A roof covering structure and a roof construction tool

Through the combination of prefabricated cladding layer structure and roof construction tools, the problems of complex construction and poor bonding of existing roof structures are solved, and the construction cycle is shortened and structural strength is improved.

CN119308475BActive Publication Date: 2025-05-02THE 8TH CONSTR CO LTD OF CHINA CONSTR SIXTH ENG BUREAU
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411854111.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-05-02
Estimated Expiration
2044-12-17

AI Technical Summary

Technical Problem

The construction process of the existing roof layer structure is complex, the construction period is long, and the combination between levels is weak, resulting in low construction efficiency and easy structure damage.

Method used

The prefabricated cover layer structure is adopted, including a waterproof coil layer, a foam insulation layer and a pre-embedded seat. The construction process is simplified through prefabricated processing and molding, and the roof construction tools are used for laying and pouring to improve construction efficiency.

Benefits of technology

The construction cycle of the roof covering structure is shortened, the bonding tightness between levels is improved, and the overall strength and service life of the roof structure are enhanced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119308475B_ABST
    Figure CN119308475B_ABST
Patent Text Reader

Abstract

The present invention discloses a roof covering layer structure and a roof construction tool, comprising a roof structure layer, the roof structure layer is cast by concrete, a plurality of connecting bars arranged in a matrix are embedded in the roof structure layer, a leveling layer is laid on the upper layer of the roof structure layer, and a prefabricated covering layer is arranged on the leveling layer. The present invention relates to the field of roof structure and construction technology, a roof construction tool is used to construct a roof structure covering layer, a waterproof layer and a thermal insulation layer structure of the roof covering layer are prefabricated, the construction period of the entire roof covering layer structure is shortened, the roof construction tool simultaneously lays the prefabricated covering layer and casts the leveling layer, the construction process used is simple, less construction equipment needs to be prepared, management is convenient, and the construction period is further accelerated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of roof structure and construction, in particular to a roof covering layer structure and a roof construction tool. Background Art

[0002] In modern building structures, the roof structure is an important component of the building structure. The roof layer structure is mainly arranged on the top of the main body of the building, and plays the role of waterproofing, heat preservation and maintaining structural integrity. The commonly used roof layers are mainly divided into flat roof, sloped surface and curved surface structures. The more common roof structure in modern buildings is the flat roof structure.

[0003] At present, the roof structure usually adopts a multi-layer structure in order to meet the requirements of waterproofing, windproofing, heat preservation and structural strength. According to the common inverted roof structure, it is divided into several structures including concrete structure layer, leveling layer, waterproof layer and thermal insulation layer. Therefore, during the construction process, different construction processes are required according to different layers. The bonding between the layers of this structure is weak.

[0004] At present, the roof structure adopts a multi-layer stacking method, which requires multi-layer construction. However, this construction method has complicated procedures and a long construction period. For example, when laying the leveling layer on the concrete structure, it is necessary to wait for the solidification of the structural layer and clean the solidified layer, which takes a very long time to use.

[0005] Moreover, since different levels require different construction techniques, more construction tools and supporting equipment are needed, which increases the difficulty of equipment and personnel management.

[0006] In view of this, an in-depth study was conducted on the above-mentioned issues, which led to the present case. Summary of the invention

[0007] In view of the deficiencies in the prior art, the present invention provides a roof covering layer structure and a roof construction tool, which solve the problems existing in the background technology.

[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions: a roof covering structure, comprising a roof structure layer, the roof structure layer is cast by concrete, a plurality of connecting bars arranged in a matrix are pre-embedded in the roof structure layer, a leveling layer is laid on the upper layer of the roof structure layer, and a prefabricated covering layer is arranged on the leveling layer;

[0009] The prefabricated covering layer comprises a pair of waterproof coiled material layers, a skeleton layer is arranged between the pair of waterproof coiled material layers, and a foam insulation layer is filled between the pair of waterproof coiled material layers;

[0010] A pair of waterproof coiled material layers of the lower layer are provided with a plurality of fixing holes, a plurality of pre-embedded sleeves are embedded in the plurality of fixing holes, and a plurality of pre-embedded sleeves are sleeved outside a plurality of connecting ribs;

[0011] The skeleton layer is composed of a plurality of embedded sleeves, and the skeleton layer also includes a plurality of connecting rods. The ends of the plurality of embedded sleeves are embedded in the foam insulation layer. A plurality of connecting rods are arranged on the waterproof coiled material layer on the upper side of a pair of centers, and the plurality of connecting rods are reversely connected with the plurality of embedded sleeves.

[0012] The prefabricated covering layer also includes a filling groove, a filling groove is provided between the waterproof coiled material layer and the foamed insulation layer, and the filling groove is used to fill cement mortar;

[0013] A pouring pipeline is provided between the connecting rod and the embedded sleeve, the pouring pipeline includes a pouring inlet, a pouring inlet is provided at the end of the connecting rod and arranged along the axial direction of the connecting rod, the pouring inlet penetrates into the embedded sleeve, and a plurality of connecting holes are arranged in a ring array on the embedded sleeve and penetrate between a pair of waterproof coiled material layers;

[0014] A 20-30 mm thick concrete protective layer is laid on the top of the prefabricated covering layer.

[0015] Preferably, the leveling layer is a cement mortar layer, the horizontal slope of the leveling layer is between 5° and 10°, and the thickness of the leveling layer is between 30-40 mm.

