Public auxiliary equipment control method, control equipment, production execution system and related device
By determining the total demand load of the workshop for public and auxiliary equipment and optimizing the start-up and shutdown strategies, the problem of energy waste of public and auxiliary equipment in the factory is solved, and the efficient utilization and reliability of the equipment are achieved.
Patent Information
- Application Number
- CN202411302397.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-18
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2044-09-18
AI Technical Summary
In the factory production process, public auxiliary equipment still needs to be in operation when not needed, resulting in waste of energy and high emissions.
By determining the total demand load of the workshop for public auxiliary equipment, starting the minimum number of public auxiliary equipment to meet the needs, starting and delaying the shutdown of the equipment in advance, avoiding frequent power switch-offs, and combining the requested start instructions and standard operating procedures of automated production equipment, optimize Use of public auxiliary equipment.
It reduces the energy consumption and waste of public and auxiliary equipment, improves the load rate of equipment, reduces the risk of errors caused by manual operations, extends the life of the equipment, and avoids failure of production tasks caused by insufficient equipment.
Smart Images

Figure CN119165801A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of intelligent manufacturing, and more specifically, to a public auxiliary equipment control method, control equipment, production execution system and related devices. Background Art
[0002] In the factory production process, in addition to the main process equipment, some necessary edge equipment and public auxiliary equipment are often required, such as constant temperature dehumidification units, vacuum units, chillers, circulating water units, compressed air units, nitrogen generators, etc. These equipment do not directly participate in production, but provide assistance to production equipment, but edge equipment and public auxiliary equipment are high energy consumption and high emission equipment.
[0003] Usually, a factory will configure at least one set of necessary public auxiliary units for multiple equipment or even the entire workshop. This means that even if only one production line needs to be operated, all the public auxiliary equipment of the public auxiliary unit needs to be in operation, resulting in energy waste. Summary of the invention
[0004] The present application provides a public auxiliary equipment control method, control equipment, production execution system and related devices to reduce the energy waste of existing public auxiliary units.
[0005] In a first aspect, the present application provides a method for controlling public auxiliary equipment, which is applied to a server, and the method includes: determining whether a workshop needs to use public auxiliary equipment within a preset time period from the current moment; if the workshop needs to use the public auxiliary equipment, determining the total required load of the workshop for the public auxiliary equipment; based on the total required load, determining the number of public auxiliary equipment that needs to be started; wherein the starting number is the minimum number that satisfies the need to start the public auxiliary equipment so that the total load is greater than or equal to the total required load; and starting the public auxiliary equipment that matches the starting number.
[0006] In the embodiment of the present application, by determining the total demand load of the workshop for the public auxiliary equipment, the startup number can be determined according to the total demand load, and the startup number is the minimum number that satisfies the total load of the public auxiliary equipment that needs to be started is greater than or equal to the total demand load. That is, the public auxiliary equipment of this startup number can not only meet the use of the public auxiliary equipment by the workshop, but also reduce the number of public auxiliary equipment started as much as possible. In this way, the minimum number of public auxiliary equipment can be started without affecting the normal production work of the workshop, so that there will not be too much public auxiliary equipment idling, resulting in energy waste. Moreover, in this way, the public auxiliary equipment that is started will provide assistance to the workshop, and the load rate of the public auxiliary equipment can also be increased. And this scheme does not require manual operation to start the public auxiliary equipment. Compared with the existing scheme of manually starting and stopping the public auxiliary equipment, this scheme will not cause production accidents due to the staff forgetting to start and stop the public auxiliary equipment, thereby improving reliability.
[0007] In combination with the technical solution provided in the first aspect above, in some possible implementations, determining whether a workshop needs to use public auxiliary equipment within a preset time period from the current moment includes: obtaining all production tasks in the workshop within the preset time period from the current moment; obtaining the standard operating procedures associated with each production task, the standard operating procedures including process steps and process conditions for each process step; and determining whether the workshop needs public auxiliary equipment to assist in achieving the process conditions based on the process conditions.
[0008] In the embodiment of the present application, since the process steps of the standard operating procedure correspond to process conditions, it is possible to determine whether each production task requires the use of public auxiliary equipment based on the process conditions. This determination method is based on the standard operating procedure, so it is possible to accurately determine whether each production task requires the use of public auxiliary equipment, thereby improving the accuracy of the present solution.
[0009] In combination with the technical solution provided in the first aspect above, in some possible implementations, the total demand load of the workshop for the public and auxiliary equipment is determined, including: for each production task within a preset time period, based on the process conditions included in the standard operating procedure associated with the production task, determining the demand load of the production task for the public and auxiliary equipment; based on all determined demand loads, obtaining the total demand load.
[0010] In the embodiment of the present application, since different production tasks may have different demand loads on public auxiliary equipment, the demand load corresponding to each production task is determined by process conditions, so that the demand load of each production task obtained is more accurate, and thus the total demand load obtained in the end is more accurate.
[0011] In combination with the technical solution provided in the first aspect above, in some possible implementations, the process steps also include the start time of the execution conditions, starting the public and auxiliary equipment that matches the start quantity, including: determining the earliest start time of all process steps that require the public and auxiliary equipment as the target start time; taking the target start time as the base point, starting the public and auxiliary equipment that matches the start quantity a specified time in advance; wherein the specified time is the time required for the public and auxiliary equipment to go from startup to stable operation.
[0012] In the embodiment of the present application, since it takes a certain amount of time for the public auxiliary equipment to start up and run stably, if the starting time of the process conditions can be known through the process steps, the public auxiliary equipment can be started in advance, so that when the production task requires the assistance of the public auxiliary equipment, the public auxiliary equipment is in a stable operation state, so that the process conditions can be stably met. This prevents the public auxiliary equipment from being unstable in operation at the initial startup stage, resulting in the inability to provide stable assistance for the production task, causing the process conditions to be unsatisfied and the production task to fail.
[0013] In combination with the technical solution provided in the first aspect above, in some possible implementations, if there is a process step that also includes specifying public and auxiliary equipment, starting the public and auxiliary equipment that matches the startup quantity includes: starting the public and auxiliary equipment that includes the specified public and auxiliary equipment and matches the startup quantity.
