Track control network arrangement method, device, equipment and product of track engineering
By establishing a virtual construction environment in track engineering and using computer simulation, the track control network is automatically arranged, and the accuracy and efficiency problems of traditional manual measurement and empirical judgment are solved, and efficient, accurate and flexible track control network layout is achieved.
Patent Information
- Application Number
- CN202411269865.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-11
- Publication Date
- 2025-02-18
AI Technical Summary
In traditional track engineering, the layout of the CPⅢ control network relies on manual measurement and empirical judgment, resulting in limited accuracy, inefficiency, difficulty in adjustment and increased engineering risks.
By establishing a virtual construction environment, using computer simulation and algorithm optimization, the track control network is automatically arranged, and the measurement accuracy and construction efficiency are improved, and human errors are reduced.
It realizes efficient, precise and flexible layout of the track control network, improves construction safety and project quality, and supports dynamic adjustment and optimization.
Smart Images

Figure CN119475478A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of engineering construction, and in particular to a method, device, equipment and product for arranging a track control network of a track engineering project. Background Art
[0002] In traditional rail engineering construction, in order to efficiently and accurately establish the CPⅢ control network, the CPⅡ control network is encrypted online based on the situation of the existing CPⅡ control network. The CPⅢ control network is the track control network, and the CPⅡ control network is the plane control network.
[0003] In traditional track engineering construction, the layout of the CPⅢ control network is a complex and critical step, which directly affects the track laying accuracy and engineering quality. The CPⅢ control network is the track control network. However, the existing technology mainly relies on manual measurement and experience judgment, and has the following limitations: 1) Limited accuracy: Manual measurement may be limited by operator skills and environmental factors, making it difficult to achieve high accuracy requirements.
[0004] 2) Inefficiency: Manual layout of the control network requires a lot of time and labor, affecting the progress of the project.
[0005] 3) Difficulty in adjustment: Once the control network is laid out, it is very difficult to adjust and optimize it, and may require re-measurement and re-construction.
[0006] 4) Risk Management: Errors in manual measurement and layout processes may lead to increased project risks.
[0007] At present, traditional surveying tools such as total stations and levels are usually used for field measurements, relying on the experience of engineers to plan and design the control network, and determining the location and number of control points through drawings and manual calculations. Summary of the invention
[0008] The present invention provides a track control network layout method, device, equipment and product for track engineering, which are used to solve the defects of existing use of traditional measurement tools, such as total stations, levels, etc. for field measurement, relying on the experience of engineers to plan and design the control network, and determining the position and number of control points through drawings and manual calculations, and lacking an efficient, accurate and flexible computer simulation method to optimize the layout process of the track control network.
[0009] According to a first aspect of the present invention, a method for arranging a track control network of a track engineering project is provided, comprising: Establishing a virtual construction environment for the rail engineering project, wherein the virtual construction environment is a simulated construction environment in which the plane control network nodes and the line leveling base points are arranged; Based on the virtual construction environment, evaluating the track control network layout environment; When the evaluation results meet the layout conditions, the track control network is arranged along the track.
[0010] According to an embodiment of the present invention, the evaluation of the track control network layout environment specifically includes: Based on the virtual construction environment, accurate network re-measurement is performed on the arranged plane control network nodes and the line leveling base points; and / or, based on the virtual construction environment, measuring settlement and deformation along the track; And / or, based on the virtual construction environment, re-survey the plane and elevation positions along the track.
[0011] Specifically, this embodiment provides an implementation method for evaluating the layout environment of a rail control network.
[0012] According to one embodiment of the present invention, the arrangement of the track control network along the track specifically includes: Based on the virtual construction environment, obtaining piers arranged along the extension direction of the track; Based on the pier, a bridge fixed support, a bridge and a crash wall are determined, wherein the bridge fixed support is connected to the pier, the bridge is connected to a side of the bridge fixed support away from the pier, and the crash wall is arranged on the bridge along the extension direction of the track; A pair of track control network nodes are arranged on the surface of the crash barrier away from the bridge, wherein the distance between the track control network node and the end surface of the bridge is within a set distance range; Repeat the above steps to obtain N track control network nodes, where N is a positive integer greater than or equal to 2; The track control network is generated based on all the track control network nodes.
