Super-high cantilever balcony formwork and construction method

By using a combined structure of assembled aluminum mold mechanism, support components and support base in construction, the problems of material consumption and safety hazards of high-altitude cantilever balcony formwork are solved, and material saving and construction safety are improved.

CN119266527APending Publication Date: 2025-01-07CHINA RAILWAY NO 5 ENG GRP BUILDING ENG +1
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411409966.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2025-01-07

AI Technical Summary

Technical Problem

During construction, the existing technology consumes a lot of frame materials when erecting ultra-high cantilever balcony forms, and poses safety risks in high altitude operations.

Method used

The combination of assembled aluminum mold mechanism, support components and support base is adopted to realize fixed support of the aluminum mold mechanism through structures such as embedded U-shaped cards and cylinders, reducing material consumption and reducing the risk of high-altitude operation.

Benefits of technology

It effectively reduces the consumption of frame materials and improves construction safety. Through the coordination of support components and support base, the aluminum mold mechanism is fixed to form a stable cantilever balcony structure formwork support system, which improves construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119266527A_ABST
    Figure CN119266527A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to an ultra-high cantilever balcony formwork and a construction method.The ultra-high cantilever balcony formwork comprises an aluminum formwork splicing mechanism used for being spliced with a main body connecting aluminum formwork unit; the supporting assembly is located below and connected with the aluminum mold assembling mechanism and can move relative to the aluminum mold assembling mechanism; and the supporting base can be connected with a main body concrete structure layer below the main body structure aluminum mold unit, can be connected with the bottom of the supporting assembly and can support the supporting assembly. According to the super-high cantilever balcony formwork and the construction method, through cooperative use of the supporting base and the supporting assembly, the splicing aluminum formwork mechanism can be fixedly supported in the main body concrete structure layer, and therefore consumption of a large number of frame body materials is avoided, and high-altitude operation of workers during frame body material building is also avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to an ultra-high cantilevered balcony formwork and a construction method. Background Art

[0002] High-support formwork engineering is a relatively dangerous engineering that is often encountered in the construction of the main structure. In the fourth-generation ecological housing that is common today, a 9-meter-high formwork support frame is required for the location of the cantilevered staggered balcony. The existing technology for building a cantilevered staggered balcony usually uses a buckle frame to directly build a wooden formwork support system. When the cantilevered staggered balcony needs to use an aluminum formwork, a conversion platform is set in the middle of the frame to convert the buckle poles and the aluminum formwork poles. The above methods all consume a large amount of frame materials, and manual high-altitude operations have certain safety hazards. For this reason, the present invention provides an ultra-high cantilever balcony formwork and a construction method. Summary of the invention

[0003] In view of the above-mentioned problems existing in the existing ultra-high cantilever balcony formwork and construction method, the present invention is proposed.

[0004] Therefore, one of the objects of the present invention is to provide an ultra-high cantilevered balcony formwork, the purpose of which is to reduce the consumption of frame materials.

[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: an ultra-high cantilevered balcony formwork, comprising an assembling aluminum formwork mechanism, which is used to connect the aluminum formwork unit with the main body for splicing;

[0006] A support assembly, which is located below the aluminum mold assembly mechanism and is connected to the aluminum mold assembly mechanism and can move relative to the aluminum mold assembly mechanism; and

[0007] The support base can be connected to the main concrete structure layer below the main structural aluminum formwork unit, and can be connected to the bottom of the support assembly and support the support assembly.

[0008] As a preferred solution of the ultra-high cantilevered balcony formwork of the present invention, the support assembly includes a telescopic rod 1 and a telescopic rod 2 rotatably arranged below the assembled aluminum formwork mechanism;

[0009] The telescopic rod 1 and the telescopic rod 2 are plug-connected with the end of the support base.

[0010] As a preferred solution of the super-high cantilevered balcony formwork of the present invention, wherein: a vertical card slot and an oblique card slot are provided at the end of the support base;

[0011] One end of the telescopic rod is inserted into the vertical slot, and the other end of the telescopic rod is inserted into the oblique slot.

[0012] As a preferred solution of the super-high cantilevered balcony formwork described in the present invention, the support base includes a sleeve, a steel body slidably arranged in the sleeve, and a cylinder 1 arranged between the sleeve and the steel body.

