Construction method for cornice installation
By prefabricating and assembling the ground and lifting the eaves structure module with lifting equipment, and precisely positioning with three-dimensional scanning technology, the problems of high altitude operation and high safety risks in the existing eaves installation methods are solved, and an efficient and safe construction process is achieved.
Patent Information
- Application Number
- CN202411490433.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-24
- Publication Date
- 2024-12-27
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing eaves installation method requires a lot of assembly work at high altitudes, resulting in high construction difficulty, high safety risks, long construction cycles and difficulty in ensuring accuracy.
The eaves structure is divided into eaves and ceiling combination modules, gutter modules and inclined roof modules, and prefabricated on the ground. Then, the lifting equipment is lifted one by one and connected to the building main body, and the three-dimensional scanning technology is used for precise positioning and adjustment.
It greatly reduces the working time at high altitudes, improves construction efficiency and safety, ensures construction accuracy, and makes the construction progress more controllable and fast.
Smart Images

Figure CN119195496A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method for installing an eave. Background Art
[0002] With the continuous development and progress of architectural design, people's requirements for the structure and aesthetics of public buildings are gradually increasing. As an important part of public buildings, cornices are located above the entrances and exits of public buildings. They not only protect against wind and rain, but also achieve the shape and three-dimensional sense of the building through the design of cornices. It can be said that the installation of cornice system is one of the important links in the entire construction.
[0003] At present, the installation of eaves mainly adopts the on-site assembly method, in which each component of the eaves is installed one by one to the main body of the building. A large amount of assembly work of each component is required at high altitude. The construction is difficult and the safety risk is high, resulting in a long construction period. In addition, it is difficult for construction workers to ensure accuracy when operating at high altitude, which can easily lead to installation errors and appearance defects.
[0004] Therefore, it is urgent to propose a construction method for cornice installation to solve the above technical problems. Summary of the invention
[0005] The purpose of the present invention is to provide a construction method for installing an eaves, which can reduce high-altitude operations, improve construction efficiency and reduce safety risks, and also make it easier to ensure construction accuracy.
[0006] As conceived above, the technical solution adopted by the present invention is:
[0007] The present invention provides a construction method for installing an eaves, which is used for installing an eaves structure to an eaves installation position of a building main body, wherein the eaves structure comprises an eaves and ceiling combination module, a gutter module and a sloping roof module; the construction method for installing the eaves comprises:
[0008] Prefabricate and assemble the cornice and ceiling combination module, the gutter module and the sloping roof module on the ground;
[0009] Lifting the eaves and ceiling combination module to the eaves installation position by a lifting device, and fixing the eaves and ceiling combination module to the bottom of the eaves installation position;
[0010] Lift the gutter module close to the eaves and ceiling combination module by a lifting device, so that the gutter module is connected to the gutter groove reserved on the eaves and ceiling combination module;
[0011] The sloping roof module is lifted to the eaves installation position by a lifting device, the sloping roof module is fixedly connected to the slope of the eaves installation position, and one end of the sloping roof module close to the gutter module is connected to the gutter module.
[0012] In some embodiments, the cornice and ceiling combination module, the gutter module and the sloping roof module all include a keel structure and a curtain wall structure; when the cornice and ceiling combination module, the gutter module and the sloping roof module are prefabricated and assembled on the ground, the prefabrication and assembly of any of the modules specifically includes:
[0013] Setting up an assembly tire stand on the ground;
[0014] Assembling and adjusting the keel structure of the module by means of the assembly frame;
[0015] After the keel structure is assembled, the curtain wall structure is connected to the keel structure;
[0016] Carry out a comprehensive inspection and test on the assembled modules to ensure that they meet the installation requirements.
[0017] In some embodiments, the curtain wall structure includes a waterproof layer and a decorative surface layer, and the decorative surface layer is arranged on the outer surface of the keel structure; connecting the curtain wall structure to the keel structure includes:
[0018] After the keel structure is assembled, the waterproof layer is first installed on the keel structure, and then the decorative surface layer is installed on the outer surface of the keel structure.
[0019] In some embodiments, before the cornice and ceiling assembly module, the gutter module and the sloping roof module are prefabricated and assembled on the ground, the method further includes:
[0020] Model establishment: according to the architectural design drawings, a complete cornice structure model is established, and a collision check is performed to ensure the precise positioning and coordination of the cornice and ceiling combination module, the gutter module and the sloping roof module;
[0021] Deepening design: Based on the premise of the whole modular installation of the cornice structure, the integrated design of the cornice structure to be installed on the main building body is carried out;
[0022] Component processing: According to the drawings and requirements of the in-depth design, the components of the eaves and ceiling combination module, the gutter module and the sloping roof module are processed to ensure that each component meets the design specifications and quality requirements.