[0013] Specifically, this embodiment provides an implementation method for arranging the track control network along the track.
[0014] According to one embodiment of the present invention, the arrangement of the track control network along the track specifically includes: When the bridge is a simply supported beam, obtaining a first length parameter of the simply supported beam; When the distance of the simply supported beams identified by the first length parameter is less than or equal to the first set length, a pair of track control network nodes are set at the distance between every two piers; When the distance of the simply supported beam indicated by the first length parameter is greater than the first set length, a pair of track control network nodes are set at the distance of each pier.
[0015] Specifically, this embodiment provides another implementation method for arranging the track control network along the track.
[0016] According to one embodiment of the present invention, the arrangement of the track control network along the track specifically includes: In the case where the bridge is a common continuous beam, obtaining a second length parameter of the common continuous beam; When the length of the ordinary continuous beam indicated by the second length parameter is less than or equal to the second set length, the track control network node is arranged at the position of the crash barrier corresponding to the bridge fixed support; When the length of the ordinary continuous beam indicated by the second length parameter is greater than the second set length, the track control network node is arranged at the position of the crash wall corresponding to the fixed bearing of the bridge, and at least two first supplementary layout points of the ordinary continuous beam, and the first supplementary layout points are located between 50m and the second set length, and the second set length is greater than 50m.
[0017] Specifically, this embodiment provides another implementation method for arranging the track control network along the track.
[0018] According to one embodiment of the present invention, the arrangement of the track control network along the track specifically includes: In the case where the bridge is a special bridge structure, obtaining structural parameters and a third length parameter of the special bridge structure, wherein the structural parameters at least include the structural form, span and material of the special bridge structure, and the special bridge structure at least includes a long-span continuous beam, a suspension bridge, an arch bridge and a cable-stayed bridge; determining a third set length of the special bridge structure based on the structural parameters; Determining the number and positions of second supplementary arrangement points of the special bridge structure based on the third length parameter and the third set length; Based on the second supplementary arrangement point, the track control network nodes of the special bridge structure are supplementarily arranged.
[0019] Specifically, this embodiment provides another implementation method for arranging the track control network along the track.
[0020] According to one embodiment of the present invention, the arrangement of the track control network along the track specifically includes: When the bridge is within the station area, obtaining the platform eaves of the station area; Based on the bridge and the station area, determining the intersection area of the platform eaves and the crash barrier; Based on the intersection area, the track control network nodes arranged on the platform eaves and the crash barrier are determined.
[0021] Specifically, this embodiment also provides an implementation method for arranging the track control network along the track.
[0022] According to a second aspect of the present invention, a track control network arrangement device for a track engineering project is provided, comprising: An environment establishment module is used to establish a virtual construction environment for the rail engineering project, wherein the virtual construction environment is a simulated construction environment in which the plane control network nodes and the line leveling base points are arranged; An environmental assessment module, used to assess the track control network layout environment based on the virtual construction environment; The arrangement execution module is used to arrange the track control network along the track when the evaluation result meets the arrangement conditions.
[0023] According to a third aspect of the present invention, an electronic device is provided, comprising: a memory and a processor; The memory and the processor communicate with each other via a bus; The memory stores computer instructions that can be executed on the processor; When the processor calls the computer instructions, it can execute the above-mentioned track control network layout method for track engineering.
[0024] According to a fourth aspect of the present invention, a computer program product is provided, which includes a non-transitory machine-readable medium storing a computer program, and when the computer program is executed by a processor, the steps of the track control network layout method for track engineering are implemented.
