High-rise building steel structure corridor and construction method thereof

By designing a steel structure corridor of high-rise buildings with drive components and articulated seats, the safety hazards and the problem of height adjustment in the existing technology are solved, convenient installation and height adjustment are achieved, and installation difficulty is reduced and support Recycle.

CN119177713AInactive Publication Date: 2024-12-24CHINA MCC17 GRP CO LTD

Patent Information

Application Number
CN202411580226.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-07
Publication Date
2024-12-24
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing high-rise building corridor installation method requires tower crane lifting and manual transportation, which poses safety hazards, cannot adjust the height and cannot be recycled.

Method used

A steel structure corridor of high-rise building including fixed plates, lifting tracks, drive components and articulated seats is designed. The lifting shell is driven up and down through the drive motor, and the winding components and fixed components are combined to achieve convenient installation and height adjustment.

Benefits of technology

It realizes convenient transportation and height adjustment, reduces installation difficulty and safety risks, and supports flexible installation and recycling of corridors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119177713A_ABST
    Figure CN119177713A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of corridors, and discloses a high-rise building steel structure corridor which comprises a fixing plate and two lifting shells symmetrically distributed front and back, lifting rails symmetrically distributed front and back are fixedly connected to the bottom of the fixing plate, and tooth blocks vertically distributed at equal intervals are arranged in the lifting rails. Driving assemblies which extend to the opposite sides of the lifting shells and are matched with the tooth blocks are arranged in the lifting shells. The high-rise building steel structure corridor has the advantages of being convenient to transport, install, adjust the height and the like, and solves the problems that according to a current common corridor installation mode, hoisting outside a building is needed through a tower crane, materials need to be manually transported in the building as a main body, the material transporting mode is troublesome, potential safety hazards can be caused in the manual transporting process, and the construction efficiency is high. The height of the corridor cannot be freely adjusted, and the corridor cannot be recycled after being used.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of corridors, in particular to a steel structure corridor of a high-rise building. Background Art

[0002] With the development of urban construction, the design requirements for building functions and appearance are becoming higher and higher. In the structure of high-rise buildings, in order to connect two high-rise buildings together, it is usually necessary to build a corridor between the two high-rise buildings to facilitate the connection between the two high-rise buildings.

[0003] At present, most common corridor installation methods require lifting outside the building through a tower crane and manually transporting materials inside the building. This material transportation method is not only troublesome, but also causes safety hazards during manual transportation. In addition, common corridors cannot adjust their height freely and cannot be recycled after use. Therefore, a high-rise building steel structure corridor is proposed to solve the above problems. Summary of the invention

[0004] 1. Technical issues to be resolved

[0005] In view of the deficiencies in the prior art, the present invention provides a steel structure corridor for a high-rise building and a construction method thereof, which has the advantages of being easy to transport, install and adjust the height, and solves the problem that the current common corridor installation method mostly requires lifting the materials outside the building by a tower crane and manually transporting the materials inside the building. This material transportation method is not only troublesome, but also creates safety hazards during the manual transportation process. In addition, the common corridor cannot freely adjust the height and cannot be recycled after use.

[0006] (II) Technical solution

[0007] The technical solution of the present invention to solve the above technical problems is as follows: A high-rise building steel structure corridor, comprising a fixed plate and two lifting shells symmetrically distributed front and back, the bottom of the fixed plate is fixedly connected with a lifting track symmetrically distributed front and back, the interior of the lifting track is provided with tooth blocks distributed vertically equidistantly, the interior of the lifting shell is provided with a driving assembly extending to the opposite side thereof and adapted to the tooth block, the interior of the lifting shell is provided with a transmission assembly connected to the driving assembly, the back side of the lifting shell is provided with a pulley adapted to the lifting track, the opposite side of the lifting shell is fixedly connected with a driving shell, the interior of the driving shell is fixedly connected with a driving motor connected to an adjacent driving assembly, the right side of the lifting shell is fixedly connected with an articulated seat, the opposite side of the articulated seat is articulated with the same gallery plate, the top of the gallery plate is provided with a fixed assembly, the right side of the lifting shell is fixedly connected with the same winding shell, the interior of the winding shell is provided with a winding assembly connected to the fixed assembly, the right side of the gallery plate is fixedly connected with a stable steel frame, and the bottom of the stable steel frame is fixedly connected with a connecting steel plate adapted to the lifting shell.

