Assembly system

By designing the blank assembly system, including the plate-up machine, glue-dropper machine and layered conveying device, the problems of unstable adsorption and low glue-dropping quality in the plate-based blank production line are solved, and the rapid, precise bonding and efficient production of the plate are achieved. .

CN119217482AActive Publication Date: 2024-12-31SHANDONG CHANGXING WOOD MACHINERY CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202411500411.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-25
Publication Date
2024-12-31
Estimated Expiration
2044-10-25

AI Technical Summary

Technical Problem

In the existing plate blank production line, the adsorption of the loading conveyor device is unstable, the conveying efficiency is low, and the equipment adaptability is poor, resulting in low bonding quality.

Method used

A blank-assembly system is designed, including a plate-up machine for conveying and adsorbing plates, a glue-spraying machine for spraying glue liquid, a layered conveying device and a receiving conveying device, using a liftable and lowered glue-separated box and a uniformly distributed drain. The glue holes, combined with the flow guide and grid plate, ensure precise control and even distribution of the glue liquid, and improve adsorption stability through shock absorbing components.

Benefits of technology

The rapid and precise bonding of the plate is achieved, the consistency of production efficiency and bonding quality is improved, the production cost is reduced, and the vibration of the equipment is reduced through shock absorbing components, which improves stability and reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119217482A_ABST
    Figure CN119217482A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of plate processing, and particularly discloses an assembly system which comprises a first adsorption plate feeding machine used for conveying a first layer plate, a second adsorption plate feeding machine used for conveying a second layer plate, a glue spraying machine used for spraying a glue solution, and a first conveying device used for conveying plates for glue spraying. The layering conveying device is used for separating and conveying a first layer plate and a second layer plate, the bearing conveying device is used for bearing the first layer plate and the second layer plate, and the third adsorption plate feeding machine is used for conveying a third layer plate; the first adsorption plate feeding machine and the second adsorption plate feeding machine transfer plates to the first conveying device, the plates are sprayed through the glue spraying machine and conveyed to the bearing conveying device in a layered mode through the layering device to be preliminarily bonded, the third adsorption plate feeding machine adsorbs non-glue plates to the upper side of the third adsorption plate feeding machine to complete final bonding, and the production efficiency and the quality stability are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of plate processing, and in particular relates to an assembly system. Background Art

[0002] In existing sheet assembly production lines, the loading and conveying devices often have problems such as unstable adsorption of non-adhesive sheets, low conveying efficiency, and poor equipment adaptability.

[0003] Although there are cases of adsorbing plates for transportation, the suction cups on the adsorption components are unevenly distributed, resulting in uneven distribution of adsorption force, which further reduces the stability and reliability of adsorption of non-glue plates; and the glue head design of traditional glue spraying machines is often not precise enough, and the distribution of glue spraying holes is not uniform, resulting in uneven distribution of glue on the material, discontinuous glue lines, and affecting the quality of glue spraying. Finally, under the influence of various factors, the quality of the plate bonding assembly is low. Summary of the invention

[0004] In view of the problem that the quality of sheet bonding assembly in the prior art needs to be improved, a system for assembling sheets is now proposed. The present invention provides the following technical solutions: A blank assembly system, comprising A first adsorption board loading machine for conveying the first layer of boards; A second adsorption board loading machine for conveying the second layer of boards; Glue spraying machine for spraying glue liquid; A first conveying device for conveying a plate for glue spraying; A layered conveying device for separating and conveying a first layer of boards and a second layer of boards; A receiving and conveying device for receiving the first layer of boards and the second layer of boards; The third adsorption board loading machine for conveying the third layer of boards; The first adsorption loading machine and the second adsorption loading machine transfer the plate to the first conveying device, which is sprayed by the glue spraying machine and conveyed in layers to the receiving conveying device through the layering device for preliminary bonding. The third adsorption loading machine then adsorbs the glue-free plate to its upper side to complete the final bonding.

[0005] Preferably, it also includes a stacking machine for receiving the boards and the non-glue boards after preliminary bonding, and the stacking machine includes a stacking lifting mechanism and a stacking conveying mechanism arranged on the stacking lifting mechanism.

[0006] Preferably, the first adsorption loading machine includes a first frame, a first linear drive device and a first negative pressure pump, the frame is fixedly connected to a first guide rail extending in a front-to-rear direction, and the first guide rail is slidably connected to a first mounting frame; the first mounting frame is rotatably connected to first rollers on both sides, and the first rollers are in rolling contact with the first guide rail; a first lifting drive device is installed on the mounting frame, and the output end of the lower side of the first lifting drive device is fixedly connected to a first suction plate assembly, the first suction plate assembly includes a first fixed bracket and a first suction plate unit, the first fixed bracket is arranged in a rectangular shape, and the first suction plate unit is arranged in a rectangular shape on the first fixed bracket; the first suction plate unit includes a first suction pipe and a first suction cup, the first suction pipe is installed and connected to the first mounting frame, the lower side of the first suction pipe is connected to the first suction cup, and the upper side of the first suction pipe is connected to the first negative pressure pump through a first connecting pipe.

