Job ticket approval method and device, storage medium and electronic equipment

By introducing an operation ticket approval system in chemical enterprises, and determining the approval nodes based on the type, time period and voltage value of the operation ticket, the problem of complex and low efficiency of the power outage or power transmission approval process is solved, and the approval efficiency and safety are improved.

CN119180614APending Publication Date: 2024-12-24DONGTU TECH (YICHANG) CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411352064.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-26
Publication Date
2024-12-24

AI Technical Summary

Technical Problem

During the power outage or power transmission process of chemical enterprises, the approval process is complex, inefficient, and lack of supervision, resulting in safety hazards.

Method used

When the job ticket submission request is triggered, the approval process that matches the job ticket type is started, and the approval node is determined based on the power outage time period and voltage value is determined. The job ticket is submitted to the corresponding approver for approval, and a high-voltage safety approver is added to ensure safety operate.

Benefits of technology

The approval efficiency of the power outage process has been improved, ensuring that the approval process meets the actual needs of the site, and the safety management of high-voltage operations has been enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119180614A_ABST
    Figure CN119180614A_ABST
Patent Text Reader

Abstract

The invention relates to a job ticket approval method and device, a storage medium and electronic equipment. The method comprises the following steps: when a job ticket submission request is triggered, starting an approval program matched with a job ticket type of a job ticket; determining an approver of the approval node in the approval program according to the power-off and power-on time period and the power-off and power-on voltage value in the work ticket; and submitting the work ticket to an approver for approval. The technical problems of complex approval process and low efficiency in the power failure or power transmission process are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of job ticket approval, and in particular to a job ticket approval method, device, storage medium and electronic device. Background Art

[0002] During the electricity use process, for chemical enterprises, if power outages or power supply after a power outage is required, they cannot be shut down or supplied immediately due to the impact of chemical operations. Instead, they should check that the chemical work is correct before shutting down or supplying power to avoid sudden power outages or power supply affecting chemical operations and causing safety hazards.

[0003] In this process, the approval of power outage or power supply is usually passed on by word of mouth, such as staff confirming with managers, managers confirming with on-site personnel, or confirming through telephone, instant messaging software, etc. After confirmation and inspection, power outage or power supply is carried out. This method makes the approval process of power outage or power supply complicated, lacks supervision, and is inefficient. Summary of the invention

[0004] The present application provides a method, device, storage medium and electronic device for approving a work ticket to solve the technical problems of complex approval process and low efficiency during power outage or power supply.

[0005] In a first aspect, the present application provides a method for approving a work ticket, comprising: when a work ticket submission request is triggered, starting an approval procedure that matches the work ticket type of the work ticket; determining the approver of the approval node in the approval procedure based on the power outage time period and the power outage voltage value in the work ticket; and submitting the work ticket to the approver for approval.

[0006] In the second aspect, the present application provides an approval device for a work ticket, comprising: a starting module, which is used to start the approval procedure that matches the work ticket type of the work ticket when a work ticket submission request is triggered; a determination module, which is used to determine the approver of the approval node in the approval procedure based on the power outage time period and the power outage voltage value in the work ticket; and a submission module, which is used to submit the work ticket to the approver for approval.

[0007] As an optional example, the startup module includes: a startup unit, which is used to obtain the power supply address in the job ticket when the job ticket type is a power supply type; query the historical power outage data of the power supply address, and start the power supply approval process when the historical power outage data indicates that the power supply address is in a power outage state; and end the approval procedure when the historical power outage data indicates that the power supply address is in a power supply state.

[0008] As an optional example, the device also includes: a search module, which is used to traverse the labels of the work ticket when the work ticket is an electronic ticket before determining the approver of the approval node in the approval procedure based on the power outage time period and the power outage voltage value in the work ticket, wherein the work ticket has preset labels added at the positions of the power outage time period and the power outage voltage value; determine the time period after the traversed time label as the power outage time period, and determine the numerical value after the traversed voltage label as the power outage voltage value.

[0009] As an optional example, the determination module includes: a first determination unit, used to determine a technician as the approver of the approval procedure when the power outage time period is a working time period; and to determine a duty personnel as the approver of the approval procedure when the power outage time period is a rest time period.

