Charging pile charging control method, device and equipment and storage medium

By obtaining the demand of charging piles and the status of the photovoltaic power grid, judging the power supply type and controlling the charging switch, the problem of low efficiency in photovoltaic power generation power is solved, more efficient grid energy management is achieved, and the consumption of conventional power grids is reduced.

CN119189771APending Publication Date: 2024-12-27SHENZHEN CAR ENERGY NET CO LTD
View PDF 0 Cites 3 Cited by

Patent Information

Application Number
CN202411270783.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-11
Publication Date
2024-12-27

AI Technical Summary

Technical Problem

The existing photo storage and charging system is difficult to meet the charging power requirements of electric vehicles during peak charging periods, and the use efficiency of photovoltaic power generation is low, so it is impossible to accurately switch between photovoltaic and power grids, resulting in high distribution capacity of the power grid and increased energy consumption. .

Method used

By obtaining the power demand of the charging pile, the total load power of the photovoltaic grid, the predicted power of the photovoltaic power generation and other charging pile load power, judge the power supply type, and control the charging switch based on the arbitration value, decide whether to use the photovoltaic grid or the conventional grid to supply power, and optimize the power supply type Improve the efficiency of photovoltaic power generation.

Benefits of technology

It improves the efficiency of photovoltaic power generation, reduces the energy consumption of conventional power grids, and extends the switching service life of charging piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119189771A_ABST
    Figure CN119189771A_ABST
Patent Text Reader

Abstract

The invention provides a charging pile charging control method and device, equipment and a storage medium. The charging pile charging control method provided by the invention comprises the following steps: acquiring a current charging pile demand charging power, a current total load power of a photovoltaic power grid, a current photovoltaic power generation prediction power of the photovoltaic power grid and load powers of other charging piles of a system where the current charging pile is located; according to the current charging pile demand charging power, the total load power, the photovoltaic power generation prediction power and the load power of the other charging piles, the power supply type of the current charging pile is judged, wherein the power supply type comprises photovoltaic power grid power supply or conventional power grid power supply; and controlling a charging switch of the current charging pile according to the judged power supply type. According to the charging control method of the charging pile, the use efficiency of photovoltaic power generation power can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of charging piles, and in particular to a charging pile charging control method, device, equipment and storage medium. Background Art

[0002] With the rapid development of the new energy industry, the number of electric vehicles is growing rapidly, and electric vehicles have higher and higher requirements for charging technology. Traditional charging facilities use AC charging or AC / DC charging, which has high requirements for the power distribution capacity of the power grid. During peak charging periods, it may be difficult to meet the charging power of electric vehicles. The existing photovoltaic storage and charging system can effectively increase the charging power and reduce the power distribution capacity of the power grid. This photovoltaic storage and charging system is composed of a battery management system, a bidirectional energy conversion system, etc. However, this photovoltaic storage and charging system has a relatively simple control strategy for photovoltaics and power grids, and cannot accurately realize the switching of photovoltaic and power grid charging, resulting in low efficiency in the use of photovoltaic power generation. Summary of the invention

[0003] The object of the present invention is to provide a charging pile charging control method, device, equipment and storage medium to solve the technical problem of low utilization efficiency of photovoltaic power generation in the prior art.

[0004] The technical solution of the present invention is as follows, which provides a charging pile charging control method, comprising:

[0005] Obtain the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located;

[0006] Determine the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, the power supply type including photovoltaic power grid power supply or conventional power grid power supply;

[0007] The charging switch of the current charging pile is controlled according to the determined power supply type.

[0008] Further, judging the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles includes:

[0009] The power supply type of the current charging pile is determined according to the required charging power of the current charging pile, the total load power, the predicted photovoltaic power generation power and the load power of the other charging piles, and a power supply type arbitration value is determined. When the power supply type arbitration value is greater than a preset value, the power supply type of the current charging pile is determined to be photovoltaic power grid power supply; otherwise, the power supply type of the current charging pile is determined to be conventional power grid power supply.

