Warm shed comprehensive heat storage winter construction method and device
Through the use of thermal storage in the winter concrete projects in winter construction, the construction method and installation of the winter heat storage winter period is used, and the heater maintenance structure and the special scaffold structure are used to combine the industrial heater and the waste heat of the power plant to solve the problem of humidity caused by traditional heating methods. Significantly improved the effect of concrete molding.
Patent Information
- Application Number
- CN202411334133.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-24
- Publication Date
- 2025-01-24
AI Technical Summary
In cold winter environments, when traditional industrial fan heats to heat concrete for curing, the humidity drops too quickly, which can easily lead to dry shrinkage cracks in the concrete, affecting the molding effect.
Adopt the constructive method and device of the comprehensive heat storage winter during the winter heat storage, through setting the heater maintenance structure on the scaffold structure, and using the scaffolding structure composed of the outer pipe, the inner riser, the horizontal connection beam, and the vertical connection beam, combined with the industrial heating fan Thermal source and power plant thermal power heat can be achieved to achieve effective heating and moisturizing the concrete.
Effectively maintain the appropriate temperature and humidity of the concrete molding environment, avoid the occurrence of shrinkage cracks, and improve the strength and effect of concrete molding.
Smart Images

Figure CN119352758A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field related to concrete maintenance, and specifically to a construction method and device for a greenhouse with comprehensive heat storage in winter. Background Art
[0002] Concrete curing is to artificially create certain humidity and temperature conditions so that the newly poured concrete can harden and increase its strength normally or accelerate its hardening. The reason why concrete can gradually harden and increase its strength is the result of cement hydration, and cement hydration requires certain temperature and humidity conditions. If the surrounding environment does not have these conditions, artificial curing of concrete is required;
[0003] Since the cold environment in winter is not conducive to the solidification and molding of concrete, artificial heating is usually used in the prior art to assist the maintenance of concrete in the cold environment in winter. However, the traditional industrial heater heating method causes the environmental humidity to drop too quickly, which can easily cause shrinkage cracks in the concrete, thereby easily affecting the molding effect of the concrete. Therefore, the present invention proposes a greenhouse comprehensive heat storage winter construction method and device to solve the above problems. Summary of the invention
[0004] The purpose of the present invention is to provide a method and device for winter construction of a greenhouse with comprehensive heat storage, so as to solve the problems raised in the above-mentioned background technology.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solution: a construction method for a greenhouse with comprehensive heat storage in winter, the construction method for a greenhouse with comprehensive heat storage in winter comprising:
[0006] Excavation of foundation pit;
[0007] Trench earth excavation;
[0008] Steel bar engineering, building the steel bar structure of the main building;
[0009] Formwork engineering, building the concrete pouring formwork around the steel structure of the main building;
[0010] Scaffolding engineering, building the scaffolding structure outside the concrete pouring formwork;
[0011] Insulation layer construction project;
[0012] Concrete engineering, pouring concrete into concrete pouring formwork;
[0013] Concrete curing project, by setting up a greenhouse curing structure on the scaffolding structure, and curing the poured concrete through heating.
[0014] Preferably, a demolding gap is left between the scaffolding structure and the concrete pouring formwork to facilitate demolding of the concrete pouring formwork after the scaffolding structure is completed.
[0015] A greenhouse comprehensive heat storage winter construction device, the greenhouse comprehensive heat storage winter construction device is used to implement the above greenhouse comprehensive heat storage winter construction method, the scaffolding structure includes:
[0016] An outer riser, the outer riser is used to connect and install the insulation layer;
[0017] The inner riser, the inner riser and the outer riser are both steel pipe structures, and the upper and lower sides of the outer riser and the inner riser are respectively fixedly welded with an upper connection plate and a lower connection plate, the upper connection plate and the lower connection plate are both provided with connection holes, and the lower surface of the upper connection plate and the upper surface of the lower connection plate are both provided with connection seats;
[0018] A transverse connecting beam, wherein the transverse connecting beam is used to connect adjacent outer risers and adjacent inner risers;
[0019] A longitudinal connecting beam is used to connect adjacent outer risers and adjacent inner risers.
[0020] Preferably, a pipe connector is provided on the side wall of the outer riser, the pipe connector is communicated with the tube cavity of the outer riser, a stop valve is provided on the pipe connector, a mounting groove is provided on the side wall of the outer riser, an air avoidance groove is provided at the upper end of the mounting groove toward the outside, an air port is provided through the bottom of the mounting groove, a radiator is installed between the mounting grooves on adjacent outer risers, an air duct is provided on the radiator, and when the radiator is actually installed, the air duct is aligned with the air port.
[0021] Preferably, a sealing groove is provided at the edge of the air outlet, a sealing gasket is fixedly glued in the sealing groove, and when the radiator is actually installed, the sealing gasket is arranged to abut against the end of the radiator.