[0025] The above one or more technical solutions in the present invention have at least one of the following technical effects: the present invention provides a method, device, equipment and product for arranging a track control network for a track engineering project, which optimizes the layout of the control network by utilizing advanced algorithms, realizes the automated simulation of the layout process of the track control network during track construction, improves measurement accuracy and construction efficiency, and simulates the reduction of human errors, improves construction safety, and realizes dynamic adjustment and optimization of the control network layout during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0027] Figure 1 It is a schematic flow chart of a method for arranging a track control network of a track engineering project provided by the present invention.
[0028] Figure 2 It is a schematic diagram of the arrangement relationship of piers, bridge fixed supports, bridges and crash barriers in the track engineering provided by the present invention.
[0029] Figure 3 It is a structural schematic diagram of a track control network arrangement device for a track engineering provided by the present invention.
[0030] Figure 4 It is a structural schematic diagram of the electronic device provided by the present invention.
[0031] Reference numerals: 10. Pier; 20. Bridge fixed support; 30. Bridge; 40. Crash wall; 100, environment establishment module; 200, environment assessment module; 300, arrangement execution module; 810, processor; 820, communication interface; 830, memory; 840, communication bus. DETAILED DESCRIPTION
[0032] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] The present invention is described in detail below in conjunction with the accompanying drawings of the specification. The specific operating method in the method embodiment can also be applied to the device embodiment or the system embodiment. In the description of the present invention, unless otherwise specified, "at least one" includes one or more. "Multiple" refers to two or more. For example, at least one of A, B and C includes: A exists alone, B exists alone, A and B exist at the same time, A and C exist at the same time, B and C exist at the same time, and A, B and C exist at the same time. In the present invention, " / " means or, for example, A / B can mean A or B; "and / or" in this article is only a kind of association relationship that describes the associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone.
[0034] The present invention will be described in detail below in conjunction with specific implementation modes.
[0035] In some specific embodiments of the present invention, Figure 1 and Figure 2 As shown, this solution provides a method for arranging a track control network of a track engineering, comprising: Establish a virtual construction environment for rail engineering, which is a simulated construction environment with the plane control network nodes and line leveling base points arranged; Evaluate the track control network layout environment based on the virtual construction environment; When the evaluation results meet the layout conditions, the track control network will be laid out along the track.
[0036] In some possible implementations of the present invention, evaluating the layout environment of the track control network specifically includes: Based on the virtual construction environment, the arranged plane control network nodes and line leveling base points are accurately re-measured; and / or, based on a virtual construction environment, measuring settlement and deformation along the track; And / or, based on the virtual construction environment, re-survey the plane and elevation positions along the track.
[0037] Specifically, this embodiment provides an implementation method for evaluating the layout environment of the track control network. Before the track control network is laid out, the layout environment of the track control network needs to be evaluated. The present invention uses computer technology to achieve the evaluation of the layout environment of the track control network in a virtual environment based on the relevant data that has been surveyed, thereby providing a data basis for the layout of the track control network.
[0038] In a possible embodiment, before the track control network (CPⅢ) is built, a comprehensive re-survey of the precision measurement network should be carried out to ensure the connection of the track control network (CPⅢ), that is, the arranged plane control network nodes and line leveling base points should be accurately re-surveyed.
[0039] In a possible embodiment, the track control network (CPⅢ) measurement should be carried out only after the settlement and deformation of the offline engineering meets the specification requirements and the track laying condition assessment is passed, that is, the settlement and deformation along the track are measured.
[0040] In a possible embodiment, the completed offline project should be re-surveyed in plane and elevation before track laying to deal with the error limit caused by construction layout in advance and lay a good foundation for track laying, that is, re-survey the plane and elevation along the track.
[0041] In some possible implementations of the present invention, the arrangement of a track control network along the track specifically includes: Based on the virtual construction environment, a pier 10 arranged along the extension direction of the track is obtained; Based on the pier 10, the bridge 30 fixed support 20, the bridge 30 and the crash wall 40 are determined, the bridge fixed support 20 is connected to the pier 10, the bridge 30 is connected to the side of the bridge fixed support 20 away from the pier 10, and the crash wall 40 is set on the bridge 30 along the extension direction of the track; A pair of track control network nodes are arranged on the surface of the crash wall 40 away from the bridge 30, wherein the distance between the track control network node and the end surface of the bridge 30 is within a set distance range; Repeat the above steps to obtain N track control network nodes, where N is a positive integer greater than or equal to 2; Generate a track control network based on all track control network nodes.
