Water conservancy and hydropower construction drainage structure and method
By designing the drainage structure of multi-layer filtering and cleaning components in water conservancy and hydropower construction, the problem of easy blockage of the filter net is solved, efficient drainage and impurity treatment are achieved, and construction efficiency is improved.
Patent Information
- Application Number
- CN202411374942.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-24
AI Technical Summary
During the actual use of the existing water conservancy and hydropower construction drainage structure, the filter mesh structure is easily blocked by debris, resulting in low drainage efficiency.
A drainage structure including transport frame, large flow drainage pump, sewage container, filter box, pump head and other components is designed. Multi-layer filtration is carried out through the primary filter, crushing roller and fine filter, combining the blower and rotation Motors ensure that impurities in the water are effectively filtered and cleaned, prevent clogging, and set up cleaning components to facilitate impurities handling.
It realizes rapid drainage, prevents impurities from entering the pump body and blocking it, improves drainage efficiency, and ensures the efficiency of construction work through the recycled filter components.
Smart Images

Figure CN119177708A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of water conservancy and hydropower engineering, and specifically relates to a water conservancy and hydropower construction drainage structure and method. Background Art
[0002] During the construction of water conservancy and hydropower, foundation pit excavation is carried out. The foundation pit is an earth pit excavated at the foundation design location according to the base elevation and foundation plane dimensions. Before excavation, the excavation plan should be determined based on geological and hydrological data and the conditions of nearby buildings on site, and waterproofing and drainage work should be done well.
[0003] Before carrying out water conservancy and hydropower construction in the operation area, the accumulated water at the operation site needs to be drained to avoid hindering the workers during construction and to reduce safety hazards. However, there are usually a large amount of impurities in the accumulated water at the operation site, which poses a great challenge to the drainage equipment.
[0004] In order to ensure drainage efficiency, it is usually necessary to filter the pumping pipes to prevent impurities from being transmitted to the pump and causing blockage. Although the existing water conservancy and hydropower construction drainage structure can filter the drainage pipeline through a fine filter structure to prevent impurities from clogging the pipes and pump bodies, in actual use, the filter structure is easily clogged by debris. In order to ensure drainage efficiency, the drainage filter structure needs to be cleaned frequently. Summary of the invention
[0005] The purpose of the present invention is to address the problem of low drainage efficiency caused by the filter structure of the existing water conservancy and hydropower construction drainage structure being easily blocked by debris during actual use. A water conservancy and hydropower construction drainage structure and method are proposed, which can quickly drain the accumulated water in the water conservancy and hydropower construction area, and can filter impurities in the water to prevent them from being introduced into the drainage pump body and causing blockage. A cleaning component is provided to facilitate cleaning of intercepted impurities, and a plurality of recyclable drainage filter components are provided, which can be recycled, thereby ensuring the working efficiency of the water conservancy and hydropower construction drainage work.
