Splicing nodes and construction methods of steel tube concrete composite columns and reinforced concrete columns

By setting an annular splicing part and pressed steel plates on the steel pipe concrete stacked columns and reinforced concrete columns, the problem of lack of reliable splicing methods in the prior art is solved, and efficient and firm connections are achieved, which are suitable for high-rise buildings.

CN119332829BActive Publication Date: 2025-03-28HUAQIAO UNIVERSITY

Patent Information

Application Number
CN202411896628.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-12-23
Publication Date
2025-03-28
Estimated Expiration
2044-12-23

AI Technical Summary

Technical Problem

The prior art lacks reliable methods for splicing steel pipe concrete stacked columns and reinforced concrete columns, which limits the application of steel pipe concrete stacked columns in high-rise buildings.

Method used

Using splicing nodes including an annular splicing part and a pressed steel plate, a plurality of through holes and slots are provided on the steel pipe concrete stacking column and the reinforced concrete column, and the steel plate and the clamping part are connected, a stable splicing is achieved.

Benefits of technology

The firm connection between the steel pipe concrete stacked column and the reinforced concrete column is achieved, ensuring load transfer, improving stress performance, and simplifying the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119332829B_ABST
    Figure CN119332829B_ABST
Patent Text Reader

Abstract

The present invention provides a splicing node and construction method of a steel tube concrete composite column and a reinforced concrete column, wherein the splicing node comprises a steel tube concrete composite column, a reinforced concrete column, a splicing portion and a corrugated steel plate. Through the arrangement of the splicing portion and the corrugated steel plate, the splicing node structure of the steel tube concrete composite column and the reinforced concrete column is firm, and the load transfer between the reinforced concrete composite column and the reinforced concrete column can be ensured; the lower end of the steel bar is anchored in the external concrete of the steel tube concrete composite column, the connecting steel plate resists the slip between the external concrete and the steel tube, the corrugated steel plate can be used as a part of the template when pouring concrete, and does not need to be removed after pouring is completed, and can form a firm whole with other components of the splicing node to work together, thereby improving its force performance; at the same time, the node has a simple structure and is convenient to construct, and realizes the splicing of the steel tube concrete composite column and the reinforced concrete column, and has broad application prospects in high-rise buildings.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building structures, and in particular to a splicing node of a steel tube concrete composite column and a reinforced concrete column and a construction method. Background Art

[0002] Steel tube concrete composite column is a new type of efficient composite component developed in recent years. It can give full play to the material properties of both steel and concrete, and has the advantages of high bearing capacity and good seismic performance. At the same time, it is also conducive to the application of high-strength concrete, which can reduce the cross-sectional size of the column, thus having greater advantages in the spatial layout of the building. However, with the increase in building height, the vertical load on the structure of the high-rise building gradually decreases, and it is no longer necessary to continue to use steel tube concrete composite columns. Therefore, after the building reaches a certain height, the steel tube concrete composite column can be replaced with an ordinary reinforced concrete column to save steel and reduce costs. However, since there is currently no more reliable way to splice the two, the application and development of steel tube concrete composite columns in high-rise buildings is restricted. Summary of the invention

[0003] The invention discloses a splicing node of a steel tube concrete composite column and a reinforced concrete column and a construction method to solve the above problems.

[0004] The present invention adopts the following scheme:

[0005] The present application provides a splicing node of a steel tube concrete composite column and a reinforced concrete column, comprising a steel tube concrete composite column and a reinforced concrete column, and also comprising an annular splicing portion and a corrugated steel plate, wherein the splicing portion is provided with a plurality of first through holes along an annular direction, and a plurality of first slots with outer openings;

[0006] Two connecting steel plates are arranged at intervals along the vertical direction on the outer side of the steel tube of the steel tube concrete composite column, the connecting steel plate at the upper end is provided with a second through hole and a second slot corresponding to the first through hole and the first slot, and the connecting steel plate at the lower end is provided with a third slot corresponding to the second slot; the splicing part is sleeved and connected to the steel tube and placed on the connecting steel plate at the upper end; the corrugated steel plate is provided with a clamping part adapted to the slot, and the clamping part is arranged outside the steel tube;

[0007] The longitudinal reinforcement of the reinforced concrete column is inserted into the through hole; and concrete is poured in the corrugated steel plate.