[0016] Preferably, the pair of waterproof membrane layers are a pair of self-adhesive rubber asphalt waterproof membranes, the thickness of the pair of waterproof membrane layers is not less than 2 mm, and the inner sides of the pair of waterproof membrane layers are compounded with a pair of rubber reinforcement layers with a thickness of not less than 5 mm.

[0017] Preferably, the top edge of the prefabricated covering layer and the building gap are sealed by sealant, and the building inner corner and the top edge of the prefabricated covering layer and the upper part of the building gap are sealed by a waterproof tape.

[0018] A roof construction tool, used for laying the above-mentioned roof covering structure, comprising a pair of transverse tracks, the pair of transverse tracks are arranged in parallel on the roof, and the pair of transverse tracks are equipped with a motion control mechanism;

[0019] The motion control mechanism is provided with a coil unwinding mechanism, the prefabricated covering layer is arranged in a roll on the coil unwinding mechanism, one side of the coil unwinding mechanism is separately connected with a coil flattening structure, the coil flattening structure presses the prefabricated covering layer laid on the roof, so that the prefabricated covering layer is laid flat on the roof;

[0020] The coiled material flattening structure comprises a telescopic frame, the telescopic frame is mounted on the motion control mechanism, a telescopic adjuster is arranged on the telescopic frame, a hanging frame is arranged on the telescopic adjuster, the hanging frame is divided into a plurality of guide grooves, a roller is arranged on any of the guide grooves, and a pin is movably installed in the middle of the roller;

[0021] The roller press is a plate of a columnar structure, and a shaft cavity matching the pin shaft is opened in the middle of the roller press, and a pair of limit bearing sleeves are arranged on the pin shaft on both sides of the shaft cavity;

[0022] A pair of lifting sliders are arranged at both ends of the pin shaft, a pair of control buffers are mounted on the guide groove, the ends of the pair of control buffers are connected to a pair of lifting sliders, and the pair of lifting sliders are movably matched with both ends of the pin shaft;

[0023] The motion control mechanism is also provided with a pouring controller, which is used for pouring inside the prefabricated covering layer.

[0024] Preferably, the motion control mechanism includes a pair of sliding guide blocks, the pair of sliding guide blocks are assembled on a pair of transverse rails, the pair of sliding guide blocks are laterally fixed with at least a pair of reinforcing rods by screws, a pair of transverse wheel groups are arranged on one side of the transverse rails, and a sliding control system is arranged between the pair of transverse wheel groups.

[0025] Preferably, the sliding control system includes a sliding control motor, the driving end of the sliding control motor is connected to a gear box, the gear box is a reduction wheel group, the output end of the gear box is connected to the central axis of the transverse shift wheel group, a pair of the transverse shift wheel groups are provided with a transmission belt, a pair of the transverse shift wheel groups and the transmission belt form a belt drive, a cross-linking block is provided on the transmission belt, the cross-linking block is connected to the sliding guide block, a slot is opened on the sliding guide block, the cross-linking block is arranged corresponding to the slot, and the cross-linking block is connected to the slot.

[0026] Preferably, the coil unwinding mechanism includes a support roller, both ends of which are movably mounted on a pair of sliding guide blocks, one side of the support roller is connected to a winding and unwinding assembly, the winding and unwinding assembly is used to control the rotation of the support roller, the prefabricated covering layer is wound on the support roller, and a disassembly and replacement assembly is provided at the end of the support roller.

[0027] Preferably, the reeling and winding assembly includes a rotating shaft tube, which is installed on a sliding guide block, and the rotating shaft tube is movably matched with the sliding guide block. A rotating groove is provided on the sliding guide block, and the rotating shaft tube is assembled on the rotating groove. One end of the support roller is inserted into the rotating shaft tube, and the ends of the rotating shaft tube and the support roller are limited by a shaft key. A reeling and winding motor is connected to one side of the rotating shaft tube, and the reeling and winding motor controls the rotation of the rotating shaft tube through a gear set.

[0028] Preferably, the disassembly and assembly component includes an axis end tube, and the axis end tube corresponds to the rotating axis tube and is arranged on the sliding guide block on the other side. A guide groove is opened on the axis end tube, and the support roller is inserted from one side of the guide groove. A socket is set on the axis end tube, and a positioning hole is set at the end of the support roller corresponding to the socket, and a limiting rod is inserted in the socket and connected to the positioning hole.

[0029] Preferably, the pouring controller includes a synchronous frame, which is mounted on a pair of sliding guide blocks. A pouring pump is provided on the synchronous frame. A lifting controller is connected to the discharge end of the pouring pump. A feeding pipe is installed on the lifting controller. A diversion pipe is connected to one side of the feeding pipe. A plurality of branch feed pipes are evenly distributed on the diversion pipe, and the branch feed pipes correspond to the positions of the connecting rods.