[0014] In combination with the technical solution provided in the first aspect above, in some possible implementations, the process steps also include the start-up time and the shutdown time of the public and auxiliary equipment, and the method also includes: obtaining the standard operating procedure associated with each production task in the workshop within the next preset time period; based on the standard operating procedure corresponding to the preset time period and the standard operating procedure corresponding to the next preset time period, determining the time difference between the shutdown time of the public and auxiliary equipment within the preset time period and the start-up time of the public and auxiliary equipment within the next preset time period; if the time difference is less than the preset time difference threshold, the public and auxiliary equipment is not shut down at the shutdown time within the preset time period; if the time difference is greater than or equal to the preset time difference threshold, the public and auxiliary equipment is shut down at the shutdown time within the preset time period.
[0015] In the embodiment of the present application, the more frequently the public auxiliary equipment is turned on and off, the shorter the life of the public auxiliary equipment. Therefore, if the time difference between the two times is less than the preset time difference threshold, the public auxiliary equipment will not be turned off. Otherwise, the public auxiliary equipment will be turned off to balance the life of the public auxiliary equipment and the energy consumption.
[0016] In combination with the technical solution provided in the first aspect above, in some possible implementations, determining whether a workshop needs to use public auxiliary equipment within a preset time period from the current moment includes: determining whether a request to start instruction is received from the automated production equipment in the workshop within the preset time period from the current moment; wherein, receipt of the request to start instruction indicates that the workshop needs to use the public auxiliary equipment, and failure to receive the request to start instruction indicates that the workshop does not need to use the public auxiliary equipment; accordingly, determining the total demand load of the workshop for the public auxiliary equipment includes: parsing the request to start instruction to obtain the total demand load.
[0017] In the embodiment of the present application, by judging whether the automated production equipment sends a request to start instruction, it is determined whether the workshop needs to use the public auxiliary equipment. Therefore, it is easier and more convenient to determine whether the workshop needs to use the public auxiliary equipment and the total demand load of the public auxiliary equipment.
[0018] In combination with the technical solution provided in the first aspect above, in some possible implementations, when the public auxiliary equipment is environmental public auxiliary equipment, determining whether the workshop needs to use the public auxiliary equipment within a preset time period starting from the current moment includes: obtaining all production tasks in the workshop within the preset time period starting from the current moment; and determining whether the production task needs to use the public auxiliary equipment for each product type produced by the production task.
[0019] In the embodiment of the present application, since the production process of different products requires different environments, and the production process environment is usually provided by public auxiliary equipment, therefore, the type of product produced by the production task can be used to know what type of public auxiliary equipment is needed for the production task, so as to determine whether the production task needs to use public auxiliary equipment.
[0020] In combination with the technical solution provided in the first aspect above, in some possible implementations, the number of public auxiliary equipment that needs to be started is determined based on the total demand load, including: if the total demand load corresponding to the public auxiliary equipment is greater than the total load of all the public auxiliary equipment, some production tasks in the workshop will be postponed so that the total demand load of the public auxiliary equipment for the production tasks that are not postponed is less than or equal to the total load.
[0021] In the embodiment of the present application, if the total demand load corresponding to the public auxiliary equipment is greater than the total load of all public auxiliary equipment, it means that the public auxiliary equipment cannot bear all the production tasks of the current workshop. Therefore, it is necessary to postpone the execution of some production tasks to prevent the failure of production tasks due to insufficient capacity of public auxiliary equipment.
[0022] In combination with the technical solution provided in the first aspect above, in some possible implementations, the method further includes: if all production tasks in the workshop are completed within the preset time period, shutting down all the public and auxiliary equipment.
[0023] In an embodiment of the present application, when it is determined that all production in the workshop has been completed within a preset time period, it indicates that the public auxiliary equipment does not need to be kept turned on. Therefore, all public auxiliary equipment is directly turned off to prevent energy waste caused by idle public auxiliary equipment.
[0024] In the second aspect, the present application provides a method for controlling public auxiliary equipment, which is applied to the control equipment of production equipment, and the method includes: obtaining the process steps to be executed; determining the process conditions corresponding to the process steps to be executed based on a preset standard operating procedure; the standard operating procedure includes process steps, and process conditions for each process step; based on the process conditions, determining whether public auxiliary equipment is needed to assist in achieving the process conditions; if the public auxiliary equipment is needed, sending a request to start command to start the public auxiliary equipment.
[0025] In an embodiment of the present application, the control device determines the public and auxiliary equipment required for the production equipment to execute the process step through the process conditions corresponding to the process step, thereby accurately determining the public and auxiliary equipment required to be used, and thus there is no need to start all types of public and auxiliary equipment, thereby reducing the energy consumption of the public and auxiliary equipment.
[0026] In combination with the technical solution provided in the second aspect above, in some possible implementations, the sending of the request to start instruction includes: sending the request to start instruction to the server; the request to start instruction indicates that the public auxiliary equipment needs to be used, so that the server starts the public auxiliary equipment after receiving the request to start instruction.
[0027] In the embodiment of the present application, the public auxiliary equipment is started by the server, so that all the public auxiliary equipment can be controlled in a unified manner through the server. In addition, since multiple production equipment may need to use the same type of public auxiliary equipment in the same time period, the server receives the request to start command sent by each production equipment, which can integrate the needs of multiple production equipment to minimize the number of public auxiliary equipment started.
[0028] In combination with the technical solution provided in the second aspect above, in some possible implementations, the sending of the request to start instruction includes: sending the request to start instruction to the public auxiliary equipment; the request to start instruction indicates that the public auxiliary equipment needs to be used, so that the public auxiliary equipment starts in response to the request to start instruction.
[0029] In the embodiment of the present application, the opening and closing of the public auxiliary equipment is directly controlled by the control device, thereby reducing the steps of information transmission and improving the efficiency of information transmission.
[0030] In the third aspect, the present application provides a control device for a production equipment, comprising: a communication unit and a processor; the communication unit and the processor are electrically connected; the communication unit is used to obtain the process steps to be executed; the processor is used to determine the process conditions corresponding to the process steps to be executed based on a preset standard operating procedure; the standard operating procedure includes process steps, and process conditions for each process step; based on the process conditions, it is determined whether public and auxiliary equipment is needed to assist in achieving the process conditions; the communication unit is also used to send a request to start instruction to start the public and auxiliary equipment if the public and auxiliary equipment is needed.
[0031] In a fourth aspect, the present application provides a production execution system, comprising: a server that executes the method described in the first aspect above and / or in combination with any possible implementation scheme of the first aspect above, multiple public and auxiliary equipment, multiple production equipment, and a control device corresponding to each production equipment; the server is communicatively connected with each of the public and auxiliary equipment and each of the control equipment; each of the control equipment executes the method described in the second aspect above and / or in combination with any possible implementation scheme of the second aspect above.
