One-way electric energy meter on-site calibration instrument wiring device and test method
By designing a unidirectional electric energy meter on -site inspection instrument wiring device using an insulating resin body, spring probe, and plug, the problem of slow wiring speed and difficulty connecting load in existing technologies have been solved. And meet the wiring requirements of different specifications.
Patent Information
- Application Number
- CN202411586275.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-08
- Publication Date
- 2025-01-28
AI Technical Summary
It is difficult for existing power meter wiring devices to quickly and safely complete the wiring of single-phase power performance field calibrator, and it is difficult to cope with the situation where the power meter needs to be connected to the load when there is no load.
Design a one -way electrical meter on -site inspection instrument wiring device, using the combination of insulating resin body, spring probe and plug. Complete wiring and detection safely.
A quickly and securely complete completion of the single -phase power meter on -site inspection instrument wiring, and can connect the load for the power meter when needed, improve the wiring speed and security, and meet the wiring requirements of different specifications of electrical energy meters.
Smart Images

Figure CN119375812A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric energy meter field calibrators, and in particular to a wiring device and a testing method for a one-way electric energy meter field calibrator. Background Art
[0002] In the traditional single-phase electric energy meter calibration process, the voltage of the on-site calibrator is connected to the screw of the electric energy meter terminal through the voltage wire clamp, the pulse line is also connected to the pulse port of the electric energy meter through the wire clamp, and then the current clamp is connected to the incoming line of the electric energy meter to perform on-site calibration of the electric energy meter. Because the contact area between the wire clamp of the single-phase electric energy meter field calibrator and the electric energy meter terminal post is small, the wiring often falls off, and the staff needs to repeatedly perform live wiring. Usually, the screws on the electric energy meter terminal post head are backed out 3-4 threads so that the voltage line does not fall off. In this way, sometimes the staff forgets to tighten the backed screws, resulting in loose wiring of the electric energy meter. After retrieval, the patent with application number CN201721541395.1 discloses an integrated wiring device for an electric energy meter field calibrator, wherein the fixed bracket is provided with an opening for a fastener to pass through the opening to fix the fixed bracket to the electric energy meter; the mobile bracket includes a base and a side frame, both sides of the base are connected with side frames that can be hung on the fixed bracket, and the base is provided with multiple ejectors, and the ejectors are all provided with leads.
[0003] The process of fixing the above device to the electric energy meter is rather cumbersome, and the position needs to be adjusted to align the ejector pin with the terminal post of the electric energy meter, resulting in a slower use speed. There is no obvious speed improvement compared to the original wiring method, and it is also difficult to cope with the situation where a load needs to be connected when the electric energy meter is not under load. Summary of the invention
[0004] In view of the deficiencies in the prior art, the present invention provides a one-way electric energy meter field calibrator wiring device and a testing method, which solves the problem that the existing electric energy meter wiring device is difficult to quickly and safely complete the wiring of the single-phase electric energy meter field calibrator, while meeting the requirement of connecting the electric energy meter to the load when needed.
[0005] To achieve the above-mentioned object, the present invention provides the following technical solutions: a one-way electric energy meter field tester wiring device, comprising an insulating resin body, the insulating resin body comprising a base and two side columns respectively wrapping the electric energy meter from two sides, the base and the side columns are integrally cast by insulating resin, a plurality of limiting holes corresponding to the wiring columns of the electric energy meter are opened on one side of the insulating resin body, a spring probe with both ends extending to the outside thereof is arranged in the limiting hole, and one end of the spring probe is connected to a plug;
[0006] The spring probe includes a longitudinal rod with one end extending into the limiting hole, the top of the longitudinal rod is connected to a longitudinal tube, the top of the longitudinal tube is provided with a voltage contact with one end movably extending into the interior thereof, the end of the voltage contact away from the longitudinal tube is spherical to ensure the stability of the connection, and an adjustment component for adjusting the position of the voltage contact is provided inside the longitudinal tube.
[0007] Preferably, the adjustment assembly includes a spring movably arranged inside the longitudinal tube, a steel ball is slidably connected to the bottom of the spring, an internal thread groove is provided on the inner wall of the longitudinal tube, a threaded rod 1 adapted to the internal thread groove is fixedly connected to the top of the longitudinal rod, and one end of the threaded rod 1 movably extends into the interior of the longitudinal tube.
