Pouring system as well as pouring equipment and pouring method thereof

By introducing heating parts and feed parts into the casting equipment, the problem of slow pouring speed is solved, a more efficient casting process is achieved, and product quality is improved.

CN119458722APending Publication Date: 2025-02-18MOTIC (XIAMEN) INTELLIGENT ELECTRIC CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411802187.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-09
Publication Date
2025-02-18

AI Technical Summary

Technical Problem

The existing casting equipment has the problem of slow casting speed during use, which affects the casting efficiency of the mold.

Method used

A casting device is designed, including a first housing, a second housing, a heating member and a material injection member, and the material is injected into the second receiving chamber at a preset air pressure through the material injection member. , provide the injection pressure to speed up the pouring speed.

Benefits of technology

Through heating and filling pressure, the pouring speed is significantly accelerated, the pouring efficiency is improved, and the intrinsic and appearance quality of the product is improved, reducing defects of bubbles and partial missing.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119458722A_ABST
    Figure CN119458722A_ABST
Patent Text Reader

Abstract

The invention provides a pouring system and pouring equipment and a pouring method thereof, and relates to the field of pouring device.The pouring equipment comprises a first shell, a second shell, a heating piece and a pouring piece, and the second shell and the first shell are installed in a matched mode to jointly define a first containing cavity and a second containing cavity; the first containing cavity is annularly arranged around the second containing cavity, the first containing cavity communicates with the second containing cavity, the heating piece is arranged on the first shell and the second shell, and the injection piece can penetrate through the first containing cavity to be inserted into the second containing cavity. And the material injection piece is used for injecting a material into the second containing cavity at preset air pressure so as to block an air flow channel between the first containing cavity and the second containing cavity. According to the pouring device, the speed of injecting the materials into the second containing cavity can be increased, the pouring speed is increased, and the pouring efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of pouring equipment, and in particular to a pouring system and pouring equipment and a pouring method thereof. Background Art

[0002] Compared with normal pressure pouring, vacuum pouring can effectively prevent the appearance of bubbles in the pouring object, thereby greatly improving the intrinsic quality and appearance quality of the product.

[0003] The related pouring equipment has the problem of slow pouring speed during use, which affects the pouring efficiency of the mold. Summary of the invention

[0004] In order to overcome the deficiencies in the prior art, the present application provides a pouring system and pouring equipment and a pouring method thereof.

[0005] In the first aspect, the present application provides a casting equipment, comprising: a first shell, a second shell, a heating element and an injection element, the second shell and the first shell are installed in cooperation to jointly define a first accommodating cavity and a second accommodating cavity, the first accommodating cavity is arranged in a ring around the second accommodating cavity, and the first accommodating cavity is communicated with the second accommodating cavity, the heating element is arranged on the first shell and the second shell, the injection element can pass through the first accommodating cavity and be inserted into the second accommodating cavity to block the airflow path between the first accommodating cavity and the second accommodating cavity, and the injection element is used to inject material into the second accommodating cavity at a preset air pressure.

[0006] In combination with the first aspect, in a possible embodiment, the injection piece includes a plug-in end 410, the first accommodating cavity has a first vacuum degree, and the second accommodating cavity has a second vacuum degree. When the first vacuum degree and / or the second vacuum degree are equal to a preset vacuum degree, the plug-in end 410 passes through the first accommodating cavity and is inserted into the second accommodating cavity to inject the material into the second accommodating cavity.

[0007] In combination with the first aspect, in a possible embodiment, the first shell includes: a bearing portion and an enclosure portion, the heating element is arranged in the bearing portion, the enclosure portion is arranged on the bearing portion, the enclosure portion is connected to the bearing portion, and the bearing portion, the enclosure portion and the second shell form the first accommodating cavity and the second accommodating cavity.

[0008] In combination with the first aspect, in a possible embodiment, a first interface and a second interface are provided on the enclosure portion, a suction piece is provided in the first interface, the suction piece passes through the first interface and is inserted into the first accommodating cavity, the suction piece is used to perform a vacuum treatment on the first accommodating cavity, and the injection piece passes through the second interface and is inserted into the second accommodating cavity.