[0007] Preferably, a rotating rod and a shock absorbing assembly are provided at the lower side of the first mounting frame, and the shock absorbing assembly includes a bushing, a guide rod, a shock absorbing spring and a spring seat, the spring seat is fixedly mounted on the first mounting frame, the first roller is connected to the end of the rotating rod, the bushing is sleeved on the middle part of the rotating rod, the guide rod is fixedly mounted on the bushing, the shock absorbing spring is sleeved outside the guide rod and the upper end is connected to the spring seat, and the upper end of the shock absorbing spring is connected to the spring seat.

[0008] Preferably, the third adsorption loading machine includes a third frame, a conveying support device for conveying the glue-free board and a traveling vehicle for driving the glue-free board forward, the traveling vehicle moves back and forth above the third frame, the conveying support device is arranged at the lower side of the traveling vehicle, the traveling vehicle is connected with an adsorption assembly under the first lifting device, the adsorption assembly is installed with a third longitudinal plate lifting device and is connected with a drop plate pressing plate assembly for unloading through the third longitudinal plate lifting device.

[0009] Preferably, the adsorption assembly includes a ventilation pipe and a suction cup for connecting to an external air source, the suction cup is in communication with the ventilation pipe, and each adsorption assembly includes at least two ventilation pipes, and the ventilation pipes are arranged parallel to each other.

[0010] Preferably, each ventilation pipe is extended left and right, and each ventilation pipe is commonly connected to a third longitudinal plate, and the third longitudinal plates are symmetrically arranged on both sides of the ventilation pipe; a guide mounting plate and a push material lifting mounting plate are connected between the two third longitudinal plates, and the third longitudinal plate lifting device is installed and connected to the push material lifting mounting plate.

[0011] Preferably, the glue spraying machine includes a fourth frame, on which a glue spraying conveying device and an installation box are installed, the installation box is mounted on the glue spraying conveying device, a lifting drive device is arranged in the installation box, the lifting drive device is driven and connected with a lifting connecting piece, the lower end of the lifting connecting piece is connected with a glue dispensing box for storing glue liquid, a colloid pump is installed on the glue dispensing box, a glue spraying head is detachably connected to the bottom of the glue dispensing box, the glue dispensing box is connected with the glue spraying head, and a plurality of rows of glue spraying holes are evenly distributed on the bottom of the glue spraying head.

[0012] Preferably, a guide head for assisting the glue liquid to connect into a line is detachably connected under the glue spraying hole; a liquid collecting port is arranged above the guide head, and a glue outlet is arranged below the guide head; the liquid collecting port and the glue outlet are connected to form a glue collecting cavity.

[0013] Preferably, a grid plate for uniformly distributing the glue liquid is installed in the glue collecting chamber, and the grid plate is provided with grid holes, and the width of the grid holes is smaller than the diameter of the glue spraying hole.