[0008] Further, the splicing portion includes two annular steel plates arranged at intervals in the vertical direction, and longitudinal steel plates connected between the outer ends of the two annular steel plates; the annular steel plates are placed inside the longitudinal steel plates and are provided with a plurality of the first through holes and a plurality of first clamping grooves with outer openings along the circumferential direction, and the longitudinal steel plates are provided with through grooves corresponding to the outer openings.

[0009] Further, the annular steel plates are U-shaped steel plates, and the longitudinal steel plates include angle steels connected between the four corners of the two U-shaped steel plates, and four square steel plates placed between the angle steels and connecting the U-shaped steel plates, and a through groove is formed by arranging the square steel plates and the angle steels at intervals.

[0010] Further, the first connecting steel plate placed at the upper outer side of the steel pipe includes four transverse angle steels, one web is welded to the outer side edge of the steel pipe, and the other web is provided with the second through hole and the second clamping groove; the second connecting steel plate at the lower end is four transverse channel steels in the shape of a C, and the middle web is welded to the outer side edge of the steel pipe, and the upper and lower wing plates are provided with the third clamping groove.

[0011] Further, the profiled steel sheet is formed by connecting four steel sheets with through-length clamping portions, and the steel sheets are mutually buckled through the bent portions on the sides.

[0012] Further, a limiting plate for limiting with the connecting steel plate at the upper outer side of the steel pipe or the upper end face of the splicing portion is arranged inside the profiled steel sheet.

[0013] Further, high-strength concrete is poured into the steel pipe, and high-ductility concrete is poured between the profiled steel sheet and the steel pipe.

[0014] A construction method for a splicing joint of the steel pipe concrete composite column and the reinforced concrete column as described above includes the following steps: welding two U-shaped steel plates, four angle steels and four square steel plates into a splicing portion; welding the first connecting steel plate and the second connecting steel plate on the outer side edge of the steel pipe;

[0015] Sleeving the splicing portion on the steel pipe and placing it on the first connecting steel plate, and welding and fixing it;

[0016] Aligning the clamping portions of the profiled steel sheet, and sequentially passing through the splicing component, the first connecting steel plate and the second connecting steel plate from top to bottom, and surrounding the outside of the steel pipe;

[0017] Sequentially vertically passing the longitudinal bars of the reinforced concrete column through the through holes from top to bottom, extending into the pouring space formed by the steel pipe and the profiled steel sheet, and performing spot welding and fixing at the positions of the through holes;

[0018] The casting formwork is set up outside the longitudinal reinforcement, and then concrete is poured inside the steel pipe, in the casting space composed of the steel pipe and the corrugated steel plate, and in the casting formwork.

[0019] Furthermore, high-strength concrete is first poured into the steel pipe, and then high-ductility concrete is poured between the corrugated steel plate and the steel pipe, and finally ordinary concrete is poured into the pouring template.

[0020] By adopting the above technical solution, the present invention can achieve the following technical effects:

[0021] The present invention provides a splicing node of a steel tube concrete composite column and a reinforced concrete column. The splicing part and the corrugated steel plate are arranged to make the splicing node structure of the steel tube concrete composite column and the reinforced concrete column firm, and can ensure the load transfer between the reinforced concrete composite column and the reinforced concrete column; the lower end of the steel bar is anchored in the external concrete of the steel tube concrete composite column, the connecting steel plate resists the slip between the external concrete and the steel tube, the corrugated steel plate can be used as a part of the template when pouring concrete, and does not need to be removed after the pouring is completed, and can form a firm whole with other components of the splicing node to work together, thereby improving its stress performance; at the same time, the node has a simple structure and is convenient to construct, and realizes the splicing of the steel tube concrete composite column and the reinforced concrete column, and has broad application prospects in high-rise buildings. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of a joint structure of a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0023] Figure 2 It is a schematic structural diagram of a splicing portion of a splicing node of a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0024] Figure 3 It is a schematic diagram of the top view of the structure of a splicing portion of a splicing node of a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0025] Figure 4 It is a structural schematic diagram of welding steel pipes, transverse angle steels and transverse channel steels at a splicing node of a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0026] Figure 5 It is a schematic diagram of a corrugated steel plate structure of a splicing node between a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0027] Figure 6 It is a schematic diagram of the top view of the structure of a steel tube concrete composite column after assembly at a splicing node of a steel tube concrete composite column and a reinforced concrete column according to an embodiment of the present invention;