[0023] In some embodiments, assembling and adjusting the keel structure of the module by the assembly frame specifically includes:
[0024] Combined with the eaves structure model, the keel structure is measured and adjusted using three-dimensional scanning technology.
[0025] In some embodiments, after assembling and adjusting the keel structure of the module by the assembly frame, the method further includes:
[0026] Performing error measurement on the building main body;
[0027] According to the assembly status of the keel structure and the error measurement results of the building main body, combined with the eaves structure model, three-dimensional scanning technology is used to check and debug the connectors of the modules, which are used to connect the modules to the building main body.
[0028] In some embodiments, during the process of installing the eaves and ceiling combination module, the gutter module and the sloping roof module to the building body, three-dimensional scanning technology is used to coordinately control the fixed points of the connecting parts one by one.
[0029] In some embodiments, after the eaves and ceiling combination module, the gutter module and the sloping roof module are all installed on the building body, the method further includes:
[0030] The joints are waterproofed and decorated.
[0031] In some embodiments, after the eaves and ceiling combination module, the gutter module and the sloping roof module are all installed on the building body, the method further includes:
[0032] A roof covering layer is arranged on the top of the building body, so that the end of the inclined roof module away from the gutter module is overlapped or connected with the roof covering layer.
[0033] In some embodiments, the roof covering layer is a waterproof layer.
[0034] Beneficial effects of the present invention:
[0035] The construction method for installing the eaves provided by the present invention divides the eaves structure into an eaves and ceiling combination module, a gutter module and a sloping roof module, and then prefabricates and assembles each module on the ground in advance, and then hoists and connects the assembled modules in sequence to the main building. By completing most of the assembly work on the ground, the time for high-altitude operations is greatly reduced, which can improve construction efficiency and reduce safety risks. At the same time, the difficulty of the operation is low when assembling on the ground, and it is easier to ensure construction accuracy. In addition, when the module assembly operation is performed on the ground, other construction operations can be carried out simultaneously on the main building, thereby improving the overall construction efficiency and making the construction progress more controllable and rapid. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments of the present invention. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the contents of the embodiments of the present invention and these drawings without paying any creative work.
[0037] Figure 1 It is a structural schematic diagram of the cornice and ceiling combination module and the assembly frame provided by an embodiment of the present invention;
[0038] Figure 2 It is a structural schematic diagram of a building main body provided by an embodiment of the present invention when the eaves structure is not installed;
[0039] Figure 3 It is a structural schematic diagram of the cornice and ceiling assembly module provided by an embodiment of the present invention;
[0040] Figure 4 It is a structural schematic diagram of the cornice and ceiling combination module provided by an embodiment of the present invention connected to the building main body;
[0041] Figure 5 It is a structural schematic diagram of an embodiment of the present invention in which the eaves structure provided by the embodiment of the present invention is completely connected to the main body of the building.
[0042] In the figure:
[0043] 1. Eaves and ceiling combination module;
[0044] 2. Gutter module;
[0045] 3. Sloped roof module;
[0046] 4. Assemble the tire frame;
[0047] 5. Connectors;
[0048] 6. Roof covering;
[0049] 100. Cornice structure;
[0050] 200. Building main body; 210. Eaves installation location; 211. Bottom; 212. Slant surface. DETAILED DESCRIPTION
[0051] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0052] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0054] In the description of the present invention, it should be noted that the terms "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or are the positions or positional relationships in which the inventive product is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In the description of the present invention, unless otherwise specified, "multiple" means two or more.
[0055] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "disposed" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0056] In the present invention, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0057] Embodiments of the present invention are described in detail below, examples of which are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be understood as limiting the present invention.
[0058] like Figure 1 to Figure 5 As shown, the construction method for eaves installation provided in this embodiment is used to install the eaves structure 100 to the eaves installation position 210 of the building body 200. The eaves structure 100 includes an eaves and ceiling combination module 1, a gutter module 2 and a sloping roof module 3.