[0014] Compared with the prior art, the present invention has the following beneficial effects: 1. Through the automated assembly system, the rapid and accurate bonding of the panels is achieved, which reduces manual operations, improves production efficiency, and ensures the consistency of bonding quality; 2. The glue spraying machine adopts a liftable glue dispensing box and evenly distributed glue spraying holes, combined with a guide head and a grid plate, to achieve precise control and even distribution of the glue liquid, improve glue spraying quality, and reduce production costs; 3. The first suction plate assembly and the shock-absorbing assembly are used to improve the stability of adsorption and reduce vibration during movement, thereby improving the stability and reliability of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 This is a schematic diagram of the overall structure of the first adsorption loading machine; Figure 3 It is a schematic diagram of the specific structure of the first adsorption board loading machine; Figure 4 This is a front view structural diagram of the glue spraying machine; Figure 5 It is a three-dimensional structural diagram of the glue spraying machine; Figure 6 It is a front view structural diagram of the guide head of the glue spraying machine; Figure 7 It is a schematic diagram of the cross-section structure of the guide head of the glue spraying machine; Figure 8 It is a three-dimensional structural schematic diagram of the layered conveying device; Fig. 9It is a three-dimensional structural diagram of the third adsorption loading machine; Fig.10 This is a schematic diagram of the specific structure of the third adsorption loading machine; In the accompanying drawings, 1. First adsorption board loading machine; 11. First frame; 12. First linear drive device; 121. First servo motor; 122. First pulley; 123. First belt; 13. First guide rail; 14. First negative pressure pump; 15. First mounting frame; 16. First roller; 17. First lifting drive device; 171. First drive cylinder; 172. First output rod; 173. First guide sub-rod; 18. First suction plate assembly; 181. First fixed bracket; 1811. First horizontal plate; 1812. First vertical plate; 182. First suction plate unit; 1821. First suction pipe; 1822. First suction cup; 19. First distance sensor; 110. First limit plate; 2. The second adsorption board loading machine; 3. A first conveying device; 4. Glue spraying machine; 41. Fourth frame; 42. Glue spraying conveying device; 421. Glue spraying conveying driving motor; 422. Active shaft; 423. First driven shaft; 424. Second driven shaft; 425. Third driven shaft; 426. Glue spraying belt wheel; 427. Glue spraying belt body; 43. Lifting connecting piece; 44. Installation box; 45. Glue dispensing pipe; 451. Liquid inlet pipe; 452. Liquid dispensing pipe; 453. Connecting pipe; 46. Glue dispensing box; 47. Glue spraying head; 48. Collection bin; 481. Support plate; 49. Glue return filtering device; 491. Material collecting hopper; 492. Plate net; 4921. Silk screen; 493. Material return pipe; 410. Guide head; 4101. Buckle; 4102. Installation platform; 4103. Liquid collecting port; 4104. Glue outlet; 411. Grid plate; 5. Layered conveying device; 51. Lower conveyor belt; 52. Upper rear conveyor belt; 53. Upper front conveyor belt; 54. Layered mounting frame; 55. Upper lifting device; 56. Upper hinged support device; 6. Undertake conveying device; 7. Stacking machine; 8. Conveyor platform; 9. The third adsorption loading machine; 91. The third frame; 92. The conveying support device; 93. The traveling vehicle; 931. The frame; 932. The traveling drive motor; 933. The driving shaft; 934. The traveling wheel; 94. The first lifting device; 95. The third longitudinal plate lifting device; 96. The adsorption assembly; 961. The ventilation pipe; 962. The third suction cup; 97. The drop plate pressing plate assembly; 971. The H-shaped bracket; 972. The push rod; 98. The glue-free plate; 991. The left support rod; 992. The right support rod; 910. The loading rack; 911. The third longitudinal plate; 912. The guide mounting plate; 913. The pusher lifting mounting plate; 914. The lifting connecting frame. DETAILED DESCRIPTION

[0016] In order to enable those skilled in the art to better understand the technical solution of the present invention, the technical solution of the present invention is clearly and completely described below in conjunction with the accompanying drawings of the present invention. The directional words mentioned in the following embodiments, such as "up", "down", "left" and "right", etc., are only reference to the directions of the accompanying drawings. Therefore, the directional words used are used to illustrate rather than limit the invention.

[0017] Example 1 like Figure 1 As shown, a blank assembly system includes The first adsorption board loading machine 1 is used to convey the first layer of boards; specifically, the first layer of boards is a vertical grain veneer; The second adsorption board loading machine 2 is used to convey the second layer of boards; specifically, the second layer of boards is a horizontally striped single board; The glue spraying machine 4 is used for spraying glue liquid; the glue spraying machine 4 sprays glue on the upper board surface of the first layer board and the second layer board; A first conveying device 3, used for conveying the plate for glue spraying; A layered conveying device 5, used for separating and conveying the first layer of boards from the second layer of boards; A receiving and conveying device 6, used for receiving the first layer of boards and the second layer of boards; The third adsorption board loading machine 9 is used to convey the third layer of boards; specifically, the third layer of boards is a non-glue board 98; The first adsorption loading machine 1 and the second adsorption loading machine 2 transfer the plate to the first conveying device 3, which is sprayed by the glue spraying machine 4 and conveyed in layers to the receiving conveying device 6 through the layering device for preliminary bonding. The third adsorption loading machine 9 then adsorbs the glue-free plate 98 to its upper side to complete the final bonding, thereby improving production efficiency and quality stability.

[0018] Preferably, it also includes a stacking machine 7 for receiving the boards and the non-glue boards 98 after preliminary bonding. The stacking machine 7 includes a stacking lifting mechanism and a stacking conveying mechanism arranged on the stacking lifting mechanism. The first layer of boards is first moved to the stacking conveying mechanism, and then the second layer of boards is moved to the first layer of boards. Subsequently, the non-glue board 98 is moved to the second layer of boards by the third adsorption loading machine 9 to complete a board product. During this process, it is lowered by the stacking lifting mechanism, and then cyclically stacked, and the board product is horizontally moved to the outer conveying table 8 for unloading by the stacking conveying mechanism, which reduces manual operation and improves the overall production efficiency.