[0010] As an optional example, the determination module includes: a second determination unit, used to determine that the electrical technician is the approver in the approval procedure when the power outage voltage value is a high voltage; when the power outage voltage value is a low voltage, the approval procedure flows to the next approval node.

[0011] As an optional example, the determination module includes: a third determination unit, used to determine the first approver in the approval procedure based on the power outage time period, and to determine the second approver in the approval procedure based on the power outage voltage value, wherein the second approver is used to perform high-voltage safety operation approval, and in the approval procedure, the approval of the first approver precedes the approval of the second approver.

[0012] As an optional example, the device also includes: a power outage module, which is used to transfer the approval procedure to a third approver after the work ticket is submitted to the approval user for approval and after the second approver approves it, wherein the third approver is used to approve and confirm the power outage measures.

[0013] In a third aspect, the present application provides an electronic device comprising: at least one communication interface; at least one bus connected to the at least one communication interface; at least one processor connected to the at least one bus; and at least one memory connected to the at least one bus, wherein the memory stores a computer program, and the processor is configured to implement any one of the above-mentioned job ticket approval methods when executing the computer program.

[0014] In a fourth aspect, the present application further provides a computer storage medium storing computer executable instructions, wherein the computer executable instructions are used to execute any of the above-mentioned job ticket approval methods of the present application.

[0015] The above technical solution provided by the embodiment of the present application has the following advantages compared with the prior art: this embodiment starts the approval procedure matching the work ticket type of the work ticket when triggering the work ticket submission request; determines the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the work ticket; submits the work ticket to the approver for approval, so that when approving the power outage or power supply, the work ticket is used as the power outage or power supply content for approval, and the approver is determined by the power outage time period and the power outage voltage value, and the approver is distinguished according to the power outage time period in the work ticket, which meets the actual work scene requirements on site; adds a high-voltage safety approver according to the high and low voltage conditions in the work ticket to determine the high-voltage safety operation. The effect of improving the approval efficiency of the power outage process is achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.

[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0018] One or more embodiments are exemplarily described by pictures in the corresponding drawings, and these exemplified descriptions do not constitute limitations on the embodiments. Elements with the same reference numerals in the drawings represent similar elements, and unless otherwise stated, the figures in the drawings do not constitute proportional limitations.

[0019] Figure 1 A flowchart of a method for approving a job ticket provided in an embodiment of the present application;

[0020] Figure 2 A power outage flow chart of a method for approving a work ticket provided in an embodiment of the present application;

[0021] Figure 3 A power outage flow chart of another method for approving a work ticket provided in an embodiment of the present application;

[0022] Figure 4 A power flow chart of a method for approving a work ticket provided in an embodiment of the present application;

[0023] Figure 5 A schematic diagram of the structure of a work ticket approval device provided in an embodiment of the present application;

[0024] Figure 6A schematic diagram of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0026] The disclosure below provides many different embodiments or examples to implement different structures of the present invention. In order to simplify the disclosure of the present invention, the parts and settings of specific examples are described below. Of course, they are only examples, and the purpose is not to limit the present invention. In addition, the present invention can repeat reference numbers and / or letters in different examples. This repetition is for the purpose of simplification and clarity, and does not itself indicate the relationship between the various embodiments and / or settings discussed.

[0027] In order to solve the technical problems of complex approval process and low efficiency in the power outage or power supply process in the prior art, the present application provides an approval method for a work ticket, which can improve the approval efficiency of the power outage or power supply process.

[0028] Figure 1 A flowchart of a method for approving a work ticket provided in an embodiment of the present application. Figure 1 As shown, the approval methods for the above work tickets include:

[0029] S102, when a job ticket submission request is triggered, starting an approval procedure that matches the job ticket type of the job ticket;

[0030] S104, determining the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket;

[0031] S106, submitting the work ticket to the approver for approval.

[0032] This application can be applied in chemical plant areas. When safety production is carried out in chemical plant areas, if it involves power outages or power supply, due to the instability of chemical materials, the power outage and power supply time must be planned in advance so that the power outage and power supply matters can be carried out within a controllable range.

