EVA (Ethylene Vinyl Acetate) wool cleaning equipment for lamination treatment of solar panel
By designing a combination of scraping structure and softening thermal spray structure in solar panel lamination treatment, the problem of high difficulty in cleaning EVA wool is solved, and efficient and safe wool is cleaned, suitable for edge and corner positions.
Patent Information
- Application Number
- CN202411661981.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-20
- Publication Date
- 2025-01-03
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Under the traditional cleaning method, the EVA wool in the lamination process of solar panels has a high hardness after curing, which leads to high difficulty in cleaning, consumes a lot of manpower and time, and is prone to scratch damage to the edges of solar panels, especially difficult to operate at corner positions.
A cleaning device including a scraping structure and a softening thermal spray structure is designed. The cured EVA wool is jet-softened by softening the thermal spray structure, and the combined structure of arc-shaped rubber scraper and conveying mesh belt is used to achieve effective scraping of wool. In addition, it is suitable for cleaning the edges and corners of solar panels.
It effectively reduces the difficulty of cleaning wool materials, saves manpower and time, avoids scratches on solar panels, and facilitates the cleaning of corner positions.
Smart Images

Figure CN119237397A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of cleaning equipment, in particular to an EVA wool cleaning equipment for solar panel lamination processing. Background Art
[0002] As we all know, solar panel lamination refers to the process of laminating and bonding glass, EVA, solar panels, EVA and backboard, so that the EVA material melts and bonds the solar panels, glass and backboard to form a complete solar panel. After the EVA melts, it extends outward under pressure to solidify and forms excess hair at the edge of the solar panel, so the excess EVA hair needs to be cleaned. The traditional cleaning method is for workers to directly scrape the hair with a scraper. However, after the hair solidifies, due to its high hardness, it is difficult to scrape and clean, which consumes more manpower and time. At the same time, manual cleaning can easily cause scratches on the edge of the solar panel, and the corners of the solar panel are not easy to operate, making it difficult to clean. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides an EVA wool cleaning device for solar panel lamination processing.
[0004] In order to achieve the above object, the technical solution adopted by the present invention is: EVA wool cleaning equipment for solar panel lamination treatment includes an external fixing box, wherein a scraping structure and a softening hot spraying structure are arranged in the external fixing box, and the softening hot spraying structure is used for performing jet softening treatment on the solidified EVA; The scraping structure comprises two rotating shafts, belt rollers are installed on the rotating shafts, conveyor mesh belts are laid on the outer walls of the two belt rollers, and a plurality of arc-shaped rubber scrapers are obliquely arranged on the outer wall of the conveyor mesh belt. First sliders are rotatably installed at both ends of the rotating shaft, and slide plates are arranged on the upper and lower sides of the conveyor mesh belt. The first slider is slidably installed in the slide plate, and a first leaf spring is installed between the two first sliders in the slide plate; The arc-shaped rubber scraper is inclined in the direction along the rotation direction of the conveyor belt, and the first leaf spring pushes the first slider to contact the end position of the inner wall of the slide plate.
[0005] Further, the softening hot spray structure includes a first air guide bin and two second air guide bins, the two second air guide bins are respectively located at the front and rear sides of the first air guide bin, and the second air guide bin is slidably inserted into the first air guide bin, the first air guide bin is connected to the second air guide bin, and the side walls of the first air guide bin and the side walls of the second air guide bin are both provided with inclined holes, and the inclined holes are inclined downward; A first connecting frame is installed on the second air guide bin, an outer end of the first connecting frame is fixed on the first sliding block, a second connecting frame is installed on the first air guide bin, and the second connecting frame is installed on the slide plate; It also includes an air intake pipe, which is connected and installed on the first air guide bin.