[0022] Preferably, the end edge line of the sealing gasket is chamfered, and there are three ways to set the mounting groove on the outer vertical pipe, including a single setting, a pair of settings at an angle of 180 degrees, and a pair of settings at an angle of 90 degrees.
[0023] Preferably, column holes are provided on the upper and lower sides of both ends of the radiator, and when the radiator is actually installed, adjacent radiators are separated by columns, and both ends of the columns are respectively inserted into the column holes on the upper and lower radiators.
[0024] Preferably, a hook is fixedly welded on the outer side surface of the outer vertical pipe, a connecting rope is sewn on the inner side surface of the thermal insulation layer, and when the thermal insulation layer is actually installed, the connecting rope is tied to the hook.
[0025] Preferably, the thermal insulation layer is composed of a health-preserving film, a double-layer quilt, and a polyvinyl chloride film from the inside to the outside.
[0026] Preferably, the heat source connected to the pipe connector is an industrial heater heat source and waste heat from thermal power generation in a power plant.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] 1. By setting up a warm shed comprehensive heat storage winter construction method consisting of foundation pit excavation, trench excavation, steel bar engineering, formwork engineering, scaffolding engineering, insulation layer construction engineering, concrete engineering, and concrete maintenance engineering, the concrete poured in the low temperature environment in winter is maintained to avoid the influence of the forming effect of the concrete structure due to the excessively low temperature, thereby effectively ensuring the forming strength of the concrete structure;
[0029] 2. A scaffolding structure composed of an outer riser, an inner riser, a transverse connecting beam and a longitudinal connecting beam is set up, and installation grooves and air ports are opened on the outer riser, and the outer risers on both sides are connected by setting radiators, so that warm air is transported from one side to the outer riser, so that warm air flows into the radiator, and heat is dissipated into the insulation layer, thereby ensuring that the ambient temperature of the concrete solidification molding can be maintained within an appropriate range, thereby ensuring the molding effect of the concrete, and this method will not take away excessive moisture in the concrete, so compared with the traditional industrial heater heating method, it can avoid the rapid drop in ambient humidity, thereby avoiding shrinkage cracks in the concrete, thereby effectively improving the molding effect of the concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the construction process of the present invention;
[0031] Figure 2 It is a schematic diagram of the structure of the present invention;
[0032] Figure 3 This is a schematic diagram of the installation of the scaffold of the present invention;
[0033] Figure 4 It is a schematic diagram of the scaffold structure of the present invention;
[0034] Figure 5 It is a half-section view of the scaffold of the present invention;
[0035] Figure 6 for Figure 5 A schematic diagram of the structure enlargement in the middle;
[0036] Figure 7 This is a schematic diagram of the outer riser structure of the present invention;
[0037] Figure 8 for Figure 7 A magnified schematic diagram of the structure at B in the middle;
[0038] Fig. 9 for Figure 7 Enlarged schematic diagram of the structure at point C in the middle.
[0039] In the figure: insulation layer 2, concrete structure 3, outer riser 4, inner riser 5, transverse connecting beam 6, longitudinal connecting beam 7, radiator 8, construction platform 9, lower connecting plate 10, upper connecting plate 11, connecting hole 12, connecting seat 13, pipe connector 14, pipe cavity 15, mounting groove 16, air port 17, air duct 18, column hole 19, column 20, sealing groove 21, sealing gasket 22, air avoidance groove 23, hook 24. DETAILED DESCRIPTION
[0040] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0041] In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "one", "first", "second", "third", "fourth", "fifth", "sixth" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0042] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0043] For the purpose of simplicity and illustration, the principles of the embodiments are mainly described by reference to examples. In the following description, many specific details are proposed to provide a thorough understanding of the embodiments. However, it is obvious that for those of ordinary skill in the art, these embodiments may not be limited to these specific details in practice. In some instances, known methods and structures are not described in detail to avoid making these embodiments unnecessarily difficult to understand. In addition, all embodiments can be used in combination with each other.
[0044] See also Figure 1-9 The present invention provides the following three preferred embodiments:
[0045] Embodiment 1, the construction method of the greenhouse with comprehensive heat storage in winter, the construction method of the greenhouse with comprehensive heat storage in winter includes excavation of foundation pit; excavation of trench; reinforcement engineering, building the reinforcement structure of the building main body; formwork engineering, building the concrete casting formwork around the reinforcement structure of the building main body; scaffolding engineering, building the scaffolding structure on the outside of the concrete casting formwork; insulation layer construction engineering; concrete engineering, pouring concrete in the concrete casting formwork; concrete curing engineering, by setting the greenhouse curing structure on the scaffolding structure, and curing the cast concrete by heating.