[0032] In a fifth aspect, the present application provides a public auxiliary equipment control system, comprising: multiple public auxiliary equipment and a server that executes the method described in the first aspect above and / or in combination with any possible implementation method of the first aspect above, and the server is communicatively connected to each of the public auxiliary equipment.
[0033] In a sixth aspect, the present application provides a computer program product, comprising a computer program. When the computer program is executed by a processor, it implements the method described in the first aspect above and / or in combination with any possible implementation of the first aspect above, or implements the method described in the second aspect above and / or in combination with any possible implementation of the second aspect above.
[0034] In a seventh aspect, the present application provides an electronic device, comprising: a memory and a processor, the memory and the processor being connected; the memory being used to store programs; the processor being used to call the programs stored in the memory to execute the method described in the first aspect above and / or in combination with any possible implementation of the first aspect above, or to execute the method described in the second aspect above and / or in combination with any possible implementation of the second aspect above.
[0035] In an eighth aspect, the present application provides a computer-readable storage medium having a computer program stored thereon. When the computer program is executed by a computer, the computer program executes the method described in the first aspect above and / or in combination with any possible implementation of the first aspect above, or executes the method described in the second aspect above and / or in combination with any possible implementation of the second aspect above. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0037] Figure 1 A method for controlling public auxiliary equipment applied to a server is shown in an embodiment of the present application;
[0038] Figure 2 A schematic diagram of a standard operating process of multiple production lines shown in an embodiment of the present application;
[0039] Figure 3 A method for controlling public auxiliary equipment applied to a control device is shown in an embodiment of the present application;
[0040] Figure 4 A structural block diagram of a control device shown in an embodiment of the present application;
[0041] Figure 5 A structural block diagram of a production execution system shown in an embodiment of the present application;
[0042] Figure 6 This is a structural block diagram of a public auxiliary equipment control system shown in an embodiment of the present application;
[0043] Figure 7 A structural block diagram of an electronic device shown in an embodiment of the present application. DETAILED DESCRIPTION
[0044] The technical solutions in the embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application.
[0045] It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it is not necessary to further define and explain it in the subsequent drawings. At the same time, in the description of this application, relational terms such as "first", "second", etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the term "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements includes not only those elements, but also includes other elements that are not clearly listed, or also includes elements inherent to such process, method, article or equipment. In the absence of more restrictions, the elements limited by the sentence "including one..." do not exclude the existence of other identical elements in the process, method, article or equipment including the elements.
[0046] The technical solution of the present application will be described in detail below with reference to the accompanying drawings.
[0047] In order to reduce the waste of energy by existing public auxiliary units (also called public auxiliary equipment), the present application provides a public auxiliary equipment control method to reduce the waste of energy by public auxiliary units. The public auxiliary equipment control method is applied to a server. Among them, the public auxiliary equipment controlled by this scheme is equipped with an interface for remote status acquisition and remote control. So that the server can detect the status of each public auxiliary equipment and control the start and stop of the public auxiliary equipment.
[0048] Among them, it can be to add PLC hardware, WIFI module interface, Modbus communication interface, etc. to the public auxiliary equipment to enable the public auxiliary equipment to have data communication capabilities. Or enable other equipment (such as computers or control devices) to remotely obtain the status data of the public auxiliary equipment through the added interface and have the ability to control the equipment.
[0049] See also Figure 1 , Figure 1 This is a flow chart of a method for controlling a public auxiliary equipment shown in an embodiment of the present application. Figure 1 Describe the steps it involves.
[0050] S100: Determine whether the workshop needs to use public auxiliary equipment within a preset time period starting from the current moment.
[0051] The specific length of the preset time period can be set according to actual needs, and its specific length is not limited here.
[0052] Public auxiliary equipment refers to equipment or environmental equipment for achieving process conditions, such as constant temperature dehumidification equipment, vacuum equipment, cold water equipment, circulating water equipment, compressed air equipment, nitrogen production equipment, etc. Any type of public auxiliary equipment can be controlled using the public auxiliary equipment control method.
[0053] Among them, constant temperature dehumidification equipment, cold water equipment, circulating water equipment, compressed air equipment, etc. are public auxiliary equipment to achieve process conditions. Nitrogen production equipment and vacuum equipment are environmental equipment.
[0054] When there are multiple types of public auxiliary equipment at the same time, each type of public auxiliary equipment can be controlled by using the public auxiliary equipment control method.
[0055] There are several ways to determine whether a workshop needs to use public auxiliary equipment.
[0056] In the first implementation, the specific method for determining whether the workshop needs to use public auxiliary equipment within the preset time period from the current moment can be: first, all production tasks in the workshop within the preset time period from the current moment are obtained. Then, the standard operating procedures associated with each production task are obtained, and the standard operating procedures include process steps and process conditions for each process step. Then, based on the process conditions, it is determined whether the workshop needs public auxiliary equipment to assist in achieving the process conditions.
[0057] Since the process steps of the standard operating procedure correspond to process conditions, it is possible to determine whether each production task requires the use of public auxiliary equipment based on the process conditions. This determination method starts from the standard operating procedure, so it can accurately determine whether each production task requires the use of public auxiliary equipment, thereby improving the accuracy of this solution.
[0058] The process conditions include whether vacuum is required, temperature range, etc. The parameters may be setting parameters of the stirring device, such as rotation speed, stirring time, etc.
[0059] Optionally, the standard operating procedure may also include a formula for each process step. The formula is the type and quantity of materials that need to be added. The specific implementation method of the process conditions or parameters and the formula is not limited here.
[0060] Since the process conditions specify the execution environment of the process steps, and the execution environment often needs to be generated and maintained through public and auxiliary equipment, after clarifying the process conditions, it can be determined whether public and auxiliary equipment is needed.
[0061] For example, if the public auxiliary equipment is a vacuum equipment, then when the process conditions require vacuum, it indicates that the public auxiliary equipment needs to be used. The examples here are only for ease of understanding and should not be used as a limitation to this application.
[0062] The production tasks and the standard operating procedures associated with each production task can be pre-acquired and stored in a storage medium, and can be directly called when needed. Alternatively, the production tasks and the standard operating procedures associated with each production task can also be obtained from the production equipment in the workshop.
[0063] Under the second implementation mode, determining whether the workshop needs to use public auxiliary equipment within a preset time period starting from the current moment includes: first determining whether a request to start instruction is received from the automated production equipment in the workshop; wherein, receipt of the request to start instruction indicates that the workshop needs to use public auxiliary equipment, and failure to receive the request to start instruction indicates that the workshop does not need to use public auxiliary equipment.