[0006] Furthermore, it also includes a first worm and two first worm wheels, the first worm wheel is installed on the rotating shaft, the two first worm wheels are meshed with the first worm, a third connecting frame is installed in the middle of the first worm, the third connecting frame is rotatably connected with the first worm, and the third connecting frame is fixed to the outer wall of the slide plate, both ends of the first worm are installed with second worm wheels, the second worm wheel is meshed with a second worm, one end of the second worm is rotatably installed on the inner wall of the outer fixed box, and the other end of the second worm is provided with a transmission structure; An elastic supporting structure is arranged in the outer fixing box, and the elastic supporting structure is used to support the scraping structure.
[0007] Further, the transmission structure includes two transmission wheels, which are respectively mounted on the inner wall of the outer fixed box and the end of the second worm, the transmission wheel on the outer fixed box is rotatably connected to the outer fixed box, a sleeve is arranged between the two transmission wheels, one end of the sleeve is mounted on one transmission wheel, and the other end of the sleeve is in sliding contact with the other transmission wheel, a torsion spring is arranged in the sleeve, one end of the torsion spring is fixed on one transmission wheel, and the other end of the torsion spring is fixed on the other transmission wheel.
[0008] Further, the elastic support structure includes a sliding sleeve installed on the outer fixed box, a sliding rod is slidably inserted in the sliding sleeve, a moving plate is installed at the end of the sliding rod located inside the outer fixed box, a second leaf spring is installed on the side wall of the moving plate, and the outer end of the second leaf spring is installed on the inner wall of the outer fixed box; Four insertion rods are installed on the circumferential outer wall of the movable disk. The insertion rods are along the radial direction of the movable disk and are slidably inserted into the movable disk. Two push-pull plates are rotatably installed on the outer ends of the insertion rods. The push-pull plates are inclined, and the outer end of one push-pull plate on the insertion rod is rotatably installed on the outer wall of the slide plate, and the outer end of the other push-pull plate on the insertion rod is rotatably installed on the inner wall of the external fixed box.
[0009] Furthermore, it also includes a collecting bucket, which is installed on the outer wall of the slide plate located on the lower side of the rotating shaft, the opening of the collecting bucket faces upward, an air suction pipe is installed in the collecting bucket, the top of the air suction pipe is set to be conical, and a suction port is opened at the bottom of the air suction pipe.
[0010] Furthermore, two transverse guide slots are provided on the inner side wall of the outer fixed box, a second slider is slidably arranged in the guide slot, and the second slider is rotationally connected to the second worm gear.
[0011] Furthermore, a right-angle bracket is installed on the outer wall of the outer fixing box, and a motor is installed on the right-angle bracket; It also includes three pulleys, one pulley is installed on the output end of the motor, and the remaining two pulleys are respectively connected to the two transmission wheels on the external fixed box, and belts are laid on the three pulleys.
[0012] Compared with the prior art, the beneficial effects of the present invention are as follows: the EVA wool at the edge of the solar panel is softened by the softening hot spray structure, and the softened wool is scraped and cleaned by the scraping structure, thereby effectively reducing the difficulty of cleaning the wool, saving manpower and time, avoiding excessive scraping force and causing scratches and damage to the solar panel, and facilitating the cleaning of the wool at the corner of the solar panel. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0014] Figure 1 It is a schematic diagram of the structure of the present invention; Figure 2 yes Figure 1 Schematic diagram of the left view of the structure of the middle and outer fixed boxes; Figure 3 yes Figure 1 Schematic diagram of the structure of the Chinese and foreign fixed boxes viewed from above; Figure 4 yes Figure 1 Schematic diagram of the cross-sectional structure of the Chinese and foreign fixed boxes; Figure 5 yes Figure 3 Schematic diagram of the right view of the middle casing section; Figure 6 yes Figure 5 The schematic diagram of the local structure at A is shown below; Figure 7 yes Figure 3 Schematic diagram of the enlarged structure of the scraping structure; Figure 8 yes Figure 4 A schematic diagram of the enlarged structure of the medium-softening hot spray structure; Markings in the attached drawings: 1. external fixed box; 2. rotating shaft; 3. belt roller; 4. conveyor belt; 5. arc-shaped rubber scraper; 6. first slider; 7. slide plate; 8. first leaf spring; 9. first air guide bin; 10. second air guide bin; 11. first connecting frame; 12. second connecting frame; 13. air inlet pipe; 14. first worm gear; 15. first worm; 16. third connecting frame; 17. second worm gear; 18. second worm; 19. transmission wheel; 20. sleeve; 21. torsion spring; 22. sleeve; 23. slide rod; 24. movable disk; 25. second leaf spring; 26. plug rod; 27. push-pull plate; 28. collecting bucket; 29. suction pipe; 30. guide slide; 31. second slider; 32. right-angle frame; 33. motor; 34. pulley; 35. belt. DETAILED DESCRIPTION
[0015] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0016] In the description of the present invention, it should be noted that the orientations or positional relationships indicated by “center”, “up”, “down”, “left”, “right”, “vertical”, “horizontal”, “inside” and “outside”, etc., are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0017] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. This embodiment is written in a progressive manner.