[0006] In order to solve the above technical problems, the present invention provides a drainage structure and method for water conservancy and hydropower construction, including: a transport frame, a large-flow drainage pump, a sewage collecting box, a filter box, and a pumping head. The large-flow drainage pump is fixedly installed on the top of the transport frame, the transport frame is fixedly installed with a load-bearing bracket, the sewage collecting box is placed in the load-bearing bracket, the sewage collecting box is fixedly connected with a sewage valve, the transport frame is fixedly installed with a support frame, the support frame is fixedly connected to the filter box, the filter box is fixedly installed with a rotating motor, the driving end of the rotating motor is fixedly connected with a filter cartridge, the filter cartridge is evenly opened with filter holes, the inner wall of the filter hole is fixedly installed with a fine filter screen, and the filter box is fixedly installed with a blowing air filter. The blower is fixedly connected with a blow hopper, the filter box is fixedly connected with a connecting pipe, the connecting pipe is fixedly connected with a sewage collecting box, the large-flow drainage pump is fixedly connected with a drainage pipe and a water pumping pipe, the water pumping pipe is fixedly connected with the filter box, the filter box is fixedly connected with a connecting pipe, the connecting pipe is fixedly connected with a water pumping head, the inner wall of the water pumping head is provided with a conveying chamber and a sealing chamber, the conveying chamber is rotatably connected with a crushing roller, two crushing rollers are provided, the two crushing rollers are fixedly installed with transmission gears, the transmission gears on both sides are meshed and connected, the sealing chamber is fixedly installed with a rotating motor, the driving end of the rotating motor is fixedly connected with the crushing roller, and the water pumping head is fixedly installed with a primary filter screen; The method of use includes the following steps: S1: Move the high-flow drainage pump to the drainage area through the transport frame, select a connecting pipe of appropriate length to connect with the pumping head according to the depth of the water source, and put the pumping head into the water to start the high-flow drainage pump for drainage operation; S2: The water outside the pumping head is pumped into the conveying chamber of the pumping head through the primary filter. The primary filter can preliminarily filter the impurities in the water to prevent large-volume debris from entering. The rotating motor is started to rotate the crushing roller. The transmission gears of the two crushing rollers are meshed and connected, so that the crushing rollers on both sides can rotate in the conveying chamber to crush the impurities in the water, thereby performing preliminary treatment when the water is pumped in, thereby ensuring smooth drainage; S3: Water is transported to the filter box through the connecting pipe, and then to the pumping pipe through the filter holes of the filter cartridge. The fine filter in the filter holes can filter the impurities in the water for a second time, thereby preventing the impurities in the water from entering the large-flow drainage pump and causing blockage. The large-flow drainage pump can discharge the extracted water through the drainage pipe, thereby meeting the drainage needs and facilitating subsequent construction. S4: When the filter cartridge in the filter box filters water, the rotating motor is started to rotate the filter cartridge at a constant speed, so that the filter holes in the filter cartridge corresponding to the connecting pipe and the water pumping pipe can be recycled, and impurities can be collected in the filter holes under the filtering effect of the fine filter mesh. When the filter cartridge rotates, it can drive the impurities in the filter holes to move until they are connected with the connecting pipe. The air blower can blow air to the filter holes through the air blowing hopper, so that the impurities in the filter holes can be quickly introduced into the sewage collecting box for collection under the action of gravity and wind force, and the sewage discharge valve can be opened to discharge them uniformly for treatment.
[0007] Based on the above technical solution, the present invention can also be improved as follows.
[0008] Preferably, the sealed cavity is provided with a rotating hole corresponding to the crushing roller, and the inner wall of the rotating hole is rotatably connected to the crushing roller via a sealed bearing, so that the crushing roller can rotate more stably in the sealed cavity to crush the passing materials.
[0009] Preferably, the primary filter is configured as an arc-shaped structure, which has a larger contact area with the water body, making water source pumping smoother.
[0010] Preferably, the upper and lower sides of the filter cartridge are tightly fitted with the inner wall of the filter box and are rotatably connected to the filter box, so that the filter cartridge can stably rotate in the filter box.
[0011] Preferably, the filter holes are evenly opened in a ring shape at the filter cartridge, and the filter holes can be changed for filtering by rotating the filter cartridge in the filter box.
[0012] Preferably, the dirt collecting box is fixedly connected to an exhaust pipe so that the sucked gas can be discharged quickly.
[0013] Preferably, the transmission gear is placed in a sealed cavity to prevent it from being damaged by water erosion and to increase its service life.
[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. In this scheme, the water outside the pumping head is pumped into the conveying cavity of the pumping head through the primary filter. The primary filter can initially filter the impurities in the water to prevent large-volume debris from entering.
[0015] 2. This solution starts the rotary motor to rotate the crushing rollers, and the crushing rollers on both sides can rotate in the conveying chamber to crush the impurities in the water, so as to perform preliminary treatment when the water is pumped in, thereby ensuring smooth drainage.