[0019] like Figure 2 and Figure 3 As shown, the first adsorption loading machine 1 includes a first frame 11, a first linear drive device 12 and a first negative pressure pump 14, the first frame 11 is fixedly connected with a first guide rail 13 extending in the front-to-back direction, and the first mounting frame 15 is slidably connected with the first guide rail 13; the first mounting frame 15 is rotatably connected with first rollers 16 on both sides, and the first rollers 16 are in rolling contact with the first guide rail 13, which reduces friction resistance and improves movement efficiency; the first mounting frame 15 is installed with a first lifting drive device 17, and the output end of the lower side of the first lifting drive device 17 is fixedly connected with a first suction plate assembly 18, and the first suction plate assembly 18 includes a first fixed bracket 181 and a first suction plate unit 182, the first fixed bracket 181 is arranged in a rectangular shape, and the first suction plate unit 182 is arranged in a rectangular shape on the first fixed bracket 181, ensuring stable adsorption of materials such as veneer; the first suction plate unit 182 includes a first suction pipe 1821 and a first suction cup 1822, the first suction pipe 1821 is installed and connected to the installation frame, the lower side of the first suction pipe 1821 is connected to the first suction cup 1822, and the upper side of the first suction pipe 1821 is connected to the first negative pressure pump 14 through the connecting pipe 453, thereby realizing adsorption of materials such as veneer, and after adsorption, it can be lifted and lowered by the first lifting drive device 17, and then transversely transferred by the first linear drive device 12, with stable structure and low cost.

[0020] Furthermore, the first lifting drive device 17 includes a first driving cylinder 171, a first output rod 172 and a first guide sub-rod 173. A guide plate is fixedly connected to the first mounting frame 15, and a guide hole is provided on the guide plate. The first driving cylinder 171 is installed and connected to the guide plate, and the first guide sub-rod 173 is fixedly connected to the first fixed bracket 181; the first output rod 172 is slidably connected to the guide hole up and down, ensuring the stability and accuracy of the lifting action.

[0021] Furthermore, the first fixed bracket 181 includes a first transverse plate 1811 and a first longitudinal plate 1812, the first transverse plate 1811 is extended left and right, the first longitudinal plate 1812 is extended front and back, the first transverse plate 1811 and the first longitudinal plate 1812 are vertically connected, the end of the first transverse plate 1811 extends out of the first longitudinal plate 1812, and the first suction plate unit 182 is also installed at the position extending out of the first longitudinal plate 1812, so that the first suction plate assembly 18 is more stable and can more flexibly adapt to materials such as veneers of different sizes.

[0022] Furthermore, a first distance sensor 19 for detecting the position of the veneer is vertically fixedly connected to the first mounting frame 15, which can monitor the position of the veneer in real time, ensure the accurate adsorption of the first suction cup 1822, and improve work efficiency and accuracy.

[0023] Furthermore, the first lifting drive device 17 adopts a cylinder; the first linear drive device 12 includes a first servo motor 121, a first pulley 122 and a first belt 123, the first belt 123 is arranged parallel to the first guide rail 13 and connected to the first mounting frame 15, and the smooth movement and precise positioning of the first mounting frame 15 are achieved through the precise control of the first servo motor 121.

[0024] Furthermore, first limit plates 110 are provided at the front and rear ends of the first frame 11, which can be used to limit the maximum movement range of the first mounting frame 15, ensure its movement range and safety on the first guide rail 13, and improve the reliability and safety of the equipment.

[0025] The second adsorption loading machine 2 is arranged in an analogous manner to the first adsorption loading machine 1, and includes a second frame, a second linear drive device and a second negative pressure pump, the second frame is fixedly connected with a second guide rail extending in the front-to-back direction, and the second mounting frame is slidably connected with the second guide rail; second rollers are rotatably connected with second mounting frames on both sides, and the second rollers are in rolling contact with the second guide rails, which reduces friction resistance and improves movement efficiency; a second lifting drive device is installed on the second mounting frame, and a second fixed bracket is fixedly connected with the output end of the lower side of the second lifting drive device, the second fixed bracket includes a second fixed bracket and a second suction plate unit, the second fixed bracket is arranged in a rectangular shape, and the second suction plate unit is arranged in a rectangular shape on the second fixed bracket, ensuring stable adsorption of materials such as veneer; the second suction plate unit includes a second suction pipe and a second suction cup, the second suction pipe is installed and connected to the mounting frame, the lower side of the second suction pipe is connected to the second suction cup, and the upper side of the second suction pipe is connected to the second negative pressure pump through a pipe fitting.

[0026] like Fig. 9 and Fig.10As shown, the third adsorption loading machine 9 includes a third frame 91, a conveying support device 92 for conveying the glue-free plate 98 and a traveling vehicle 93 for driving the glue-free plate 98 forward, the traveling vehicle 93 moves back and forth above the third frame 91, the conveying support device 92 is arranged at the lower side of the traveling vehicle 93, the traveling vehicle 93 is connected with an adsorption assembly 96 through a first lifting device 94, the adsorption assembly 96 is installed with a third longitudinal plate 911 lifting device 95 and is connected with a drop plate pressing plate assembly 97 for unloading through the third longitudinal plate 911 lifting device 95, and two adsorption assemblies 96 are arranged side by side under the traveling vehicle 93, which realizes the material suction and lifting, lateral transfer and downward pushing to release the glue-free plate 98, thereby improving the continuity, efficiency and stability.