[0059] The construction methods of cornice installation include:
[0060] Prefabricate and assemble cornice and ceiling combination module 1, gutter module 2 and sloping roof module 3 on the ground;
[0061] The eaves and ceiling combination module 1 is lifted to the eaves installation part 210 by a lifting device, and the eaves and ceiling combination module 1 is fixedly connected to the bottom 211 of the eaves installation part 210;
[0062] Lift the gutter module 2 close to the eaves and ceiling combination module 1 by the lifting device, so that the gutter module 2 is connected to the gutter groove reserved on the eaves and ceiling combination module 1;
[0063] The sloping roof module 3 is lifted to the eaves installation part 210 by a lifting device, and is fixedly connected to the slope 212 of the eaves installation part 210 , and one end of the sloping roof module 3 close to the gutter module 2 is connected to the gutter module 2 .
[0064] Among them, the eaves and ceiling combination module 1 includes an eaves part and a suspended top part, the suspended top part is connected to the bottom 211 of the eaves installation part 210, the eaves part is cantilevered out of the outside of the eaves installation part 210, and the gutter module 2 is connected to the eaves part. The gutter module 2 is used for water collection and drainage, and can collect external water (such as rainwater) falling from the sloping roof module 3, and discharge the collected external water to prevent external water from entering the eaves and ceiling combination module 1.
[0065] This embodiment provides a construction method for cornice installation, where the cornice structure 100 is divided into a cornice and ceiling combination module 1, a gutter module 2, and a sloping roof module 3, and then each module is prefabricated and assembled on the ground in advance, and then each assembled module is hoisted and connected to the building main body 200 in sequence. By completing most of the assembly work on the ground, the high-altitude operation time is greatly reduced, which can improve construction efficiency and reduce safety risks. At the same time, the operation difficulty is low when assembling on the ground, and it is easier to ensure construction accuracy. In addition, when the module assembly operation is performed on the ground, other construction operations can be performed simultaneously on the building main body 200, thereby improving the overall construction efficiency and making the construction progress more controllable and rapid.
[0066] The lifting equipment may be a truck crane, a crawler crane, an electric hoist, etc., which is not specifically limited here.
[0067] Specifically, the cornice and ceiling combination module 1, the gutter module 2 and the sloping roof module 3 all include a keel structure and a curtain wall structure. When the cornice and ceiling combination module 1, the gutter module 2 and the sloping roof module 3 are prefabricated and assembled on the ground, the prefabrication and assembly of any of the modules specifically includes the following steps:
[0068] An assembly tire frame 4 is arranged on the ground;
[0069] The keel structure of the module is assembled and adjusted by assembling the tire frame 4; specifically, the keel structure can be set as a steel structure;
[0070] After the keel structure is assembled, the curtain wall structure is connected to the keel structure;
[0071] Carry out a comprehensive inspection and test on the assembled modules to ensure that they meet the installation requirements.
[0072] Among them, the comprehensive inspection test includes appearance inspection and waterproof function inspection to ensure that the systems of the assembled modules function normally, the structure is stable, and meet the design requirements.
[0073] The assembly frame 4 is provided to facilitate the assembly and adjustment of different components in each module and ensure the assembly accuracy of each module. In particular, for modules with curved surfaces, the assembly frame 4 is used to adjust the curved surface accuracy and installation quality.
[0074] The assembled tire frame 4 can adopt a conventional structure in the art, which will not be described in detail here.
[0075] More specifically, the curtain wall structure includes a waterproof layer and a decorative surface layer, and the decorative surface layer is arranged on the outer surface of the keel structure. Connecting the curtain wall structure to the keel structure includes:
[0076] After the keel structure is assembled, the waterproof layer is first installed on the keel structure, and then the decorative surface layer is installed on the outer surface of the keel structure.
[0077] By completing the installation of a waterproof layer on the ground, the waterproof performance of each module is ensured, thereby improving the waterproof effect of the entire eaves structure 100; the outermost decorative surface layer plays a decorative and aesthetic role. During installation, it is necessary to ensure that the decorative surface layer is flat, beautiful, and in line with the design effect.
[0078] In some embodiments, before the cornice and ceiling assembly module 1, the gutter module 2 and the sloping roof module 3 are prefabricated on the ground, the following steps are further included:
[0079] Model establishment: According to the architectural design drawings, a complete cornice structure model is established and collision checks are performed to ensure the precise positioning and coordination of the cornice and ceiling combination module 1, the gutter module 2 and the sloping roof module 3;
[0080] Further design: Based on the premise of the whole modular installation of the cornice structure 100, an integrated design of installing the cornice structure 100 to the building main body 200 is performed;
[0081] Component processing: According to the drawings and requirements of the in-depth design, the components of the eaves and ceiling combination module 1, the gutter module 2 and the sloping roof module 3 are processed to ensure that each component meets the design specifications and quality requirements.