[0016] 3. In this scheme, the water is transported to the filter box through the connecting pipe, and the water passes through the filter holes of the filter cartridge to the pumping pipe. The fine filter in the filter holes can perform secondary fine filtration on impurities in the water, thereby preventing impurities in the water from being transmitted into the large-flow drainage pump and causing blockage.
[0017] 4. The large-flow drainage pump of this scheme can discharge the extracted water through the drainage pipe, thus meeting the drainage needs and facilitating subsequent construction.
[0018] 5. This solution starts the rotating motor to rotate the filter cartridge at a constant speed when filtering water in the filter cartridge in the filter box, so that the filter holes in the filter cartridge corresponding to the connecting pipe and the water pumping pipe can be recycled, and impurities can be collected in the filter holes under the filtering action of the fine filter mesh, so that the impurities in the extracted water source can be filtered without affecting the pump body.
[0019] 6. The filter cartridge of this scheme can drive the impurities in the filter holes to move when rotating until it is connected with the connecting pipe. The air blower can blow air to the filter holes through the air blowing hopper, so that the impurities in the filter holes can be quickly introduced into the sewage collection box for collection under the action of gravity and wind force. The sewage valve can be opened to discharge them uniformly for treatment. Such a fine filtering structure can finely filter the impurities in the water, and can circulate and discharge the filtered impurities to prevent them from clogging the drainage pipe.
[0020] 7. This solution is equipped with a cleaning component to facilitate the cleaning of intercepted impurities. It is equipped with multiple recyclable drainage filter components that can be recycled to ensure the filtering effect without affecting the flow efficiency, thereby ensuring the work efficiency of water conservancy and hydropower construction drainage work. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings. The drawings are only for the purpose of illustrating preferred embodiments and are not to be considered as limiting the present invention. Also, the same reference symbols are used throughout the drawings to represent the same parts.
[0022] Figure 1 A front view of a water conservancy and hydropower construction drainage structure provided by one embodiment of the present invention; Figure 2 A schematic diagram of the structure of a filter box provided in one embodiment of the present invention; Figure 3 A schematic structural diagram of a water pumping head provided in one embodiment of the present invention; Figure 4 A schematic diagram of the structure of a pumping head provided by an embodiment of the present invention from a top view angle; Figure 5 A schematic structural diagram of a filter cartridge provided in one embodiment of the present invention.
[0023] In the accompanying drawings, the components represented by the reference numerals are listed as follows: 1. Transport frame; 2. Large flow drainage pump; 3. Load-bearing bracket; 4. Sewage collecting box; 5. Exhaust pipe; 6. Drain valve; 7. Support frame; 8. Filter box; 9. Rotating motor; 10. Filter cartridge; 11. Filter hole; 12. Fine filter; 13. Blowing fan; 14. Blowing bucket; 15. Connecting pipe; 16. Drain pipe; 17. Pumping pipe; 18. Connecting pipe; 19. Pumping head; 20. Conveying chamber; 21. Sealing chamber; 22. Crushing roller; 23. Transmission gear; 24. Rotating motor; 25. Primary filter. DETAILED DESCRIPTION
[0024] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the present invention is described in detail as a preferred embodiment in conjunction with the accompanying drawings and embodiments. It should be understood that the specific implementation method described herein is only an optimal embodiment of the present invention, which is only used to explain the present invention and does not limit the scope of protection of the present invention. All other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0025] Example 1: Figure 1-5 As shown, the present invention provides a drainage structure and method for water conservancy and hydropower construction, including a transport frame 1, a large-flow drainage pump 2, a sewage collecting box 4, a filter box 8, and a pumping head 19. The large-flow drainage pump 2 is fixedly installed on the top of the transport frame 1, the transport frame 1 is fixedly installed with a load-bearing bracket 3, the sewage collecting box 4 is placed in the load-bearing bracket 3, the sewage collecting box 4 is fixedly connected with a sewage valve 6, the transport frame 1 is fixedly installed with a support frame 7, the support frame 7 is fixedly connected to the filter box 8, the filter box 8 is fixedly installed with a rotating motor 9, the driving end of the rotating motor 9 is fixedly