[0027] Specifically, the first lifting device 94 and the third longitudinal plate 911 lifting device 95 both use cylinders.

[0028] Specifically, the adsorption component 96 includes a ventilation pipe 961 and a third suction cup 962 for connecting to an external air source. The third suction cup 962 is communicated with the ventilation pipe 961. Each adsorption component 96 includes two ventilation pipes 961. The ventilation pipes 961 are arranged parallel to each other, ensuring uniform distribution of adsorption force, effectively avoiding slipping or deviation of the glue-free plate 98 during transportation, and improving the stability and accuracy of transportation.

[0029] Specifically, a plurality of third suction cups 962 are arranged on each ventilation pipe 961 , and the third suction cups 962 are arranged at equal intervals. Each third suction cup 962 can play its role, thereby improving the adsorption efficiency and further enhancing the adsorption stability of the glue-free plate 98 .

[0030] Specifically, each ventilation pipe 961 is extended left and right, and each ventilation pipe 961 is commonly connected to a third longitudinal plate 911. The third longitudinal plates 911 are symmetrically arranged on both sides of the ventilation pipe 961, which enhances the overall stability of the adsorption assembly 96 and facilitates subsequent maintenance.

[0031] Specifically, a guide mounting plate 912 and a push material lifting mounting plate 913 are connected between the two third longitudinal plates 911. The third longitudinal plate 911 lifting device 95 is installed and connected to the push material lifting mounting plate 913 to flexibly adjust the height of the drop plate pressure plate assembly 97 to adapt to the processing requirements of non-glue plates 98 of different thicknesses and sizes, and perform suction and lifting and lowering and releasing operations, thereby improving the versatility and flexibility of the equipment.

[0032] Specifically, a lifting connection frame 914 is installed on the third longitudinal plate 911, and the output end of the first lifting device 94 is connected to the lifting connection frame 914, and the third longitudinal plate 911 and the adsorption assembly 96 are driven to lift and lower through the lifting connection frame 914; a guide shaft is also installed on the guide mounting plate 912, and a guide cylinder is installed on the traveling vehicle 93. The guide shaft and the guide cylinder are connected for up and down sliding. A shock-absorbing spring is connected between the auxiliary lifting frame and the guide mounting plate 912 to improve the stability of lifting and lowering.

[0033] Specifically, the drop plate pressure plate assembly 97 includes an H-shaped bracket 971 and a push rod 972 connected to the front and rear ends of the H-shaped bracket 971, the push rod 972 and the H-shaped bracket 971 are connected flush, the third longitudinal plate 911 lifting device 95 is connected to the middle part of the H-shaped bracket 971, and the push rod 972 is arranged between two adjacent ventilation pipes 961 of the same adsorption assembly 96, so that the drop plate pressure plate assembly 97 can smoothly and accurately descend and press the non-glue plate 98, thereby realizing the unloading operation of the non-glue plate 98 and avoiding damage to the non-glue plate 98 or equipment failure caused by improper unloading.

[0034] Specifically, the traveling vehicle 93 includes a frame 931, a traveling drive motor 932, a driving shaft 933, and a traveling wheel 934. The traveling drive motor 932 on the third frame 91 is installed on the upper side of the third frame 91 and is driven and connected to the driving shaft 933. The driving shaft 933 is rotatably connected to the frame 931 and the end is connected to the traveling wheel 934. A guide wheel is installed on the frame 931. The rotating shaft of the guide wheel is vertically arranged and abuts against the lateral side wall of the third frame 91, thereby ensuring the stability and accuracy of the traveling vehicle 93 during the movement, and reducing equipment failures and damage to the non-glue board 98 caused by offset or jamming.

[0035] Specifically, the third frame 91 includes a support frame and a traveling frame arranged on the upper side of the support frame, the traveling frame includes a left support rod 991 and a right support rod 992 arranged in parallel with a left and right interval, a traveling channel is formed between the left support rod 991 and the right support rod 992, and the right side wall of the left support rod 991 and the left side wall of the right support rod 992 are both abutted with guide wheels, so that the traveling vehicle 93 can move stably and straight.