[0064] By judging whether the automated production equipment sends a request to start command, it is determined whether the workshop needs to use the public auxiliary equipment. This makes it easier and more convenient to determine whether the workshop needs to use the public auxiliary equipment and the total demand load for the public auxiliary equipment.
[0065] Among them, the request to start the instruction also needs to include the demand load corresponding to the production equipment, so as to facilitate the subsequent determination of the total demand load of the workshop for public and auxiliary equipment.
[0066] In the third implementation mode, when the public auxiliary equipment is an environmental public auxiliary equipment, the method for determining whether the workshop needs to use the public auxiliary equipment within the preset time period from the current moment can be: first, all production tasks in the workshop within the preset time period from the current moment are obtained. Then, for the product type produced by each production task, it is determined whether the production task needs to use the public auxiliary equipment.
[0067] Among them, the production tasks have been clearly described in the previous article. For the sake of brief description, they will not be repeated here.
[0068] Since the production process of different products requires different environments, and the production process environment is usually provided by public auxiliary equipment, therefore, the type of product produced by the production task can tell what type of public auxiliary equipment is needed for the production task, and thus determine whether the production task needs to use public auxiliary equipment.
[0069] For example, if the product generated by the production task is an adhesive, it can be determined that the production process of the product requires humidity control. Therefore, it can be determined that the production task requires the use of public auxiliary equipment for controlling humidity. The examples here are only for ease of understanding and should not be used as limitations on this application.
[0070] Optionally, a correspondence table between product types and public auxiliary equipment types can be pre-stored. When it is necessary to determine whether a production task requires the use of public auxiliary equipment, the type of product produced by the production task can be determined, and then the public auxiliary equipment corresponding to the product type can be found from the pre-stored correspondence table.
[0071] Among them, the same product type can correspond to multiple different public and auxiliary equipment.
[0072] If it is determined that the workshop does not need public auxiliary equipment, all public auxiliary equipment can be shut down.
[0073] S200: If the workshop needs to use public auxiliary equipment, determine the total demand load of the workshop for the public auxiliary equipment.
[0074] There are several ways to determine the total demand load of the workshop for public and auxiliary equipment.
[0075] In the first implementation, if the standard operating procedures associated with each production task have been obtained before, the method for determining the total demand load of the workshop for public auxiliary equipment can be: for each production task within a preset time period, based on the process conditions included in the standard operating procedures associated with the production task, determine the demand load of the production task for public auxiliary equipment. Then, based on all the determined demand loads, the total demand load is obtained.
[0076] Since different production tasks may have different demand loads on public and auxiliary equipment, the demand load corresponding to each production task is determined by process conditions, making the demand load of each production task more accurate, and thus making the final total demand load more accurate.
[0077] Optionally, in the standard operating procedure, the demand load may be pre-marked for each process condition. Based on the process conditions included in the standard operating procedure associated with the production task, the demand load for public and auxiliary equipment of the production task may be determined by directly obtaining the demand load corresponding to the process conditions from the process conditions.
[0078] Optionally, in the standard operating procedure, a demand load level may be pre-marked for each process condition. Accordingly, the method for determining the demand load of the production task for the public and auxiliary equipment based on the process conditions included in the standard operating procedure associated with the production task may be: determining the demand load of the production task for the public and auxiliary equipment based on the demand load level corresponding to the process conditions included in the standard operating procedure associated with the production task.
[0079] The number and names of the required load levels can be set according to actual needs and are not restricted here.
[0080] The demand load can be expressed in numerical values, and accordingly, the load capacity of public auxiliary equipment can also be expressed in numerical values.
[0081] Alternatively, the demand load may also be expressed in levels, and different levels of demand loads may have different load capacities required of the public auxiliary equipment. In this case, the load capacity of the public auxiliary equipment may be expressed as the number of demand loads that can be supported at each level.
[0082] The levels of demand load may be divided according to actual demand, and the specific division method is not limited here.
[0083] For example, if the demand load can be divided into two levels, low load and high load, the load capacity of the public auxiliary equipment can be expressed as follows: the first public auxiliary equipment can support two high loads at the same time, or support five low loads at the same time.
[0084] In the second implementation mode, if whether the workshop needs to use the auxiliary equipment within the preset period from the current moment is determined by whether the request to start command sent by the automated production equipment in the workshop is received, then the specific method of determining the total demand load of the workshop for the auxiliary equipment can be: parsing all the request to start commands received within the preset period from the current moment to obtain the total demand load.
[0085] Since the request to open instruction already includes the required load, multiple required loads can be obtained by parsing each request to open instruction.
[0086] Optionally, after parsing and obtaining the demand load corresponding to each request to start instruction, the total demand load may be obtained by summing the demand load corresponding to each request to start instruction to obtain the total demand load.
[0087] Alternatively, after parsing and obtaining the demand load corresponding to each request to start instruction, the total demand load can be obtained by summing the demand load corresponding to each request to start instruction, and adding the redundant load to the sum value to obtain the total demand load. The redundant load is used to provide redundancy for the obtained total demand load to ensure that the total demand load can meet the demand of all production tasks of the workshop for the public auxiliary equipment within the preset time period.
[0088] S300: Determine the number of public auxiliary equipment that need to be started based on the total demand load.
[0089] Among them, the startup quantity is the minimum quantity that satisfies the requirement that the total load of public auxiliary equipment started is greater than or equal to the total demand load.
[0090] In one implementation, if the required load is expressed as a numerical value, the total required load and the load capacity of the public auxiliary equipment are both expressed as numerical values. Then, to determine the number of public auxiliary equipment that needs to be started, it is only necessary to make the sum of the loads of multiple public auxiliary equipment greater than the total required load, and the sum of the number of public auxiliary equipment is the starting number.
[0091] For example, if the total required load is 33, and the load capacity of each public auxiliary device is 5, then it can be determined that the number of public auxiliary devices required to be started is 7. The examples here are only for ease of understanding and should not be used as a limitation to this application.
[0092] In one implementation, since the load capacities of different public auxiliary devices may be different, in this case, based on the total required load, the specific method for determining the number of public auxiliary devices to be started may be: first, the load capacity of each public auxiliary device is obtained. Then, multiple public auxiliary devices whose sum of load capacities is greater than or equal to the total required load and whose difference with the total required load is the smallest are determined as the public auxiliary devices to be started, and the number of public auxiliary devices to be started is the starting number.