[0033] In this embodiment, the above-mentioned "work ticket" is an authorization ticket that clarifies the on-site construction content, checks the operation risks, and implements safety measures. It is also the first checkpoint for on-site construction work safety management. The essence of the work ticket is a paper or electronic application form, which states the time, location, and content of the application. The work ticket in this embodiment is an electronic version, which states the time, scope, measures, and remarks of the power outage (power outage or power supply).

[0034] Any authorized employee can initiate a work ticket submission request. In the request, an electronic version of the work ticket must be included. The electronic version can specify the power outage or power supply to be applied for, the time period for the power outage or power supply, the area of ​​the power outage or power supply, the initiator and other information.

[0035] The work ticket type in this embodiment can be used to indicate whether the work ticket is a work ticket for applying for power outage or a work ticket for applying for power supply. The work ticket type can be declared in the data area of ​​the work ticket, such as including a selection / fill-in item for power outage or power supply in the work ticket.

[0036] Different approval procedures can be started according to different types of work tickets. Different approval procedures may involve different approvers. For example, approval procedure 1 may correspond to a group of people, from which approvers are selected. Approval procedure 2 may correspond to another group of people, from which approvers are selected. Different approval procedures may also correspond to different approval methods, approval deadlines, etc. The approval method can be electronic approval, whether a stamp is required, whether it needs to be converted to paper and signed, etc. The approval deadline can be set differently according to different approval processes. For example, a certain node requires approval within one day, a certain node requires approval within one hour, and so on.

[0037] In this embodiment, the work ticket submission request carries the work ticket, and the work ticket records the power outage time period or the power outage voltage. The power outage in this embodiment refers to the situation of power outage or power supply. The power outage time period is the time period of the applied power outage or power supply, and the power outage voltage value is the voltage before the power outage or the voltage of the power supply.

[0038] According to the power outage time period and the power outage voltage value, the approval user in the approval procedure is determined. The approval user involved in the approval procedure is determined from a group of people who match the job ticket type. After the approval user is determined, the job ticket is submitted to the first approver among the approval users, and multiple approval users approve in series or in parallel according to the approval process.

[0039] For example, in a chemical plant, an employee who has applied for a power outage initiates a power outage request. The power outage request includes an electronic copy of a work ticket, which records the initiator, the power outage time period, the power outage area, and a mark indicating that the request is a power outage operation, and then submits the request. Based on the request, the system determines that it is a power outage. Therefore, from among the multiple people responsible for the power outage, the system determines the approving user based on the power outage time period and the power outage voltage value in the work ticket, and sends the work ticket to the first user among the approving users. Figure 2 As shown, when a power outage request is initiated, an approval user is selected from the power outage staff, and then the job ticket is sent to the first user in the approval process for approval.

[0040] This embodiment starts the approval procedure that matches the work ticket type of the work ticket when triggering the work ticket submission request; determines the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the work ticket; submits the work ticket to the approver for approval, so that when approving power outage or power supply, the work ticket is used as the power outage or power supply content for approval, and the approver is determined by the power outage time period and the power outage voltage value, and the approver is distinguished according to the power outage time period in the work ticket, which meets the actual work scene requirements on site; according to the high and low voltage conditions in the work ticket, a high-voltage safety approver is added to determine the high-voltage safety operation. The effect of improving the approval efficiency of the power outage process is achieved.

[0041] As an optional example, when a job ticket submission request is triggered, initiating an approval procedure that matches the job ticket type of the job ticket includes: when the job ticket type is a power supply type, obtaining the power supply address in the job ticket; querying the historical power outage data of the power supply address, and when the historical power outage data indicates that the power supply address is in a power outage state, initiating the power supply approval process; when the historical power outage data indicates that the power supply address is in a power supply state, ending the approval procedure.

[0042] In this embodiment, when the operation ticket type is a power outage type, it means that the power is currently in a supply state and a power outage operation is required. At this time, a power outage application is initiated by initiating an operation ticket to start the power outage approval process. If the received operation ticket type is a power supply type, it is necessary to determine whether the current state is a power outage or a power supply state. If it is a power outage state, an approval process for power supply can be initiated. If it is a power supply state, there is no need to repeatedly initiate the power supply process, and only the process can be stopped.