[0008] Preferably, the plug comprises male and female plugs and an integrated female plug respectively connected to different spring probes, a connector corresponding to the female plug of the male and female plugs is provided at the bottom of the spring probe, and the integrated female plug is connected to the male plug of the male and female plugs.
[0009] Preferably, a convex column is provided on the side opposite to the side column, and a stress release groove is provided on the side of the side column away from the base.
[0010] Preferably, a slide groove penetrating the base is provided on one side of the base, two limit frames are provided in the slide groove, rubber blocks corresponding to the limit holes are slidably connected inside the limit frames, and the limit holes penetrate the rubber blocks.
[0011] Preferably, both ends of the limit frame are slidably connected to the inner wall of the slide slot, and a clamping assembly for fixing the position of the limit frame is provided inside the slide slot.
[0012] Preferably, the clamping assembly includes a second threaded rod with both ends fixedly connected to the inner wall of the slide groove, a through hole corresponding to the second threaded rod is opened on one side of the limit frame, and nuts sleeved on the outside of the second threaded rod are provided on both sides of the limit frame.
[0013] Preferably, one side of the limiting frame is open, and an extrusion plate covering the opening is slidably connected between two sides of the inner wall of the limiting frame, and a plurality of rubber pads are fixedly connected to one side of the extrusion plate close to the rubber block.
[0014] Preferably, the top of the base is provided with two circular grooves passing through the side columns, the inner bottom of the circular groove is fixedly connected with a bottom plate, the top of the bottom plate is provided with a longitudinal plate with one end extending to the outside of the base, the top of the longitudinal plate is fixedly connected with a top plate, a lifting plate is slidably connected to one side of the longitudinal plate, a spring 2 is fixedly connected between the bottom plate and the lifting plate, a convex column is installed between the lifting plate and the top plate, one end of the convex column movably extends to the inside of the base, and a plurality of anti-slip pads are fixedly connected to the bottom of the top plate.
[0015] A method for testing the wiring device of the one-way electric energy meter field tester comprises the following steps:
[0016] Step 1: Fix the electric energy meter. Put the insulating resin body on the bottom of the electric energy meter near the terminal. The side posts clamp the electric energy meter from both sides. Fix the insulating resin body on the electric energy meter. At this time, the spring probe is pressed against the terminal of the electric energy meter.
[0017] Step 2: Detect the pulse. Use a spring probe to lead out the pulse line on the energy meter, connect it to the female plug of the male and female plugs, and then connect it to the calibrator through the male plug of the male and female plugs. Apply a 10N pulling force at the connection to test whether the connection is disconnected and count the connection time.
[0018] Step 3: Detect the voltage. The voltage and current of the energy meter are drawn out through the spring probe, connected to the male plug of the male and female plugs, and then connected to the calibrator through the female plugs of the male and female plugs. Measure the fixed time, simulate the weight of the calibrator line, apply a pulling force of 20N, and count the number of times the connector is disconnected;
[0019] Step 4: Provide a load, lead out the live wire and the neutral wire of the energy meter with a spring probe, connect them to the female plug of the male and female plugs, then connect the male plug to the integrated female plug, connect it to the load through the integrated female plug, count the connection time, and then apply a pulling force of 10N to test whether the connection is disconnected.
[0020] Compared with the prior art, the present invention provides a wiring device and a testing method for a one-way electric energy meter field tester, which has the following beneficial effects:
[0021] 1. Through the setting of insulating resin body, spring probe and plug, the wiring of single-phase electric energy meter field calibrator can be completed quickly and safely, and the demand of electric energy meter to be connected to load when needed can be met.
[0022] 2. By setting the adjustment component inside the spring probe, the probe has good elasticity and can adapt well to the different lengths of the nut left outside the terminal head due to the different thicknesses of the input and output lines of the electric energy meter, so that the probe can form good contact with the terminal posts of the electric energy meter in different conditions.
[0023] 3. By setting the steel ball and spring, the extension distance of the voltage contact and the force of pressing the terminal can be adjusted according to the needs, which is convenient for adjusting the contact between the voltage contact and the terminal of different lengths, and can also improve the firmness of the connection between the voltage contact and the terminal.