[0010] Further, the power supply type of the current charging pile is determined according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, and the power supply type arbitration value is determined, including:

[0011] The power supply type of the current charging pile is determined according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, the load power of the other charging piles and an arbitration formula, and the power supply type arbitration value is determined. The arbitration formula includes

[0012] C(t)=CarNeed(t)*k1+SystemLoad(t)*k2+Power(t)*k3+WorkState(t)*k4

[0013] Among them, C(t) is the arbitration value of the power supply type, CarNeed(t) is the charging power required by the current charging pile, SystemLoad(t) is the total load power, Power(t) is the predicted photovoltaic power generation power, WorkState(t) is the load power of other charging piles, k1, k2, k3, k4 are the first weight coefficient, the second weight coefficient, the third weight coefficient and the fourth weight coefficient respectively.

[0014] Furthermore, the charging pile charging control method further includes:

[0015] The expectation of the current charging power required by the charging pile is obtained, and the current load power required by the charging pile is obtained according to the percentage of the battery power of the vehicle corresponding to the current charging pile, and the first weight coefficient is determined according to the expectation and the current load required by the charging pile.

[0016] Furthermore, the charging pile charging control method further includes:

[0017] Acquire current weather data, current time data and current photovoltaic generator power data, and acquire the photovoltaic power generation prediction power according to the current weather data, the current time data, the current photovoltaic generator power data and a power prediction model; the power prediction model is trained according to historical weather data, historical time data, historical photovoltaic generator power data and an initial power prediction model.

[0018] Furthermore, the initial power prediction model includes an input layer, a hidden layer and an output layer.

[0019] Furthermore, the hidden layer is used to extract the influence weights of the historical weather data and the historical time data on the historical photovoltaic generator power data.

[0020] Another technical solution of the present invention is as follows: a charging pile charging control device is also provided, including a power data acquisition module, a power supply type judgment module and a charging switch control module;

[0021] The power data acquisition module is used to obtain the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located;

[0022] The power supply type judgment module is used to judge the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, and the power supply type includes photovoltaic power grid power supply or conventional power grid power supply;

[0023] The charging switch control module is used to control the charging switch of the current charging pile according to the determined power supply type.

[0024] Another technical solution of the present invention is as follows: an electronic device is provided, including a memory and a processor, wherein:

[0025] The memory is used to store computer programs;

[0026] The processor is used to read the computer program in the memory and execute the steps of the charging pile charging control method as described in any of the above technical solutions.

[0027] Another technical solution of the present invention is as follows: a computer-readable storage medium is provided, on which a readable computer program is stored. When the program is executed by a processor, the steps of the charging pile charging control method as described in any of the above technical solutions are implemented.

[0028] The beneficial effects of the present invention are: obtaining the charging power required by the current charging pile, the total load power of the current photovoltaic power grid, the predicted photovoltaic power generation power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located; judging the power supply type of the current charging pile according to the charging power required by the current charging pile, the total load power, the predicted photovoltaic power generation power, and the load power of the other charging piles, the power supply type including photovoltaic power grid power supply or conventional power grid power supply; controlling the charging switch of the current charging pile according to the determined power supply type; through the above technical scheme, the utilization efficiency of photovoltaic power generation can be improved, thereby reducing the energy consumption of conventional power grids. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 A schematic diagram of a flow chart of a charging pile charging control method provided by an embodiment of the present invention;

[0030] Figure 2 A schematic diagram of the structure of a charging pile charging control device provided by an embodiment of the present invention;

[0031] Figure 3 A schematic diagram of the structure of an electronic device provided by an embodiment of the present invention;

[0032] Figure 4 A schematic diagram of the structure of a computer-readable storage medium provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0035] Figure 1 It is a flow chart of the charging pile charging control method of the embodiment of the present invention. It should be noted that if there is substantially the same result, the charging pile charging control method of the present invention is not based on Figure 1 The process sequence shown is limited. Figure 1 As shown, the charging pile charging control method mainly includes the following steps:

[0036] S101, obtaining the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located;

[0037] S102, judging the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, the power supply type including photovoltaic power grid power supply or conventional power grid power supply;

[0038] In some embodiments, judging the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, and the load power of the other charging piles includes:

[0039] The power supply type of the current charging pile is determined according to the required charging power of the current charging pile, the total load power, the predicted photovoltaic power generation power and the load power of the other charging piles, and a power supply type arbitration value is determined. When the power supply type arbitration value is greater than a preset value, the power supply type of the current charging pile is determined to be photovoltaic power grid power supply; otherwise, the power supply type of the current charging pile is determined to be conventional power grid power supply.