[0018] like Figures 1 to 8 As shown, an EVA wool cleaning device for solar panel lamination processing of the present invention comprises an external fixing box 1, wherein a scraping structure and a softening hot spraying structure are arranged in the external fixing box 1, and the softening hot spraying structure is used to perform jet softening processing on the solidified EVA; The scraping structure comprises two rotating shafts 2, on which belt rollers 3 are installed, on the outer walls of the two belt rollers 3, a conveyor mesh belt 4 is laid, on the outer wall of the conveyor mesh belt 4, a plurality of arc-shaped rubber scrapers 5 are obliquely arranged, first sliders 6 are rotatably installed at both ends of the rotating shaft 2, and a slide plate 7 is arranged on the upper and lower sides of the conveyor mesh belt 4, the first slider 6 is slidably installed in the slide plate 7, and a first leaf spring 8 is installed between the two first sliders 6 in the slide plate 7; The arc-shaped rubber scraper 5 is inclined in the direction along the rotation direction of the conveyor mesh belt 4 , and the first leaf spring 8 pushes the first slider 6 to contact the end position of the inner wall of the slide plate 7 .
[0019] In this embodiment, the rotating shaft 2 is rotated, and the rotating shaft 2 drives the conveyor belt 4 and multiple curved rubber scrapers 5 to rotate synchronously through the belt roller 3, and the conveyor belt 4 and the curved rubber scraper 5 are attached to the edge of the solar panel. The hot air flow sprayed by the softening hot spray structure passes through the conveyor belt 4 and softens the EVA wool at the edge of the solar panel. The rotating curved rubber scraper 5 scrapes and cleans the softened EVA. Since the curved rubber scraper 5 is inclined along the rotation direction of the conveyor belt 4, the curved rubber scraper 5 can push the scraped and cleaned wool downward, thereby facilitating the wool to separate from the solar panel and improving the scraping effect. When it is necessary to scrape and clean the wool at the corner of the solar panel, the solar panel hanging corner squeezes and pushes the conveyor belt 4 is concave, so that the conveyor belt 4 wraps the corner position, reducing the cleaning difficulty of this position. When the conveyor belt 4 is concave, the two belt rollers 3 approach each other, and the two belt rollers 3 drive the two first sliders 6 on the slide plate 7 to approach each other, and the first leaf spring 8 is elastically deformed. When the conveyor belt 4 cleans the edge position of the solar panel again, the first leaf spring 8 pushes the two belt rollers 3 to return to the initial position. At this time, the first slider 6 contacts the inner wall end of the slide plate 7 again. The equipment can realize the softening, scraping and cleaning of the EVA wool material, effectively reducing the difficulty of wool material cleaning, saving manpower and time, avoiding excessive scraping force and scratching and damage to the solar panel, and facilitating the cleaning of the wool material at the corner position of the solar panel.
[0020] In this embodiment, the external fixing box 1 can be installed on the external movable truss, so that the external fixing box 1 and the scraping structure and softening hot spray structure therein can automatically move around the solar panel.