[0030] Beneficial Effects

[0031] The present invention provides a roof covering structure and a roof construction tool, which have the following beneficial effects: the roof construction tool is used to construct the roof structure covering layer, the waterproof layer and the thermal insulation layer structure of the roof covering layer are prefabricated, shortening the construction period of the entire roof covering structure, and the roof construction tool simultaneously lays the prefabricated covering layer and casts the leveling layer, the construction process used is simple, less construction equipment is required, management is convenient, and the construction period is further accelerated. It also has the following specific advantages;

[0032] 1. The prefabricated covering layer in the roof structure layer, which plays a role of waterproofing and heat preservation, is prefabricated and formed. The structural design of the prefabricated covering layer takes into account both the waterproofing and heat preservation functions. Since the prefabricated covering layer structure is used for paving and pouring construction, the demand for layered construction can be reduced, the construction period can be effectively shortened, and the construction efficiency can be improved;

[0033] 2. The structural design of the prefabricated covering layer takes into account both waterproofing and thermal insulation. A double waterproof layer is set to improve the waterproofing effect. Pre-embedded sleeves are set on the prefabricated covering layer. The pre-embedded sleeves set in a matrix form a skeleton with the connecting rods to play a supporting effect. At the same time, they can correspond to the connecting ribs of the roof structure layer. After the prefabricated covering layer is laid, it is connected by grouting, making the structure of the prefabricated covering layer and the roof structure more organic and tight, and improving the tightness of the combination between various layers of the roof;

[0034] 3. The roof construction tools corresponding to the above roof layer structure adopt an integrated design and modular installation method, which are divided into several independent modules including motion control mechanism, coil unwinding mechanism, coil paving structure and pouring controller, which can effectively meet various construction processes of roof construction, have simple structure, high integration degree and convenient control, and are easy to carry out construction and management;

[0035] 4. After the construction is completed, the concrete structure between the leveling layer, the roof structure layer and the filling layer in the prefabricated covering layer is combined to form a tighter connection, making the roof structure more integrated, improving the structural strength, reducing cracking and other problems, and effectively improving the service life of the roof surface structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 The figure is a three-dimensional structural schematic diagram of a roof covering layer structure of the present invention.

[0037] Figure 2 The present invention is a partial cross-sectional structural schematic diagram of a roof covering layer structure.

[0038] Figure 3 It is a schematic diagram of the blasting structure of a roof covering structure of the present invention.

[0039] Figure 4 It is a partially enlarged structural schematic diagram of a roof covering layer structure of the present invention.

[0040] Figure 5 The figure is a three-dimensional structural schematic diagram of a roof construction tool of the present invention.

[0041] Figure 6 It is a first three-dimensional structural schematic diagram of a roofing construction tool of the present invention.

[0042] Figure 7 It is a second three-dimensional structural schematic diagram of a roofing construction tool of the present invention.

[0043] Figure 8 It is a schematic side view of the coiled material leveling structure of a roof construction tool of the present invention.

[0044] Fig. 9 It is a third stereoscopic structural schematic diagram of a roofing construction tool of the present invention.

[0045] Fig.10 It is a fourth three-dimensional structural schematic diagram of a roofing construction tool of the present invention.

[0046] Fig.11 It is a fifth three-dimensional structural schematic diagram of a roofing construction tool of the present invention.

[0047] Fig.12 The present invention is a schematic diagram of the side structure of a pouring controller of a roof construction tool.

[0048] In the figure: 1. roof structure layer; 2. leveling layer; 3. prefabricated covering layer; 4. concrete protective layer; 5. transverse track; 6. motion control mechanism; 7. coil unwinding mechanism; 8. coil paving structure; 9. pouring controller; 11. connecting ribs; 31. waterproof coil layer; 32. foam insulation layer; 33. embedded sleeve; 34. connecting rod; 35. filling slot; 341. pouring inlet; 351. middle hole; 352. connecting hole; 81. telescopic frame; 82. telescopic adjuster; 83. hoisting frame; 84. guide slot; 85 , roller press; 86, lifting slider; 87, control buffer; 61, sliding guide block; 62, transverse wheel group; 63, sliding control motor; 64, gear box; 65, transmission belt; 66, cross-connecting block; 71, support roller; 72, winding and unwinding assembly; 73, disassembly assembly; 721, rotating shaft tube; 722, winding and unwinding motor; 723, gear group; 731, shaft end tube; 732, limit rod; 91, synchronous frame; 92, casting pump; 93, lifting controller; 94, feeding pipe; 95, diversion pipe; 96, diversion feed pipe. DETAILED DESCRIPTION

[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0050] See also Figure 1-12 The present invention provides an implementation scheme: In the roof structure of modern buildings, most flat roof layers are cast with concrete. However, this concrete roof covering structure has the following problems during application: the covering is divided into multiple layers, and the construction process of each layer is different, so the construction period is long, and due to the different construction processes of the multi-layer structure, the bonding between the layers is poor, which easily causes damage to the roof structure.

[0051] Embodiment 1: In view of the above problems, according to the attached Figure 1 -Attached Figure 4It can be seen that the present application discloses a roof covering layer structure, which is designed for a flat roof structure. Specifically, the roof structure layer 1 is based on the roof structure layer 1. The roof structure layer 1 is cast with concrete and is the main body of the top structure of the house. At the same time, a plurality of connecting bars 11 arranged in a matrix are pre-embedded in the roof structure layer 1. The bottoms of the plurality of connecting bars 11 are laid in the roof structure layer 1 with a steel grid structure. A leveling layer 2 is laid on the upper layer of the roof structure layer 1. The leveling layer 2 is used to level the roof surface layer. The leveling layer 2 is a cement mortar layer. The horizontal slope of the leveling layer 2 is between 5° and 10°, and the thickness of the leveling layer 2 is between 30-40 mm. A prefabricated covering layer 3 is arranged on the leveling layer 2. In order to improve the construction efficiency, the prefabricated covering layer 3 is prefabricated in advance. During construction, the prefabricated covering layer 3 is directly laid so that the prefabricated covering layer 3 covers the top of the house. The prefabricated covering layer 3 is prefabricated in multiple layers to play a waterproof and heat-insulating role.