[0082] During model building, the eaves structure model may be a BIM model (Building Information Modeling), which refers to a digital three-dimensional model created based on architectural design drawings, including the shape, material, connection method, etc. of the eaves structure 100.
[0083] Through such settings, model building helps to discover and solve potential conflicts or problems in the design stage, thereby reducing rework and adjustments during the construction process. The in-depth design is based on the modular installation of the entire cornice structure 100, ensuring that both the design and construction stages can be carried out in a modular manner, thereby ensuring the high consistency and coordination of all modules during the installation process, and avoiding installation mismatch problems on site. Based on this, component processing is then carried out, which is conducive to ensuring the processing quality and processing accuracy of the components.
[0084] In some embodiments, the keel structure of the module is assembled and adjusted by assembling the tire frame 4, specifically including:
[0085] Combined with the eaves structure model, 3D scanning technology is used to measure and adjust the keel structure.
[0086] Through such a setting, 3D scanning technology can be used to measure and locate each part of the keel structure with high precision, and compared with the BIM model of the cornice structure to ensure that the actual assembly position of the keel is completely consistent with the designed position. 3D scanning can also detect the deviation of the keel structure in real time, quickly identify errors in size, position or shape, so that the construction team can make timely adjustments to avoid cumulative errors. In other words: it is conducive to improving the assembly accuracy of the keel structure and reducing the risk of deformation during the subsequent installation process.
[0087] In some embodiments, after assembling and adjusting the keel structure of the module by assembling the tire frame 4, the following steps are further included:
[0088] Perform error measurement on the building main body 200;
[0089] According to the assembly of the keel structure and the error measurement results of the building main body 200, combined with the eaves structure model, the three-dimensional scanning technology is used to check and debug the connector 5 of the module, which is used to connect the module to the building main body 200.
[0090] like Figure 1 As shown, a connecting piece 5 is shown on the cornice and ceiling combination module 1, and similar arrangements are used in the remaining modules.
[0091] By measuring the error of the building main body 200, the deviation between the building main body 200 and the design model in actual construction can be accurately identified. Combined with the assembly of the keel structure and the eaves structure model, the three-dimensional scanning technology can be used to accurately adjust the size, angle, etc. of the connector 5 to compensate for these deviations, ensuring that the module can be accurately connected to the building main body 200, reducing the risk of deformation during subsequent installation.
[0092] In some embodiments, during the process of installing the cornice and ceiling assembly module 1, the gutter module 2 and the sloping roof module 3 to the building main body 200, the three-dimensional scanning technology is used to coordinately control the fixed points of the connector 5 one by one. Such a setting can ensure that the position of the fixed point of each connector 5 during installation is completely consistent with the design requirements, which can avoid the accumulation of deviations, the occurrence of misalignment or misalignment, and improve the accuracy of the overall installation.
[0093] In some embodiments, after the cornice and ceiling assembly module 1, the gutter module 2 and the sloping roof module 3 are all installed to the building body 200, the following steps are further included:
[0094] The joints are waterproofed and decorated.
[0095] By performing secondary waterproofing treatment on the gaps and cracks that may occur during the installation and fixing process, and completing the necessary decoration, the waterproof performance is further enhanced to prevent leakage problems.
[0096] In some embodiments, after the cornice and ceiling assembly module 1, the gutter module 2 and the sloping roof module 3 are all installed to the building body 200, the following steps are further included:
[0097] A roof covering layer 6 is arranged on the top of the building body 200 , so that one end of the sloping roof module 3 away from the gutter module 2 is overlapped or connected to the roof covering layer 6 .
[0098] With such arrangement, the roof covering layer 6 covers and protects the top of the building body 200 .
[0099] In this embodiment, the eaves structure 100 is first installed on the building body 200, and then the roof covering layer 6 is set. In other embodiments, the order of construction can also be changed. The roof covering layer 6 is first set on the top of the building body 200, and then the eaves structure 100 is installed. The specific order can be determined according to actual conditions.
[0100] Optionally, the roof covering layer 6 is a waterproof layer to prevent rainwater and snow water from penetrating into the interior of the building body 200.
[0101] Optionally, the roof covering layer 6 is a thermal insulation layer to provide thermal insulation and reduce energy consumption.