[0093] For example, if the total required load is 33, and the load capacity of public auxiliary equipment 1 is 10, the load capacity of public auxiliary equipment 2 is 8, the load capacity of public auxiliary equipment 3 is 15, and the load capacity of public auxiliary equipment 4 is 9. Since the sum of the load capacities of public auxiliary equipment 1, public auxiliary equipment 2, and public auxiliary equipment 3 is 33, which is equal to the total required load, the startup quantity is determined to be 3. And the public auxiliary equipment to be started is public auxiliary equipment 1, public auxiliary equipment 2, and public auxiliary equipment 3. The examples here are only for ease of understanding and should not be used as limitations on this application.
[0094] In one implementation mode, if the total demand load corresponding to the public auxiliary equipment is greater than the total load of all public auxiliary equipment, some production tasks in the workshop are postponed so that the total demand load of the public auxiliary equipment for the production tasks that are not postponed is less than or equal to the total load.
[0095] If the total demand load corresponding to the public auxiliary equipment is greater than the total load of all public auxiliary equipment, it means that the public auxiliary equipment cannot bear all the production tasks of the current workshop. Therefore, it is necessary to postpone the execution of some production tasks to prevent the failure of production tasks due to insufficient capacity of public auxiliary equipment.
[0096] Among them, the production tasks may be randomly selected for delayed execution. Alternatively, the production task priorities may be preset, and the production tasks with lower priorities may be delayed until the total demand load of the remaining production tasks on the public auxiliary equipment is less than or equal to the total load.
[0097] The specific duration of the delay can be set according to actual needs, for example, it can be delayed by the length of the above-mentioned preset time period. Alternatively, a delay duration can be preset, and the production task that needs to be delayed can be delayed by the delay duration. The delay duration is greater than the length of the above-mentioned preset time period.
[0098] S400: Start the public auxiliary equipment that matches the start-up quantity.
[0099] In one implementation, if the load capacity of the same type of public auxiliary equipment is the same, the public auxiliary equipment matching the start-up quantity can be randomly started from all public auxiliary equipment, or selected from high to low according to the preset public auxiliary equipment priority.
[0100] If the load capacities of the same type of public auxiliary equipment may be different, the public auxiliary equipment to be started has been confirmed in S300 (that is, the sum of the aforementioned load capacities is greater than or equal to the total required load, and the difference between the load capacities and the total required load is the smallest), then all the public auxiliary equipment to be started will be started.
[0101] In one implementation, if the standard operating procedures associated with each production task are obtained, and the process steps of the standard operating procedures also include the start time of the execution conditions, the specific method of starting the public auxiliary equipment that matches the start quantity can be: first determine the earliest start time of all process steps that require the public auxiliary equipment as the target start time. Then, based on the target start time, start the public auxiliary equipment that matches the start quantity for a specified time in advance; wherein the specified time is the time required for the public auxiliary equipment to start and run smoothly.
[0102] Since it takes a certain amount of time for the auxiliary equipment to start up and run stably, if the starting time of the process conditions can be known through the process steps, the auxiliary equipment can be started in advance, so that when the production task requires the assistance of the auxiliary equipment, the auxiliary equipment is in a stable operation state, so that the process conditions can be stably met. This prevents the instability of the auxiliary equipment in the initial startup stage, which leads to the inability to provide stable assistance for the production task, resulting in the failure of the process conditions to be met, and the failure of the production task.
[0103] The start time of the execution condition is the start time point of the time period that needs to meet the execution condition.
[0104] For example, if the vacuum environment needs to be met at 07:50, then 07:50 is the starting time of the process condition (meeting the vacuum environment). The example here is only for ease of understanding and should not be regarded as a limitation to the present application.
[0105] Among them, the implementation method of starting the public auxiliary equipment that matches the starting quantity has been clearly described in the previous article. For the sake of brief description, it will not be repeated here.
[0106] For ease of understanding, let's take the example of three process steps that require vacuum equipment. If in process step 1, the vacuum environment (process condition) needs to be met at 07:50 (start time); in process step 2, the vacuum environment (process condition) needs to be met at 07:55 (start time); in process step 3, the vacuum environment (process condition) needs to be met at 07:57 (start time), then it can be confirmed that 07:50 is the earliest start time, so the target start time is 07:50.
[0107] If the specified duration is 10 minutes (that is, it takes 10 minutes for the vacuum equipment to start and run smoothly), the vacuum equipment matching the start-up quantity needs to be started at 07:40.
[0108] The examples given here are only for ease of understanding and should not be construed as limiting the present application.
[0109] In one implementation mode, if the standard operating procedure associated with each production task is obtained, and there are process steps that also include designated public and auxiliary equipment, the specific implementation method of starting the public and auxiliary equipment that matches the start-up quantity can be: starting the public and auxiliary equipment that includes the designated public and auxiliary equipment and matches the start-up quantity.
[0110] Optionally, if the load capacities of the same type of public auxiliary equipment are the same, after determining the startup quantity, one of the public auxiliary equipment is determined as the designated public auxiliary equipment, and the remaining public auxiliary equipment is selected randomly or according to the preset public auxiliary equipment priority.
[0111] Optionally, if the load capacities of the same type of public auxiliary equipment may be different, then based on the total required load, the specific method for determining the number of public auxiliary equipment that needs to be started can be: first obtain the load capacity of each public auxiliary equipment. Then determine that the sum of the load capacities is greater than or equal to the total required load, and the multiple public auxiliary equipment including the designated public auxiliary equipment with the smallest difference from the total required load are the public auxiliary equipment to be started, and the number of public auxiliary equipment to be started is the starting number. Correspondingly, the method for starting the public auxiliary equipment that matches the starting number is: start all the public auxiliary equipment to be started.
[0112] In one implementation, if the standard operating procedures associated with each production task are obtained, and the process steps also include the start-up time and the shutdown time of the public auxiliary equipment, the standard operating procedures associated with each production task in the workshop within the next preset time period can also be obtained. Then, based on the standard operating procedures corresponding to the preset time period and the standard operating procedures corresponding to the next preset time period, the time difference between the shutdown time of the public auxiliary equipment within the preset time period and the start-up time of the public auxiliary equipment within the next preset time period is determined.
[0113] If the time difference is less than the preset time difference threshold, the public auxiliary equipment will not be shut down during the shutdown time within the preset time period.
[0114] If the time difference is greater than or equal to the preset time difference threshold, the public auxiliary equipment is turned off at the shutdown time within the preset time period.