[0052] According to the instruction manual Figure 1 -Attached Figure 4 It can be known that the above-mentioned prefabricated covering layer 3 includes a pair of waterproof roll material layers 31, the pair of waterproof roll material layers 31 are a pair of self-adhesive rubber asphalt waterproof roll materials, the thickness of the pair of waterproof roll material layers 31 is not less than 2mm, and the inner side of the pair of waterproof roll material layers 31 is compounded with a pair of rubber reinforcement layers with a thickness of not less than 5mm, a skeleton layer is arranged between the pair of waterproof roll material layers 31, and a foam insulation layer 32 is filled between the pair of waterproof roll material layers 31. The pair of waterproof roll material layers 31 are the upper and lower closing devices of the prefabricated covering layer 3, and the skeleton layer arranged between the pair of waterproof roll material layers 31 plays a role in supporting the pair of waterproof roll material layers 31. The foam insulation layer 32 is close to the upper waterproof roll material layer 31, and the foam insulation layer 32 is an insulation attachment layer of extruded polystyrene material with a thickness between 30mm-40mm;

[0053] Furthermore, a pair of lower waterproof coiled material layers 31 are provided with a plurality of fixing holes, a plurality of embedded sleeves 33 are embedded in the plurality of fixing holes, and the plurality of embedded sleeves 33 are sleeved outside the plurality of connecting ribs 11. After the plurality of connecting ribs 11 and the plurality of embedded sleeves 33 are connected, anchor points are provided for laying the prefabricated covering layer 3, thereby fixing the prefabricated covering layer 3 and preventing the prefabricated covering layer 3 from moving.

[0054] According to the instruction manual Figure 1 -Attached Figure 4It can be seen that the above-mentioned skeleton layer is composed of a plurality of embedded sleeves 33, and the skeleton layer also includes a plurality of connecting rods 34. The ends of the plurality of embedded sleeves 33 are embedded in the foam insulation layer 32. The two ends of the embedded sleeves 33 respectively support a pair of waterproof coiled material layers 31. A plurality of connecting rods 34 are arranged on the waterproof coiled material layer 31 on the upper side of the pair. The plurality of connecting rods 34 are reversely connected with the plurality of embedded sleeves 33, so that the pair of waterproof coiled material layers 31 and the foam insulation layer 32 are relatively tied together to avoid the problem of the outlet wires of the pair of waterproof coiled material layers 31 being damaged.

[0055] According to the instruction manual Figure 2 It can be seen that the above-mentioned prefabricated covering layer 3 also includes a filling groove 35. Specifically, a filling groove 35 is provided between the lower waterproof coiled material layer 31 and the foamed insulation layer 32. The filling groove 35 is used to fill cement mortar. After the prefabricated covering layer 3 is laid, a layer of cement mortar needs to be filled in the filling layer to increase the weight of the prefabricated covering layer 3 so that it is close to the leveling layer 2, and to improve the overall structural strength of the prefabricated covering layer 3.

[0056] According to the instruction manual Figure 3 -Attached Figure 4 It can be seen that a pouring pipeline is provided between the connecting rod 34 and the embedded sleeve 33, and the pouring pipeline includes a pouring inlet 341. The end of the connecting rod 34 is provided with a pouring inlet 341, and the pouring inlet 341 is arranged along the axial direction of the connecting rod 34. The pouring inlet 341 penetrates into the embedded sleeve 33, and a plurality of connecting holes 352 are arranged in a ring array on the embedded sleeve 33 and penetrate between a pair of waterproof coiled material layers 31;

[0057] In the specific implementation process, the pouring inlet 341 adopts a socket structure, and an intermediate hole 351 is opened on the central axis of the embedded sleeve 33 to connect with the pouring inlet 341. During pouring, cement mortar enters the intermediate hole 351 under the action of high-pressure pushing. In the intermediate hole 351, the connecting rib 11 is inserted from the bottom of the intermediate hole 351. Under the action of cement mortar, the embedded sleeve 33 and the connecting rib 11 are connected as a whole, and then the connecting hole 352 is set on the outside of the intermediate hole 351. The cement mortar enters between the foamed insulation layer 32 and the waterproof membrane layer 31 from the connecting hole 352 to fill the space between the two and play a supporting role after drying. After the pouring is completed, the pouring inlet 341 of the connecting rod 34 needs to be sealed, and the sealing material uses the same material as the waterproof membrane layer 31.

[0058] Furthermore, a 20-30 mm thick concrete protective layer 4 is laid on the top of the prefabricated covering layer 3 to seal the top and maintain the structural integrity and aesthetics of the top building roof.

[0059] It should also be noted that after the prefabricated covering layer 3 is laid, there will be a gap between the top edge of the prefabricated covering layer 3 and the side wall of the building roof. Therefore, the gap needs to be sealed with sealant, and the building inner corner and the top edge of the prefabricated covering layer 3 and the upper part of the building gap are closed with a waterproof tape. The waterproof tape is cut with the same material as the waterproof membrane layer 31 and should be a rounded structure when closed.