[0102] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.
Claims
1. The construction method of cornice installation is characterized in that: Used for installing an eaves structure (100) to an eaves installation position (210) of a building main body (200), the eaves structure (100) comprising an eaves and ceiling combination module (1), a gutter module (2) and a sloping roof module (3); the eaves installation construction method comprises: Prefabricating and assembling the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) on the ground; The eaves and ceiling combination module (1) is lifted to the eaves installation position (210) by means of a lifting device, and the eaves and ceiling combination module (1) is fixedly connected to the bottom (211) of the eaves installation position (210); The gutter module (2) is lifted by a lifting device to be close to the eaves and ceiling combination module (1), so that the gutter module (2) is connected to the gutter groove reserved on the eaves and ceiling combination module (1); The sloping roof module (3) is lifted to the eaves installation position (210) by means of a lifting device, the sloping roof module (3) is fixedly connected to the sloping surface (212) of the eaves installation position (210), and one end of the sloping roof module (3) close to the gutter module (2) is connected to the gutter module (2).
2. The method for installing the eaves according to claim 1, characterized in that: The cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) all include a keel structure and a curtain wall structure; when the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) are prefabricated and assembled on the ground, the prefabrication and assembly of any one of the modules specifically includes: Arranging an assembly tire frame (4) on the ground; Assembling and adjusting the keel structure of the module through the assembly frame (4); After the keel structure is assembled, the curtain wall structure is connected to the keel structure; Carry out a comprehensive inspection and test on the assembled modules to ensure that they meet the installation requirements.
3. The construction method for installing the eaves according to claim 2, characterized in that: The curtain wall structure comprises a waterproof layer and a decorative surface layer, and the decorative surface layer is arranged on the outer surface of the keel structure; Connecting the curtain wall structure to the keel structure comprises: After the keel structure is assembled, the waterproof layer is first installed on the keel structure, and then the decorative surface layer is installed on the outer surface of the keel structure.
4. The construction method for installing the eaves according to claim 2 or 3, characterized in that: Before the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) are prefabricated and assembled on the ground, the method further comprises: Model establishment: according to the architectural design drawings, a complete cornice structure model is established, and a collision check is performed to ensure the accurate positioning and coordination of the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3); Further design: Based on the premise of the modular installation of the cornice structure (100), an integrated design of installing the cornice structure (100) to the building main body (200) is performed; Component processing: According to the drawings and requirements of the detailed design, the components of the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) are processed to ensure that each component meets the design specifications and quality requirements.
5. The method for installing the eaves according to claim 4, characterized in that: Assembling and adjusting the keel structure of the module by means of the assembly frame (4) specifically includes: Combined with the eaves structure model, the keel structure is measured and adjusted using three-dimensional scanning technology.
6. The method for installing the cornice according to claim 4, characterized in that: After the keel structure of the module is assembled and adjusted by the assembly frame (4), the method further comprises: Performing error measurement on the building body (200); According to the assembly status of the keel structure and the error measurement result of the building main body (200), combined with the eaves structure model, a three-dimensional scanning technology is used to check and debug the connector (5) of the module, wherein the connector (5) is used to connect the module to the building main body (200).
7. The method for installing the cornice according to claim 6, characterized in that: In the process of installing the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) to the building body (200), three-dimensional scanning technology is used to coordinately control the fixed points of the connecting parts (5) one by one.
8. The method for installing the cornice according to claim 1, characterized in that: After the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) are all installed on the building body (200), the method further comprises: The joints are waterproofed and decorated.
9. The method for installing the cornice according to claim 1, characterized in that: After the cornice and ceiling combination module (1), the gutter module (2) and the sloping roof module (3) are all installed on the building body (200), the method further comprises: A roof covering layer (6) is arranged on the top of the building body (200), so that an end of the sloping roof module (3) away from the gutter module (2) is overlapped or connected to the roof covering layer (6).
10. The method for installing the eaves according to claim 9, characterized in that: The roof covering layer (6) is a waterproof layer.
Citation Information
Patent Citations
Construction method for modular prefabrication and interval hoisting of arc-shaped cornice
CN113503030A
Construction method for double-curved-surface cornice keel of station building project
CN115434515A
Roof cornice keel unitization hoisting method
CN116517312A
Modularized assembling construction method for large-span multi-curvature deformed steel truss roof
CN116677201A
Metal roof and gutter lap joint structure
CN218933635U