[0008] A high-rise building steel structure corridor and a construction method thereof, comprising the following steps:

[0009] Step 1: Install the drive assembly into the lifting track to connect the lifting track with the lifting shell;

[0010] Step 2: Install the installed lifting rail on the outside of the building through the fixing plate, and continue to splice the lifting rail upwards until it reaches the appropriate height;

[0011] Step 3: Use two drive motors to drive the drive components on both sides to rotate synchronously, driving the lifting shell to move up and down;

[0012] Step 4: When the lifting shell reaches the appropriate position, the gallery plate is rotated around the hinge seat through the cooperation of the winding assembly and the fixing assembly until the connecting steel plate fits the lifting track, and then connected to complete the installation.

[0013] The beneficial effects of the present invention are:

[0014] 1) During use, first install the drive assembly into the lifting track, then connect the lifting track with the lifting shell, and then install the installed lifting track on the outside of the building through the fixed plate, and then continue to splice the lifting track upward until it reaches a suitable height, and then drive the drive assemblies on both sides to rotate synchronously through two drive motors, and then make multiple drive assemblies rotate synchronously through the transmission assembly, so that with the cooperation of the gear block, the lifting shell can be driven up and down to a suitable position, which has the advantages of easy transportation and height adjustment.

[0015] 2) When the lifting shell reaches the appropriate position, the gallery plate can be rotated around the hinge seat by simply cooperating with the winding component and the fixing component until the connecting steel plate fits the lifting track, and then they are connected to complete the installation, which has the advantage of easy installation.

[0016] Based on the above technical solution, the present invention can also be improved as follows.

[0017] Furthermore, the driving assembly includes a driving shaft, a driving gear and a driving gear. The interior of the lifting shell is rotatably connected to a driving shaft extending to the opposite side thereof, the opposite side of the driving shaft is fixedly connected to a driving gear meshing with a gear block, one end of the driving shaft located inside the lifting shell is fixedly connected to the driving gear, and the output end of the driving motor is fixedly connected to the adjacent driving shaft.

[0018] The beneficial effect of adopting the above further solution is that the driving shaft connected to the driving motor can be driven to rotate, thereby causing the driving gear to rotate.

[0019] Furthermore, the transmission assembly includes a transmission shaft and a transmission gear. The interior of the lifting shell is fixedly connected with a transmission shaft located between the driving shafts, and the outer surface of the transmission shaft is fixedly connected with a transmission gear meshing with an adjacent driving gear.

[0020] The beneficial effect of adopting the above further solution is that the driving gear can drive the transmission gear meshing with it to rotate, so that another driving gear meshing with the transmission gear rotates synchronously with the previous driving gear.

[0021] Furthermore, the fixing assembly includes a fixing shaft and a connecting block, the interior of the gallery plate is fixedly connected with the fixing shaft, and the outer surface of the fixing shaft is rotatably connected with the connecting blocks symmetrically distributed front and back;

[0022] Furthermore, the winding assembly includes a winding dual-axis motor, a winding wheel and a steel cable. The interior of the winding shell is fixedly connected to the winding dual-axis motor, the output ends of the winding dual-axis motor are fixedly connected to the winding wheel, and the outer surfaces of the winding wheels are fixedly connected to the steel cables fixedly connected to the adjacent connecting blocks.

[0023] The beneficial effect of adopting the above further scheme is that by driving the winding wheel to rotate through the output end of the winding double-axis motor, the steel cable can be moved to the outside of the winding shell, so that the connecting block has movement space, thereby allowing the corridor board to rotate around the hinge seat.

[0024] Furthermore, the lifting rails can be spliced ​​with each other, and the left sides of the lifting rails are fixedly connected with support frames.

