIe control system 1 through the DI card port of the excitation system control signal baseboard 21 .

[0055]

[0056] Table 4 DI point table of the second DI input signal

[0057] Exemplarily, before sending the first DI input signal, the sub-signals in the first DI input signal are renamed according to a preset rule.

[0058] Exemplarily, before sending the second DI input signal, the sub-signals in the second DI input signal are renamed according to a preset rule.

[0059] Compared with the prior art, the MARK VIe control architecture of a gas turbine provided in an embodiment of the present invention adopts DI (digital input), DO (digital output), AI (analog input), and AO (analog output) terminals for hard wiring connection to replace the original EGD communication mode: the LCI system 3 and the excitation system 2 input the input signal to the MARK VIe control system through the newly added DI and AI terminal card boards to participate in the control. The output signal output by the MARK VIe control system is sent to the LCI system 3 and the excitation system 2 through the DO and AO terminal output card boards to realize the control of the equipment.

[0060] Without using EDG communication mode, the MARK VIe control system is given logic assignment, and the LCI system 3 and the excitation system 2 can be correctly interconnected and the control technology can keep the original MARK VIe control LCI and excitation system 2 logic unchanged.

[0061] The gas turbine MARK VIe control system 1 adds a terminal card mode, which can connect various signals from the domestic LCI system 3 and excitation system 2 control hard wiring with the MARK VIe control system signal, and use a special signal replacement assignment method to assign various signals from the domestic LCI and excitation system 2 control hard wiring to the original control logic, and cancel the original GE company LCI and excitation system 2EGD control signal points.

[0062] The gas turbine MARK VIe control system 1 adds the independently developed and innovative LCI control system logic communication to realize the normal startup and interconnection and mutual control technology of the LCI system 3 (including at least one LCI device).

[0063] In addition, the original gas turbine MARK VIe control system 1LCI and excitation control system HMI screens can be modified, the original EGD Ethernet communication reading and writing mode can be cancelled, and a new control screen can be adopted. The gas turbine MARK VIe control system 1 signal reading and writing mode can be adaptively changed according to the signal at the second communication port of the MARK VIe communication switch, so as to realize the normal startup, adjustment, monitoring and interconnection and mutual control technology of the domestically produced LCI and excitation control systems on the HMI screen.

[0064] The above is a preferred embodiment of the present invention. It should be pointed out that a person skilled in the art can make several improvements and modifications without departing from the principle of the present invention. These improvements and modifications are also considered to be within the scope of protection of the present invention.

Claims

1. A MARK VIe control architecture for gas turbines, include: Gas turbine MARK VIe control system, excitation system, LCI system and gas turbine MARK VIe communication switch; The DI card port of the gas engine MARK VIe control system is connected to the DI card port of the excitation system, and the DI card port of the gas engine MARK VIe control system is connected to the DI card port of the LCI system; the DO card port of the gas engine MARK VIe control system is connected to the DO card port of the excitation system, and the DO card port of the gas engine MARK VIe control system is connected to the DO card port of the LCI system; the AI ​​card port of the gas engine MARK VIe control system is connected to the AI ​​card port of the excitation system, and the AI ​​card port of the gas engine MARK VIe control system is connected to the AI ​​card port of the LCI system; the AO card port of the gas engine MARK VIe control system is connected to the AO card port of the excitation system, and the AO card port of the gas engine MARK VIe control system is connected to the AO card port of the LCI system; The communication end of the gas turbine MARK VIe control system is connected to the first communication end of the gas turbine MARK VIe communication switch; the gas turbine MARK VIe communication switch is connected to the external MARK VIe communication system through the second communication end.

2. A MARK VIe control architecture for a gas turbine as claimed in claim 1, It is characterized in that The gas engine MARK VIe control system includes a gas engine MARK VIe controller and a gas engine MARK VIe signal terminal board; the gas engine MARK VIe controller is communicatively connected with the gas engine MARK VIe signal terminal board; The DI card port of the gas turbine MARK VIe signal terminal board is connected to the DI card port of the excitation system, and the DI card port of the gas turbine MARK VIe signal terminal board is connected to the DI card port of the LCI system; the DO card port of the gas turbine MARK VIe signal terminal board is connected to the DO card port of the excitation system, and the DO card port of the gas turbine MARK VIe signal terminal board is connected to the DO card port of the LCI system; the AI ​​card port of the gas turbine MARK VIe signal terminal board is connected to the AI ​​card port of the excitation system, and the AI ​​card port of the gas turbine MARK VIe signal terminal board is connected to the AI ​​card port of the LCI system; the AO card port of the gas turbine MARK VIe signal terminal board is connected to the AO card port of the excitation system, and the AO card port of the gas turbine MARK VIe signal terminal board is connected to the AO card port of the LCI system; The communication end of the gas engine MARK VIe controller is connected to the first communication end of the gas engine MARK VIe communication switch.