[0009] In combination with the first aspect, in a possible embodiment, the enclosure portion includes: a first enclosure portion and a second enclosure portion, the first enclosure portion is connected to the bearing portion, and the bearing portion, the first enclosure portion and the second shell form the first accommodating cavity, the first enclosure portion is arranged in a ring around the second enclosure portion, and the bearing portion, the second enclosure portion and the second shell form the second accommodating cavity.

[0010] In combination with the first aspect, in a possible embodiment, the second shell includes: a cover portion and a protruding portion, the cover portion and the bearing portion are arranged opposite to each other, the heating element is arranged in the cover portion, the protruding portion is arranged on a side of the cover portion close to the bearing portion, and the protruding portion is inserted in the first enclosure portion to form the first accommodating cavity with the first enclosure portion and the bearing portion, and to form the second accommodating cavity with the second enclosure portion and the bearing portion.

[0011] In combination with the first aspect, in a possible embodiment, a recessed area is provided on the protruding portion, and the recessed area is recessed in a direction away from the second enclosing portion to form a groove, and when the protruding portion is inserted in the first enclosing portion, an end of the second enclosing portion away from the bearing portion is inserted in the groove to form the second accommodating cavity.

[0012] In combination with the first aspect, in a possible embodiment, the first shell further includes a first insulation portion, which is arranged on the bearing portion and is arranged in a ring around the enclosure portion, and the second shell further includes a second insulation portion, which is arranged on the cover portion and is arranged in a ring around the protrusion, the bearing portion and the first insulation portion, the second insulation portion and the cover portion form an insulation cavity, and the insulation cavity is arranged in a ring around the first accommodating cavity.

[0013] In a second aspect, the present application provides a pouring system, comprising the above-mentioned pouring equipment.

[0014] In a third aspect, the present application provides a casting method, which uses the casting equipment described above, and the casting method comprises the following steps:

[0015] Obtain a suction piece, material and an air source, insert the suction piece into the first accommodating chamber to vacuum the first accommodating chamber, and when the vacuum degree in the first accommodating chamber reaches a preset vacuum degree, drive the material along the injection piece into the second accommodating chamber through the air source so that the material has a preset shape.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] The casting equipment provided in the present application is characterized in that the second shell is installed in cooperation with the first shell to jointly define the first accommodating cavity and the second accommodating cavity, and the second shell and the first shell are provided with the heating element to heat the material injected into the second accommodating cavity, thereby accelerating the solidification and molding speed of the material and improving the casting speed. In addition, the injection element is used to inject the material into the second accommodating cavity at the preset air pressure and provide injection pressure for the material to be injected into the second accommodating cavity. On the one hand, it can effectively improve the defects of bubbles and partial missing parts of the product after casting and molding, thereby improving the quality of the product after casting and molding. On the other hand, the injection pressure can accelerate the injection speed of the material into the second accommodating cavity, thereby accelerating the casting speed and improving the casting efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0019] Figure 1 The overall structural diagram of the pouring equipment is shown;

[0020] Figure 2 A schematic structural diagram showing another angle of the pouring equipment;

[0021] Figure 3 A schematic diagram of the exploded structure of the pouring equipment is shown;

[0022] Figure 4 Another exploded structural schematic diagram of the pouring equipment is shown;

[0023] Figure 5 A schematic diagram of the structure of the protruding part of the pouring equipment is shown;

[0024] Figure 6 A schematic diagram of the side structure of the pouring equipment is shown;

[0025] Figure 7 A schematic cross-sectional view of a pouring device is shown;

[0026] Figure 8 A schematic flow diagram of the casting method is shown.

[0027] Description of main component symbols:

[0028] 100-first shell; 110-bearing part; 120-enclosing part; 121-first interface; 122-second interface; 123-first enclosing part; 124-second enclosing part; 130-first heat-insulating part; 200-second shell; 210-cover part; 220-protrusion; 221-groove; 222-flow guide channel; 230-second heat-insulating part; 300-heating element; 400-injection element; 410-plug-in end; 500-first accommodating chamber; 600-second accommodating chamber; 700-suction element; 710-vacuum valve; 800-connecting frame. DETAILED DESCRIPTION

[0029] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0030] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0031] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0032] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0033] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0034] Embodiment 1