[0013] As a preferred solution of the ultra-high cantilevered balcony formwork of the present invention, wherein: the support assembly further comprises a plurality of cylinders 2 rotatably arranged below the assembled aluminum formwork mechanism;

[0014] The telescopic rod 1 and the telescopic rod 2 are both connected to the cylinder 2.

[0015] As a preferred solution of the super-high cantilever balcony formwork described in the present invention, there are multiple support assemblies and support bases, and at least one support assembly has a supplementary telescopic rod rotatably provided on the bottom, and the end of the supplementary telescopic rod is inserted in the middle of the support base.

[0016] The beneficial effects of the ultra-high cantilevered balcony formwork of the present invention are as follows: through the coordinated use of the support base and the support assembly, the assembled aluminum formwork mechanism can be fixedly supported in the main concrete structure layer, thereby avoiding the consumption of a large amount of frame materials and also avoiding high-altitude operations of workers when constructing the frame materials.

[0017] One of the purposes of the present invention is to provide a method for constructing an ultra-high cantilevered balcony, the purpose of which is to reduce the consumption of frame materials.

[0018] In order to solve the above technical problems, the present invention provides the following technical solutions: a super-high cantilever balcony construction method, comprising a super-high cantilever balcony formwork,

[0019] By pre-embedding U-shaped cards in the main concrete structure layer below the main connecting aluminum formwork unit;

[0020] Fix the support base with a U-shaped clip;

[0021] By raising the assembled aluminum mold mechanism and connecting the aluminum mold unit with the main body for splicing; and,

[0022] The assembled aluminum mold mechanism is supported by connecting the support assembly to the support base.

[0023] As a preferred solution of the ultra-high cantilever balcony formwork and construction method described in the present invention, wherein: it is fixed with the assembled aluminum formwork mechanism through a scissors-type lifting mechanism, and when the scissors-type lifting mechanism is raised, the assembled aluminum formwork mechanism is raised to the main body connected to the aluminum formwork unit, so that the two are spliced ​​and fixed.

[0024] As a preferred solution of the ultra-high cantilever balcony formwork and construction method described in the present invention, wherein: it is fixed with the assembled aluminum formwork mechanism through a scissors-type lifting mechanism, and when the scissors-type lifting mechanism is raised, the assembled aluminum formwork mechanism is raised to the main body connected to the aluminum formwork unit, so that the two are spliced ​​and fixed.

[0025] As a preferred solution of the ultra-high cantilever balcony formwork and construction method described in the present invention, when the concrete strength at the main body connecting aluminum formwork unit reaches 100%, the ultra-high cantilever balcony formwork is completely dismantled, cleaned and reused.

[0026] The beneficial effects of the present invention are as follows: the assembled aluminum formwork mechanism is raised and connected to the main body aluminum formwork unit for splicing, and then the assembled aluminum formwork mechanism is fixed in the main body concrete structure layer under the coordinated use of the support assembly and the support base. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0028] Figure 1 It is a schematic diagram of the overall structure of the super-high cantilevered balcony formwork of the present invention.

[0029] Figure 2 It is a schematic diagram of the support component structure of the super-high cantilevered balcony formwork of the present invention.

[0030] Figure 3 for Figure 1 A magnified image of area A.

[0031] Figure 4 It is a schematic diagram of the support base structure of the super-high cantilevered balcony formwork of the present invention.

[0032] Figure 5 It is a schematic diagram of the structure of the supplementary telescopic rod of the ultra-high cantilevered balcony formwork of the present invention.

[0033] Figure 6 for Figure 5 Enlarged view of area B.

[0034] Figure 7 It is a schematic diagram of the process steps of the super-high cantilever balcony construction method of the present invention. DETAILED DESCRIPTION

[0035] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0036] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0037] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0038] Secondly, the present invention is described in detail with reference to the schematic diagram. When describing the embodiments of the present invention in detail, for the sake of convenience, the cross-sectional diagrams showing the device structure will not be partially enlarged according to the general scale, and the schematic diagrams are only examples, which should not limit the scope of protection of the present invention. In addition, in actual production, the three-dimensional dimensions of length, width and depth should be included.