[0028] Figure 7 It is a schematic structural diagram of a splicing node of a steel tube concrete composite column and a reinforced concrete column after the longitudinal reinforcement of the reinforced concrete is assembled according to an embodiment of the present invention;

[0029] Icon: splicing part 1, U-shaped steel plate 11, angle steel 12, square steel plate 13, first through hole 14; first slot 15, steel tube concrete composite column 2, steel tube 21, transverse angle steel 22, transverse channel steel 23, corrugated steel plate 24, reinforced concrete column 3, longitudinal reinforcement 31, second through hole 221, second slot 222, third slot 231, clamping part 241. DETAILED DESCRIPTION

[0030] Example

[0031] Combination Figures 1 to 7 As shown, this embodiment provides a splicing node of a steel tube concrete composite column and a reinforced concrete column, including a steel tube concrete composite column 2 and a reinforced concrete column 3, and also includes an annular splicing portion 1 and a corrugated steel plate 24, wherein the splicing portion 1 is provided with a plurality of first through holes 14 along the annular direction, and a plurality of first slots 15 with outer openings;

[0032] Two connecting steel plates are arranged at intervals along the vertical direction on the outer side of the steel tube 21 of the steel tube concrete composite column 2, wherein the connecting steel plate at the upper end is provided with a second through hole 221 and a second slot 222 corresponding to the first through hole 14 and the first slot 15, and the connecting steel plate at the lower end is provided with a third slot 231 corresponding to the second slot 222; the splicing portion 1 is sleeved and connected to the steel tube 21 and placed on the connecting steel plate at the upper end; the corrugated steel plate 24 is provided with a clamping portion 241 adapted to the slot, and the clamping portion 241 is arranged outside the steel tube 21;

[0033] The longitudinal reinforcement 31 of the reinforced concrete column 3 is inserted into the through hole; and concrete is poured in the corrugated steel plate 24 .

[0034] By setting the splicing part 1 and the corrugated steel plate 24, the splicing node structure of the steel tube concrete composite column 2 and the reinforced concrete column 3 is made firm, which can ensure the load transfer between the reinforced concrete composite column and the reinforced concrete column 3; the lower end of the steel bar is anchored in the external concrete of the steel tube concrete composite column 2, and the connecting steel plate resists the slippage between the external concrete and the steel tube 21. The corrugated steel plate 24 can be used as a part of the template when pouring concrete, and does not need to be removed after the pouring is completed. It can form a firm whole with other components of the splicing node to work together and improve its stress performance; at the same time, the node has a simple structure and convenient construction, which realizes the splicing of the steel tube concrete composite column 2 and the reinforced concrete column 3, and has broad application prospects in high-rise buildings.

[0035] In this embodiment, the square steel tube concrete composite column 2 and the reinforced concrete column 3 are taken as examples. Figure 2 As shown, the splicing part 1 includes two U-shaped steel plates 11 spaced apart in the vertical direction, and a longitudinal steel plate welded between the outer ends of the two U-shaped steel plates 11; the annular steel plate is placed on the inner side of the longitudinal steel plate and is provided with a plurality of the first through holes 14 along the annular direction, and a plurality of first slots 15 with outer openings, and the longitudinal steel plate is provided with through slots corresponding to the outer openings. The longitudinal steel plate includes an angle steel 12 connected between the four corners of the two U-shaped steel plates 11, and four square steel plates 13 placed between the angle steels 12 and connected to the U-shaped steel plates 11, and the square steel plates 13 and the angle steels 12 are spaced apart to form the through slots.