[0040] In a specific embodiment, the power supply type of the current charging pile includes photovoltaic power grid power supply or conventional power grid power supply. The current charging pile uses photovoltaic power grid power supply or conventional power grid power supply. The conventional power grid can be a power grid connected to the mains. The above preset value can be determined according to actual needs. When the power supply type arbitration value is greater than the preset value, it is determined that the power supply type of the current charging pile is photovoltaic power grid power supply, otherwise it is determined that the power supply type of the current charging pile is conventional power grid power supply.

[0041] In some embodiments, determining the power supply type of the current charging pile and determining the power supply type arbitration value according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, and the load power of the other charging piles includes:

[0042] The power supply type of the current charging pile is determined according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, the load power of the other charging piles and an arbitration formula, and the power supply type arbitration value is determined. The arbitration formula includes

[0043] C(t)=CarNeed(t)*k1+SystemLoad(t)*k2+Power(t)*k3+WorkState(t)*k4

[0044] Among them, C(t) is the arbitration value of the power supply type, CarNeed(t) is the charging power required by the current charging pile, SystemLoad(t) is the total load power, Power(t) is the predicted photovoltaic power generation power, WorkState(t) is the load power of other charging piles, k1, k2, k3, k4 are the first weight coefficient, the second weight coefficient, the third weight coefficient and the fourth weight coefficient respectively.

[0045] In a specific embodiment, CarNeed(t) is the required charging power of the current charging pile, that is, the required charging power of the current charging pile corresponding to the car, and its size will change over time during the charging process; SystemLoad(t) is the total load power of the current photovoltaic power grid, and the current charging pile can obtain the total load power of the current photovoltaic power grid through the physical link with the photovoltaic power generation system; Power(t) is the predicted photovoltaic power generation power of the current photovoltaic power grid, and WorkState(t) is the load power of other charging piles in the system where the current charging pile is located. The system where the current charging pile is located can be the charging system where the current charging pile is located. The load power of other charging piles in the system where the current charging pile is located can be obtained through the current charging pile's own WIFI or network port local networking transmission information.

[0046] In a specific embodiment, the first weight coefficient k1, the second weight coefficient k2, the third weight coefficient k3 and the fourth weight coefficient k4 all take values ​​between 0 and 1, and the magnitude of the values ​​represents the corresponding power weights.

[0047] In some embodiments, the charging pile charging control method further includes:

[0048] The expectation of the current charging power required by the charging pile is obtained, and the current load power required by the charging pile is obtained according to the percentage of the battery power of the vehicle corresponding to the current charging pile, and the first weight coefficient is determined according to the expectation and the current load required by the charging pile.

[0049] In a specific embodiment, the expected charging power E(x) of the current charging pile demand is obtained, that is, the charging power required by the current charging pile for the car, and a normal distribution diagram of the current charging pile demand charging power x and a curve of the current charging pile demand charging power x for time t are drawn according to the historical data of the current charging pile demand charging power x. Because the load of the charging pile on the photovoltaic power grid is determined by the charging power demand of the car, the load curve generated by the charging pile on the photovoltaic system in a day can be obtained through the above data. After the charging pile is based on the SOC of the car (the percentage of the car battery power, where 0 means that the car battery is out of power and 100 means that the car battery is fully charged), the time the car will stay and the load generated on the photovoltaic power grid during this period, that is, the current charging pile demand load power, can be estimated according to this load curve. According to the expected charging power E(x) of the current charging pile demand and the current charging pile demand load power P, the first weight coefficient k1 with the best efficiency can be determined, and k1 can be P / E(x).