[0043] Continuing with the example of the chemical plant area above, an employee who has applied for a power outage initiates a power outage request. The power outage request includes an electronic copy of the work ticket, which records the initiator, the power outage time period, the power outage area, and the information that the request is a power outage operation, and then submits the request. Upon receiving the request, the power outage approval process is initiated to perform the power outage operation. If an employee who has applied for power supply initiates a power supply request, the power supply request includes an electronic copy of the work ticket, which records the initiator, the power supply time period, the power supply area, and the information that the request is a power supply operation, and then submits the request. Upon receiving the request, first check whether the current state is a power outage state. If it is a power outage state, then power supply approval is performed. If it is not a power outage state, no approval is performed, the process is terminated, and a prompt message is fed back to the user who initiated the power supply request.

[0044] As an optional example, before determining the approver of the approval node in the approval procedure based on the power outage time period and the power outage voltage value in the work ticket, the method also includes: when the work ticket is an electronic ticket, traversing the labels of the work ticket, wherein the work ticket has preset labels added at the positions of the power outage time period and the power outage voltage value; determining the time period after the traversed time label as the power outage time period, and determining the numerical value after the traversed voltage label as the power outage voltage value.

[0045] In this embodiment, the power outage operation ticket and the power supply operation ticket have their own templates. The operation ticket includes operation items or virtual buttons for filling in or selecting the power outage time period and the power outage voltage value. When processing the electronic ticket, the user can fill in the power outage time period and the power outage voltage value. The system pre-sets labels in the power outage time period and the power outage voltage value area of ​​the template. After obtaining the electronic component, the data of the place marked by the label is obtained according to the label, thereby obtaining the power outage time period and the power outage voltage value.

[0046] As an optional example, determining the approver of the approval node in the approval procedure based on the power outage time period includes: when the power outage time period is a working time period, determining the technician as the approver of the approval procedure; when the power outage time period is a rest time period, determining the on-duty personnel as the approver of the approval procedure.

[0047] The above-mentioned working time period and rest time period can be different time periods in a day, or different time intervals, for example, the working time period is Monday to Friday, the rest time period is Saturday and Sunday, the working time period is daytime, and the rest time period is evening, etc.

[0048] In this embodiment, different approval personnel are determined as approval users in the approval process according to different power outage time periods. If it is a power outage matter, and the time period is a working time period, such as daytime, a technical staff member is determined from multiple people related to the power outage as the first approval user in the approval process, responsible for approving the location, progress, whether the machine needs to be stopped, and other information of the chemical products during the power outage. If it is at night, the night duty staff is determined from multiple people related to the power outage as the first approval user in the approval process. Different personnel are selected as the first approval user in the approval process according to different time periods.

[0049] As an optional example, determining the approver of the approval node in the approval procedure based on the power outage voltage value includes: when the power outage voltage value is a high voltage, determining the electrician as the approver in the approval procedure; when the power outage voltage value is a low voltage, the approval procedure flows to the next approval node.

[0050] In this embodiment, after the first approval user in the approval process is determined according to the power transmission time period, it can be determined whether to add an approval node according to the power transmission voltage value. If the voltage value indicates that the voltage is high, then a node can be added after the first approval personnel, and the node can be an electrical worker, which is used to approve the impact of power outages and power transmission that may be caused by high voltage. If the power transmission voltage is low, there is no need to add electrical workers, and the approval process automatically transfers to the next approval node.

[0051] As an optional example, determining the approver of the approval node in the approval procedure based on the power outage time period and the power outage voltage value in the work ticket includes: determining the first approver in the approval procedure based on the power outage time period, and determining the second approver in the approval procedure based on the power outage voltage value, wherein the second approver is used to perform high-voltage safety operation approval, and in the approval procedure, the approval of the first approver precedes the approval of the second approver.

[0052] Continue to explain with the above example. At the first approval node, the first approver is determined to be a technician or a duty officer based on the power outage time period. At the second approval node, whether to add an electrical technician approver is determined based on whether the voltage is high or low. If the voltage value indicates that the voltage is low, there is no need to add the approver. That is, after the first approver, go directly to the power outage and power supply nodes, and the personnel at the corresponding nodes directly perform the power outage and power supply operations.