[0036] like Figure 4 As shown, the steel pipe 21 is a square steel pipe, and the first connecting steel plate and the second connecting steel plate are welded at intervals along the vertical direction on the outer side thereof. The first connecting steel plate at the upper end includes four transverse angle steels 22, one web of which is welded to the outer side of the steel pipe 21, and the other web is provided with the second through hole 221 and the second clamping groove 222; the second connecting steel plate at the lower end is four transverse channel steels 23 in the shape of a Chinese character, the middle web of which is welded to the outer side of the steel pipe 21, and the upper and lower wing plates are provided with the third clamping groove 231.

[0037] In this embodiment, if Figure 5 As shown, the corrugated steel plate 24 is formed by connecting four steel plates with a full-length clamping portion 241, and the steel plates are buckled with each other through the bending portion of the side. Of course, the four steel plates can also be formed into an integrated corrugated steel plate 24 by welding the side. The inner side of the corrugated steel plate 24 is provided with a limit plate that limits the connection steel plate at the upper end of the outer side of the steel pipe 21 or the upper end surface of the splicing portion 1. So that the corrugated steel plate 24 can prevent it from sliding down when the clamping portion 241 is aligned with the clamping groove and is sleeved on the outer side of the steel pipe 21 from top to bottom; so that the upper end surface of the corrugated steel plate 24 is flush with the upper end surface of the splicing portion 1, or partially higher than the upper end surface of the splicing portion 1.

[0038] like Figure 7As shown, the longitudinal reinforcement 31 of the reinforced concrete column 3 passes through the first through hole 14 and the second through hole 221 and abuts against the transverse channel steel 23; is placed in the casting space between the steel pipe 21 and the corrugated steel plate 24, and is fixed by electric welding at the through hole; and the longitudinal reinforcement 31 placed outside the casting space is hooped with stirrups. Of course, in other embodiments, the steel cage of the reinforced concrete column 3 can be prefabricated, and the longitudinal reinforcement 31 at one end of the steel cage is reserved with a plug-in section without the stirrup, and the plug-in section is plugged into the through hole after the steel cage is hoisted, and then fixed by spot welding.

[0039] Preferably, in this embodiment, high-strength concrete is poured inside the steel pipe 21, high-ductility concrete is poured between the corrugated steel plate 24 and the steel pipe 21, and a casting formwork is set up outside the longitudinal reinforcement 31 and ordinary concrete is poured.

[0040] A construction method for a splicing node of a steel tube concrete composite column and a reinforced concrete column comprises the following steps:

[0041] Weld two U-shaped steel plates 11, four angle steels 12 and four square steel plates 13 into a splicing portion 1; weld a first connecting steel plate and a second connecting steel plate on the outer side of the steel pipe 21;

[0042] The splicing part 1 is sleeved on the steel pipe 21 and placed on the first connecting steel plate, and then fixed by welding;

[0043] The clamping portion 241 of the corrugated steel plate 24 is aligned with the clamping port, and passes through the splicing portion 1, the first connecting steel plate and the second connecting steel plate in sequence from top to bottom, and is arranged outside the steel pipe 21;

[0044] The longitudinal reinforcement 31 of the reinforced concrete column 3 is passed vertically through the through holes from top to bottom, and extends into the casting space formed by the steel pipe 21 and the corrugated steel plate 24, and is fixed by spot welding at the through hole position;

[0045] A casting formwork is set up outside the longitudinal reinforcement 31, and then concrete is poured into the steel pipe 21, into the casting space formed by the steel pipe 21 and the corrugated steel plate 24, and into the casting formwork.

[0046] When pouring concrete, high-strength concrete is first poured into the steel pipe 21 , and then high-ductility concrete is poured between the corrugated steel plate 24 and the steel pipe 21 , and finally ordinary concrete is poured into the pouring template.

[0047] It should be understood that the above are only preferred implementations of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention.