[0025] The beneficial effect of adopting the above further solution is that the connection strength of the lifting rail can be strengthened by the support frame.

[0026] Furthermore, the right side of the gallery plate is provided with mounting holes distributed in a rectangular array.

[0027] The beneficial effect of adopting the above further solution is that the guardrail of the corridor can be installed through the installation holes. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 This is a schematic diagram of the lifting track of the present invention;

[0029] Figure 2 This is a schematic diagram of the lifting shell of the present invention;

[0030] Figure 3 It is a right side view of the gallery board of the present invention;

[0031] Figure 4 This is a left side view of the gallery board of the present invention;

[0032] Figure 5 It is a left side cross-sectional view of the drive assembly of the present invention;

[0033] Figure 6 It is a left side cross-sectional view of the winding assembly of the present invention;

[0034] Figure 7 This is a connection diagram between the lifting track and the driving assembly of the present invention.

[0035] In the figure: 1. fixed plate; 2. lifting track; 21. gear block; 3. support frame; 4. lifting shell; 5. driving assembly; 51. driving shaft; 52. driving gear; 53. driving gear; 6. transmission assembly; 61. transmission shaft; 62. transmission gear; 7. pulley; 8. driving shell; 9. driving motor; 10. hinge seat; 11. gallery plate; 111. mounting hole; 12. fixing assembly; 121. fixing shaft; 122. connecting block; 13. winding shell; 14. winding assembly; 141. winding double-axis motor; 142. winding wheel; 143. steel cable; 15. stabilizing steel frame; 16. connecting steel plate. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] Embodiment 1, by Figure 1-7A steel structure corridor of a high-rise building is provided. The present invention comprises a fixed plate 1 and two lifting shells 4 which are symmetrically distributed front and back. The bottom of the fixed plate 1 is fixedly connected with a lifting track 2 which is symmetrically distributed front and back. The interior of the lifting track 2 is provided with tooth blocks 21 which are distributed vertically at equal distances. The interior of the lifting shell 4 is provided with a driving assembly 5 which extends to the opposite side thereof and is adapted to the tooth blocks 21. The interior of the lifting shell 4 is provided with a transmission assembly 6 which is transmission-connected to the driving assembly 5. The back side of the lifting shell 4 is provided with a pulley 7 which is adapted to the lifting track 2. The opposite side of the lifting shell 4 is fixed. A driving shell 8 is connected, and a driving motor 9 connected to an adjacent driving assembly 5 is fixedly connected inside the driving shell 8. A hinge seat 10 is fixedly connected to the right side of the lifting shell 4. The opposite side of the hinge seat 10 is hinged with the same gallery plate 11. A fixing assembly 12 is provided on the top of the gallery plate 11. A same winding shell 13 is fixedly connected to the right side of the lifting shell 4. A winding assembly 14 connected to the fixing assembly 12 is provided inside the winding shell 13. A stabilizing steel frame 15 is fixedly connected to the right side of the gallery plate 11. A connecting steel plate 16 adapted to the lifting shell 4 is fixedly connected to the bottom of the stabilizing steel frame 15.

[0038] The driving assembly 5 includes a driving shaft 51, a driving gear 52 and a driving gear 53. The interior of the lifting shell 4 is rotatably connected to the driving shaft 51 extending to the opposite side thereof. The opposite side of the driving shaft 51 is fixedly connected to the driving gear 52 meshing with the gear block 21. One end of the driving shaft 51 located inside the lifting shell 4 is fixedly connected to the driving gear 53. The output end of the driving motor 9 is fixedly connected to the adjacent driving shaft 51.

[0039] The driving motor 9 can drive the driving shaft 51 connected thereto to rotate, thereby causing the driving gear 52 to rotate;

[0040] The transmission assembly 6 includes a transmission shaft 61 and a transmission gear 62. The interior of the lifting shell 4 is fixedly connected with the transmission shaft 61 located between the driving shafts 51, and the outer surface of the transmission shaft 61 is fixedly connected with the transmission gear 62 meshing with the adjacent driving gear 53;

[0041] The driving gear 52 can drive the transmission gear 62 meshing with it to rotate, so that another driving gear 52 meshing with the transmission gear 62 can rotate synchronously with the previous driving gear 52 .