[0021] As a preferred embodiment of the above, the softening hot spray structure includes a first air guide bin 9 and two second air guide bins 10, the two second air guide bins 10 are respectively located at the front and rear sides of the first air guide bin 9, and the second air guide bin 10 is slidably inserted into the first air guide bin 9, the first air guide bin 9 is connected to the second air guide bin 10, and the side walls of the first air guide bin 9 and the side walls of the second air guide bin 10 are both provided with inclined holes, and the inclined holes are inclined downward; A first connecting frame 11 is installed on the second air guide bin 10, and the outer end of the first connecting frame 11 is fixed on the first sliding block 6. A second connecting frame 12 is installed on the first air guide bin 9, and the second connecting frame 12 is installed on the slide plate 7. It also includes an air intake pipe 13 , which is connected and installed on the first air guide bin 9 .
[0022] In this embodiment, the hot air flow is pumped into the first air guide bin 9 through the air inlet pipe 13, the hot air flow in the first air guide bin 9 enters the second air guide bin 10, and the hot air flows in the first air guide bin 9 and the second air guide bin 10 are obliquely ejected through the inclined holes, and the ejected hot air flows through the conveyor mesh belt 4 and heats and softens the EVA wool at the edge of the solar panel. At the same time, when the two rotating shafts 2 approach each other, the first slider 6 pushes the second air guide bin 10 to slide in the first air guide bin 9 through the first connecting frame 11, thereby reducing the side wall area of the second air guide bin 10 at the outside, which is convenient for adjusting the number of inclined holes.
[0023] As a preferred embodiment of the above embodiment, it also includes a first worm 15 and two first worm wheels 14, the first worm wheel 14 is installed on the rotating shaft 2, the two first worm wheels 14 are meshed with the first worm 15, a third connecting frame 16 is installed in the middle of the first worm 15, the third connecting frame 16 is rotatably connected with the first worm 15, and the third connecting frame 16 is fixed to the outer wall of the slide plate 7, both ends of the first worm 15 are installed with second worm wheels 17, the second worm wheel 17 is meshed with a second worm 18, one end of the second worm 18 is rotatably installed on the inner wall of the outer fixed box 1, and the other end of the second worm 18 is provided with a transmission structure; An elastic support structure is arranged inside the outer fixing box 1, and the elastic support structure is used to support the scraping structure.
[0024] In this embodiment, the two second worm gears 18 are driven by the transmission structure. The rotating second worm gears 18 drive the rotating shaft 2 to rotate through the second worm wheel 17, the first worm gear 15 and the first worm wheel 14, so that the conveyor belt 4 and the arc-shaped rubber scraper 5 thereon scrape and clean the softened wool material. When the two rotating shafts 2 are close to each other, the first worm gear 15 always maintains a meshing state with the first worm wheel 14, so that the first worm gear 15 always drives the rotating shaft 2. When the scraping structure moves along the axis of the second worm gear 18, the second worm wheel 17 and the second worm gear 18 always maintain a meshing state, so that when the rotating shaft 2 moves horizontally and vertically, the second worm gear 18 can always transmit power to the rotating shaft 2.
[0025] As a preferred embodiment of the above embodiment, the transmission structure includes two transmission wheels 19, which are respectively mounted on the inner wall of the outer fixed box 1 and the end of the second worm 18, the transmission wheel 19 on the outer fixed box 1 is rotatably connected to the outer fixed box 1, a sleeve 20 is arranged between the two transmission wheels 19, one end of the sleeve 20 is mounted on one transmission wheel 19, and the other end of the sleeve 20 is in sliding contact with the other transmission wheel 19, a torsion spring 21 is arranged in the sleeve 20, one end of the torsion spring 21 is fixed to one transmission wheel 19, and the other end of the torsion spring 21 is fixed to the other transmission wheel 19.