connected with a filter cartridge 10, the filter cartridge 10 is evenly opened with filter holes 11, the inner wall of the filter hole 11 is fixedly installed with a fine filter screen 12, the filter box 8 is fixedly installed with an air blower 13, and the air blower 13 is fixedly installed It is connected with an air blowing hopper 14, the filter box 8 is fixedly connected with a connecting pipe 15, the connecting pipe 15 is fixedly connected with the sewage collecting box 4, the large-flow drainage pump 2 is fixedly connected with a drainage pipe 16 and a water pumping pipe 17, the water pumping pipe 17 is fixedly connected with the filter box 8, the filter box 8 is fixedly connected with a connecting pipe 18, the connecting pipe 18 is fixedly connected with a pumping head 19, the inner wall of the pumping head 19 is provided with a conveying chamber 20 and a sealing chamber 21, the conveying chamber 20 is rotatably connected with a crushing roller 22, two crushing rollers 22 are provided, both crushing rollers 22 are fixedly installed with transmission gears 23, and the transmission gears 23 on both sides are meshed and connected, the sealing chamber 21 is fixedly installed with a rotating motor 24, the driving end of the rotating motor 24 is fixedly connected with the crushing roller 22, and the pumping head 19 is fixedly installed with a primary filter screen 25.
[0026] Among them, the filter cartridge of the present scheme can drive the impurities in the filter holes to move when it rotates until it is connected with the connecting pipe. The air blower can blow air to the filter holes through the air blowing funnel, so that the impurities in the filter holes can be quickly introduced into the sewage collecting box for collection under the action of gravity and wind force, and the impurities can be discharged uniformly for treatment by opening the sewage valve. Such a fine filtering structure can finely filter the impurities in the water, and can circulate and discharge the filtered impurities to prevent them from clogging the drainage pipe.
[0027] This embodiment is also provided with a cleaning component to facilitate the cleaning of intercepted impurities, and a plurality of recyclable drainage filter components are provided, which can be recycled to ensure the filtering effect without affecting the flow efficiency, thereby ensuring the working efficiency of drainage work in water conservancy and hydropower construction. Among them, the cleaning component includes components such as a filter cartridge.
[0028] In this embodiment, the water outside the pumping head is pumped into the conveying cavity of the pumping head through the primary filter screen, and the primary filter screen can perform preliminary filtering on impurities in the water to prevent large-volume debris from entering.
[0029] Preferably, a rotating hole is opened in the sealed cavity 21 corresponding to the crushing roller 22, and the inner wall of the rotating hole is rotatably connected to the crushing roller 22 through a sealed bearing, so that the crushing roller can rotate more stably in the sealed cavity to crush the passing materials.
[0030] In this embodiment, the pulverizing rollers are rotated by starting the rotary motor. The pulverizing rollers on both sides can rotate in the conveying chamber to pulverize impurities in the water, thereby performing preliminary treatment when the water is pumped in, thereby ensuring smooth drainage.
[0031] Preferably, the primary filter 25 is configured as an arc-shaped structure, which has a larger contact area with the water body, making water source pumping smoother.
[0032] Preferably, the upper and lower sides of the filter cartridge 10 are tightly fitted with the inner wall of the filter box 8 and are rotatably connected to the filter box 8, so that the filter cartridge can stably rotate in the filter box.
[0033] Preferably, the filter holes 11 are evenly opened in a ring shape at the filter cartridge 10, and the filter holes can be changed for filtering work by rotating the filter cartridge in the filter box.
[0034] The water in this embodiment is transported to the filter box through the connecting pipe, and the water is transmitted to the pumping pipe through the filter holes of the filter cartridge. The fine filter mesh in the filter holes can perform secondary fine filtration on impurities in the water, thereby preventing impurities in the water from being transmitted into the large-flow drainage pump and causing blockage. At the same time, this solution starts the rotating motor to rotate the filter cartridge at a constant speed when the filter cartridge in the filter box filters the water, so that the filter holes in the filter cartridge corresponding to the connecting pipe and the pumping pipe can be recycled, and impurities can be collected in the filter holes under the filtering action of the fine filter mesh, so that the impurities in the extracted water source can be filtered without affecting the pump body.