[0053] As an optional example, after submitting the work ticket to the approving user for approval, the method further includes: after the second approver approves, the approval procedure flows to a third approver, wherein the third approver is used to approve and confirm the power outage measures.

[0054] In this embodiment, after approval, the power outage and power supply nodes can execute the power outage and power supply operations or approvals. The third approver here can be the final approver before the power outage and power supply, or the executor of the power outage and power supply, or the power outage and power supply results can be monitored to check whether they are executed in accordance with the power outage time period and power outage area in the above-mentioned work ticket.

[0055] Monitoring can be performed through the system. The hardware of the system has a built-in rechargeable electronic meter. When the power is cut off, the electronic meter will count the time. After the power is restored, the system will check the power outage time period by comparing the network time. The same is true for power restoration. By obtaining the network time and comparing it with the electronic meter, the power supply time period can be checked to complete the monitoring.

[0056] Figure 3 This is the power outage flowchart. Figure 4 This is a flow chart for power supply during a power outage. This embodiment specifies the process nodes of the power outage operation ticket in advance, and different time periods and high and low voltages have different operation processes to meet the actual production conditions of chemical companies. If the application time is within the day shift cycle (within the first time period), the person in charge of the node is the corresponding day shift process technician (first user); if the application time is within the night shift cycle (within the second time period), the person in charge of the node is the current on-duty leader (second user), who can flexibly approve the operation ticket in a timely manner. If there may be special safety hazards in the high voltage situation, this embodiment distinguishes between high and low voltage. If it is high voltage, an additional electrical technician approval node (third user) will be added, which is located after the first user or the second user to make a rationality judgment on the high voltage situation.

[0057] For example, after submitting a power outage application, the person who handles the subsequent nodes is determined according to the power outage application time and voltage value, and flexible and safe processing is performed. If the power outage time is during the day shift (8:30-17:30), the process node goes to the 'Process Technician: Power Outage Approval' node, and the process technician signs and confirms. If the power outage time is during the night shift (17:30-08:30), the process node goes to the 'Duty Leader: Power Outage Approval', and the duty leader signs and confirms. If it is high voltage, exceeding 400V, then after the process technician or the duty leader, it is necessary to go to the 'Electrical Technician: Power Outage Approval' node, and the electrical technician signs and confirms, providing additional safety approval work for the high voltage application. Finally, the power outage executor will cut off the power and sign and confirm.

[0058] Only when the power outage status ticket is in progress can the power supply ticket operation be applied for. When applying for power supply, the person who handles the subsequent nodes is determined according to the power supply application time and voltage value, and flexible and safe processing is performed. If the power supply time is during the day shift (8:30-17:30), the process node goes to the "Process Technician: Power Supply Approval" node, and the process technician signs and confirms. If the power supply time is during the night shift (17:30-08:30), the process node goes to the "Duty Leader: Power Outage Approval", and the duty leader signs and confirms. If it is high voltage, exceeding 400V, it is necessary to go to the "Electrical Technician: Power Outage Approval" node after the process technician or the duty leader, and the electrical technician signs and confirms, providing additional safety approval work for the high voltage application. Finally, the power supply executor supplies the power and signs and confirms. Safety supervision and execution can be carried out according to the shifts and low and high voltage nodes.

[0059] Figure 5 This is a schematic diagram of the structure of a work ticket approval device provided in an embodiment of the present application. Figure 5 As shown, the above-mentioned work ticket approval device includes:

[0060] A start module 502, for starting an approval procedure matching the job ticket type of the job ticket when a job ticket submission request is triggered;

[0061] A determination module 504, configured to determine the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket;

[0062] The submission module 506 is used to submit the work ticket to the approver for approval. This application can be applied in a chemical plant area. When safety production is carried out in a chemical plant area, if it involves power outage or power supply, due to the instability of chemical materials, the power outage and power supply time must be planned in advance, so that the power outage and power supply matters can be carried out within a controllable range.