[0035] See also Figure 1 , the present application embodiment provides a casting device, the casting device comprising: a first shell 100, a second shell 200, a heating element 300 and an injection element 400. Please refer to Figure 7 The second housing 200 is installed in cooperation with the first housing 100 to define a first accommodating chamber 500 and a second accommodating chamber 600. The first accommodating chamber 500 is arranged in an annular shape around the second accommodating chamber 600, and the first accommodating chamber 500 is communicated with the second accommodating chamber 600. The heating element 300 is arranged on the first housing 100 and the second housing 200. The injection piece 400 can pass through the first accommodating chamber 500 and be inserted into the second accommodating chamber 600 to block the air flow passage between the first accommodating chamber 500 and the second accommodating chamber 600, and the injection piece 400 is used to inject material into the second accommodating chamber 600 at a preset air pressure. The heating element 300 can heat the material injected into the second accommodating cavity 600, can accelerate the speed of solidification of the material, and can improve the pouring speed. The injection element 400 is used to inject the material into the second accommodating cavity 600 at the preset air pressure, and can provide injection pressure for the material to be injected into the second accommodating cavity 600. On the one hand, it can effectively improve the defects of bubbles and partial missing of the product after pouring and molding, and improve the quality of the product after pouring and molding. On the other hand, the injection pressure can accelerate the speed of injecting the material into the second accommodating cavity 600, accelerate the pouring speed, and improve the efficiency of pouring.

[0036] See also Figure 2 and Figure 3In some embodiments, the first shell 100 includes: a bearing portion 110 and an enclosure portion 120. The bearing portion 110 is arranged along a first preset direction. The enclosure portion 120 is arranged along a second preset direction. The second preset direction is perpendicular to the first preset direction. The enclosure portion 120 is arranged on the bearing portion 110, and the enclosure portion 120 is arranged in an annular shape around the periphery of the bearing portion 110. The enclosure portion 120 is connected to the bearing portion 110, and the bearing portion 110, the enclosure portion 120 and the second shell 200 form the first accommodating cavity 500 and the second accommodating cavity 600.

[0037] In some embodiments, the second accommodating cavity 600 is a casting cavity, and the second accommodating cavity 600 has a preset shape. The preset shape is the shape of the material after casting, and the preset shape can be adjusted according to actual needs.

[0038] In some embodiments, the heating element 300 is a heating rod, and the heating element 300 is disposed in the carrier.

[0039] It can be understood that the first accommodating cavity 500 surrounding the second accommodating cavity 600 can slow down the heat loss in the second accommodating cavity 600 and play a role in heat preservation, thereby accelerating the curing and molding speed of the material in the second accommodating cavity 600 and improving the casting efficiency.

[0040] See also Figure 3 In some embodiments, the enclosure 120 is provided with a first interface 121 and a second interface 122. The first interface 121 is provided at one side of the enclosure 120, and the number of the first interfaces 121 is two, and the first interface 121 is a vacuum port. The second interface 122 is provided at a side of the enclosure 120 away from the first interface 121, and the number of the second interface 122 is one, and the second interface 122 is a material injection port.

[0041] In other embodiments, the number of the first interfaces 121 may be adjusted to three, four, five, six, etc. according to actual needs, which will not be listed here one by one.

[0042] See also Figure 3 and Figure 7 In some embodiments, a suction piece 700 is disposed in the first interface 121. The suction piece 700 passes through the first interface 121 and is inserted into the first accommodating cavity 500. The suction piece 700 is used to perform a vacuum process on the first accommodating cavity 500. The injection piece 400 passes through the second interface 122 and is inserted into the second accommodating cavity 600.

[0043] See also Figure 1 and Figure 2 In some embodiments, the suction member 700 includes: a vacuum valve 710 and a vacuum pump. The vacuum valve 710 is a solenoid valve, and the vacuum valve 710 has an input end and an output end. The input end is connected to the vacuum pump. The output end passes through the first interface 121 and extends into the first accommodating chamber 500.

[0044] It is understandable that the vacuum pump is started and the flow of the vacuum valve 710 is adjusted so that the first vacuum degree in the first accommodating chamber 500 can be adjusted according to actual needs, and the second accommodating chamber 600 is connected to the first accommodating chamber 500, so that the second vacuum degree in the second accommodating chamber 600 can be adjusted synchronously and the second vacuum degree can be equal to the first vacuum degree. The first accommodating chamber 500 in a vacuum can further slow down the heat loss rate in the second accommodating chamber 600, enhance the thermal insulation performance, and improve the sealing of the second accommodating chamber 600, and enable the second accommodating chamber 600 to be poured in a vacuum environment.