[0050] In a specific embodiment, the second weight coefficient k2, the third weight coefficient k3 and the fourth weight coefficient k4 can be determined according to actual needs. As an example, when determining the second weight coefficient k2, because the factor corresponding to the second weight coefficient k2 is the total load power of the current photovoltaic power grid, it can be converted into the sum of the loads generated by each charging pile in the entire system on the photovoltaic power grid. The second weight coefficient k2 can be determined by steps similar to the above process, that is, obtaining the expectation of the total load power of the current photovoltaic power grid and the total load power required by the current photovoltaic power grid to obtain the second weight coefficient k2. Since the power that the transformer in the station can provide in the actual process is fixed, and the transformer needs to be responsible for the power supply of other electrical appliances in the station in addition to supplying power to the charging piles, the power used by these electrical appliances will change over time. Therefore, when determining the third weight coefficient k3, in addition to calculating the parameters (expectations) of the photovoltaic power generation power through the above process, it is also necessary to calculate the power on the ordinary power grid to obtain the user's power consumption expectations. According to these two expectations and the photovoltaic power generation load power, the value of the third weight coefficient k3 is determined. When determining the fourth weight coefficient k4, it is necessary to calculate the value of k4 by calculating the corresponding expectation and listing the normal distribution graph versus time curve through the switching times of the charging piles on the control matrix in the historical data.

[0051] In some embodiments, the charging pile charging control method further includes:

[0052] Acquire current weather data, current time data and current photovoltaic generator power data, and acquire the photovoltaic power generation prediction power according to the current weather data, the current time data, the current photovoltaic generator power data and a power prediction model; the power prediction model is trained according to historical weather data, historical time data, historical photovoltaic generator power data and an initial power prediction model.

[0053] In a specific embodiment, a large amount of historical weather data, historical time data and corresponding historical photovoltaic generator power data are obtained, and an initial power prediction model is trained based on the historical weather data, historical time data and historical photovoltaic generator power data to obtain a power prediction model.

[0054] In some embodiments, the initial power prediction model includes an input layer, a hidden layer, and an output layer.

[0055] In a specific embodiment, the initial power prediction model may be a neural network model.

[0056] In some embodiments, the hidden layer is used to extract the influence weights of the historical weather data and the historical time data on the historical photovoltaic generator power data.

[0057] In a specific embodiment, the input layer is used to receive raw input data, such as historical weather data, historical time data, etc., and pass it to the hidden layer. The hidden layer is used to calculate and extract the nonlinear characteristics and features of the input data. Specifically, the hidden layer is used to extract the influence weights of historical weather data and historical time data on historical photovoltaic generator power data. The output layer is used to receive the output data of the hidden layer and output the final prediction result.

[0058] In a specific embodiment, after obtaining the photovoltaic power generation prediction power according to the current weather data, the current time data, the current photovoltaic generator power data and the power prediction model, the power supply type arbitration value is obtained through the arbitration formula, thereby obtaining the determination result of the power supply type of the current charging pile, thereby improving the utilization efficiency of the photovoltaic power generation power. The actual photovoltaic power generation power corresponding to the current charging pile can be compared with the photovoltaic power generation prediction power to repeatedly optimize the power prediction model and improve the accuracy of the power prediction model.

[0059] S103: Control the charging switch of the current charging pile according to the determined power supply type.

[0060] In a specific embodiment, if it is determined that the power supply type of the current charging pile is photovoltaic power grid power supply, the charging switch (control switch) of the current charging pile is controlled to connect the current charging pile to the photovoltaic power grid, and the current charging pile uses the photovoltaic power grid to power the corresponding electric vehicle. If it is determined that the power supply type of the current charging pile is conventional power grid power supply, the charging switch of the current charging pile is controlled to connect the current charging pile to the conventional power grid, and the current charging pile uses the conventional power grid to power the corresponding electric vehicle.

[0061] The charging pile charging control method provided by the embodiment of the present invention obtains the charging power required by the current charging pile, the total load power of the current photovoltaic power grid, the predicted photovoltaic power generation power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located; the power supply type of the current charging pile is judged according to the charging power required by the current charging pile, the total load power, the predicted photovoltaic power generation power, and the load power of the other charging piles, and the power supply type includes photovoltaic power grid power supply or conventional power grid power supply; the charging switch of the current charging pile is controlled according to the determined power supply type, so as to improve the utilization efficiency of photovoltaic power generation, reduce the energy consumption of conventional power grids, and extend the service life of the switch of the charging pile.