[0039] Example 1, reference Figure 1-Figure 3 , which is the first embodiment of the present invention, provides an ultra-high cantilevered balcony template, the template includes an assembled aluminum mold mechanism 100, which is used to be spliced ​​with a main body connected aluminum mold unit 1, the assembled aluminum mold mechanism 100 is composed of segmented aluminum molds, the segmented aluminum molds are directly reinforced as a whole so that the assembled aluminum mold mechanism 100 forms an integral structure, and the main body connected aluminum mold unit 1 includes a main structure bottom mold 1-a and a slot 1-b.

[0040] The assembled aluminum mold mechanism 100 includes a supporting plane 101 and a latch plate 102 arranged on the side of the supporting plane, wherein the latch plate 102 is plugged into the slot 1-b of the main body connected aluminum mold unit 1, and a plurality of triangular plates 103 are provided on the latch plate 102, wherein when the latch plate 102 is plugged into the slot 1-b, the triangular plates 103 can be plugged into the outer wall of the slot 1-b to realize the splicing of the assembled aluminum mold mechanism 100 and the main body connected aluminum mold unit 1.

[0041] This template also includes a support component 200 and a support base 300, wherein the support component 200 is located below the assembled aluminum mold mechanism 100 and is connected and can move relative to the assembled aluminum mold mechanism 100, wherein the support component 200 can be made of a long rod rotatably arranged below the assembled aluminum mold mechanism 100, which can contact the support base 300 when rotating.

[0042] The support base 300 can be connected to the main concrete structure layer 2 below the main structure aluminum formwork unit, and the main concrete structure layer 2 has multiple layers, such as Figure 1As shown, it is specifically divided into F, F+1, F+2, and F+3, wherein F+3 is the main body connected aluminum formwork unit 1, and at the same time, a plurality of aluminum formwork support rods 3 for supporting the main body connected aluminum formwork unit 1 are arranged on the F+2 layer concrete structure layer, wherein the F+2 layer is also provided with a pre-embedded U-shaped card 4, wherein the support base 300 is made of a long metal rod, and when the support assembly 200 rotates and contacts the support base 300, the two can be fixed by bolts, and at this time, the support base 300 and the support assembly 200 are combined to support the assembled aluminum formwork mechanism 100, thereby forming a cantilever balcony structure formwork support system, which is convenient for steel bar construction, acceptance, and concrete pouring.

[0043] Furthermore, the support assembly 200 includes a telescopic rod 1 201 and a telescopic rod 202 rotatably disposed below the aluminum mold assembly mechanism 100; the telescopic rod 1 201 and the telescopic rod 202 are plug-connected to the end of the support base 300. The telescopic rod 1 201 and the telescopic rod 202 can be multi-stage telescopic rods.

[0044] At the same time, a vertical slot 301 and an oblique slot 302 are provided at the end of the support base 300; the end of the telescopic rod 1 201 is inserted into the vertical slot 301, and the end of the telescopic rod 202 is inserted into the oblique slot 302. When the telescopic rod 1 201 and the telescopic rod 202 are inserted into the vertical slot 301 and the oblique slot 302 respectively, the telescopic rod 1 201, the telescopic rod 202 and the assembled aluminum mold mechanism 100 form a fixed frame, and the fixed frame is preferably a triangle.

[0045] During use, first, the U-shaped card 4 is pre-buried before pouring the F+2 layer of concrete. After the concrete pouring is completed and the strength is reached, the formwork is removed and the I-beam is installed and fixed through the U-shaped card 4; and the main body connecting aluminum mold unit 1 and the aluminum mold support rod 3 are installed in advance;

[0046] Afterwards, when constructing the ultra-high cantilevered balcony, the assembled aluminum formwork mechanism 100 is sent to the main body connection aluminum formwork unit 1 and the two are spliced ​​and fixed, and the support base 300 is fixed in the U-shaped card 4 at the same time, and then the angles of the telescopic rod 1 201 and the telescopic rod 202 are rotated, and the telescopic rod 1 201 and the telescopic rod 202 are controlled to extend and plug into the vertical card slot 301 and the oblique card slot 302 respectively, so as to realize the connection between the support assembly 200 and the support base 300, so that the telescopic rod 1 201, the telescopic rod 202 and the assembled aluminum formwork mechanism 100 form a stable fixed frame to support the assembled aluminum formwork mechanism 100, thereby forming an F+3-layer cantilevered balcony structure formwork support system, and carrying out steel bar construction, acceptance, and concrete pouring;

[0047] When the concrete strength of the F+3 layer cantilever balcony structure reaches 100%, the telescopic rod 202 and the telescopic rod 1 201 are retracted, and the assembled aluminum mold mechanism 100 and the supporting base 300 are disassembled, cleaned, and then rotated for use.