[0024] 4. By setting the convex column and stress release groove, the convex column can be used to reduce the gap between the electric energy meter and the insulating resin body, making the connection between the wiring device and the electric energy meter more secure. At the same time, space is reserved to accommodate the convex column and side column that are deformed after being squeezed, so as to prevent the convex column and side column from being squeezed and damaged by the electric energy meter.
[0025] 5. By setting the limit frame, the position of the spring probe can be flexibly adjusted along the width direction of the insulating resin body, so that the spring probe can be connected with the terminal of different specifications of electric energy meters, thereby improving the adaptability of the wiring device to different specifications of electric energy meters.
[0026] 6. The clamping assembly is provided to facilitate adjustment of the position of the spring probe in different directions so that the spring probe is aligned with the terminal of the electric energy meter, and to facilitate fixing the spring probe after the position is adjusted.
[0027] 7. By setting the bottom plate, top plate, lifting plate and spring 2, it is convenient to replace the boss, reduce the influence of the boss on the connection firmness between the wiring device and the electric energy meter after wear, and ensure that the wiring device can still be firmly installed on the electric energy meter after long-term use. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0029] Figure 1 It is a schematic diagram of the overall structure of the wiring device in the present invention;
[0030] Figure 2 is a cross-sectional schematic diagram of the entire wiring device of the present invention;
[0031] Figure 3 It is a schematic diagram of the structure of the spring probe in the present invention;
[0032] Figure 4 A partial cross-sectional view of a spring probe in the present invention;
[0033] Figure 5 It is a schematic diagram of the structure of the insulating resin body and the limiting frame in the present invention;
[0034] Figure 6 It is a schematic diagram of the structure of the limit frame and the clamping assembly in the present invention;
[0035] Figure 7 It is a schematic diagram of the structure of the longitudinal plate and the convex column in the present invention;
[0036] Figure 8 It is a schematic diagram of the structure of the longitudinal plate, the bottom plate and the top plate in the present invention;
[0037] Fig. 9 It is a schematic structural diagram of the insulating resin body in the present invention.
[0038] In the figure: 1. insulating resin body; 101. base; 102. side column; 2. boss; 3. limit hole; 4. spring probe; 41. longitudinal rod; 42. longitudinal tube; 43. voltage contact; 44. adjustment assembly; 441. spring one; 442. steel ball; 443. threaded rod one; 5. plug; 51. male and female plugs; 52. integrated female plug; 6. stress relief groove; 7. limit frame; 8. rubber block; 9. clamping assembly; 91. threaded rod two; 92. nut; 10. extrusion plate; 11. rubber pad; 12. bottom plate; 13. longitudinal plate; 14. top plate; 15. lifting plate; 16. spring two; 17. anti-slip pad. DETAILED DESCRIPTION
[0039] The following will describe the implementation methods of the present application in detail with the help of accompanying drawings and examples, so that the implementation process of how the present application uses technical means to solve technical problems and achieve technical effects can be fully understood and implemented accordingly.
[0040] Embodiment 1
[0041] In order to quickly, safely and firmly connect the field calibrator to the energy meter, Figure 1-Figure 4 An embodiment of the present invention can quickly fix the wiring device on the electric energy meter and dock with the terminal of the electric energy meter to prevent the wiring from falling off the electric energy meter, thereby reducing the time wasted by repeated wiring. A wiring device for a one-way electric energy meter field tester includes an insulating resin body 1, the insulating resin body 1 includes a base 101 and two side columns 102 that wrap the electric energy meter from two sides respectively, the base 101 and the side columns 102 are integrally cast by insulating resin, one side of the insulating resin body 1 is provided with a plurality of limiting holes 3 corresponding to the terminal of the electric energy meter, the limiting hole 3 is provided with a spring probe 4 with both ends extending to the outside thereof, one end of the spring probe 4 is connected to a plug 5, when in use The size of the insulating resin block is designed according to the size of the electric energy meter, so that the insulating resin body 1 can wrap the electric energy meter from three sides after it is close to the electric energy meter, so that the insulating resin body 1 is stuck on the electric energy meter, and the insulating resin body 1 and the electric energy meter are fixed. In this process, the spring probe 4 gradually approaches the electric energy meter and is finally pressed on the terminal of the electric energy meter. The terminal of the electric energy meter is led out with the spring probe 4, and then according to the needs of the detection, the spring probe 4 is connected to the calibrator with the plug 5 respectively, and the pulse and voltage of the electric energy meter are detected. At the same time, a load is provided to the electric energy meter, which can quickly and safely complete the wiring of the single-phase electric energy meter field calibrator, and at the same time meet the needs of the electric energy meter to connect to the load when needed.