[0063] In this embodiment, the above-mentioned "work ticket" is an authorization ticket that clarifies the on-site construction content, checks the operation risks, and implements safety measures. It is also the first checkpoint for on-site construction work safety management. The essence of the work ticket is a paper or electronic application form, which states the time, location, and content of the application. The work ticket in this embodiment is an electronic version, which states the time, scope, measures, and remarks of the power outage (power outage or power supply).

[0064] Any authorized employee can initiate a work ticket submission request. In the request, an electronic version of the work ticket must be included. The electronic version can specify the power outage or power supply to be applied for, the time period for the power outage or power supply, the area of ​​the power outage or power supply, the initiator and other information.

[0065] The work ticket type in this embodiment can be used to indicate whether the work ticket is a work ticket for applying for power outage or a work ticket for applying for power supply. The work ticket type can be declared in the data area of ​​the work ticket, such as including a selection / fill-in item for power outage or power supply in the work ticket.

[0066] Different approval procedures can be started according to different types of work tickets. Different approval procedures may involve different approvers. For example, approval procedure 1 may correspond to a group of people, from which approvers are selected. Approval procedure 2 may correspond to another group of people, from which approvers are selected. Different approval procedures may also correspond to different approval methods, approval deadlines, etc. The approval method can be electronic approval, whether a stamp is required, whether it needs to be converted to paper and signed, etc. The approval deadline can be set differently according to different approval processes. For example, a certain node requires approval within one day, a certain node requires approval within one hour, and so on.

[0067] In this embodiment, the work ticket submission request carries the work ticket, and the work ticket records the power outage time period or the power outage voltage. The power outage in this embodiment refers to the situation of power outage or power supply. The power outage time period is the time period of the applied power outage or power supply, and the power outage voltage value is the voltage before the power outage or the voltage of the power supply.

[0068] According to the power outage time period and the power outage voltage value, the approval user in the approval procedure is determined. The approval user involved in the approval procedure is determined from a group of people who match the job ticket type. After the approval user is determined, the job ticket is submitted to the first approver among the approval users, and multiple approval users approve in series or in parallel according to the approval process.

[0069] For example, in a chemical plant, an employee who has applied for a power outage initiates a power outage request. The power outage request includes an electronic copy of a work ticket, which records the initiator, the power outage time period, the power outage area, and a mark indicating that the request is a power outage operation, and then submits the request. Based on the request, the system determines that it is a power outage. Therefore, from among the multiple people responsible for the power outage, the system determines the approving user based on the power outage time period and the power outage voltage value in the work ticket, and sends the work ticket to the first user among the approving users. Figure 2 As shown, when a power outage request is initiated, an approval user is selected from the power outage staff, and then the job ticket is sent to the first user in the approval process for approval.

[0070] This embodiment starts the approval procedure that matches the work ticket type of the work ticket when triggering the work ticket submission request; determines the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the work ticket; submits the work ticket to the approver for approval, so that when approving power outage or power supply, the work ticket is used as the power outage or power supply content for approval, and the approver is determined by the power outage time period and the power outage voltage value, and the approver is distinguished according to the power outage time period in the work ticket, which meets the actual work scene requirements on site; according to the high and low voltage conditions in the work ticket, a high-voltage safety approver is added to determine the high-voltage safety operation. The effect of improving the approval efficiency of the power outage process is achieved.

[0071] For other examples of this embodiment, please refer to the above examples and will not be described in detail here.

[0072] like Figure 6 As shown, an embodiment of the present application provides an electronic device, including a processor 111, a communication interface 112, a memory 113 and a communication bus 114, wherein the processor 111, the communication interface 112, and the memory 113 communicate with each other through the communication bus 114.

[0073] Memory 113, used for storing computer programs;

[0074] In one embodiment of the present application, the processor 111 is used to implement the job ticket approval method provided by any of the aforementioned method embodiments when executing the program stored in the memory 113.

[0075] An embodiment of the present application also provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, a method for approving a job ticket as provided in any of the aforementioned method embodiments is implemented.