[0045] In some embodiments, the pouring equipment further comprises: a pouring tank. The material is stored in the pouring tank, and a discharge valve is provided on the pouring tank. The discharge valve is a solenoid valve, which is connected to the injection piece 400 and is used to control the amount of the material output from the pouring tank to the injection piece 400.

[0046] It can be understood that, compared with the traditional method of transporting materials through pipelines, transporting materials through the pouring tank can reduce the use of pipelines, thereby reducing the maintenance work of the pipelines.

[0047] See also Figure 6 and Figure 7 In some embodiments, the injection piece 400 includes a plug end 410 and a driving end. When the first vacuum degree and the second vacuum degree are both equal to the preset vacuum degree, the plug end 410 sequentially passes through the second interface 122 and the first accommodating cavity 500 and is inserted into the second accommodating cavity 600. The driving end is connected to the discharge valve.

[0048] In other embodiments, when the first vacuum degree is equal to the preset vacuum degree, or when the second vacuum degree is equal to the preset vacuum degree, the plug-in end 410 is inserted into the second accommodating cavity 600 .

[0049] In some embodiments, the pouring tank is connected to an air source, which is compressed air, and the air source drives the material in the pouring tank to pass through the discharge valve, the drive end, and the plug end 410 in sequence, and is output from the plug end 410 to the second accommodating cavity 600 .

[0050] It can be understood that by driving the material to be injected into the second accommodating cavity 600 by compressed air, the injection speed can be accelerated and the casting efficiency can be improved.

[0051] See also Figure 3 In some embodiments, the enclosure 120 includes: a first enclosure 123 and a second enclosure 124. The first enclosure 123 is connected to the bearing portion 110, and the bearing portion 110, the first enclosure 123 and the second shell 200 form the first accommodating cavity 500, and the first enclosure 123 is arranged in an annular manner around the second enclosure 124. The second enclosure 124 is arranged in an annular manner around the central axis of the bearing portion 110. The bearing portion 110, the second enclosure 124 and the second shell 200 form the second accommodating cavity 600.

[0052] In some embodiments, the first enclosure portion 123 is two enclosure sheets arranged opposite to each other. The second interface 122 is arranged at the connection between the two enclosure sheets.

[0053] In some embodiments, the second enclosure portion 124 is a conductor, a central axis of the second enclosure portion 124 coincides with a central axis of the first enclosure portion 123 , and the second enclosure portion 124 is circular.

[0054] See also Figure 4 and Figure 5 In some embodiments, the second shell 200 includes: a cover portion 210 and a protrusion 220. The cover portion 210 is arranged opposite to the bearing portion 110. The heating element 300 is also arranged in the cover portion 210. The protrusion 220 is arranged on a side of the cover portion 210 close to the bearing portion 110, and the protrusion 220 is inserted into the first enclosure portion 123 to form the first accommodating cavity 500 with the first enclosure portion 123 and the bearing portion 110, and to form the second accommodating cavity 600 with the second enclosure portion 124 and the bearing portion 110.

[0055] In some embodiments, the cover portion 210, the protrusion 220, the enclosure portion 120 and the support portion 110 are all made of heat-conductive materials. When the heating element 300 in the cover portion 210 and the enclosure portion 120 is in operation, the heat generated by the heating element 300 can be conducted to the first accommodating cavity 500 and the second accommodating cavity 600, so as to speed up the casting and molding of the material.

[0056] In some embodiments, a recessed area is provided on the protruding portion 220. The recessed area is recessed in a direction away from the second enclosure portion 124 to form a groove 221. When the protruding portion 220 is inserted into the first enclosure portion 123, an end of the second enclosure portion 124 away from the bearing portion 110 is inserted into the groove 221 to form the second accommodating cavity 600.

[0057] See also Figure 5 In some embodiments, the protrusion 220 is provided with a guide channel 222. The guide channel 222 is connected to the second accommodating cavity 600. The plug end 410 passes through the guide channel 222.

[0058] In some embodiments, the central axis of the recessed area coincides with the central axis of the protruding portion 220 .