[0060] Embodiment 2: According to the specification sheet Figure 5 -Attached Fig.12 It can be seen that in order to construct the above-mentioned roof covering structure, the present application also discloses a roof construction tool for laying the above-mentioned roof covering structure. The construction tool matches the use of the prefabricated covering layer 3, and adopts a combination of laying and pouring to carry out roof construction. The construction tools are few and the preparation work is simple.

[0061] Specifically, after the main body of the roof is constructed, a pair of transverse tracks 5 are set up on both sides of the roof outer wall, and are fixed by scaffolding. The pair of transverse tracks 5 are arranged in parallel on the roof, and a motion control mechanism 6 is installed on the pair of transverse tracks 5, which is used as a traveling device;

[0062] Furthermore, a coil unwinding mechanism 7 is provided on the motion control mechanism 6, and the prefabricated covering layer 3 is arranged in a roll on the coil unwinding mechanism 7. As the motion control mechanism 6 drives the coil unwinding mechanism 7 to move, the prefabricated covering layer 3 is unwound at a certain linear speed, and then a coil paving structure 8 is separately connected to one side of the coil unwinding mechanism 7. The coil paving structure 8 squeezes the prefabricated covering layer 3 laid on the roof so that the prefabricated covering layer 3 is laid flat on the roof. A pouring controller 9 is also provided on the motion control mechanism 6. The pouring controller 9 is used to pour inside the prefabricated covering layer 3. The pouring controller 9 is also responsible for the pouring construction of the roof leveling layer 2 and the concrete protective layer 4.

[0063] According to the instruction manual Figure 7 -Attached Figure 8It can be seen that the coiled material paving structure 8 includes a telescopic frame 81, which is installed on the motion control mechanism 6. A telescopic adjuster 82 is provided on the telescopic frame 81. The telescopic adjuster 82 uses a screw structure to control the lifting and lowering of the telescopic frame 81, and then a hanging frame 83 is provided on the telescopic adjuster 82. The hanging frame 83 is divided into a plurality of guide grooves 84, and each guide groove 84 is correspondingly provided with a roller press 85. A pin is movably installed in the middle of the roller press 85, and the roller press 85 can rotate with the pin as the axis. By adjusting the telescopic adjuster 82, a plurality of released prefabricated covering layers 3 on the hanging frame 83 pass through the lower part of the roller press 85. Under the pressing action of the roller press 85, the prefabricated covering layer 3 is tightly covered and pasted on the leveling layer 2. The roller press 85 is divided into a plurality of groups, which can be adjusted according to the horizontal angle of the leveling layer 2.

[0064] According to the instruction manual Figure 7 -Attached Figure 8 It can be seen that the roller press 85 is a plate of a columnar structure, and an axial cavity matching the pin shaft is opened in the middle of the roller press 85. A pair of limit bearings are provided on both sides of the axial cavity and sleeved on the pin shaft. During the movement of the roller press 85, the pair of limit bearings play a role in limiting the roller press 85, thereby preventing the roller press 85 from horizontal movement and reducing the rotation resistance of the roller press 85.

[0065] According to the instruction manual Figure 7 -Attached Figure 8 It can be seen that in order to match the horizontal slope change of the leveling layer 2, a pair of lifting sliders 86 are provided at both ends of the pin shaft, and a pair of control buffers 87 are installed on the guide groove 84. The ends of the pair of control buffers 87 are connected to the pair of lifting sliders 86. The pair of lifting sliders 86 are movably matched with the two ends of the pin shaft. The pair of lifting sliders 86 and the two sides of the pin shaft respectively control the height of the pair of lifting sliders 86 through the pair of control buffers 87, thereby adjusting the position of the pair of lifting sliders 86, so that the pair of lifting sliders 86 can synchronously adjust the height of the roller press 85;

[0066] The control buffer 87 is composed of a guide rod and a guide groove 84. The guide groove 84 is set on the hanging frame 83. The guide rod is assembled in the guide groove 84. The end of the guide rod is movably connected with the hanging slider 86. The outer sleeve of the guide rod is provided with a reset spring. The two ends of the reset spring are supported between the hanging slider 86 and the guide groove 84. As the horizontal height of the leveling layer 2 changes, the reset spring expands and contracts, and the guide rod moves in the guide groove 84 to keep the roller 85 always in contact with the prefabricated covering layer 3.

[0067] According to the instruction manual Figure 5 -Attached Figure 6It can be known that the motion control mechanism 6 includes a pair of sliding guide blocks 61, which are assembled on a pair of transverse rails 5. The pair of sliding guide blocks 61 are laterally fixed with at least a pair of reinforcing rods by screws. A pair of transverse wheel groups 62 are arranged on one side of the transverse rail 5. A sliding control system is arranged between the pair of transverse wheel groups 62. The pair of sliding guide blocks 61 are matched with the pair of transverse rails 5. The pair of transverse rails 5 play a guiding and limiting role for the pair of sliding guide blocks 61. The movement of the sliding guide blocks 61 on the transverse rails 5 is controlled by the sliding control system between the pair of transverse wheel groups 62. The pair of sliding guide blocks 61 on the transverse rails 5 are symmetrically arranged and move synchronously, so that the pair of sliding guide blocks 61 drive the casting controller 9, the coil unwinding mechanism 7 and the coil paving structure 8 to move horizontally to complete laying and casting.