[0042] In order to connect the probe to the power meter terminals with different protruding lengths, refer to Figure 2 and Figure 3The spring probe 4 includes a longitudinal rod 41 with one end extending to the inside of the limiting hole 3, the top of the longitudinal rod 41 is connected to a longitudinal tube 42, the top of the longitudinal tube 42 is provided with a voltage contact 43 with one end movably extending to the inside thereof, the end of the voltage contact 43 away from the longitudinal tube 42 is spherical, and the inside of the longitudinal tube 42 is provided with an adjustment component 44 for adjusting the position of the voltage contact 43, the adjustment component 44 includes a spring 441 movably arranged inside the longitudinal tube 42, a steel ball 442 is slidably connected to the bottom of the spring 441, the inner wall of the longitudinal tube 42 is provided with an internal thread groove, the top of the longitudinal rod 41 is fixedly connected with a threaded rod 443 adapted to the internal thread groove, one end of the threaded rod 443 movably extends to the inside of the longitudinal tube 42, and when in use, the spring A 441 pushes the voltage contact 43 to move away from the longitudinal rod 41, so that the voltage contact 43 moves to the position farthest from the insulating resin body 1, and then moves the insulating resin body 1 gradually close to the electric energy meter until the insulating resin body 1 is stuck on the electric energy meter. In this process, the spring probe 4 contacts the terminal and is then squeezed. After being squeezed, the voltage contact 43 moves toward the inside of the longitudinal tube 42, squeezing and contracting the spring 441 until the insulating resin body 1 is firmly fixed on the electric energy meter, so that the probe has good elasticity and can well adapt to the different lengths of the nut left outside the terminal post due to the different thicknesses of the electric energy meter's input and output lines, so that the probe can form good contact with the terminal of the electric energy meter in different conditions.
[0043] Since the distance that the voltage contact 43 can be extended is affected by the spring 1 441, and the firmness of the voltage contact 43 in contact with the terminal of the electric energy meter is also affected by the elastic force of the spring 1 441, in order to adjust the distance that the voltage contact 43 can be extended and the force of pressing the terminal, the number of steel balls 442 installed in the longitudinal tube 42 can be selected in this embodiment. When it is necessary to extend the voltage contact 43 to a longer distance and ensure that the voltage contact 43 is firmly connected to the terminal, the longitudinal tube 42 can be rotated until the longitudinal tube 42 is separated from the threaded rod 1 443, and then the steel balls 442 inserted into the longitudinal tube 42 are increased. The number of steel balls 442 is then reinstalled on the threaded rod 443. At this time, the increased number of steel balls 442 inside the longitudinal tube 42 pushes the spring 441 to move in the direction of the voltage contact 43, so that the spring 441 can push the voltage contact 43 to move a longer distance. In addition, the steel balls 442 increase the elastic force of the spring 441 on the voltage contact 43 by squeezing the spring 441, so that the extension distance of the voltage contact 43 and the force of pressing the terminal can be adjusted according to needs, which facilitates the adjustment of the voltage contact 43 to contact with terminals of different lengths and can also improve the firmness of the connection between the voltage contact 43 and the terminal.
[0044] In order to better connect the different connectors of the field calibrator after being led out through the spring probe 4, the plug 5 includes male and female plugs 51 and an integrated female plug 52 which are respectively connected to different spring probes 4. A connector corresponding to the female plug of the male and female plugs 51 is provided at the bottom of the spring probe 4. The integrated female plug 52 is connected to the male plug of the male and female plugs 51. When in use, the male plug or female plug of the male and female plug 51 can be connected to the spring probe 4, and then the other end of the male and female plug 51 can be connected to the field calibrator, or connected to the load through the integrated female plug 52.