[0036] Specifically, a loading rack 910 is connected to the front side of the support frame, and the upper end of the loading rack 910 is connected to the left support rod 991 and the right support rod 992. The driving channel extends to the top of the loading rack 910, so that the traveling vehicle 93 shell moves horizontally to the loading rack 910 to adsorb the non-glue plate 98 for loading, and then moves horizontally to the support frame, and then drives the drop plate pressure plate assembly 97 to push the sucked non-glue plate 98 downward through the third longitudinal plate 911 lifting device 95, so that the non-glue plate 98 can be released to the third conveying device on the lower side, and then the non-glue plate 98 is conveyed to the upper side of the second layer of the board through the third conveying device.

[0037] like Figure 4 and Figure 5 As shown, the glue spraying machine 4 includes a fourth frame 41, on which a glue spraying conveying device 42 and an installation box 44 are installed. The installation box 44 is mounted on the glue spraying conveying device 42, and a lifting drive device is arranged in the installation box 44. The lifting drive device is driven and connected with a lifting connection member 43, and the lower end of the lifting connection member 43 is connected with a glue dispensing box 46 for storing glue liquid, and a colloid pump is installed on the glue dispensing box 46. The bottom of the glue dispensing box 46 is detachably connected with a glue spraying head 47 through a buckle 4101, and the glue dispensing box 46 is connected with the glue spraying head 47. The bottom of the glue spraying head 47 is evenly distributed with multiple rows of glue spraying holes, and the glue spraying holes in each row are arranged at equal intervals on the same axis. A continuous and uniform glue line can be formed through the glue spraying holes, thereby improving the glue spraying quality. The glue spraying process can accurately control the height and flow rate of the glue liquid, improve the uniformity and efficiency of the glue spraying, and at the same time, the detachable connection structure facilitates the maintenance and replacement of the glue spraying head 47, thereby increasing the flexibility and service life of the equipment.

[0038] Specifically, the lifting drive device can be a cylinder, and the lifting connection member 43 can be a strip steel plate.

[0039] Furthermore, the glue dispensing box 46 is connected to a glue dispensing pipe 45, which includes a liquid inlet pipe 451, a liquid dispensing pipe 452 and a connecting pipe 453 from top to bottom, and the connecting pipe 453 is connected to the glue dispensing pipe 45; the liquid inlet pipe 451 is centrally arranged and passes upward through the installation box 44, which can play a guiding role and improve the stability of lifting and lowering.

[0040] Furthermore, the glue spraying conveying device 42 includes a glue spraying conveying drive motor 421 fixedly connected to the fourth frame 41 and an active shaft 422, a first driven shaft 423, a second driven shaft 424, and a third driven shaft 425 rotatably connected to the fourth frame 41. The glue spraying conveying drive motor 421 is transmission-connected to the active shaft 422. The active shaft 422, the first driven shaft 423, the second driven shaft 424, and the third driven shaft 425 are sleeved with a glue spraying belt wheel 426, and a glue spraying belt body 427 is cooperated with the glue spraying belt wheel 426. The glue spraying conveying device 42 is stable and reliable, can efficiently convey materials, and ensures the continuity of the glue spraying process.

[0041] Furthermore, the conveyor belt is enclosed to form a middle installation space, in which a collection bin 48 is arranged, a collection and discharge pipe is arranged at the bottom of the collection bin 48, and a driving shaft 422, a first driven shaft 423, a second driven shaft 424, and a third driven shaft 425 are arranged outside the collection bin 48; a plurality of support plates 481 are fixedly connected to the upper side of the collection bin 48, and the support plates 481 are arranged horizontally and parallelly along the upper end of the glue-spraying belt body 427, and the length direction of the support plates 481 is parallel to the conveying direction, which can provide stable support for the veneer and ensure a high degree of smoothness. At the same time, the collection bin 48 can effectively collect excess glue and dropped glue, reduce cleaning work, and improve the cleanliness of the working environment.

[0042] Furthermore, a return glue filtering device 49 is installed at the lower part of the fourth frame 41, and the return glue filtering device 49 includes a receiving hopper 491, and a return pipe 493 is connected to the lower part of the receiving hopper 491. A plate net 492 is installed in the receiving hopper 491, and the plate net 492 is tilted. A wire mesh 4921 is arranged at the lower corner of the plate net 492, and a filter is arranged above the return pipe 493 to effectively filter out impurities and ensure the quality of the glue liquid. A discharge valve is installed on the return pipe 493, and the return pipe 493 can be connected to the colloid pump through a pipeline to the outside, so as to realize the recycling of the glue liquid and reduce the production cost.

[0043] like Figure 8 As shown, the layered conveying device 5 includes a lower conveyor belt 51, an upper rear conveyor belt 52, an upper front conveyor belt 53, a layered mounting frame 54, an upper lifting device 55, and an upper hinge device 56; the front side of the upper rear conveyor belt 52 is hinged to the layered mounting frame 54, and the front side is flipped and fixed in the flipped state through the upper lifting device 55, and the upper hinge device 56 provides auxiliary support, thereby realizing flipping and docking transmission, and realizing layered conveying.