3. A MARK VIe control architecture for a gas turbine as claimed in claim 1, It is characterized in that The excitation system includes an excitation system controller and an excitation system control signal baseboard; the excitation system controller is communicatively connected with the excitation system control signal baseboard; The DI card port of the excitation system control signal baseboard is connected to the DI card port of the gas turbine MARK VIe control system, and the DI card port of the excitation system control signal baseboard is connected to the DI card port of the LCI system; the DO card port of the excitation system control signal baseboard is connected to the DO card port of the gas turbine MARK VIe control system, and the DO card port of the excitation system control signal baseboard is connected to the DO card port of the LCI system; the AI ​​card port of the excitation system control signal baseboard is connected to the AI ​​card port of the gas turbine MARK VIe control system, and the AI ​​card port of the excitation system control signal baseboard is connected to the AI ​​card port of the LCI system; the AO card port of the excitation system control signal baseboard is connected to the AO card port of the gas turbine MARK VIe control system, and the AO card port of the excitation system control signal baseboard is connected to the AO card port of the LCI system.

4. A MARK VIe control architecture for a gas turbine as claimed in claim 1, It is characterized in that The LCI system includes an LCI system controller and an LCI system control signal backplane; the LCI system controller is communicatively connected with the LCI system control signal backplane; The DI card port of the LCI system control signal baseboard is connected to the DI card port of the gas turbine MARK VIe control system, and the DI card port of the LCI system control signal baseboard is connected to the DI card port of the excitation system; the DO card port of the LCI system control signal baseboard is connected to the DO card port of the gas turbine MARK VIe control system, and the DO card port of the LCI system control signal baseboard is connected to the DO card port of the excitation system; the AI ​​card port of the LCI system control signal baseboard is connected to the AI ​​card port of the gas turbine MARK VIe control system, and the AI ​​card port of the LCI system control signal baseboard is connected to the AI ​​card port of the excitation system; the AO card port of the LCI system control signal baseboard is connected to the AO card port of the gas turbine MARK VIe control system, and the AO card port of the LCI system control signal baseboard is connected to the AO card port of the excitation system.

5. A MARK VIe control architecture for a gas turbine as claimed in claim 4, It is characterized in that The LCI system sends a first DI input signal to the DI card port of the gas turbine MARK VIe control system through the DI card port of the LCI system control signal backplane, and the first DI input signal includes LCI system availability information and system service information after configuration modification.

6. A MARK VIe control architecture for a gas turbine as claimed in claim 2, It is characterized in that The gas turbine MARK VIe control system sends a DO output signal to the DO card port of the LCI system through the DO card port of the gas turbine MARK VIe signal terminal board. The DO output signal includes power-on request information, start selection information, LCI service confirmation information after configuration modification, remote signal reset information and unit start information.

7. A MARK VIe control architecture for a gas turbine as claimed in claim 2, It is characterized in that The gas engine MARK VIe control system sends an AO output signal to the AO card port of the LCI system through the AO card port of the gas engine MARK VIe signal terminal board, and the AO output signal includes LCT speed reference information.

8. A MARK VIe control architecture for a gas turbine as claimed in claim 3, It is characterized in that The excitation system sends a second DI input signal to the DI card port of the gas engine MARK VIe control system through the DI card port of the excitation system control signal baseboard.

9. A MARK VIe control architecture for a gas turbine as claimed in claim 5, It is characterized in that Before sending the first DI input signal, the sub-signals in the first DI input signal are renamed according to a preset rule.

10. A MARK VIe control architecture for a gas turbine as claimed in claim 9, It is characterized in that Before sending the second DI input signal, the sub-signals in the second DI input signal are renamed according to a preset rule.