[0035] Preferably, the dirt collecting box 4 is fixedly connected with an exhaust pipe 5 so that the sucked gas can be discharged quickly.
[0036] Preferably, the transmission gear 23 is placed in the sealing cavity 21 to prevent it from being damaged by water erosion and to increase its service life.
[0037] The specific working principle and use method of the present invention are: S1: Move the high-flow drainage pump 2 to the drainage area through the transport frame 1, select a connecting pipe 18 of appropriate length to connect with the pumping head 19 according to the depth of the water source, and put the pumping head 19 into the water to start the high-flow drainage pump 2 for drainage operation; S2: Water outside the pumping head 19 is pumped into the conveying chamber 20 of the pumping head 19 through the primary filter 25. The primary filter 25 can preliminarily filter impurities in the water to prevent large-volume debris from entering. The rotating motor 24 is started to rotate the crushing roller 22. The transmission gears 23 of the two crushing rollers 22 are meshed and connected, so that the crushing rollers 22 on both sides can rotate in the conveying chamber 20 to crush the impurities passing through the water, thereby performing preliminary processing when the water is pumped in, thereby ensuring smooth drainage; S3: Water is transported to the filter box 8 through the connecting pipe 18, and the water passes through the filter hole 11 of the filter cartridge 10 to the water pump 17. The fine filter 12 in the filter hole 11 can perform secondary fine filtration on impurities in the water, thereby preventing impurities in the water from entering the large-flow drainage pump 2 and causing blockage. The large-flow drainage pump 2 can discharge the extracted water through the drainage pipe 16, thereby meeting the drainage demand and facilitating subsequent construction; S4: When the filter cartridge 10 in the filter box 8 filters water, start the rotating motor 9 to rotate the filter cartridge 10 at a constant speed, so that the filter holes 11 in the filter cartridge 10 corresponding to the connecting pipe 18 and the water suction pipe 17 can be recycled, and impurities can be collected in the filter holes 11 under the filtering action of the fine filter mesh 12. When the filter cartridge 10 rotates, it can drive the impurities in the filter holes 11 to move until it is connected with the connecting pipe 15. The air blower 13 can blow air to the filter holes 11 through the air blowing hopper 14, so that the impurities in the filter holes 11 can be quickly introduced into the sewage collecting box 4 for collection under the action of gravity and wind force, and the sewage valve 6 can be opened to discharge them uniformly for treatment.
[0038] The above specific embodiments are preferred embodiments of the present invention, and are not intended to limit the specific implementation scope of the present invention. The scope of the present invention includes but is not limited to the present specific embodiments. All equivalent changes made in accordance with the shape, structure, and method of the present invention are within the protection scope of the present invention.
Claims
1. A drainage structure for water conservancy and hydropower construction, characterized in that: The invention comprises a transport frame (1), a large-flow drainage pump (2), a sewage collecting box (4), a filter box (8), and a pumping head (19), wherein the large-flow drainage pump (2) is fixedly mounted on the top of the transport frame (1), the transport frame (1) is fixedly mounted with a load-bearing bracket (3), the sewage collecting box (4) is placed in the load-bearing bracket (3), the sewage collecting box (4) is fixedly connected to a sewage discharge valve (6), the transport frame (1) is fixedly mounted with a support frame (7), the support frame (7) is fixedly connected to the filter box (8), the filter box (8) is fixedly mounted with a rotating motor (9), the driving end of the rotating motor (9) is fixedly connected to a filter cartridge (10), the filter cartridge (10) is evenly provided with filter holes (11), the inner wall of the filter hole (11) is fixedly mounted with a fine filter screen (12), the filter box (8) is fixedly mounted with an air blower (13), the air blower (13) is fixedly connected to an air blow hopper (14), the filter box (8) is fixedly connected with a connecting pipe (15), the connecting pipe (15) is fixedly connected with the sewage collecting box (4), the large flow drainage pump (2) is fixedly connected with a drainage pipe (16) and a water pumping pipe (17), the water pumping pipe (17) is fixedly connected with the filter box (8), the filter box (8) is fixedly connected with a connecting pipe (18), the connecting pipe (18) is fixedly connected with a water pumping head (19), the inner wall of the water pumping head (19) is provided with a conveying chamber (20) and a sealing chamber (21), the conveying chamber (20) is rotatably connected with a crushing roller (22), two crushing rollers (22) are provided, the two crushing rollers (22) are fixedly installed with a transmission gear (23), the transmission gears (23) on both sides are meshed and connected, the sealing chamber (21) is fixedly installed with a rotating motor (24), the driving end of the rotating motor (24) is fixedly connected with the crushing roller (22), and the water pumping head (19) is fixedly installed with a primary filter (25).
2. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The sealed cavity (21) is provided with a rotation hole corresponding to the crushing roller (22), and the inner wall of the rotation hole is rotationally connected to the crushing roller (22) via a sealed bearing.
3. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The primary filter screen (25) is configured as an arc-shaped structure.
4. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The upper and lower sides of the filter cartridge (10) are tightly fitted to the inner wall of the filter box (8) and are rotatably connected to the filter box (8).
5. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The filter holes (11) are evenly arranged in a ring shape on the filter cylinder (10).
6. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The dirt collecting box (4) is fixedly connected to an exhaust pipe (5).
7. A water conservancy and hydropower construction drainage structure according to claim 1, characterized in that: The transmission gear (23) is placed in the sealed cavity (21).
8. A water conservancy and hydropower construction drainage method, applicable to a water conservancy and hydropower construction drainage structure as claimed in claim 1, characterized in that: The steps include: S1: Move the large-flow drainage pump (2) to the drainage area by means of a transport frame (1), select a connecting pipe (18) of suitable length according to the depth of the water source to connect it with the pumping head (19), and place the pumping head (19) into the water to allow the large-flow drainage pump (2) to perform drainage operations; S2: Water outside the pumping head (19) is pumped into the conveying chamber (20) of the pumping head (19) through the primary filter (25). The primary filter (25) performs preliminary filtering on impurities in the water to prevent large-volume debris from entering. The rotating motor (24) is started to rotate the crushing roller (22). The transmission gears (23) of the two crushing rollers (22) are meshed and connected, so that the crushing rollers (22) on both sides rotate in the conveying chamber (20) to crush the impurities passing through the water, thereby performing preliminary processing when the water is pumped in, thereby ensuring smooth drainage; S3: Water is transported to the filter box (8) through the connecting pipe (18), and the water passes through the filter holes (11) of the filter cartridge (10) and is transmitted to the water extraction pipe (17). The fine filter mesh (12) in the filter holes (11) performs secondary fine filtration on impurities in the water, thereby preventing the impurities in the water from being transmitted into the large-flow drainage pump (2) and causing blockage. The large-flow drainage pump (2) discharges the extracted water through the drainage pipe (16), thereby meeting the drainage demand and facilitating subsequent construction. S4: When the filter cartridge (10) in the filter box (8) filters water, the rotating motor (9) is started to rotate the filter cartridge (10) at a constant speed, so that the filter holes (11) in the filter cartridge (10) corresponding to the connecting pipe (18) and the water pumping pipe (17) are circulated, and impurities are collected in the filter holes (11) under the filtering action of the fine filter mesh (12). When the filter cartridge (10) rotates, the impurities in the filter holes (11) are driven to move until they are connected to the connecting pipe (15), and the air blower (13) blows air to the filter holes (11) through the air blowing hopper (14), so that the impurities in the filter holes (11) are quickly introduced into the sewage collecting box (4) under the action of gravity and wind force for collection, and the sewage discharge valve (6) is opened to discharge them uniformly for treatment.