[0048] The above description of the drawings used in the implementation manner only illustrates certain embodiments of the present invention and should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

Claims

1. A splicing node of a steel tube concrete composite column and a reinforced concrete column, comprising a steel tube concrete composite column and a reinforced concrete column, characterized in that: It further includes an annular splicing part and profiled steel sheets. Multiple first through holes and multiple first card slots with outer openings are arranged on the splicing part along the circumferential direction. Two connecting steel plates are arranged at intervals along the vertical direction on the outer side of the steel pipe of the concrete-filled steel tube composite column. The upper connecting steel plate is provided with second through holes and second card slots corresponding to the first through holes and the first card slots, and the lower connecting steel plate is provided with third card slots corresponding to the second card slots. The splicing part is sleeved and connected to the steel pipe and placed on the upper connecting steel plate. The profiled steel sheet is provided with a clamping part adapted to the card slot, and the clamping part is clamped around the outer side of the steel pipe. The longitudinal bars of the reinforced concrete column are inserted into the through holes. Concrete is poured into the profiled steel sheet.

2. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 1 is characterized in that: The splicing part includes two annular steel plates arranged at intervals along the vertical direction and longitudinal steel plates connected between the outer ends of the two annular steel plates. The annular steel plates are placed inside the longitudinal steel plates and are provided with multiple first through holes and multiple first card slots with outer openings along the circumferential direction. The longitudinal steel plates are provided with through slots corresponding to the outer openings.

3. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 2 is characterized in that: The annular steel plates are U-shaped steel plates. The longitudinal steel plates include angle steels connected between the four corners of the two U-shaped steel plates and four square steel plates placed between the angle steels to connect the U-shaped steel plates. A through slot is formed by the interval between the square steel plates and the angle steels.

4. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 3 is characterized in that: The first connecting steel plate placed at the upper outer side of the steel pipe includes four transverse angle steels. One web is welded to the outer side edge of the steel pipe, and the other web is provided with the second through holes and the second card slots. The lower second connecting steel plate is four transverse channel steels in a C shape. The middle web is welded to the outer side edge of the steel pipe, and the upper and lower wing plates are provided with the third card slots.

5. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 4, characterized in that: The profiled steel sheet is formed by connecting four steel sheets with through-length clamping parts, and the steel sheets are buckled with each other through the bending parts on the side edges.

6. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 1, characterized in that: A limiting plate for limiting with the connecting steel plate at the upper outer side of the steel pipe or the upper end face of the splicing part is arranged on the inner side of the profiled steel sheet.

7. The splicing node of the steel tube concrete composite column and the reinforced concrete column according to claim 1, characterized in that: High-strength concrete is poured into the steel pipe, and high-ductility concrete is poured between the profiled steel sheet and the steel pipe.

8. A construction method for a joint of a steel tube concrete composite column and a reinforced concrete column as claimed in any one of claims 3 to 7, characterized in that: It includes the following steps: welding two U-shaped steel plates, four angle steels and four square steel plates into a splicing part; welding the first connecting steel plate and the second connecting steel plate on the outer side edge of the steel pipe; sleeving the splicing part on the steel pipe and placing it on the first connecting steel plate, and welding and fixing it; opposing the clamping part of the profiled steel sheet to the bayonet, passing through the splicing part, the first connecting steel plate and the second connecting steel plate from top to bottom in sequence, and clamping around the outer side of the steel pipe; vertically passing the longitudinal bars of the reinforced concrete column through the through holes from top to bottom in sequence, extending into the pouring space formed by the steel pipe and the profiled steel sheet, and performing spot welding and fixing at the positions of the through holes; erecting a pouring form outside the longitudinal bars, and then pouring concrete into the steel pipe, the pouring space formed by the steel pipe and the profiled steel sheet, and the pouring form.

9. The construction method of the joint node of the steel tube concrete composite column and the reinforced concrete column according to claim 8, characterized in that: Firstly, high-strength concrete is poured in the steel pipe, then high-ductility concrete is poured between the corrugated steel plate and the steel pipe, and finally ordinary concrete is poured in the pouring formwork.

Citation Information

Patent Citations

  • Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method

    CN103437425A

  • Ring plate splicing type hollow sandwich concrete-filled steel tube composite joint and installation method

    CN108532759A

Cited By

  • A steel pipe concrete column and composite column connecting joint and construction method

    CN120575647B