[0042] Embodiment 2, based on embodiment 1, the fixing assembly 12 comprises a fixing shaft 121 and a connecting block 122, the fixing shaft 121 is fixedly connected inside the gallery plate 11, and the outer surface of the fixing shaft 121 is rotatably connected to the connecting blocks 122 which are symmetrically distributed front and back;

[0043] The winding assembly 14 includes a winding double-axis motor 141, a winding wheel 142 and a steel cable 143. The winding double-axis motor 141 is fixedly connected to the interior of the winding shell 13, and the output ends of the winding double-axis motor 141 are fixedly connected to the winding wheel 142. The outer surface of the winding wheel 142 is fixedly connected to the steel cable 143 fixedly connected to the adjacent connecting block 122.

[0044] The output end of the winding double-axis motor 141 drives the winding wheel 142 to rotate, so that the steel cable 143 can move to the outside of the winding shell 13, so that the connecting block 122 has a movement space, so that the gallery board 11 rotates around the hinge seat 10;

[0045] The lifting rails 2 can be connected to each other, and the left side of the lifting rails 2 is fixedly connected with a support frame 3;

[0046] The connection strength of the lifting track 2 can be enhanced by the support frame 3;

[0047] The right side of the gallery plate 11 is provided with mounting holes 111 distributed in a rectangular array;

[0048] The guardrail of the corridor can be installed through the installation hole 111.

[0049] Working principle:

[0050] The first step to implement the innovation point:

[0051] Step 1: First, install the driving assembly 5 inside the lifting track 2, and then connect the lifting track 2 with the lifting shell 4;

[0052] Step 2: Install the installed lifting rail 2 on the outside of the building through the fixing plate 1, and then continue to splice the lifting rail 2 upward until it reaches a suitable height;

[0053] Step 3: Finally, the two driving motors 9 drive the driving components 5 on both sides to rotate synchronously, so that the multiple driving components 5 can rotate synchronously through the transmission component 6, so that with the cooperation of the gear block 21, the lifting shell 4 can be driven to move up and down until it reaches a suitable position.

[0054] The second innovation point implementation steps:

[0055] Step 1: When the lifting shell 4 reaches a suitable position, the output end of the winding dual-axis motor 141 drives the winding wheel 142 to rotate, so that the steel cable 143 moves to the outside of the winding shell 13;

[0056] Step 2: so that the connecting block 122 has room to move, so that the gallery board 11 rotates around the hinge seat 10;

[0057] Step 3: Finally, make the connecting steel plate 16 fit with the lifting rail 2 and then connect them.

Claims

1. A steel structure corridor of a high-rise building, comprising a fixed plate (1) and two lifting shells (4) symmetrically distributed front and back, characterized in that: The bottom of the fixed plate (1) is fixedly connected to a lifting track (2) which is symmetrically distributed in the front and back directions; the lifting track (2) is provided with tooth blocks (21) which are distributed at equal distances in the vertical direction; the lifting shell (4) is provided with a driving assembly (5) which extends to the opposite side thereof and is adapted to the tooth block (21); the lifting shell (4) is provided with a transmission assembly (6) which is transmission-connected to the driving assembly (5); the lifting shell (4) is provided with a pulley (7) which is adapted to the lifting track (2) on the opposite side thereof; the lifting shell (4) is fixedly connected to a driving shell (8) on the opposite side thereof; the driving shell (8) is fixedly connected to a pulley (7) which is adapted to the lifting track (2) on the opposite side thereof; The driving motor (9) is connected to the driving assembly (5); the right side of the lifting shell (4) is fixedly connected to a hinge seat (10); the opposite side of the hinge seat (10) is hinged to the same gallery plate (11); the top of the gallery plate (11) is provided with a fixing assembly (12); the right side of the lifting shell (4) is fixedly connected to the same winding shell (13); the interior of the winding shell (13) is provided with a winding assembly (14) connected to the fixing assembly (12); the right side of the gallery plate (11) is fixedly connected to a stabilizing steel frame (15); the bottom of the stabilizing steel frame (15) is fixedly connected to a connecting steel plate (16) adapted to the lifting shell (4).