[0068] According to the instruction manual Figure 5 -Attached Figure 6 It can be known that the above-mentioned sliding control system includes a sliding control motor 63, the driving end of the sliding control motor 63 is connected to a gear box 64, the gear box 64 is a reduction wheel group, the output end of the gear box 64 is connected to the central axis of the transverse shift wheel group 62, a pair of transverse shift wheel groups 62 are sleeved with a transmission belt 65, a pair of transverse shift wheel groups 62 and the transmission belt 65 form a belt drive, a transverse connecting block 66 is arranged on the transmission belt 65 and connected to the sliding guide block 61, a slot is opened on the sliding guide block 61, the transverse connecting block 66 is arranged corresponding to the slot, and the transverse connecting block 66 is fixedly connected to the slot by bolts;

[0069] During the specific implementation process, the sliding control motor 63 drives the gear box 64 to rotate, so that the gear box 64 drives the transverse shifting wheel group 62 on one side to rotate, and a pair of transverse shifting wheel groups 62 and the transmission belt 65 form a belt drive, and then the pair of transverse shifting wheel groups 62 drive the transverse connecting block 66 to move. The transverse connecting block 66 is fixedly connected to the slot by bolts, so that the transverse connecting block 66 synchronously drives the sliding guide block 61 to move during the movement.

[0070] According to the instruction manual Fig. 9 -Attached Fig.10 It can be seen that the coil unwinding mechanism 7 includes a support roller 71, both ends of the support roller 71 are movably assembled on a pair of sliding guide blocks 61, one side of the support roller 71 is connected to a reeling and unreeling assembly 72, the reeling and unreeling assembly 72 is used to control the rotation of the support roller 71, the prefabricated covering layer 3 is wound on the support roller 71, and a disassembly assembly 73 is provided at the end of the support roller 71;

[0071] In the specific implementation process, the support roller 71 is used to place and support the material roll of the prefabricated covering layer 3. One end of the support roller 71 is controlled by the reel-in assembly 72. The reel-in assembly 72 controls the rotation of the support roller 71, so that the support roller 71 drives the prefabricated covering layer 3 to rotate to complete the reeling and unreeling of the material roll. A disassembly assembly 73 is provided at the end of the support roller 71 for installing and fixing the support roller 71.

[0072] According to the instruction manual Fig. 9 -Attached Fig.10 It can be known that the above-mentioned winding and unwinding assembly 72 includes a rotating shaft tube 721, which is installed on the sliding guide block 61, and the rotating shaft tube 721 and the sliding guide block 61 are movably matched. The sliding guide block 61 is provided with a rotating groove, and the rotating shaft tube 721 is assembled on the rotating groove. One end of the support roller 71 is inserted into the rotating shaft tube 721, and the rotating shaft tube 721 and the end of the support roller 71 are limited by the shaft key. One side of the rotating shaft tube 721 is connected to the winding and unwinding motor 722, and the winding and unwinding motor 722 controls the rotation of the rotating shaft tube 721 through the gear set 723;

[0073] During the specific implementation process, the rotating shaft tube 721 cooperates with the rotating groove, and an opening on one side of the rotating shaft tube 721 is used to insert the support roller 71. A gear set 723 is set on the rotating shaft tube 721, and the gear set 723 is connected to the rewinding and unwinding motor 722. The rewinding and unwinding motor 722 drives the gear set 723 to rotate, and then the gear set 723 is used to increase the transmission torque, so that the rotating shaft tube 721 drives the support roller 71 to rotate through the shaft key.

[0074] According to the instruction manual Figure 9-10 It can be known that the above-mentioned disassembly and assembly components include an axle end tube 731, which is arranged on the sliding guide block 61 on the other side corresponding to the rotating axle tube 721, and a guide groove 84 is provided on the axle end tube 731, and the support roller 71 is inserted from one side of the guide groove 84, and a plug hole is provided on the axle end tube 731, and a positioning hole is provided at the end of the support roller 71 corresponding to the plug hole, and a limit rod 732 is inserted in the plug hole and connected to the positioning hole;

[0075] During the specific implementation process, the shaft end tube 731 is movably installed on the sliding guide block 61, and the guide groove 84 on the shaft end tube 731 is used for the support roller 71 to pass through. The insertion hole on the shaft end tube 731 corresponds to the positioning hole at the end of the support roller 71. The shaft end of the support roller 71 is radially limited by the limiting rod 732, so that the shaft end tube 731 and the support roller 71 can rotate together, and the outside of the shaft end tube 731 is movably connected to the sliding guide block 61 to play a role in reducing drag.

[0076] According to the instruction manual Fig.11 -Attached Fig.12It can be seen that the above-mentioned pouring controller 9 includes a synchronous frame 91, which is mounted on a pair of sliding guide blocks 61, and a pouring pump 92 is arranged on the synchronous frame 91. A lifting controller 93 is connected to the unloading end of the pouring pump 92, and a feeding pipe 94 is installed on the lifting controller 93. A shunt pipe 95 is connected to one side of the feeding pipe 94, and a plurality of branch feeding pipes 96 are evenly arranged on the shunt pipe 95, and the branch feeding pipes 96 correspond to the position of the connecting rod 34;

[0077] In the specific implementation process, the synchronous frame 91 is separately connected with a pair of sliding guide blocks 61, and a pouring pump 92 is mounted on the synchronous frame 91. When pouring, the pouring pump 92 is connected to the concrete truck through a conveying pipe, and the feed pipe 94 adjusts its height under the control of the lifting controller 93, so that the feed pipe 94 drives the diversion pipe 95 to move, and a plurality of branch feed pipes 96 are connected to the diversion pipe 95. Under the diversion effect of the branch feed pipes 96, the mortar is diverted, and the branch feed pipes 96 are inserted into the pouring inlet 341 of the connecting rod 34. Under the pumping effect of the branch feed pipes 96, the mortar is pumped into the filling layer.