[0042] Specifically, this embodiment provides an implementation method for arranging a track control network along the track. By acquiring the features of the pier 10, the fixed support 20 of the bridge 30, the bridge 30 and the crash barrier 40 during the track construction process in a virtual environment, the layout of the track control network nodes in different environments during the track laying process is realized, making the virtual environment closer to the actual situation for the layout of the track control network nodes, improving work efficiency while ensuring accuracy.
[0043] In some possible implementations of the present invention, the arrangement of a track control network along the track specifically includes: When the bridge 30 is a simply supported beam, a first length parameter of the simply supported beam is obtained; When the distance of the simply supported beams identified by the first length parameter is less than or equal to the first set length, a pair of track control network nodes are set at the distance between every two piers 10; In the case where the distance of the simply supported beam identified by the first length parameter is greater than the first set length, a pair of track control network nodes are set at the distance of each pier 10.
[0044] Specifically, this embodiment provides another implementation method for arranging the track control network along the track. When the bridge 30 is a simply supported beam, the track control network nodes are arranged in combination with the length parameters of the simply supported beam.
[0045] In a possible embodiment, for a 24m or 32m simply supported beam, a pair of CPⅢ points is arranged for every 2 holes, and the distance between two adjacent pairs of CPⅢ points is about 64m (32m+32m), 56m (24m+32m) or 48m (24m+24m).
[0046] In a possible embodiment, for a 40m simply supported beam, a pair of CPIII points is arranged in each hole; for a continuous 24m simply supported beam, a pair of CPIII points may also be arranged in every three holes according to actual conditions.
[0047] In some possible implementations of the present invention, the arrangement of a track control network along the track specifically includes: When the bridge 30 is a common continuous beam, a second length parameter of the common continuous beam is obtained; When the length of the common continuous beam identified by the second length parameter is less than or equal to the second set length, the track control network node is arranged at the position of the crash wall 40 corresponding to the fixed support 20 of the bridge 30; When the length of the ordinary continuous beam indicated by the second length parameter is greater than the second set length, the track control network node is arranged at the position of the fixed support 20 of the bridge 30 corresponding to the crash wall 40, and the first supplementary layout points of at least two ordinary continuous beams, and the first supplementary layout points are located between 50m and the second set length, and the second set length is greater than 50m.
[0048] Specifically, this embodiment provides another implementation method for arranging the track control network along the track. When the bridge 30 is a common continuous beam, the track control network nodes are arranged in combination with the length parameters of the continuous beam.
[0049] In a possible embodiment, the second length parameter is greater than the first length parameter, and the second set length is greater than the first set length.
[0050] In a possible embodiment, for ordinary continuous beams, CPⅢ should be preferentially arranged above the fixed end.
[0051] In a possible embodiment, for ordinary continuous beams with a span of more than 80m, one or several pairs of CPⅢ points should be arranged as evenly as possible at intervals of 50 to 80m in the middle of the span. When using or re-measuring the CPⅢ points in the span, try to ensure that they are the same as the external environment for measurement. The entire continuous beam section should be reviewed before use.
[0052] In some possible implementations of the present invention, the arrangement of a track control network along the track specifically includes: When the bridge 30 is a special bridge structure, the structural parameters and the third length parameter of the special bridge structure are obtained, where the structural parameters at least include the structural form, span and material of the special bridge structure, and the special bridge structure at least includes a long-span continuous beam, a suspension bridge, an arch bridge and a cable-stayed bridge; determining a third set length for the particular bridge structure based on the structural parameters; determining the number and positions of the second supplementary arrangement points of the special bridge structure based on the third length parameter and the third set length; Based on the second supplementary layout point, the track control network nodes of the special bridge structure are supplemented and arranged.