2. The high-rise building steel structure corridor according to claim 1, characterized in that: The driving assembly (5) comprises a driving shaft (51), a driving gear (52) and a driving gear (53); the interior of the lifting shell (4) is rotatably connected to a driving shaft (51) extending to the opposite side thereof; the opposite side of the driving shaft (51) is fixedly connected to a driving gear (52) meshing with a gear block (21); one end of the driving shaft (51) located inside the lifting shell (4) is fixedly connected to the driving gear (53); and the output end of the driving motor (9) is fixedly connected to the adjacent driving shaft (51).

3. The high-rise building steel structure corridor according to claim 2, characterized in that: The transmission assembly (6) comprises a transmission shaft (61) and a transmission gear (62); the interior of the lifting shell (4) is fixedly connected to the transmission shaft (61) located between the drive shafts (51); the outer surface of the transmission shaft (61) is fixedly connected to the transmission gear (62) meshing with the adjacent driving gear (53).

4. The high-rise building steel structure corridor according to claim 1, characterized in that: The fixing assembly (12) comprises a fixing shaft (121) and a connecting block (122); the interior of the gallery plate (11) is fixedly connected to the fixing shaft (121); the outer surface of the fixing shaft (121) is rotatably connected to the connecting blocks (122) which are symmetrically distributed frontward and rearward.

5. The high-rise building steel structure corridor according to claim 4, characterized in that: The winding assembly (14) comprises a winding double-axis motor (141), a winding wheel (142) and a steel cable (143); the interior of the winding shell (13) is fixedly connected to the winding double-axis motor (141); the output ends of the winding double-axis motor (141) are fixedly connected to the winding wheel (142); and the outer surfaces of the winding wheels (142) are fixedly connected to the steel cables (143) fixedly connected to the adjacent connecting blocks (122).

6. The high-rise building steel structure corridor according to claim 1, characterized in that: The lifting rails (2) can be spliced ​​with each other, and the left sides of the lifting rails (2) are fixedly connected with support frames (3).

7. The high-rise building steel structure corridor according to claim 1, characterized in that: The right side of the gallery plate (11) is provided with mounting holes (111) distributed in a rectangular array.

8. A construction method for a steel structure corridor of a high-rise building according to any one of claims 1 to 7, characterized in that: The steps include: Step 1: Install the driving assembly (5) inside the lifting track (2) to connect the lifting track (2) with the lifting shell (4); Step 2: Install the installed lifting rail (2) on the outside of the building through the fixing plate (1), and continue to splice the lifting rail (2) upwards until it reaches a suitable height; Step 3: The two drive motors (9) are used to drive the drive components (5) on both sides to rotate synchronously, thereby causing the multiple drive components (5) to rotate synchronously through the transmission component (6), thereby driving the lifting shell (4) to move up and down with the cooperation of the gear block (21); Step 4: When the lifting shell (4) reaches the appropriate position, the output end of the winding double-axis motor (141) drives the winding wheel (142) to rotate, so that the steel cable (143) can move to the outside of the winding shell (13), and through the cooperation of the winding component (14) and the fixing component (12), the corridor board (11) rotates around the hinge seat (10) until the connecting steel plate (16) fits with the lifting track (2), and then connects them to complete the installation.

Citation Information

Patent Citations

  • Steel structure elevator shaft splicing device and method

    CN109279480A

  • Installation method for multistory steel frame connecting corridor between staggered towers

    CN110528678A

  • Emergency disposal equipment and use method thereof for integral lifting aerial corridor between ultra-high group towers

    CN111764498A

  • Multi-layer aerial steel corridor hoisting device and hoisting method thereof