[0046] A demolding gap is left between the scaffolding structure and the concrete pouring formwork to facilitate the demolding of the concrete pouring formwork after the scaffolding structure is built. By setting up a warm shed comprehensive heat storage winter construction method consisting of foundation pit excavation, trench excavation, steel bar engineering, formwork engineering, scaffolding engineering, insulation layer construction engineering, concrete engineering, and concrete maintenance engineering, the concrete poured in the low temperature environment in winter is maintained, thereby avoiding the influence of low temperature on the forming effect of the concrete structure, thereby effectively ensuring the forming strength of the concrete structure.
[0047] Embodiment 2, on the basis of embodiment 1, a comprehensive heat storage winter construction device for a greenhouse is provided. The comprehensive heat storage winter construction device for a greenhouse is used to implement the above-mentioned comprehensive heat storage winter construction method for a greenhouse. The scaffolding structure includes an outer riser 4, an inner riser 5, a transverse connecting beam 6 and a longitudinal connecting beam 7. The outer riser 4 is used to connect and install the insulation layer 2. The inner riser 5 and the outer riser 4 are both steel pipe structures, and the upper and lower sides of the outer riser 4 and the inner riser 5 are respectively fixedly welded with an upper connecting plate 11 and a lower connecting plate 10. The upper connecting plate 11 and the lower connecting plate 10 are both provided with connecting holes 12, and the lower surface of the upper connecting plate 11 and the upper surface of the lower connecting plate 10 are both provided with connecting seats 13. The transverse connecting beam 6 is used to connect adjacent outer risers 4 and adjacent inner risers 5, and the longitudinal connecting beam 7 is used to connect adjacent outer risers 4 and adjacent inner risers 5.
[0048] A pipe connector 14 is provided on the side wall of the outer riser 4, the pipe connector 14 is connected to the tube cavity 15 of the outer riser 4, a stop valve is provided on the pipe connector 14, a mounting groove 16 is provided on the side wall of the outer riser 4, an air avoidance groove 23 is provided at the upper end of the mounting groove 16 toward the outside, and an air port 17 is provided through the bottom of the mounting groove 16, and a radiator 8 is installed between the mounting grooves 16 on adjacent outer risers 4, an air duct 18 is provided on the radiator 8, and when the radiator 8 is actually installed, the air duct 18 is aligned with the air port 17, and a scaffold composed of the outer riser 4, the inner riser 5, the transverse connecting beam 6 and the longitudinal connecting beam 7 is provided. The structure is provided with a mounting groove 16 and an air port 17 on the outer riser 4, and the outer risers 4 on both sides are connected by arranging a radiator 8, so that warm air is transported from one side to the outer riser 4, so that warm air flows into the radiator 8, and heat is dissipated into the insulation layer 2, so as to ensure that the ambient temperature of the concrete solidification molding can be maintained within a suitable range, thereby ensuring the molding effect of the concrete, and this method will not take away too much moisture in the concrete, so compared with the traditional industrial heater heating method, it can avoid the rapid drop in ambient humidity, thereby avoiding shrinkage cracks in the concrete, thereby effectively improving the molding effect of the concrete.
[0049] A sealing groove 21 is provided at the edge of the air port 17, in which a sealing gasket 22 is fixedly glued. When the radiator 8 is actually installed, the sealing gasket 22 is arranged to abut against the end of the radiator 8 to improve the sealing of the connection position.
[0050] The end edge line of the sealing gasket 22 is chamfered, and there are three ways to set the mounting groove 16 on the outer vertical pipe 4, including a single setting, a pair of settings at an angle of 180 degrees, and a pair of settings at an angle of 90 degrees, which is convenient for application in various environments.
[0051] The upper and lower sides of both ends of the radiator 8 are provided with column holes 19, and when the radiator 8 is actually installed, adjacent radiators 8 are separated by columns 20, and the two ends of the columns 20 are respectively inserted into the column holes 19 on the upper and lower radiators 8, so as to facilitate the separation of the radiators 8.
[0052] Embodiment 3, on the basis of embodiment 2, a hook 24 is fixedly welded on the outer surface of the outer vertical pipe 4, a connecting rope is sewn on the inner side surface of the insulation layer 2, and when the insulation layer 2 is actually installed, the connecting rope is tied to the hook 24. The setting of the hook 24 improves the installation convenience of the insulation layer 2.
[0053] The heat preservation layer 2 is composed of a health-preserving film, a double-layer quilt, and a polyvinyl chloride film from the inside to the outside. The heat preservation effect is improved through the combined effect of the health-preserving film, the double-layer quilt, and the polyvinyl chloride film.
[0054] The heat sources connected to the pipe connector 14 are the heat source of an industrial heater and the waste heat from thermal power generation in a power plant. The use of the waste heat from thermal power generation in a power plant can effectively improve energy utilization.
[0055] A construction platform 9 is set up on the transverse connecting beam 6 at the bottom of the scaffolding structure to facilitate the subsequent construction of the concrete structure 3 by the later workers.