[0044] Example 2 Further, such as Figure 6 and Figure 7 As shown, on the basis of Example 1, a guide head 410 for assisting the glue liquid to connect into a line is detachably connected under the glue spraying hole. The guide head 410 can be connected to the glue spraying hole through an elastic buckle 4101 or other devices. The guide head 410 can further ensure the continuity and uniformity of the glue liquid in forming the glue line, thereby improving the glue spraying quality.

[0045] Furthermore, a liquid collecting port 4103 is provided above the guide head 410, and a glue outlet 4104 is provided below the guide head 410. The liquid collecting port 4103 and the glue outlet 4104 are connected to form a glue collecting chamber. An installation platform 4102 is provided in the glue collecting chamber, and a grid plate 411 for uniform glue liquid is placed on the installation platform 4102. The grid plate 411 is provided with grid holes, and the width of the grid holes is smaller than the diameter of the glue spraying hole; further, a plurality of installation platforms 4102 are provided, and the side walls of the glue collecting chamber are arranged in an arc shape, and the corresponding grid plates 411 gradually decrease in width from top to bottom, and the specifications of the grid holes gradually decrease. The design of the glue collecting chamber helps to concentrate the glue liquid, and the grid plate 411 can further refine the glue liquid so that it is more evenly distributed on the first layer or the first layer, thereby improving the uniformity of glue spraying; the glue liquid is refined so that it is more evenly distributed on the material, thereby improving the glue spraying effect.

[0046] During glue spraying, the material is first transported and positioned, and the material is transported by the glue spraying conveying device 42. After the material is transported to the top of the glue spraying head 47, the glue dispensing box 46 is driven to the corresponding height by the lifting drive device; during glue spraying, the colloid pump pumps the glue liquid to make the glue liquid flow out from the glue spraying hole of the glue spraying head 47 and form a thick glue line, and then after passing through the glue collecting cavity of the guide head 410 and the grid plate 411 in the glue collecting cavity and being converged and uniformed, the glue line becomes a uniform glue curtain, and then the glue curtain is lowered to the first layer of board or the first layer of board by the lifting drive device; at the same time, the colloid pump is used to prevent the glue liquid from continuing to flow downward, and the glue liquid is collected by the receiving hopper 491 and the collecting bin 48 and filtered and reused.

[0047] Example 3 On the basis of Example 1 or Example 2, further, a rotating rod and a shock absorbing assembly are arranged on the lower side of the first mounting frame 15, and the shock absorbing assembly includes a bushing, a guide rod, a shock absorbing spring and a spring seat, and the spring seat is fixedly installed on the first mounting frame 15, the first roller 16 is connected to the end of the rotating rod, the bushing is sleeved in the middle of the rotating rod, the guide rod is fixed on the bushing, the shock absorbing spring is sleeved outside the guide rod and the upper end is connected to the spring seat, and the upper end of the shock absorbing spring is connected to the spring seat, which effectively reduces the vibration during the movement and improves the stability and service life of the equipment.

[0048] Furthermore, the rotating rods are arranged symmetrically front and back about the first mounting frame 15, and the shock absorbing components are arranged symmetrically left and right on each rotating rod, which further enhances the shock absorbing effect and improves the stability and reliability of the equipment.

Claims

1. A blank assembly system, characterized in that: include A first adsorption loading machine (1) for conveying a first layer of boards; A second adsorption loading machine (2) for conveying a second layer of boards; A glue spraying machine (4) for spraying glue liquid; A first conveying device (3) for conveying a plate for glue spraying; A layered conveying device (5) for separating and conveying a first layer of board and a second layer of board; A receiving and conveying device (6) for receiving the first layer of boards and the second layer of boards; A third adsorption board loading machine (9) for conveying a third layer of boards; The first adsorption loading machine (1) and the second adsorption loading machine (2) transfer the plate to the first conveying device (3), where they are sprayed by the glue spraying machine (4) and conveyed in layers to the receiving conveying device (6) through the layering device for preliminary bonding. The third adsorption loading machine (9) then adsorbs the glue-free plate (98) to its upper side to complete the final bonding.

2. The assembly system according to claim 1, characterized in that: It also includes a stacking machine (7) for receiving the preliminarily bonded plates and the non-adhesive plates (98), wherein the stacking machine (7) includes a stacking lifting mechanism and a stacking conveying mechanism arranged on the stacking lifting mechanism.