[0045] In order to fix the wiring device and the electric energy meter more firmly, refer to Figure 1 and Figure 2 A boss 2 is provided on the side opposite to the side column 102, and a stress release groove 6 is provided on the side of the side column 102 away from the base 101. When in use, the electric energy meter is inserted between the two side columns 102. In this process, the boss 2 is squeezed and deformed, so that the electric energy meter is more firmly fixed on the insulating resin body 1. When the boss 2 is squeezed, the boss 2 can move toward the stress release groove 6 after deformation, and at the same time drive the side column 102 to move into the stress release groove 6 after deformation. The boss 2 can be used to reduce the gap between the electric energy meter and the insulating resin body 1, so that the connection between the wiring device and the electric energy meter is more firmly. At the same time, space is reserved to accommodate the boss 2 and the side column 102 that are squeezed and deformed, so as to prevent the boss 2 and the side column 102 from being squeezed and damaged by the electric energy meter.
[0046] Embodiment 2
[0047] In order to adjust the position of the spring probe 4, so that the spring probe 4 can be connected with the terminal of different specifications of electric energy meters, and adapt to the wiring work of more types of electric energy meters, refer to Figure 1-Figure 5 On the basis of the first embodiment, a slide groove penetrating the base 101 is provided on one side of the base 101, and two limit frames 7 are provided in the slide groove. A rubber block 8 corresponding to the limit hole 3 is slidably connected inside the limit frame 7, and the limit hole 3 penetrates the rubber block 8. When in use, the rubber block 8 is slid along the slide groove, thereby driving the limit hole 3 and the spring probe 4 inserted therein to move along the width direction of the insulating resin body 1 until the spring probe 4 is aligned with the terminal of the electric energy meter. The position of the spring probe 4 can be flexibly adjusted along the width direction of the insulating resin body 1, so that the spring probe 4 can be docked with the terminal of electric energy meters of different specifications, thereby improving the adaptability of the wiring device to electric energy meters of different specifications.
[0048] Embodiment 3
[0049] In order to facilitate fixing the spring probe 4 after adjusting its position, and prevent the spring probe 4 from shaking and causing a loose connection with the terminal, refer to Figure 1-Figure 6On the basis of the first embodiment, both ends of the limit frame 7 are slidably connected to the inner wall of the slide slot, and a clamping assembly 9 for fixing the position of the limit frame 7 is provided inside the slide slot. The clamping assembly 9 includes a threaded rod 91 with both ends fixedly connected to the inner wall of the slide slot, a through hole corresponding to the threaded rod 91 is provided on one side of the limit frame 7, and nuts 92 sleeved on the outside of the threaded rod 91 are provided on both sides of the limit frame 7. One side of the limit frame 7 is open, and an extrusion plate 10 covering the opening is slidably connected between the two sides of the inner wall of the limit frame 7. A plurality of rubber pads 11 are fixedly connected to the side of the extrusion plate 10 close to the rubber block 8. When in use, the limit frame 7 is first moved along the width direction of the insulating resin body 1, so that the rubber block 8 and the spring probe 4 are in contact with the rubber block 8. The terminals are in the same row, and then the extrusion plate 10 is moved away from the rubber block 8, and then the rubber block 8 is moved along the length direction of the limit frame 7, so that the spring probe 4 on the rubber block 8 is completely aligned with the position of the terminal of the electric energy meter, and then the extrusion plate 10 is pushed close to the rubber block 8, and the rubber pad 11 squeezes the rubber block 8 to fix the position of the rubber block 8, and then the nut 92 is rotated, and the nut 92 moves along the threaded rod 91, and squeezes the limit frame 7 and the extrusion plate 10 from both sides of the limit frame 7 respectively, and fixes the position of the limit frame 7, the rubber block 8 and the spring probe 4, so as to facilitate the adjustment of the position of the spring probe 4 in different directions, so that the spring probe 4 is aligned with the terminal of the electric energy meter, and at the same time, it is convenient to fix the spring probe 4 after the position is adjusted.