[0076] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, i.e., they may be located in one place, or may be distributed over multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0077] Through the description of the above implementation methods, those skilled in the art can clearly understand that each implementation method can be implemented by means of software plus a general hardware platform, and of course, it can also be implemented by hardware. Based on this understanding, the above technical solution is essentially or the part that contributes to the relevant technology can be embodied in the form of a software product, and the computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a disk, an optical disk, etc., including a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods of each embodiment or some parts of the embodiment.

[0078] It should be understood that the terms used herein are only for the purpose of describing specific example embodiments and are not intended to be limiting. Unless the context clearly indicates otherwise, the singular forms "one", "an" and "said" as used herein may also be meant to include plural forms. The terms "include", "comprise", "contain", and "have" are inclusive, and therefore specify the existence of stated features, steps, operations, elements and / or parts, but do not exclude the existence or addition of one or more other features, steps, operations, elements, parts, and / or combinations thereof. The method steps, processes, and operations described herein are not interpreted as necessarily requiring them to be performed in the specific order described or illustrated, unless the execution order is clearly indicated. It should also be understood that additional or alternative steps may be used.

[0079] The foregoing is merely a specific embodiment of the present invention, which enables those skilled in the art to understand or implement the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features claimed herein.

Claims

1. A method for approving a work ticket, characterized in that: include: When a job ticket submission request is triggered, an approval process matching the job ticket type of the job ticket is initiated; Determine the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket; Submit the job ticket to the approver for approval.

2. The method according to claim 1, characterized in that When triggering a job ticket submission request, starting an approval procedure that matches the job ticket type of the job ticket includes: When the job ticket type is a power supply type, obtain the power supply address in the job ticket; query the historical power outage data of the power supply address, and when the historical power outage data indicates that the power supply address is in a power outage state, start the power supply approval process; when the historical power outage data indicates that the power supply address is in a power supply state, end the approval procedure.

3. The method according to claim 1, characterized in that Before determining the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket, the method further includes: When the operation ticket is an electronic ticket, traversing the labels of the operation ticket, wherein the operation ticket is added with a preset label at the position of the power outage time period and the power outage voltage value; The time period after the traversed time tag is determined as the power outage time period, and the value after the traversed voltage tag is determined as the power outage voltage value.

4. The method according to claim 1, characterized in that: The approvers of the approval nodes in the approval procedure are determined according to the power outage time period and include: When the power outage time period is a working time period, the technician is determined as the approver of the approval procedure; When the power outage time period is a rest time period, the on-duty personnel are determined as the approver of the approval procedure.

5. The method according to claim 1, characterized in that The approvers of the approval node in the approval procedure are determined according to the power outage voltage value and include: When the power outage voltage value is a high voltage, determining the electrical technician as the approver in the approval procedure; When the power-off voltage value is low voltage, the approval procedure flows to the next approval node.

6. The method according to claim 1, characterized in that The determining of the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket comprises: The first approver in the approval procedure is determined according to the power outage time period, and the second approver in the approval procedure is determined according to the power outage voltage value, wherein the second approver is used to perform high-voltage safety operation approval, and in the approval procedure, the approval of the first approver precedes the approval of the second approver.

7. The method according to claim 6, characterized in that After submitting the job ticket to the approving user for approval, the method further includes: After approval by the second approver, the approval procedure is transferred to the third approver, where the third approver is used to approve and confirm the power outage measures.

8. A work ticket approval device, characterized in that: include: A start module, for starting an approval procedure matching the job ticket type of the job ticket when a job ticket submission request is triggered; A determination module, used to determine the approver of the approval node in the approval procedure according to the power outage time period and the power outage voltage value in the operation ticket; The submission module is used to submit the work ticket to the approver for approval.

9. An electronic device, characterized in that: include: at least one communication interface; at least one bus connected to the at least one communication interface; at least one processor coupled to the at least one bus; At least one memory connected to the at least one bus, wherein a computer program is stored in the memory, and when the processor executes the computer program, the method for approving a job ticket as described in any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium storing computer-executable instructions for executing the job ticket approval method according to any one of claims 1 to 7 of the present application.

Citation Information

Cited By

  • Dynamic visualization method and device for power failure and power transmission of railway yard line

    CN120994738A