[0026] In this embodiment, the transmission wheel 19 on the external fixed box 1 is rotated, and the transmission wheel 19 drives another transmission wheel 19 and the second worm 18 to rotate through the torsion spring 21. When the transmission wheel 19 on the external fixed box 1 initially rotates, the torsion spring 21 is twisted and deformed, and the torsion spring 21 transmits power to the second worm 18 through elastic force. When the transmission wheel 19 on the external fixed box 1 rotates stably, the rotation speed of the second worm 18 gradually increases. Since the second worm 18 is simultaneously subjected to the elastic force of the torsion spring 21, the rotation speed of the second worm 18 exceeds the rotation speed of the transmission wheel 19 on the external fixed box 1, and the torsion spring 21 gradually returns to its initial state and twists and deforms in the opposite direction. At this time, the speed of the second worm 18 decreases and gradually becomes lower than the rotation speed of the transmission wheel 19 on the outer fixed box 1. By adopting the torsion spring 21 for transmission, the rotation speed of the second worm 18 can be conveniently changed alternately between fast and slow, so that the rotation speeds of the conveyor mesh belt 4 and the arc-shaped rubber scraper 5 are changed alternately between fast and slow, and the vibration movement of the conveyor mesh belt 4 and the arc-shaped rubber scraper 5 when they rotate is realized, so that the wool scraped off from the arc-shaped rubber scraper 5 can be vibrated and fall off, and the wool can be prevented from sticking to the arc-shaped rubber scraper 5. When the torsion spring 21 expands and twists, the outer wall of the torsion spring 21 can contact the inner wall of the sleeve 20. At this time, the sleeve 20 can limit the expansion and twisting deformation of the torsion spring 21.
[0027] As a preferred embodiment of the above, the elastic support structure includes a sliding sleeve 22 installed on the outer fixed box 1, a sliding rod 23 is slidably inserted in the sliding sleeve 22, a moving plate 24 is installed at the end of the sliding rod 23 located inside the outer fixed box 1, a second leaf spring 25 is installed on the side wall of the moving plate 24, and the outer end of the second leaf spring 25 is installed on the inner wall of the outer fixed box 1; Four insertion rods 26 are installed on the circumferential outer wall of the movable disk 24. The insertion rods 26 are along the radial direction of the movable disk 24, and the insertion rods 26 are slidably inserted into the movable disk 24. Two push-pull plates 27 are rotatably installed on the outer ends of the insertion rods 26. The push-pull plates 27 are inclined, and the outer end of one push-pull plate 27 on the insertion rod 26 is rotatably installed on the outer wall of the slide plate 7, and the outer end of the other push-pull plate 27 on the insertion rod 26 is rotatably installed on the inner wall of the outer fixed box 1.
[0028] In this embodiment, the second leaf spring 25 generates an elastic thrust on the movable disk 24, and the movable disk 24 can drive the sliding rod 23 to slide on the sliding sleeve 22. When the movable disk 24 moves, the movable disk 24 generates a push-pull force on the two push-pull plates 27 on the insertion rod 26 through the insertion rod 26, so that the scraping structure moves along the axis direction of the second worm 18, and the insertion rod 26 slides on the movable disk 24. By arranging the sliding sleeve 22, the sliding rod 23, the movable disk 24, the second leaf spring 25, the insertion rod 26 and the push-pull plate 27, the scraping structure can be conveniently supported. When the scraping structure contacts the solar panel, the second leaf spring 25 can push the scraping structure to be close to the solar panel. By adopting the structure of the movable disk 24, the insertion rod 26 and the push-pull plate 27, the translational movement of the scraping structure can be realized, the stability of its movement is improved, and the tilting of the scraping structure is avoided.
[0029] In this example, when the moving disk 24 moves, the scraping structure moves synchronously, and the scraping structure moves on the basis of the moving disk 24, so that the moving distance of the scraping structure is larger than that of the moving disk 24, thereby increasing the activity space of the scraping structure.
[0030] As a preferred embodiment of the above embodiment, it also includes a collecting bucket 28, which is installed on the outer wall of the slide plate 7 located on the lower side of the rotating shaft 2, and the opening of the collecting bucket 28 faces upward. An air suction pipe 29 is installed in the collecting bucket 28, and the top of the air suction pipe 29 is set to be conical, and a suction port is opened at the bottom of the air suction pipe 29.