[0050] Embodiment 4
[0051] Since the protrusion 2 is constantly squeezed by the electric energy meter during use, it is easy to wear and break. After the protrusion 2 is worn, its width is reduced, and the clamping effect on the electric energy meter is reduced, which easily causes a gap between the electric energy meter and the insulating resin body 1. Figure 1-Figure 9 On the basis of the first embodiment, in order to maintain the squeezing effect of the convex column 2 on the electric energy meter, two circular grooves penetrating the side column 102 are provided on the top of the base 101, and the bottom of the inner side of the circular groove is fixedly connected with a bottom plate 12, and the top of the bottom plate 12 is provided with a longitudinal plate 13 with one end extending to the outside of the base 101, and the top of the longitudinal plate 13 is fixedly connected with a top plate 14, and a lifting plate 15 is slidably connected to one side of the longitudinal plate 13, and a spring 16 is fixedly connected between the bottom plate 12 and the lifting plate 15, and the convex column 2 is installed between the lifting plate 15 and the top plate 14, and one end of the convex column 2 is movably extended to the base 1 01 Inside, a plurality of anti-skid pads 17 are fixedly connected to the bottom of the top plate 14. When in use, the bottom of the boss 2 is placed on the lifting plate 15, and then the boss 2 is pressed downward to drive the lifting plate 15 to descend, and at the same time, the spring 2 16 is squeezed and contracted, and then the top of the boss 2 is moved to the bottom of the top plate 14, and the boss 2 is released. The spring 2 16 pushes the lifting plate 15 and the boss 2 to rise until the top of the boss 2 is pressed against the top plate 14. The top of the boss 2 is difficult to fall off from the top plate 14 due to the anti-skid pad 17. When the insulating resin body 1 is stuck on the electric energy meter, the electric energy meter squeezes and deforms the boss 2.
[0052] When the boss 2 is worn or cracked and affects its use, it is only necessary to remove the boss 2 from between the top plate 14 and the lifting plate 15, and then replace it with a new boss 2. This facilitates the replacement of the boss 2 and reduces the influence of the boss 2 on the connection firmness between the wiring device and the electric energy meter after wear and tear, ensuring that the wiring device can still be firmly installed on the electric energy meter after long-term use.
[0053] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A wiring device for a one-way electric energy meter field tester, comprising an insulating resin body (1), characterized in that: The insulating resin body (1) comprises a base (101) and two side posts (102) respectively wrapping the electric energy meter from two sides; a plurality of limiting holes (3) corresponding to the terminal posts of the electric energy meter are provided on one side of the insulating resin body (1); a spring probe (4) with both ends extending to the outside thereof is provided in the limiting hole (3); one end of the spring probe (4) is connected to a plug (5); The spring probe (4) comprises a longitudinal rod (41) with one end extending into the interior of the limiting hole (3); the top of the longitudinal rod (41) is connected to a longitudinal tube (42); the top of the longitudinal tube (42) is provided with a voltage contact (43) with one end movably extending into the interior thereof; the end of the voltage contact (43) away from the longitudinal tube (42) is spherical; and an adjustment component (44) for adjusting the position of the voltage contact (43) is provided inside the longitudinal tube (42).
2. A one-way electric energy meter field tester wiring device according to claim 1, characterized in that: The adjustment assembly (44) comprises a spring (441) movably arranged inside the longitudinal tube (42); a steel ball (442) is slidably connected to the bottom of the spring (441); an inner thread groove is provided on the inner wall of the longitudinal tube (42); a threaded rod (443) adapted to the inner thread groove is fixedly connected to the top of the longitudinal rod (41); one end of the threaded rod (443) movably extends into the interior of the longitudinal tube (42).
3. A one-way electric energy meter field tester wiring device according to claim 1, characterized in that: The plug (5) comprises male and female plugs (51) and an integrated female plug (52) respectively connected to different spring probes (4); a connector corresponding to the female plug of the male and female plugs (51) is provided at the bottom of the spring probe (4); and the integrated female plug (52) is connected to the male plug of the male and female plugs (51).
4. A one-way electric energy meter field tester wiring device according to claim 1, characterized in that: A convex column (2) is provided on the side opposite to the side column (102), and a stress release groove (6) is provided on the side of the side column (102) away from the base (101).