[0078] It should be noted that the branch feed pipe 96 is connected to the diversion pipe 95 with a threaded structure. The branch feed pipe 96 is used when the filling layer needs to be poured. The branch feed pipe 96 has a diversion function. When other pouring work is required, the branch feed pipe 96 can be removed and poured directly to increase the pouring flow rate.

[0079] Embodiment 3: In order to cooperate with the above-mentioned roof construction tools to carry out roof structure construction, the present application discloses a roof structure construction method, which specifically includes the following steps: equipment installation, leveling layer 2 construction, prefabricated covering layer 3 installation, prefabricated covering layer 3 paving, filling layer filling, corner processing and concrete protective layer 4 construction;

[0080] Equipment installation: After the main roof structure is constructed, a pair of transverse tracks 5 are symmetrically arranged on the main roof, and roof construction tools are installed through the pair of transverse tracks 5;

[0081] Construction of the leveling layer 2: connect the external concrete truck to the pouring controller 9 to feed the leveling layer 2, drive the pouring controller 9 to move through the motion control mechanism 6, pour concrete onto the roof structure layer 1 through the pouring controller 9, and manually modify the leveling layer 2 so that the horizontal slope of the leveling layer 2 is between 5° and 10°, and the thickness of the leveling layer 2 is between 30-40mm;

[0082] Installation of the prefabricated cladding layer 3: hoist the material of the prefabricated cladding layer 3 between a pair of sliding guide blocks 61 of the motion control mechanism 6, install the coil of the prefabricated cladding layer 3 on the coil unwinding mechanism 7 by installing the support roller 71 through the roll center of the prefabricated cladding layer 3;

[0083] Prefabricated covering layer 3 paving: after the leveling layer 2 is dried, one end of the prefabricated covering layer 3 is pulled out from the coil, so that the bottom surface of the prefabricated covering layer 3 is bonded to the leveling layer 2, and the coil unwinding mechanism 7 is driven by the motion control mechanism 6 to move, and the motion unwinding mechanism unwinds the prefabricated covering layer 3, and the prefabricated covering layer 3 is closely attached to the leveling layer 2 through the coil paving structure 8, and the prefabricated covering layer 3 is completely attached to the angle of the leveling layer 2;

[0084] Filling the filling layer: When the prefabricated covering layer 3 is laid, the embedded sleeve 33 on the prefabricated covering layer 3 corresponds to the connecting rib 11, and the embedded sleeve 33 covers the connecting rib 11. The cement slurry is poured from the top of the connecting rod 34. The cement slurry is filled in the filling layer and wraps the connecting rib 11. After drying, the top opening of the connecting rod 34 is sealed with a patch of waterproof membrane;

[0085] Corner treatment: After the prefabricated covering layer 3 is paved, the top edge and the building gap are sealed with sealant, and the building inner corner and the top edge of the prefabricated covering layer 3 and the upper part of the building gap are sealed with waterproof tape;

[0086] Pouring of concrete protective layer 4: After the filling layer is constructed, an external concrete truck is connected to the pouring controller 9 to feed the leveling layer 2. The pouring controller 9 is driven by the motion control mechanism 6 to pour concrete onto the prefabricated covering layer 3.

[0087] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A roof covering structure, comprising a roof structure layer (1), wherein the roof structure layer (1) is cast by concrete, wherein a plurality of connecting bars (11) arranged in a matrix are pre-embedded in the roof structure layer (1), and a leveling layer (2) is laid on the upper layer of the roof structure layer (1), characterized in that: A prefabricated covering layer (3) is arranged on the leveling layer (2); The prefabricated covering layer (3) comprises a pair of waterproof coiled material layers (31), a skeleton layer is arranged between the pair of waterproof coiled material layers (31), and a foamed thermal insulation layer (32) is filled between the pair of waterproof coiled material layers (31); A pair of lower waterproof coiled material layers (31) are provided with a plurality of fixing holes, a plurality of pre-embedded sleeves (33) are embedded in the plurality of fixing holes, and the plurality of pre-embedded sleeves (33) are sleeved outside a plurality of connecting ribs (11); The skeleton layer is composed of a plurality of embedded sleeves (33), and the skeleton layer also includes a plurality of connecting rods (34). The ends of the plurality of embedded sleeves (33) are embedded in the foam insulation layer (32). A plurality of connecting rods (34) are arranged on the waterproof coiled material layer (31) on the upper side of the center. The plurality of connecting rods (34) are connected to the plurality of embedded sleeves (33) by reverse pulling. The prefabricated covering layer (3) further comprises a filling groove (35), wherein the filling groove (35) is arranged between the waterproof coiled material layer (31) and the foamed thermal insulation layer (32), and the filling groove (35) is used to fill cement mortar; A casting pipeline is provided between the connecting rod (34) and the embedded sleeve (33); A 20-30 mm thick concrete protective layer (4) is laid on the top of the prefabricated covering layer (3).