[0059] See also Figure 3 and Figure 4 In some embodiments, the first shell 100 further includes a first heat preservation portion 130. The first heat preservation portion 130 is disposed on the bearing portion 110, and the first heat preservation portion 130 is disposed in an annular manner around the enclosure portion 120. The second shell 200 further includes a second heat preservation portion 230, the second heat preservation portion 230 is disposed on the cover portion 210, and the second heat preservation portion 230 is disposed in an annular manner around the protrusion 220. The bearing portion 110, the first heat preservation portion 130, the second heat preservation portion 230 and the cover portion 210 form a heat preservation cavity, and the heat preservation cavity is disposed in an annular manner around the first accommodating cavity 500, which can play a heat preservation role for the first accommodating cavity 500 and the second accommodating cavity 600.

[0060] See also Figure 1 and Figure 2 In some embodiments, the pouring equipment further includes: a connecting frame 800. The connecting frame 800 connects the cover plate portion 210 and the bearing portion 110, so that the cover plate portion 210 and the bearing portion 110 are detachably connected, and the first heat preservation portion 130 abuts against the second heat preservation portion 230, and the end of the second enclosure portion 124 away from the bearing portion 110 abuts against the groove 221.

[0061] In some embodiments, the pouring equipment further includes: a control component. The control component is connected to the heating component 300, the vacuum pump, the vacuum valve 710 and the discharge valve, and is used to control the operation of the heating component 300, the vacuum pump, the vacuum valve 710 and the discharge valve, and the control component can control the temperature of the heating component in different areas, so as to adjust the temperature of one or more areas of the second accommodating chamber 600.

[0062] It is understandable that the temperature, vacuum degree and injection speed can be adjusted according to actual needs through the control component to be suitable for the casting of different products.

[0063] Traditional multi-cavity casting molds use a method of heating the entire casting mold, which makes it difficult to accurately adjust the temperature of each area of ​​the casting mold, and it needs to be moved to the heating area for heating before the casting is completed, resulting in low casting efficiency. However, the casting equipment in the present application has a heating element 300 on both the first shell 100 and the second shell 200, which has its own heating function and can directly heat the casting cavity. The heat conduction efficiency is high, which improves the casting efficiency. By controlling the heating element 300, the temperature of a single casting cavity can be accurately controlled, that is, the temperature of a single casting cavity can be adjusted according to actual needs, thereby increasing the application scope of the casting equipment. In addition, the casting equipment also has the functions of preheating, casting and curing, that is, during the entire casting process, there is no need to open the first shell 100 and the second shell 200 to transfer the casting to different processes, thereby ensuring the continuity of the casting and high casting efficiency.

[0064] The present application heats the cover plate portion 210 and the bearing portion 110 through the heating element 300 to increase the temperature of the first accommodating cavity 500 and the second accommodating cavity 600, thereby accelerating the molding speed of the material in the second accommodating cavity 600 and improving the pouring efficiency. In addition, the compressed air of the pouring tank drives the material to be injected into the second accommodating cavity 600, which can accelerate the speed of injecting the material into the second accommodating cavity 600 and further improve the pouring efficiency.

[0065] Embodiment 2

[0066] An embodiment of the present application provides a pouring system (not shown in the figure), including the pouring equipment in any one of the above-mentioned embodiments, and therefore has all the beneficial effects of the pouring equipment in any one of the above-mentioned embodiments, which will not be described one by one here.

[0067] Embodiment 3

[0068] See also Figure 8 The present application provides a pouring method, wherein the pouring method adopts the pouring equipment in any one of the above-mentioned embodiments 1, and the pouring method comprises the following steps:

[0069] S100: starting the heating element and making the second receiving chamber reach a preset temperature;

[0070] S200: obtaining a suction piece, inserting the suction piece into the first accommodating chamber, and starting the suction piece to perform a vacuum process on the first accommodating chamber so that the first accommodating chamber has a preset vacuum degree;

[0071] S300: starting the injection piece to inject material into the second accommodating cavity and making the material have a preset shape;

[0072] S400: closing the suction part, and closing the injection part after standing for a preset time.

[0073] In some embodiments, the preset temperature in S100 and the preset vacuum degree in S200 are set by a control component.

[0074] It can be understood that the second accommodating chamber in S100 is preheated so that the second accommodating chamber has the preset temperature.