5. A one-way electric energy meter field tester wiring device according to claim 1, characterized in that: A slide groove penetrating the base (101) is provided on one side of the base (101), two limit frames (7) are provided in the slide groove, a rubber block (8) corresponding to the limit hole (3) is slidably connected inside the limit frame (7), and the limit hole (3) penetrates the rubber block (8).
6. A one-way electric energy meter field tester wiring device according to claim 5, characterized in that: Both ends of the limit frame (7) are slidably connected to the inner wall of the slide slot, and a clamping assembly (9) for fixing the position of the limit frame (7) is provided inside the slide slot.
7. A one-way electric energy meter field tester wiring device according to claim 6, characterized in that: The clamping assembly (9) comprises a second threaded rod (91) whose two ends are fixedly connected to the inner wall of the slide groove, a through hole corresponding to the second threaded rod (91) is opened on one side of the limit frame (7), and nuts (92) are provided on both sides of the limit frame (7) and are sleeved on the outside of the second threaded rod (91).
8. A one-way electric energy meter field tester wiring device according to claim 5, characterized in that: One side of the limit frame (7) is open, and an extrusion plate (10) covering the opening is slidably connected between the two sides of the inner wall of the limit frame (7), and a plurality of rubber pads (11) are fixedly connected to one side of the extrusion plate (10) close to the rubber block (8).
9. A one-way electric energy meter field tester wiring device according to claim 4, characterized in that: The top of the base (101) is provided with two circular grooves penetrating the side columns (102); the inner bottom of the circular groove is fixedly connected to a bottom plate (12); the top of the bottom plate (12) is provided with a longitudinal plate (13) with one end extending to the outside of the base (101); the top of the longitudinal plate (13) is fixedly connected to a top plate (14); a lifting plate (15) is slidably connected to one side of the longitudinal plate (13); a second spring (16) is fixedly connected between the bottom plate (12) and the lifting plate (15); a convex column (2) is installed between the lifting plate (15) and the top plate (14); one end of the convex column (2) movably extends to the inside of the base (101); and a plurality of anti-slip pads (17) are fixedly connected to the bottom of the top plate (14).
10. A method for testing the wiring device of the one-way electric energy meter field tester according to any one of claims 1 to 9, characterized in that: The following steps are involved: Step 1: Fix the electric energy meter by putting the insulating resin body (1) on the bottom of the electric energy meter near the terminal. The side columns (102) clamp the electric energy meter from both sides, and fix the insulating resin body (1) on the electric energy meter. At this time, the spring probe (4) is pressed against the terminal of the electric energy meter. Step 2: Detect the pulse. Use the spring probe (4) to lead out the pulse line on the electric energy meter, connect it to the female plug of the male and female plug (51), and then connect it to the calibrator through the male plug of the male and female plug (51). Apply a pulling force of 10N at the connection to test whether the connection is disconnected and count the connection time. Step 3: Detect the voltage. After the voltage and current of the electric energy meter are drawn out through the spring probe (4), they are connected to the male plug of the male and female plugs (51), and then connected to the calibrator through the female plugs of the male and female plugs (51). A fixed time is measured, the weight of the calibrator line is simulated, a pulling force of 20N is applied, and the number of times the connector is disconnected is counted; Step 4: Provide a load, lead out the live wire and the neutral wire of the electric energy meter with a spring probe (4), connect them to the female plug of the male and female plug (51), then connect the male plug to the integrated female plug (52), connect to the load through the integrated female plug (52), count the connection time, and then apply a pulling force of 10N to test whether the connection is disconnected.
Citation Information
Patent Citations
On --spot field calibration instrument integral type termination of electric energy meter
CN207366732U
Electric energy meter calibration device
CN115494444A
On-site calibrator wire holder for three-phase electric energy meter
CN115951298A
Wiring device for on-site verification of electric energy meter
CN217156783U
Safety junction box for on-site verification of three-phase intelligent electric energy meter
CN218037297U
Cited By
Insulation test equipment of single-phase intelligent electric energy meter
CN119716720A
Electric meter calibration and detection equipment for electric power marketing meter installation and power connection
CN120522629A
A power marketing meter installation and electricity meter calibration detection equipment
CN120522629B