[0062] Figure 2 2 is a schematic diagram of the structure of a charging pile charging control device provided in an embodiment of the present invention. The charging pile charging control device 20 includes a power data acquisition module 21, a power supply type judgment module 22 and a charging switch control module 23;

[0063] The power data acquisition module 21 is used to obtain the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located;

[0064] The power supply type judgment module 22 is used to judge the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, and the power supply type includes photovoltaic power grid power supply or conventional power grid power supply;

[0065] The charging switch control module 23 is used to control the charging switch of the current charging pile according to the determined power supply type.

[0066] For other details about how the modules in the above-mentioned charging pile charging control device implement the above-mentioned technical solution, please refer to the description of the charging pile charging control method provided in the above-mentioned invention embodiment, which will not be repeated here.

[0067] Figure 3 Schematic diagram of the structure of an electronic device according to an embodiment of the present invention. Figure 3 As shown, the electronic device 30 includes a processor 31 and a memory 32 that is communicatively connected to the processor 31 .

[0068] The memory 32 stores program instructions for implementing the charging pile charging control method of any of the above embodiments.

[0069] The processor 31 is used to execute the program instructions stored in the memory 32 to perform charging control of the charging pile.

[0070] The processor 31 may also be referred to as a CPU (Central Processing Unit). The processor 31 may be an integrated circuit chip having signal processing capabilities. The processor 31 may also be a general-purpose processor, a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components. The general-purpose processor may be a microprocessor or the processor may also be any conventional processor, etc.

[0071] The memory 32 may be used to store the computer programs and / or modules, and the processor 31 implements various functions of the electronic device by running or executing the computer programs and / or modules stored in the memory 32, and calling the data stored in the memory 32. The memory 32 may mainly include a program storage area and a data storage area, wherein the program storage area may store an operating system, an application required for at least one function, and the like.

[0072] The memory 32 may be integrated into the processor 31 , or may be provided separately from the processor 31 .

[0073] An embodiment of the present invention provides a computer-readable storage medium, a schematic diagram of which is shown in FIG. Figure 4 As shown, a readable computer program 41 is stored on the storage medium 40; wherein, the computer program 41 can be stored in the above storage medium 40 in the form of a software product, including several instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) or a processor to execute all or part of the steps of the method described in each embodiment of the present invention. The aforementioned storage medium 40 includes: U disk, mobile hard disk, magnetic disk or optical disk, ROM (Read-Only Memory), RAM (Random Access Memory) and other media that can store program codes, or terminal devices such as computers, servers, mobile phones, and tablets.

[0074] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the above modules is only a logical function division. There may be other division methods in actual implementation, such as multiple modules or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or modules, which can be electrical, mechanical or other forms.

[0075] The modules described above as separate components may or may not be physically separated, and the components shown as modules may or may not be physical modules, that is, they may be located in one place or distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0076] In addition, each functional module in each embodiment of the present application may be integrated into a processing module, or each module may exist physically separately, or two or more modules may be integrated into one module. The above-mentioned integrated module may be implemented in the form of hardware or in the form of a software functional module. If the above-mentioned integrated module is implemented in the form of a software functional module and sold or used as an independent product, it may be stored in a computer-readable storage medium.

[0077] In the above embodiments, all or part of the embodiments may be implemented by software, hardware, firmware or any combination thereof. When implemented by software, all or part of the embodiments may be implemented in the form of a computer program product.

[0078] The above-mentioned computer program product includes one or more computer instructions. When the above-mentioned computer program instructions are loaded and executed on a computer, the above-mentioned process or function according to the embodiment of the present application is generated in whole or in part. The above-mentioned computer may be a general-purpose computer, a special-purpose computer, a computer network or other programmable devices. The above-mentioned computer instructions may be stored in a computer-readable storage medium, or transmitted from a computer-readable storage medium to another computer-readable storage medium, for example, the above-mentioned computer instructions may be transmitted from a website site, a computer, a server or a data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) mode to another website site, computer, server or data center. The above-mentioned computer-readable storage medium may be any available medium that a computer can store or a data storage device such as a server, a data center, etc. that includes one or more available media integration. The above-mentioned available medium may be a magnetic medium, (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a semiconductor medium (e.g., a solid-state drive (SSD)), etc.

[0079] The technical solution provided by the present application is introduced in detail above. The principles and implementation methods of the present application are explained by using specific examples in the present application. The description of the above embodiments is only used to help understand the method of the present application and its core idea. At the same time, for those skilled in the art, according to the idea of ​​the present application, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as a limitation on the present application.