[0075] In some embodiments, while the injection member is started to inject the material into the second accommodating chamber in S300, the suction member performs a vacuum process on the first accommodating chamber. When the material has a preset shape, that is, the second accommodating chamber is filled with the material, the suction member is closed to break the vacuum process on the first accommodating chamber.

[0076] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0077] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A pouring device, characterized in that: include: a first shell; A second housing, wherein the second housing is installed in cooperation with the first housing to define a first accommodating cavity and a second accommodating cavity, wherein the first accommodating cavity is arranged in an annular manner around the second accommodating cavity, and the first accommodating cavity is communicated with the second accommodating cavity; A heating element, wherein the heating element is disposed on the first shell and the second shell; An injection piece, which can pass through the first accommodating cavity and be inserted into the second accommodating cavity to block the air flow passage between the first accommodating cavity and the second accommodating cavity, and the injection piece is used to inject material into the second accommodating cavity at a preset air pressure.

2. The pouring equipment according to claim 1, characterized in that: The injection piece includes a plug-in end, the first accommodating cavity has a first vacuum degree, and the second accommodating cavity has a second vacuum degree. When the first vacuum degree and / or the second vacuum degree are equal to a preset vacuum degree, the plug-in end passes through the first accommodating cavity and is inserted into the second accommodating cavity to inject the material into the second accommodating cavity.

3. The pouring equipment according to claim 1, characterized in that: The first housing comprises: a bearing portion, wherein the heating element is disposed in the bearing portion; The enclosure portion is disposed on the bearing portion, the enclosure portion is connected to the bearing portion, and the bearing portion, the enclosure portion and the second shell form the first accommodating cavity and the second accommodating cavity.

4. The pouring equipment according to claim 3, characterized in that The heating element is connected to the enclosure part, and the enclosure part is provided with a first interface and a second interface, the first interface is provided with a suction piece, the suction piece passes through the first interface and is inserted into the first accommodating cavity, the suction piece is used to vacuum the first accommodating cavity, and the injection piece passes through the second interface and is inserted into the second accommodating cavity.

5. The pouring equipment according to claim 3, characterized in that: The enclosure portion comprises: A first enclosure portion, wherein the first enclosure portion is connected to the bearing portion, and the bearing portion, the first enclosure portion and the second shell form the first accommodating cavity; A second enclosure portion, wherein the first enclosure portion is arranged in a ring shape around the second enclosure portion, and the bearing portion, the second enclosure portion and the second shell form the second accommodating cavity.

6. The pouring equipment according to claim 5, characterized in that The second housing comprises: A cover plate portion, the cover plate portion is arranged opposite to the bearing portion, and the heating element is arranged in the cover plate portion; A protruding portion, wherein the protruding portion is arranged on a side of the cover portion close to the bearing portion, and the protruding portion is inserted into the first enclosure portion to form the first accommodating cavity with the first enclosure portion and the bearing portion, and to form the second accommodating cavity with the second enclosure portion and the bearing portion.

7. The pouring equipment according to claim 6, characterized in that A recessed area is provided on the protruding portion, and the recessed area is recessed in a direction away from the second enclosing portion to form a groove. When the protruding portion is inserted into the first enclosing portion, one end of the second enclosing portion away from the bearing portion is inserted into the groove to form the second accommodating cavity.

8. The pouring equipment according to claim 6, characterized in that The first shell also includes a first insulation part, which is arranged on the bearing part and is arranged in a ring around the enclosure part. The second shell also includes a second insulation part, which is arranged on the cover part and is arranged in a ring around the protrusion. The bearing part and the first insulation part, the second insulation part and the cover part form an insulation cavity, and the insulation cavity is arranged in a ring around the first accommodating cavity.

9. A pouring system, characterized in that: The invention comprises the pouring equipment as described in any one of claims 1 to 8.

10. A casting method, characterized in that: The pouring device according to any one of claims 1 to 8 is used, and the pouring method comprises the following steps: Obtain a suction piece, material and an air source, insert the suction piece into the first accommodating chamber to vacuum the first accommodating chamber, and when the vacuum degree in the first accommodating chamber reaches a preset vacuum degree, drive the material along the injection piece into the second accommodating chamber through the air source so that the material has a preset shape.