[0048] Example 2, reference Figure 4-Figure 6 , which is the second embodiment of the present invention. This embodiment is different from the first embodiment in that: the support base 300 includes a sleeve 303, a steel body 304 slidably arranged in the sleeve 303, and a cylinder 1 305 arranged between the sleeve 303 and the steel body 304; wherein the sleeve 303 can be fixed in the F+2 layer by the U-shaped clamp 4, the end of the steel body 304 is provided with a vertical clamping groove 301 and an oblique clamping groove 302, and the cylinder 1 305 can control the steel body 304 to be extended and retracted in the sleeve, so that the steel body 304 can extend out of the F+2 layer and be suspended in the air, and at the same time, the extension length of the steel body 304 can be adjusted, and then the position of the vertical clamping groove 301 and the oblique clamping groove 302 can be adjusted, so as to facilitate the alignment of the telescopic rod 1 201 and the telescopic rod 2 202.

[0049] Furthermore, a protruding block is provided at the end of the steel body 304 , wherein the protruding block can be welded, bolted or integrally stamped at the end of the steel body 304 , and the vertical slot 301 and the oblique slot 302 are located in the protruding block.

[0050] The support assembly 200 also includes a plurality of cylinders 203 rotatably arranged below the assembled aluminum mold mechanism 100; the telescopic rod 1 201 and the telescopic rod 202 are both connected to a cylinder 203, wherein the ends of the cylinder 203 can be extended or retracted during operation, thereby being able to change the angle between the telescopic rod 1 201, the telescopic rod 202 and the assembled aluminum mold mechanism 100, thereby realizing the rotation of the telescopic rod 1 201 and the telescopic rod 202.

[0051] In the initial state, the telescopic rod 1 201 and the telescopic rod 202 are folded and stored close to the assembled aluminum mold mechanism 100 under the action of the cylinder 203, which can save space. When constructing an ultra-high cantilevered balcony, the assembled aluminum mold mechanism 100 is first spliced ​​and the sleeve is installed in the U-shaped card 4. Then, the extension of the steel body 304 is controlled, and the rotation of the telescopic rod 1 201 and the telescopic rod 202 is controlled, and the angles of the telescopic rod 1 201 and the telescopic rod 202 are adjusted, so that the telescopic rod 1 201 and the telescopic rod 202 can be smoothly plugged into the vertical card slot 301 and the oblique card slot 302 when extended to complete the splicing.

[0052] Furthermore, there are multiple support assemblies 200 and support bases 300, and at least one support assembly 200 is rotatably provided with a supplementary telescopic rod 204 at the bottom, and the end of the supplementary telescopic rod 204 is inserted into the middle of the support base 300, wherein there can be multiple supplementary telescopic rods 204, preferably, two support assemblies 200 are provided with supplementary telescopic rods 204, and they are respectively located on both sides of the multiple support assemblies 200.

[0053] The steel body 304 that cooperates with the supplementary telescopic rod 204 is provided with a plug-in groove, which can provide for the plug-in of the supplementary telescopic rod 204, further increasing the supporting firmness of the assembled aluminum mold mechanism 100. At the same time, the supplementary telescopic rod 204 is also connected to the cylinder 203, and the rotation of the supplementary telescopic rod 204 is controlled by the cylinder 203.

[0054] The remaining structures are the same as those of Example 1.

[0055] Example 3, reference Figure 7 , which is the third embodiment of the present invention, and this embodiment provides a method for constructing an ultra-high cantilevered balcony: the method comprises the following steps;

[0056] S1. By pre-embedded U-shaped card 4 in the main concrete structure layer 2 below the main connecting aluminum formwork unit 1;

[0057] The main concrete structure layer 2 has multiple layers, specifically divided into F, F+1, F+2, and F+3, wherein F+3 is the main connecting aluminum formwork unit 1, and at the same time, the F+2 layer concrete structure layer is provided with a plurality of aluminum formwork support rods 3 for supporting the main connecting aluminum formwork unit 1, and U-shaped cards 4 are pre-embedded before pouring the F+2 layer concrete.