[0080] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0081] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices and computer program products according to the present application. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of the processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0082] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0083] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0084] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A charging pile charging control method, characterized in that: include: Obtain the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located; Determine the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, the power supply type including photovoltaic power grid power supply or conventional power grid power supply; The charging switch of the current charging pile is controlled according to the determined power supply type.

2. The charging pile charging control method according to claim 1, characterized in that: The power supply type of the current charging pile is determined according to the required charging power of the current charging pile, the total load power, the predicted photovoltaic power generation power, and the load power of the other charging piles, including: The power supply type of the current charging pile is determined according to the required charging power of the current charging pile, the total load power, the predicted photovoltaic power generation power and the load power of the other charging piles, and a power supply type arbitration value is determined. When the power supply type arbitration value is greater than a preset value, the power supply type of the current charging pile is determined to be photovoltaic power grid power supply; otherwise, the power supply type of the current charging pile is determined to be conventional power grid power supply.

3. The charging pile charging control method according to claim 2, characterized in that: Determining the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, and the load power of the other charging piles, and determining the power supply type arbitration value, including: The power supply type of the current charging pile is determined according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power, the load power of the other charging piles and an arbitration formula, and the power supply type arbitration value is determined. The arbitration formula includes C(t)=CarNeed(t)*k1+SystemLoad(t)*k2+Power(t)*k3+WorkState(t)*k4 Among them, C(t) is the arbitration value of the power supply type, CarNeed(t) is the charging power required by the current charging pile, SystemLoad(t) is the total load power, Power(t) is the predicted photovoltaic power generation power, WorkState(t) is the load power of other charging piles, t is time, which means that the corresponding value changes with time, k1, k2, k3, k4 are the first weight coefficient, the second weight coefficient, the third weight coefficient and the fourth weight coefficient respectively.

4. The charging pile charging control method according to claim 3, characterized in that: The charging pile charging control method further includes: The expectation of the current charging power required by the charging pile is obtained, and the current load power required by the charging pile is obtained according to the percentage of the battery power of the vehicle corresponding to the current charging pile, and the first weight coefficient is determined according to the expectation and the current load required by the charging pile.

5. The charging pile charging control method according to claim 1, characterized in that: The charging pile charging control method further includes: Acquire current weather data, current time data and current photovoltaic generator power data, and acquire the photovoltaic power generation prediction power according to the current weather data, the current time data, the current photovoltaic generator power data and a power prediction model; the power prediction model is trained according to historical weather data, historical time data, historical photovoltaic generator power data and an initial power prediction model.

6. The charging pile charging control method according to claim 5, characterized in that: The initial power prediction model includes an input layer, a hidden layer and an output layer.

7. The charging pile charging control method according to claim 6, characterized in that: The hidden layer is used to extract the influence weights of the historical weather data and the historical time data on the historical photovoltaic generator power data.

8. A charging pile charging control device, characterized in that: It includes a power data acquisition module, a power supply type judgment module and a charging switch control module; The power data acquisition module is used to obtain the current charging pile required charging power, the total load power of the current photovoltaic power grid, the photovoltaic power generation forecast power of the current photovoltaic power grid, and the load power of other charging piles in the system where the current charging pile is located; The power supply type judgment module is used to judge the power supply type of the current charging pile according to the current charging pile required charging power, the total load power, the photovoltaic power generation predicted power and the load power of the other charging piles, and the power supply type includes photovoltaic power grid power supply or conventional power grid power supply; The charging switch control module is used to control the charging switch of the current charging pile according to the determined power supply type.

9. An electronic device, characterized in that: comprising a memory and a processor, wherein: The memory is used to store computer programs; The processor is used to read the computer program in the memory and execute the steps of the charging pile charging control method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: A readable computer program is stored thereon, and when the program is executed by a processor, the steps of the charging pile charging control method as described in any one of claims 1 to 7 are implemented.

Citation Information

Cited By

  • Starting method and device based on dummy load, photovoltaic air conditioner and storage medium

    CN120426605A

  • Power supply control method, device and equipment for photovoltaic energy storage charging pile

    CN121791432A

  • Optical storage direct flexible device energy management method and system, electronic device and storage medium