[0031] In this embodiment, an external air pump draws the air out of the collecting bucket 28 through the suction pipe 29 and the suction holes thereon, and the collecting bucket 28 sucks the air above the collecting bucket 28, thereby facilitating the suction of the scraped and detached wool into the collecting bucket 28, facilitating the collection of the wool, and by setting the suction port at the bottom of the suction pipe 29, the wool can be prevented from blocking the suction port.
[0032] As a preferred embodiment of the above, two lateral guide slots 30 are provided on the inner wall of the outer fixing box 1 , a second slider 31 is slidably disposed in the guide slot 30 , and the second slider 31 is rotationally connected to the second worm gear 17 .
[0033] In this embodiment, by providing the guide slot 30 and the second slider 31 , the second worm gear 17 can be conveniently guided and supported. Meanwhile, the guide slot 30 can limit the moving position of the second worm gear 17 through the second slider 31 .
[0034] As a preferred embodiment of the above, a right angle bracket 32 is installed on the outer wall of the outer fixing box 1, and a motor 33 is installed on the right angle bracket 32; It also includes three pulleys 34 , one pulley 34 is installed on the output end of the motor 33 , and the remaining two pulleys 34 are respectively connected to the two transmission wheels 19 on the outer fixed box 1 , and belts 35 are laid on the three pulleys 34 .
[0035] In this embodiment, the motor 33 drives the two transmission wheels 19 on the outer fixing box 1 to rotate through three pulleys 34 and a belt 35, thereby driving the two second worm gears 18 to rotate synchronously.
[0036] The EVA wool cleaning equipment for solar panel lamination processing of the present invention has common mechanical installation, connection or setting methods, which can be implemented as long as the beneficial effects can be achieved.
[0037] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. An EVA wool cleaning device for solar panel lamination processing, characterized in that: It comprises an external fixing box (1), wherein a scraping structure and a softening hot spraying structure are arranged inside the external fixing box (1), and the softening hot spraying structure is used to perform a jet softening treatment on the solidified EVA; The scraping structure comprises two rotating shafts (2), belt rollers (3) are mounted on the rotating shafts (2), conveyor mesh belts (4) are laid on the outer walls of the two belt rollers (3), a plurality of arc-shaped rubber scrapers (5) are obliquely arranged on the outer wall of the conveyor mesh belt (4), first sliders (6) are rotatably mounted on both ends of the rotating shaft (2), slide plates (7) are arranged on the upper and lower sides of the conveyor mesh belt (4), the first slider (6) is slidably mounted in the slide plate (7), and a first leaf spring (8) is installed between the two first sliders (6) in the slide plate (7); The arc-shaped rubber scraper (5) is tilted in a direction along the rotation direction of the conveyor mesh belt (4), and the first leaf spring (8) pushes the first sliding block (6) to contact the end position of the inner wall of the slide plate (7).
2. The EVA wool cleaning equipment for solar panel lamination processing according to claim 1 is characterized in that: The softening hot spray structure comprises a first air guide bin (9) and two second air guide bins (10), the two second air guide bins (10) are respectively located at the front and rear sides of the first air guide bin (9), and the second air guide bin (10) is slidably inserted into the first air guide bin (9), the first air guide bin (9) is communicated with the second air guide bin (10), and the side walls of the first air guide bin (9) and the side walls of the second air guide bin (10) are both provided with inclined holes, and the inclined holes are inclined downward; A first connecting frame (11) is installed on the second air guide bin (10), the outer end of the first connecting frame (11) is fixed on the first sliding block (6), a second connecting frame (12) is installed on the first air guide bin (9), and the second connecting frame (12) is installed on the slide plate (7); It also comprises an air intake pipe (13), wherein the air intake pipe (13) is mounted in communication with the first air guide bin (9).