3. The assembly system according to claim 1, characterized in that: The first adsorption board loading machine (1) comprises a first frame (11), a first linear drive device (12) and a first negative pressure pump (14); the frame is fixedly connected to a first guide rail (13) extending in the front-rear direction; the first guide rail (13) is slidably connected to a first mounting frame (15); first rollers (16) are rotatably connected to both sides of the first mounting frame (15); the first rollers (16) are in rolling contact with the first guide rail (13); a first lifting drive device (17) is installed on the mounting frame; the output end at the lower side of the first lifting drive device (17) is fixedly connected to a first suction plate assembly (18); the first A suction plate assembly (18) comprises a first fixed bracket (181) and a first suction plate unit (182), wherein the first fixed bracket (181) is arranged in a rectangular shape, and the first suction plate unit (182) is arranged in a rectangular shape on the first fixed bracket (181); the first suction plate unit (182) comprises a first suction pipe (1821) and a first suction cup (1822), wherein the first suction pipe (1821) is installed and connected to a first installation frame, the lower side of the first suction pipe (1821) is connected to the first suction cup (1822), and the upper side of the first suction pipe (1821) is connected to a first negative pressure pump (14) via a first connecting pipe (453).

4. The blank assembly system according to claim 3, characterized in that: A rotating rod and a shock absorbing assembly are arranged at the lower side of the first mounting frame (15), the shock absorbing assembly comprising a shaft sleeve, a guide rod, a shock absorbing spring and a spring seat, the spring seat being fixedly mounted on the first mounting frame (15), the first roller (16) being connected to the end of the rotating rod, the shaft sleeve being sleeved on the middle of the rotating rod, the guide rod being fixedly mounted on the shaft sleeve, the shock absorbing spring being sleeved outside the guide rod and having its upper end connected to the spring seat, and the upper end of the shock absorbing spring being connected to the spring seat.

5. The assembly system according to claim 1, characterized in that: The third adsorption loading machine (9) comprises a third frame (91), a conveying support device (92) for conveying the adhesive-free plate (98) and a traveling vehicle (93) for driving the adhesive-free plate (98) forward, the traveling vehicle (93) moving forward and backward above the third frame (91), the conveying support device (92) being arranged at the lower side of the traveling vehicle (93), an adsorption assembly (96) being connected to the lower side of the traveling vehicle (93) via a first lifting device (94), a third longitudinal plate (911) lifting device (95) being installed on the adsorption assembly (96) and a drop plate pressing plate assembly (97) for unloading being connected via the third longitudinal plate (911) lifting device (95).

6. The blank assembly system according to claim 5, characterized in that: The adsorption assembly (96) comprises a ventilation pipe (961) for connecting to an external air source and a suction cup, wherein the suction cup is in communication with the ventilation pipe (961), and each adsorption assembly (96) comprises at least two ventilation pipes (961), and the ventilation pipes (961) are arranged parallel to each other.

7. The blank assembly system according to claim 6, characterized in that: Each ventilation pipe (961) is extended to the left and right, and each ventilation pipe (961) is commonly connected to a third longitudinal plate (911). The third longitudinal plates (911) are symmetrically arranged on both sides of the ventilation pipe (961); a guide mounting plate (912) and a pusher lifting mounting plate (913) are connected between the two third longitudinal plates (911), and the third longitudinal plate (911) lifting device (95) is installed and connected to the pusher lifting mounting plate (913).

8. The blank assembly system according to claim 1, characterized in that: The glue spraying machine (4) comprises a fourth frame (41), on which a glue spraying conveying device (42) and an installation box (44) are installed, and the installation box (44) is mounted on the glue spraying conveying device (42). A lifting drive device is arranged in the installation box (44), and the lifting drive device is drivingly connected to a lifting connecting member (43), and the lower end of the lifting connecting member (43) is connected to a glue dispensing box (46) for storing glue liquid, and a colloid pump is installed on the glue dispensing box (46). A glue spraying head (47) is detachably connected to the bottom of the glue dispensing box (46), and the glue dispensing box (46) is connected to the glue spraying head (47), and the bottom of the glue spraying head (47) is evenly distributed with a plurality of rows of glue spraying holes.

9. The blank assembly system according to claim 8, characterized in that: A flow guide head (410) for assisting the glue liquid to be connected into a line is detachably connected below the glue spraying hole; a liquid collecting port (4103) is provided above the flow guide head (410), and a glue outlet (4104) is provided below the flow guide head (410); the liquid collecting port (4103) and the glue outlet (4104) are connected to form a glue collecting cavity.

10. The blank assembly system according to claim 9, characterized in that: A grid plate (411) for uniformly distributing the glue liquid is installed in the glue collecting chamber, and grid holes are arranged on the grid plate (411), and the width of the grid holes is smaller than the diameter of the glue spraying hole.

Citation Information

Patent Citations

  • Full-automatic production line for LVL

    CN108748459A

  • Rapid board veneering production line

    CN112776101A

  • Full-automatic household board arranging line

    CN115741911A

  • Wood board surface uniform glue spraying device

    CN116493188A

  • Efficient gluing device for plywood

    CN211137505U