[0115] Since the more frequent the power on and off frequency of the public auxiliary equipment, the shorter the life of the public auxiliary equipment. Therefore, if the time difference between the two times is less than the preset time difference threshold, the public auxiliary equipment will not be turned off. Otherwise, the public auxiliary equipment will be turned off to balance the life of the public auxiliary equipment and the energy consumption.
[0116] The end time point of the preset time period from the current moment is the start time point of the next preset time period.
[0117] Optionally, if there are multiple start-up times within the next time period, the earliest start-up time is determined as the final start-up time. Correspondingly, if there are multiple shutdown times within the preset time period, the latest shutdown time is determined as the final shutdown time.
[0118] In one implementation mode, if all production tasks in the workshop are completed within a preset time period, all public and auxiliary equipment are shut down.
[0119] When it is determined that all production in the workshop has been completed within the preset time period, it means that the public auxiliary equipment does not need to be turned on any longer. Therefore, all public auxiliary equipment is directly turned off to prevent energy waste caused by idle public auxiliary equipment.
[0120] In order to facilitate the understanding of the above-mentioned public auxiliary equipment control method, the following will be combined with Figure 2 Provide explanation.
[0121] Figure 2 Taking a workshop producing adhesive as an example, the auxiliary equipment in the workshop includes nitrogen equipment, vacuum equipment and dehumidification equipment. The auxiliary equipment control method described above can be used to control the nitrogen equipment, vacuum equipment and dehumidification equipment respectively.
[0122] Taking vacuum equipment as an example, since process 1 of production line 1 and production line 3 both require the use of vacuum equipment, the required load of process 1 of production line 1 and production line 3 for vacuum equipment can be determined respectively, and then the total required load of process 1 for vacuum equipment can be obtained. Then determine whether the total load of vacuum equipment can bear the total required load. If it can, determine the minimum start-up quantity that meets the total required load, and start the vacuum equipment that matches the start-up quantity.
[0123] If the total load of the vacuum equipment is less than the total required load, process 1 of production line 1 can be delayed by one process, that is, process 1 of production line 1 and process 2 of production lines 2 and 3 are executed synchronously. Correspondingly, other processes of production line 1 are also delayed by one process (or process 1 of production line 3 can be delayed by one process).
[0124] The vacuum equipment in each process is controlled according to this principle. For the sake of brief description, the control methods of the vacuum equipment in process 2, process 3, etc. are not described here in detail.
[0125] Similarly, the control principle of nitrogen equipment and dehumidification equipment is the same as that of vacuum equipment. For the sake of brief description, the control method of nitrogen equipment and dehumidification equipment will not be described here.
[0126] Based on the same technical concept, the present application also provides a method for controlling public auxiliary equipment of a control device applied to a production device, such as Figure 3 As shown, the following will be combined Figure 3 Describe the steps it involves.
[0127] The control device may be a PLC controller, a computer, a human-computer interaction device, or other device capable of controlling the stirring device. The control device may be independently provided from the stirring device or may be integrated in the stirring device.
[0128] S600: Obtain the process steps to be executed.
[0129] The process step to be executed is the next process step that needs to be executed by the production equipment.
[0130] Optionally, the process steps may be issued by a server, or may be manually imported by a staff member; or may be obtained from a pre-acquired standard operating procedure.
[0131] S700: Determine process conditions corresponding to the process steps to be executed based on a preset standard operating procedure.
[0132] The specific implementation method of the standard operating procedure has been clearly described in the previous article. For the sake of brief description, it will not be repeated here.
[0133] The standard operation process may be acquired in advance and stored in a local storage medium, and can be directly called when needed, or may be downloaded from a server in real time when needed.
[0134] S800: Determine whether auxiliary equipment is needed to assist in achieving the process conditions based on the process conditions.
[0135] The specific implementation method of determining whether public auxiliary equipment is needed to assist in achieving the process conditions based on the process conditions has been clearly described in the previous article. For the sake of brevity, it will not be repeated here.
[0136] S900: If public auxiliary equipment is needed, send a request to start command to start the public auxiliary equipment.
[0137] If the public auxiliary equipment is not needed, the request to start command will not be sent, and accordingly, the public auxiliary equipment will not be started.
[0138] In one implementation, the specific method of sending the request to start instruction may be: sending a request to start instruction to the server; the request to start instruction indicates that the public auxiliary equipment needs to be used, so that the server starts the public auxiliary equipment after receiving the request to start instruction.
[0139] The public auxiliary equipment is started through the server, so that all public auxiliary equipment can be controlled in a unified manner through the server. In addition, since multiple production equipment may need to use the same type of public auxiliary equipment in the same time period, the server receives the request to start instructions sent by each production equipment, which can integrate the needs of multiple production equipment to minimize the number of public auxiliary equipment started.
[0140] Among them, the execution operation after the server receives the request to open the instruction has been clearly described in the previous text and will not be repeated here.
[0141] In one implementation manner, the specific implementation method of sending the request to start instruction may also be: sending a request to start instruction to the public auxiliary device; the request to start instruction indicates that the public auxiliary device needs to be used, so that the public auxiliary device starts in response to the request to start instruction.
[0142] By directly controlling the opening and closing of public auxiliary equipment through control devices, the steps of information transmission can be reduced and the efficiency of information transmission can be improved.
[0143] Based on the same technical concept, the present application also provides a control device for a production device, such as Figure 4 As shown, the control device 100 includes a communication unit 110 and a processor 120. The communication unit 110 and the processor 120 are electrically connected.
[0144] The communication unit 110 may be an electronic component capable of sending and receiving information, such as a Bluetooth module, a WiFi module, etc. The processor 120 may be any circuit with signal processing capability, such as a CPU (Central Processing Unit), a NP (Network Processor), etc.; it may also be a DSP (Digital Signal Processor), an ASIC (Application Specific Integrated Circuit), an FPGA (Field Programmable Gate Array), or other programmable logic devices, discrete gates or transistor logic devices, or discrete hardware components.
[0145] The communication unit 110 is used to obtain the process steps to be executed.
[0146] The processor 120 is used to determine the process conditions corresponding to the process steps to be executed based on a preset standard operating procedure; the standard operating procedure includes process steps and process conditions for each process step.
[0147] The processor 120 is further configured to determine, based on the process conditions, whether auxiliary equipment is required to assist in achieving the process conditions.
[0148] The communication unit 110 is further configured to send a request to start command to start the public auxiliary device if the public auxiliary device is needed.