3. The EVA wool cleaning equipment for solar panel lamination processing according to claim 2 is characterized in that: It also comprises a first worm (15) and two first worm wheels (14), wherein the first worm wheel (14) is mounted on the rotating shaft (2), the two first worm wheels (14) are meshingly connected with the first worm (15), a third connecting frame (16) is mounted in the middle of the first worm (15), the third connecting frame (16) is rotatably connected with the first worm (15), and the third connecting frame (16) is fixed to the outer wall of the slide plate (7), second worm wheels (17) are mounted at both ends of the first worm (15), a second worm (18) is meshingly arranged on the second worm wheel (17), one end of the second worm (18) is rotatably mounted on the inner wall of the outer fixed box (1), and the other end of the second worm (18) is provided with a transmission structure; An elastic support structure is arranged inside the outer fixing box (1), and the elastic support structure is used to support the scraping structure.
4. The EVA wool cleaning equipment for solar panel lamination processing according to claim 3 is characterized in that: The transmission structure comprises two transmission wheels (19), the two transmission wheels (19) being respectively mounted on the inner wall of the outer fixed box (1) and the end of the second worm (18), the transmission wheel (19) on the outer fixed box (1) being rotationally connected to the outer fixed box (1), a sleeve (20) being arranged between the two transmission wheels (19), one end of the sleeve (20) being mounted on one transmission wheel (19), the other end of the sleeve (20) being in sliding contact with the other transmission wheel (19), a torsion spring (21) being arranged inside the sleeve (20), one end of the torsion spring (21) being fixed on one transmission wheel (19), and the other end of the torsion spring (21) being fixed on the other transmission wheel (19).
5. The EVA wool cleaning equipment for solar panel lamination processing according to claim 4 is characterized in that: The elastic support structure comprises a sliding sleeve (22) mounted on the outer fixing box (1), a sliding rod (23) slidably inserted in the sliding sleeve (22), a moving plate (24) being mounted on the end of the sliding rod (23) located inside the outer fixing box (1), a second leaf spring (25) being mounted on the side wall of the moving plate (24), and an outer end of the second leaf spring (25) being mounted on the inner wall of the outer fixing box (1); Four insertion rods (26) are installed on the circumferential outer wall of the movable disk (24). The insertion rods (26) are along the radial direction of the movable disk (24) and are slidably inserted into the movable disk (24). Two push-pull plates (27) are rotatably installed on the outer ends of the insertion rods (26). The push-pull plates (27) are inclined, and the outer end of one push-pull plate (27) on the insertion rod (26) is rotatably installed on the outer wall of the slide plate (7), and the outer end of the other push-pull plate (27) on the insertion rod (26) is rotatably installed on the inner wall of the outer fixed box (1).
6. The EVA wool cleaning equipment for solar panel lamination processing according to claim 5 is characterized in that: It also includes a collecting hopper (28), the collecting hopper (28) being mounted on the outer wall of the slide plate (7) located at the lower side of the rotating shaft (2), the opening of the collecting hopper (28) facing upward, an air suction pipe (29) being mounted in the collecting hopper (28), the top of the air suction pipe (29) being configured to be conical, and a suction port being provided at the bottom of the air suction pipe (29).
7. The EVA wool cleaning equipment for solar panel lamination processing according to claim 6 is characterized in that: Two transverse guide slots (30) are provided on the inner side wall of the outer fixed box (1), a second sliding block (31) is slidably arranged in the guide slot (30), and the second sliding block (31) is rotationally connected to the second worm gear (17).
8. The EVA wool cleaning equipment for solar panel lamination processing according to claim 7 is characterized in that: A right-angle bracket (32) is installed on the outer wall of the external fixing box (1), and a motor (33) is installed on the right-angle bracket (32); It also includes three pulleys (34), one pulley (34) is mounted on the output end of the motor (33), and the remaining two pulleys (34) are respectively connected to two transmission wheels (19) on the external fixed box (1). Belts (35) are laid on the three pulleys (34).