[0058] S2. The support base 300 is fixed by a U-shaped card 4;

[0059] When pouring concrete for the main connecting aluminum formwork unit 1 of the F+3 layer, first fix the pipe sleeve in the supporting base 300 to the U-shaped card 4, insert the pipe sleeve into the U-shaped card 4, and fix the pipe sleeve using the U-shaped card 4, and retract the steel body 304 into the sleeve.

[0060] S3. By raising the assembled aluminum mold mechanism 100 and connecting the aluminum mold unit 1 to the main body for splicing;

[0061] The assembled aluminum mold mechanism 100 is installed with a lifting rope and fixed on the hook of the crane. The assembled aluminum mold mechanism 100 is raised by the crane until it reaches the height of the main body connected aluminum mold unit 1, and then the assembled aluminum mold mechanism 100 is spliced ​​and fixed to the main body connected aluminum mold unit 1.

[0062] Further, the scissor lift mechanism 5 can be used to lift the assembled aluminum mold mechanism 100, wherein there is a concrete layer extending outward on the F layer. When using the scissor lift mechanism 5, first mark the lifting position on the F layer, use a line to remind, and then push the scissor lift mechanism 5 to the line position and fix it;

[0063] The top of the scissors-type lifting mechanism 5 also has a sliding component 6, wherein the sliding component 6 can be made of a cylinder and a slide plate, wherein the cylinder is fixed to the top of the scissors-type lifting mechanism 5, and the slide plate is controlled by the cylinder to move relative to the scissors-type lifting mechanism 5 as a whole, and the assembled aluminum mold mechanism 100 is fixedly installed on the sliding component 6. When the scissors-type lifting mechanism 5 is used to send the assembled aluminum mold mechanism 100 to the main body connected aluminum mold unit 1 of the F+3 layer, the assembled aluminum mold mechanism 100 is first made higher than the main body connected aluminum mold unit 1, and then the pin plate of the assembled aluminum mold mechanism 100 is sent to the slot of the main body connected aluminum mold unit 1 through the sliding component 6, and then the height of the scissors-type lifting mechanism 5 is lowered so that the plug plate is plugged into the slot, thereby splicing and fixing the assembled aluminum mold mechanism 100 and the main body connected aluminum mold unit 1.

[0064] S4. The assembled aluminum mold mechanism 100 is supported by connecting the support assembly 200 to the support base 300;

[0065] After the assembled aluminum formwork mechanism 100 is spliced ​​and fixed with the main body connected aluminum formwork unit 1, the steel body 304 in the support base 300 is extended, and the telescopic rod 1 201 and the telescopic rod 202 under the assembled aluminum formwork mechanism 100 are controlled to rotate and adjust the angle, and finally, it is ensured that the telescopic rod 1 201 and the telescopic rod 202 can be extended and inserted into the vertical slot 301 and the oblique slot 302 at the end of the steel body 304, so as to support the assembled aluminum formwork mechanism 100, thereby forming an F+3-story cantilever balcony structure formwork support system, and carrying out steel bar construction, acceptance, and concrete pouring. At the same time, the scissor lift mechanism 5 can also be retracted and removed, and the scissor lift mechanism 5 can continue to be used in turnover construction, thereby saving manpower and material resources and improving efficiency.

[0066] S5. Assembling the aluminum mold mechanism 100 for dismantling and turnover use;

[0067] When the strength of the concrete poured at the main connecting aluminum formwork unit 1 reaches 100%, the ultra-high cantilever balcony formwork and its construction method are completely dismantled. First, the beam side formwork of the main connecting aluminum formwork unit 1 is manually dismantled, and the beam side formwork is the part with the slot 1-b. Then, the scissors-type lifting mechanism 5 is pushed into the initial drawing position of the F layer, and then raised to contact and support the assembled aluminum formwork mechanism 100. Then, the telescopic rod 1 201 and the telescopic rod 2 202 are retracted, and the support base 300 is disassembled from the F+2 layer at the same time. Finally, the assembled aluminum formwork mechanism 100 is lowered by the scissors-type lifting mechanism 5, and the assembled aluminum formwork mechanism 100 is removed. After that, the ultra-high cantilever balcony formwork is cleaned and continued to be used.