[0149] The communication unit 110 is specifically used to send the request to start instruction to the server; the request to start instruction indicates that the public auxiliary device needs to be used, so that the server starts the public auxiliary device after receiving the request to start instruction.
[0150] The communication unit 110 is specifically configured to send the request to start instruction to the public auxiliary device; the request to start instruction indicates that the public auxiliary device needs to be used, so that the public auxiliary device starts in response to the request to start instruction.
[0151] Based on the same technical concept, the present application also provides a production execution system, such as Figure 5 The production execution system 10 includes a server 200, a plurality of public auxiliary devices 300, a plurality of production devices 400, and a control device 100 corresponding to each production device 400.
[0152] The server 200 is in communication connection with each public auxiliary device 300 and each control device 100. The server and the control device respectively execute the corresponding public auxiliary device control method, and the specific execution method has been clearly described in the previous text, so it will not be repeated here for the sake of brief description.
[0153] The multiple public auxiliary equipment 300 are of the same type of public auxiliary equipment, for example, they may all be vacuum equipment, or they may all be dehumidification equipment. The examples given here are only for ease of understanding, and the implementation method of the public auxiliary equipment is not limited to the methods given here.
[0154] The production equipment 400 may be any type of production equipment, such as a mixer, batching equipment, etc., and its specific type is not limited here.
[0155] The specific implementation of the control device 100 has been clearly described in the previous text, and for the sake of brevity, it will not be repeated here.
[0156] For ease of understanding, the production execution system may execute production tasks in the following manner: the control device first obtains production tasks within a preset time period from the current moment, and obtains the standard operating procedures associated with the production tasks. Then, based on the process conditions, it is determined whether public auxiliary equipment is needed to assist in achieving the process conditions. If not, the production equipment is controlled to execute the standard operating procedures.
[0157] If necessary, a request to start command is sent to the server. After receiving the request to start command, the server parses all request to start commands received within the preset period from the current moment to obtain the total demand load. Then, based on the total demand load, the number of public auxiliary equipment that needs to be started is determined. Finally, the public auxiliary equipment that matches the start number is started. Then the control device controls the production equipment to execute the standard operating procedure.
[0158] Based on the same technical concept, the present application also provides a public auxiliary equipment control system. Figure 6 As shown, the public auxiliary equipment control system 20 includes a server 200 and a plurality of public auxiliary equipment 300. The server 200 is connected to each public auxiliary equipment 300 for communication.
[0159] The server 200 executes the aforementioned public auxiliary equipment control method applied to the server.
[0160] The specific implementation methods of the server 200 and the multiple public auxiliary devices 300 are the same as those of the server and public auxiliary devices in the aforementioned production execution system, and will not be repeated here for the sake of brief description.
[0161] Based on the same technical concept, the present application also provides a computer program product. The computer program product includes a computer program. When the computer program is executed by a processor, the above-mentioned public auxiliary equipment control method applied to a server is implemented, or the above-mentioned public auxiliary equipment control method applied to a control device is implemented.
[0162] The computer program product may be, for example, a software installation package, an electronic document, a microservice, etc., and its specific form is not limited here.
[0163] See also Figure 7 , which is an electronic device 30 provided in an embodiment of the present application. The electronic device 30 includes: a processor 210 and a memory 220.
[0164] The memory 220 and the processor 210 are electrically connected to each other directly or indirectly to realize data transmission or interaction. For example, these elements can be electrically connected to each other through one or more communication buses or signal lines. Among them, the memory 220 is used to store computer programs, such as storing the aforementioned computer program products. Among them, the computer program product may include at least one software function module that can be stored in the memory 220 in the form of software or firmware or solidified in the operating system (OS) of the electronic device 30. The processor 210 is used to execute the executable module stored in the memory 220, such as the software function module or computer program included in the computer program product. At this time, the processor 210 is used to determine whether the workshop needs to use the public auxiliary equipment within a preset time period from the current moment; if the workshop needs to use the public auxiliary equipment, determine the total demand load of the workshop for the public auxiliary equipment; based on the total demand load, determine the start-up number of the public auxiliary equipment that needs to be started; wherein the start-up number is the minimum number that satisfies the need to start the total load of the public auxiliary equipment greater than or equal to the total demand load; start the public auxiliary equipment matching the start-up number.
[0165] Alternatively, the processor 210 is used to obtain the process steps to be executed; determine the process conditions corresponding to the process steps to be executed based on a preset standard operating procedure; the standard operating procedure includes process steps, and process conditions for each process step; determine whether public auxiliary equipment is needed to assist in achieving the process conditions based on the process conditions; if the public auxiliary equipment is needed, send a request to start the public auxiliary equipment.
[0166] Among them, the memory 220 can be, but is not limited to, RAM (Random Access Memory), ROM (Read Only Memory), PROM (Programmable Read-Only Memory), EPROM (Erasable Programmable Read-Only Memory), EEPROM (Electric Erasable Programmable Read-Only Memory), etc.
[0167] The processor 210 may be an integrated circuit chip with signal processing capabilities. The above-mentioned processor may be a general-purpose processor, including a CPU, NP, etc.; it may also be a DSP, ASIC, FPGA or other programmable logic device, discrete gate or transistor logic device, discrete hardware component. The methods, steps and logic block diagrams disclosed in the embodiments of the present application may be implemented or executed. The general-purpose processor may be a microprocessor or the processor 210 may also be any conventional processor, etc.
[0168] The electronic device 30 mentioned above includes but is not limited to a personal computer, a server, etc.
[0169] The embodiment of the present application also provides a computer-readable storage medium (hereinafter referred to as storage medium), on which a computer program is stored, and when the computer program is run by a computer such as the above-mentioned electronic device 30, the two public auxiliary equipment control methods shown above are executed. The computer-readable storage medium includes: a U disk, a mobile hard disk, a read-only memory, a random access memory, a magnetic disk or an optical disk, and other media that can store program codes.
[0170] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A method for controlling public auxiliary equipment, characterized in that: Applied to a server, the method comprises: Determine whether the workshop needs to use public auxiliary equipment within the preset time period from the current moment; If the workshop needs to use the public auxiliary equipment, determine the total demand load of the workshop for the public auxiliary equipment; Based on the total required load, determine the number of startups of the public auxiliary equipment that needs to be started; wherein the startup number is the minimum number that satisfies the need to start the public auxiliary equipment so that the total load is greater than or equal to the total required load; The public auxiliary equipment matching the startup quantity is started.