[0056] Although the above describes the illustrative specific implementation methods of the present application so that technicians in this technical field can understand the present application, the present application is not limited to the scope of the specific implementation methods. For ordinary technicians in this technical field, as long as various changes are within the spirit and scope of the present application defined and determined by the attached claims, all application creations using the concept of the present application are protected.
Claims
1. A winter construction method for a greenhouse with comprehensive heat storage, characterized by: The winter construction method of the greenhouse comprehensive heat storage comprises: Excavation of foundation pit; Trench earth excavation; Steel bar engineering, building the steel bar structure of the main building; Formwork engineering, building the concrete pouring formwork around the steel structure of the main building; Scaffolding engineering, building the scaffolding structure outside the concrete pouring formwork; Insulation layer construction project; Concrete engineering, pouring concrete into concrete pouring formwork; Concrete curing project, by setting up a greenhouse curing structure on the scaffolding structure, and curing the poured concrete through heating.
2. The greenhouse comprehensive heat storage winter construction method according to claim 1 is characterized by: A demoulding gap is left between the scaffolding structure and the concrete pouring template to facilitate demoulding of the concrete pouring template after the scaffolding structure is completed.
3. A greenhouse comprehensive heat storage winter construction device, characterized by: The greenhouse comprehensive heat storage winter construction device is used to implement any one of the greenhouse comprehensive heat storage winter construction methods of claims 1-2, and the scaffolding structure includes: An outer riser (4), wherein the outer riser (4) is used for connecting and installing the thermal insulation layer (2); An inner riser (5), wherein the inner riser (5) and the outer riser (4) are both steel pipe structures, and an upper connection plate (11) and a lower connection plate (10) are respectively fixedly welded to the upper and lower sides of the outer riser (4) and the inner riser (5), wherein the upper connection plate (11) and the lower connection plate (10) are both provided with connection holes (12), and the lower surface of the upper connection plate (11) and the upper surface of the lower connection plate (10) are both provided with connection seats (13); A transverse connecting beam (6), wherein the transverse connecting beam (6) is used to connect adjacent outer risers (4) and adjacent inner risers (5); A longitudinal connecting beam (7), wherein the longitudinal connecting beam (7) is used to connect adjacent outer risers (4) and adjacent inner risers (5).
4. The greenhouse comprehensive heat storage winter construction device according to claim 3 is characterized by: A pipe connector (14) is provided on the side wall of the outer vertical pipe (4), the pipe connector (14) is in communication with the tube cavity (15) of the outer vertical pipe (4), a stop valve is provided on the pipe connector (14), a mounting groove (16) is provided on the side wall of the outer vertical pipe (4), an air avoidance groove (23) is provided at the upper end of the mounting groove (16) toward the outside, and an air port (17) is provided through the bottom of the mounting groove (16), and a radiator (8) is installed between the mounting grooves (16) on adjacent outer vertical pipes (4), an air duct (18) is provided on the radiator (8), and when the radiator (8) is actually installed, the air duct (18) is arranged to be aligned with the air port (17).
5. The greenhouse comprehensive heat storage winter construction device according to claim 4 is characterized by: A sealing groove (21) is provided at the edge of the air port (17), a sealing gasket (22) is fixedly glued into the sealing groove (21), and when the radiator (8) is actually installed, the sealing gasket (22) is arranged to abut against the end of the radiator (8).
6. The greenhouse comprehensive heat storage winter construction device according to claim 5 is characterized by: The end edge line of the sealing gasket (22) is chamfered, and there are three ways to set the mounting groove (16) on the outer vertical pipe (4), including a single setting, a pair of settings at an angle of 180 degrees, and a pair of settings at an angle of 90 degrees.
7. The greenhouse comprehensive heat storage winter construction device according to claim 6 is characterized by: The upper and lower sides of both ends of the radiator (8) are provided with column holes (19), and when the radiator (8) is actually installed, adjacent radiators (8) are separated by columns (20), and the two ends of the columns (20) are respectively inserted into the column holes (19) on the upper and lower radiators (8).
8. The greenhouse comprehensive heat storage winter construction device according to claim 7 is characterized by: A hook (24) is fixedly welded on the outer surface of the outer vertical pipe (4), a connecting rope is sewn on the inner side of the thermal insulation layer (2), and when the thermal insulation layer (2) is actually installed, the connecting rope is tied to the hook (24).
9. The greenhouse comprehensive heat storage winter construction device according to claim 8 is characterized by: The thermal insulation layer (2) comprises, from the inside to the outside, a health-preserving film, a double-layer quilt, and a polyvinyl chloride film.
10. The greenhouse comprehensive heat storage winter construction device according to claim 9 is characterized by: The heat source connected to the pipeline connector (14) is an industrial heater heat source and waste heat from thermal power generation in a power plant.