[0068] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. An ultra-high cantilevered balcony formwork, characterized in that: include, An aluminum mold assembly mechanism (100) is used to be assembled with the main body connected aluminum mold unit (1) for assembly; A support assembly (200) located below and connected to the assembling aluminum mold mechanism (100) and capable of relative movement with respect to the assembling aluminum mold mechanism (100); as well as, The support base (300) can be connected to the main concrete structure layer (2) below the main structural aluminum formwork unit, and can be connected to the bottom of the support assembly (200) and support the support assembly (200).

2. The ultra-high cantilevered balcony formwork according to claim 1 is characterized in that: The support assembly (200) comprises a telescopic rod 1 (201) and a telescopic rod 2 (202) rotatably disposed below the assembling aluminum mold mechanism (100); The telescopic rod 1 (201) and the telescopic rod 2 (202) are plug-connected to the ends of the support base (300).

3. The ultra-high cantilevered balcony formwork according to claim 2 is characterized in that: The end of the support base (300) is provided with a vertical slot (301) and an oblique slot (302); The end of the telescopic rod one (201) is inserted into the vertical slot (301), and the end of the telescopic rod two (202) is inserted into the oblique slot (302).

4. The ultra-high cantilevered balcony formwork according to claim 3 is characterized in that: The support base (300) comprises a sleeve (303), a steel body (304) slidably disposed in the sleeve (303), and a cylinder (305) disposed between the sleeve (303) and the steel body (304).

5. The ultra-high cantilevered balcony formwork according to claim 4 is characterized in that: The support assembly (200) further comprises a plurality of cylinders (203) rotatably disposed below the aluminum mold assembly mechanism (100); The telescopic rod 1 (201) and the telescopic rod 2 (202) are both connected to the cylinder 2 (203).

6. The ultra-high cantilevered balcony formwork according to any one of claims 1 to 5, characterized in that: The support assembly (200) and the support base (300) are provided in plurality, and at least one support assembly (200) has a supplementary telescopic rod (204) rotatably provided on the bottom, and the end of the supplementary telescopic rod (204) is inserted into the middle of the support base (300).

7. A method for constructing an ultra-high cantilevered balcony, comprising an ultra-high cantilevered balcony formwork, characterized in that: By pre-embedding a U-shaped card (4) in the main concrete structure layer (2) below the main connecting aluminum formwork unit (1); The support base (300) is fixed by means of a U-shaped clamp (4); The aluminum mold assembly mechanism (100) is raised and connected to the main body aluminum mold unit (1) for assembly; and, The assembled aluminum mold mechanism (100) is supported by connecting the support assembly (200) to the support base (300).

8. The method for constructing a super-high cantilevered balcony according to claim 7, characterized in that: The scissor lift mechanism (5) is fixed to the aluminum mold assembly mechanism (100), and when the scissor lift mechanism (5) is raised, the aluminum mold assembly mechanism (100) is raised to the position where the main body is connected to the aluminum mold unit (1), so that the two are spliced ​​and fixed.

9. The method for constructing a super-high cantilevered balcony according to claim 7, characterized in that: The assembled aluminum mold mechanism (100) is fixed by a crane and lifted to the position where the main body is connected to the aluminum mold unit (1), so that the two are spliced ​​and fixed.

10. The method for constructing a super-high cantilevered balcony according to claim 7 or 9, characterized in that: When the concrete strength at the connection point of the main body to the aluminum formwork unit (1) reaches 100%, the ultra-high cantilever balcony formwork is completely dismantled and cleaned for recycling.

Citation Information

Patent Citations

  • Large cantilever beam board combined type formwork supporting system and construction method

    CN106150088A

  • Cantilever structure pouring formwork supporting device and construction method

    CN115262961A

  • Concrete suspension outer eave modeling template fixing device

    CN218758755U

  • Beam-shaped steel main ridge supporting device

    CN219931607U

  • Cantilever floor supporting device

    CN220666938U