2. The method according to claim 1, characterized in that Determine whether the workshop needs to use public auxiliary equipment within the preset time period from the current moment, including: Obtaining all production tasks in the workshop within a preset time period from the current moment; Obtaining a standard operating procedure associated with each production task, wherein the standard operating procedure includes process steps and process conditions of each process step; Based on the process conditions, it is determined whether the workshop needs public auxiliary equipment to assist in achieving the process conditions.
3. The method according to claim 2, characterized in that Determining the total demand load of the workshop for the public auxiliary equipment includes: For each production task within a preset time period, based on the process conditions included in the standard operating procedure associated with the production task, determine the required load of the production task on the public auxiliary equipment; Based on all determined demand loads, the total demand load is obtained.
4. The method according to claim 2, characterized in that: The process step also includes the starting time of the execution condition, starting the public auxiliary equipment matching the start quantity, including: Determine the earliest start time among all process steps requiring the public auxiliary equipment as the target start time; Taking the target start time as a base point, the public auxiliary equipment matching the start quantity is started in advance for a specified time period; wherein the specified time period is the time required for the public auxiliary equipment to run smoothly from startup.
5. The method according to claim 2, characterized in that: If there is a process step further including specifying public and auxiliary equipment, starting the public and auxiliary equipment matching the start-up quantity includes: The public auxiliary devices including the designated public auxiliary devices and matching the startup quantity are started.
6. The method according to claim 2, characterized in that The process steps also include the start-up time and the shutdown time of the public auxiliary equipment, and the method also includes: Obtaining the standard operating procedures associated with each production task in the workshop within the next preset time period; Determine the time difference between the shutdown time of the public auxiliary equipment in the preset time period and the startup time of the public auxiliary equipment in the next preset time period based on the standard operation process corresponding to the preset time period and the standard operation process corresponding to the next preset time period; If the time difference is less than a preset time difference threshold, the public auxiliary equipment is not shut down during the shutdown time within the preset time period; If the time difference is greater than or equal to the preset time difference threshold, the public auxiliary equipment is turned off at the turn-off time within the preset time period.
7. The method according to claim 1, characterized in that Determine whether the workshop needs to use public auxiliary equipment within the preset period from the current moment, including: Determine whether a request to start instruction sent by the automated production equipment in the workshop is received within a preset period from the current moment; wherein, receiving the request to start instruction indicates that the workshop needs to use the public auxiliary equipment, and not receiving the request to start instruction indicates that the workshop does not need to use the public auxiliary equipment; Accordingly, determining the total demand load of the workshop for the public auxiliary equipment includes: All the request-to-start instructions received within a preset time period from the current moment are parsed to obtain the total required load.
8. The method according to claim 1, characterized in that: When the public auxiliary equipment is an environmental public auxiliary equipment, the determining whether the workshop needs to use the public auxiliary equipment within a preset period from the current moment includes: Obtaining all production tasks in the workshop within a preset time period from the current moment; For the type of product produced by each of the production tasks, determine whether the production task requires the use of the public auxiliary equipment.
9. The method according to claim 1, characterized in that: The determining, based on the total demand load, the number of startups of the public auxiliary equipment that needs to be started includes: If the total demand load corresponding to the public auxiliary equipment is greater than the total load of all the public auxiliary equipment, some production tasks in the workshop will be postponed so that the total demand load of the public auxiliary equipment for the production tasks that are not postponed is less than or equal to the total load.
10. The method according to claim 1, characterized in that The method further comprises: If all production tasks in the workshop are completed within the preset time period, all public and auxiliary equipment are shut down.
11. A method for controlling public auxiliary equipment, characterized in that: A control device applied to a production device, the method comprising: Obtain the process steps to be executed; Determining the process conditions corresponding to the process steps to be performed based on a preset standard operating procedure; the standard operating procedure includes process steps and process conditions for each process step; Determining whether auxiliary equipment is needed to assist in achieving the process conditions based on the process conditions; If the public auxiliary equipment is needed, a request to start command is sent to start the public auxiliary equipment.
12. The method according to claim 11, characterized in that The sending of the request to start instruction includes: The request to start instruction is sent to the server; the request to start instruction indicates that the public auxiliary device needs to be used, so that the server starts the public auxiliary device after receiving the request to start instruction.
13. The method according to claim 11, characterized in that The sending of the request to start instruction includes: The request to start instruction is sent to the public auxiliary device; the request to start instruction indicates that the public auxiliary device needs to be used, so that the public auxiliary device starts in response to the request to start instruction.
14. A control device for a production device, characterized in that: include: A communication unit and a processor; the communication unit and the processor are electrically connected; The communication unit is used to obtain the process steps to be executed; The processor is used to determine the process conditions corresponding to the process steps to be executed based on a preset standard operating procedure; the standard operating procedure includes process steps and process conditions of each process step; Determining whether auxiliary equipment is needed to assist in achieving the process conditions based on the process conditions; The communication unit is further used to send a request to start instruction to start the public auxiliary device if the public auxiliary device is needed.
15. A production execution system, characterized in that: include: A server, multiple public auxiliary equipment, multiple production equipment and a control device corresponding to each production equipment that execute the method described in any one of claims 1 to 10; the server is communicatively connected with each of the public auxiliary equipment and each of the control devices; each of the control devices executes the method described in claims 11 to 13.
16. A public auxiliary equipment control system, characterized in that: include: A plurality of public auxiliary devices and a server for executing the method described in any one of claims 1 to 10, wherein the server is communicatively connected with each of the public auxiliary devices.
17. A computer program product, characterized in that The computer program product comprises a computer program, and when the computer program is executed by a processor, the method according to any one of claims 1 to 10 is implemented, or the method according to any one of claims 11 to 13 is implemented.
18. An electronic device, characterized in that: include: A memory and a processor, wherein the memory and the processor are connected; The memory is used to store programs; The processor is used to call the program stored in the memory to execute the method according to any one of claims 1-10, or to execute the method according to any one of claims 11-13.
19. A computer-readable storage medium, characterized in that: A computer program is stored thereon, and when the computer program is executed by a computer, the method according to any one of claims 1 to 10 is executed, or the method according to any one of claims 11 to 13 is executed.
Citation Information
Patent Citations
Monitoring analysis and energy-saving method for main and auxiliary linkage equipment
CN108256767A
Equipment remote control method and system based on wireless terminal
CN111258287A
Method and device for managing and controlling energy consumption equipment in production workshop
CN117519029A
Control method and device of air compression equipment and computer readable storage medium
CN118622670A
Air compressor control method and air compressor control system
JP2013194628A