2. A roof covering structure according to claim 1, characterized in that: The leveling layer (2) is a cement mortar layer, the horizontal slope of the leveling layer (2) is between 5° and 10°, and the thickness of the leveling layer (2) is between 30-40 mm.

3. A roof covering structure according to claim 2, characterized in that: The pair of waterproof roll material layers (31) are a pair of self-adhesive rubber asphalt waterproof roll materials, the thickness of the pair of waterproof roll material layers (31) is not less than 2 mm, and the inner sides of the pair of waterproof roll material layers (31) are compounded with a pair of rubber reinforcement layers with a thickness of not less than 5 mm.

4. A roof covering structure according to claim 3, characterized in that: The top edge of the prefabricated covering layer (3) and the building gap are sealed by means of sealant, and the building inner corner and the top edge of the prefabricated covering layer (3) and the upper part of the building gap are sealed by means of waterproof tape.

5. A roof construction tool, applied to a roof covering structure according to any one of claims 1 to 4, characterized in that: It comprises a pair of transverse tracks (5), the pair of transverse tracks (5) are arranged in parallel on the roof, and a motion control mechanism (6) is installed on the pair of transverse tracks (5); The motion control mechanism (6) is provided with a coil unwinding mechanism (7), the prefabricated covering layer (3) is arranged in a roll on the coil unwinding mechanism (7), one side of the coil unwinding mechanism (7) is separately connected to a coil flattening structure (8), and the coil flattening structure (8) presses the prefabricated covering layer (3) laid on the roof so that the prefabricated covering layer (3) is laid flat on the roof; The coiled material flattening structure (8) comprises a telescopic frame (81), the telescopic frame (81) is mounted on a motion control mechanism (6), a telescopic adjuster (82) is arranged on the telescopic frame (81), a hanging frame (83) is arranged on the telescopic adjuster (82), the hanging frame (83) is divided into a plurality of guide grooves (84), a roller press (85) is arranged on any of the guide grooves (84), and a pin is movably installed in the middle of the roller press (85); A pair of lifting sliders (86) are provided at both ends of the pin shaft, a pair of control buffers (87) are mounted on the guide groove (84), the ends of the pair of control buffers (87) are connected to the pair of lifting sliders (86), and the pair of lifting sliders (86) are movably matched with both ends of the pin shaft; The motion control mechanism (6) is also provided with a pouring controller (9), and the pouring controller (9) is used to pour the prefabricated covering layer (3).

6. A roofing construction tool according to claim 5, characterized in that: The motion control mechanism (6) comprises a pair of sliding guide blocks (61), the pair of sliding guide blocks (61) are assembled on a pair of transverse tracks (5), the pair of sliding guide blocks (61) are laterally fixedly connected with at least a pair of reinforcing rods by screws, a pair of transverse wheel groups (62) are arranged on one side of the transverse track (5), and a sliding control system is arranged between the pair of transverse wheel groups (62).

7. A roofing construction tool according to claim 6, characterized in that: The sliding control system comprises a sliding control motor (63), a driving end of the sliding control motor (63) is connected to a gear box (64), an output end of the gear box (64) is connected to a central axis of a transverse shift wheel group (62), a pair of the transverse shift wheel groups (62) are provided with a transmission belt (65), a pair of the transverse shift wheel groups (62) and the transmission belt (65) form a belt drive, a transverse connecting block (66) is provided on the transmission belt (65), and the transverse connecting block (66) is connected to a sliding guide block (61).

8. A roofing construction tool according to claim 7, characterized in that: The coil unwinding mechanism (7) comprises a supporting roller (71), the two ends of the supporting roller (71) are movably mounted on a pair of sliding guide blocks (61), one side of the supporting roller (71) is connected with a winding and unwinding assembly (72), the winding and unwinding assembly (72) is used to control the rotation of the supporting roller (71), the prefabricated covering layer (3) is wound on the supporting roller (71), and a disassembly assembly (73) is arranged at the end of the supporting roller (71).

9. A roofing construction tool according to claim 8, characterized in that: The reeling and unwinding assembly (72) comprises a rotating shaft tube (721), which is mounted on a sliding guide block (61). The rotating shaft tube (721) and the sliding guide block (61) are movably matched, and a rotating groove is provided on the sliding guide block (61). The rotating shaft tube (721) is assembled on the rotating groove. One end of the support roller (71) is inserted into the rotating shaft tube (721), and the rotating shaft tube (721) and the end of the support roller (71) are limited by a shaft key. One side of the rotating shaft tube (721) is connected to a reeling and unwinding motor (722), and the reeling and unwinding motor (722) controls the rotation of the rotating shaft tube (721) through a gear set (723).

10. A roofing construction tool according to claim 9, characterized in that: The pouring controller (9) comprises a synchronous frame (91), wherein the synchronous frame (91) is mounted on a pair of sliding guide blocks (61), a pouring pump (92) is arranged on the synchronous frame (91), a lifting controller (93) is connected to the discharge end of the pouring pump (92), a feeding pipe (94) is installed on the lifting controller (93), a branch pipe (95) is connected to one side of the feeding pipe (94), a plurality of branch feeding pipes (96) are evenly arranged on the branch feeding pipe (95), and the branch feeding pipes (96) correspond to the positions of the connecting rod (34).

Citation Information

Patent Citations

  • Foam-concrete roof structure

    CN106703302A

  • Fabricated roof waterproof structure

    CN212773194U