[0053] Specifically, this embodiment provides another implementation method for arranging the track control network along the track. When the bridge 30 is a special bridge structure, the track control network nodes are supplementarily arranged according to the structural parameters and the third length parameter of the special bridge structure.
[0054] In a possible embodiment, the third length parameter is greater than the second length parameter, and the third set length is greater than the second set length.
[0055] In a possible embodiment, the points are arranged according to the CPⅢ point pair arrangement requirements and spacing, taking into account the different beam span structural forms, spans, and materials. The spacing between adjacent point pairs can be appropriately increased, but the maximum does not exceed 90m.
[0056] In a possible embodiment, no CPⅢ point may be buried in the span of a continuous beam within 80 meters; a pair of CPⅢ points should be buried in the span of a continuous beam between 80 and 120 meters; and two pairs of CPⅢ points should be buried in the span of a continuous beam between 120 and 180 meters.
[0057] In a possible embodiment, when a CPⅢ point pair is buried in the mid-span, the CPⅢ point should be buried at the fixed end on the same continuous beam. The embedded parts of this CPⅢ point should be flush with the top surface of the crash barrier 40, and a special connecting device should be used to facilitate the installation of the total station.
[0058] In a possible embodiment, when two or more pairs of CPⅢ points are buried in the mid-span of the continuous beam, the CPⅢ points of the left and right lines should be on the same observation line of sight.
[0059] In some possible implementations of the present invention, the arrangement of a track control network along the track specifically includes: When the bridge 30 is within the station area, obtaining the platform eaves of the station area; Based on the bridge 30 and the station area, determine the intersection area of the platform eaves and the crash barrier 40; Based on the intersection area, the track control network nodes arranged on the platform eaves and the crash barrier 40 are determined.
[0060] Specifically, this embodiment also provides an implementation method for arranging the track control network along the track. When the bridge 30 is within the station area, since the clearance between the protective wall in the platform beam section and the bottom of the platform beam cannot meet the leveling measurement requirements, the CPⅢ points within the station area need to be set on the platform eaves, and the remaining sections are also set on the protective wall of the fixed support 20 of the bridge 30 to ensure the stability of the marking points.
[0061] In a possible embodiment, the CPⅢ points in the station area and the junction area should also be arranged in pairs, generally about 50 to 70 meters apart. In some special cases, the shortest distance between adjacent points is not less than 40 meters and the longest is not more than 80 meters. The mileage difference of the same point pair is not more than 3 meters, and the CPⅢ points should be arranged at roughly the same height.
[0062] In some specific embodiments of the present invention, Figure 3 As shown, this solution provides a track control network layout device for track engineering, including: The environment establishment module 100 is used to establish a virtual construction environment for the rail engineering project, where the virtual construction environment is a simulated construction environment in which the plane control network nodes and the line leveling base points are arranged; An environmental assessment module 200 is used to assess the track control network layout environment based on a virtual construction environment; The arrangement execution module 300 is used to arrange the track control network along the track when the evaluation result meets the arrangement conditions.
[0063] Optionally, the rail control network layout environment is evaluated, including: Based on the virtual construction environment, the arranged plane control network nodes and line leveling base points are accurately re-measured; and / or, based on a virtual construction environment, measuring settlement and deformation along the track; And / or, based on the virtual construction environment, re-survey the plane and elevation positions along the track.
[0064] Specifically, this embodiment provides an implementation method for evaluating the layout environment of a rail control network.
[0065] Optionally, a track control network is arranged along the track, specifically including: Based on the virtual construction environment, a pier 10 arranged along the extension direction of the track is obtained; Based on the pier 10, the bridge 30 fixed support 20, the bridge 30 and the crash wall 40 are determined, the bridge fixed support 20 is connected to the pier 10, the bridge 30 is connected to the side of the bridge fixed support 20 away from the pier 10, and the crash wall 40 is set on the bridge 30 along the extension direction of the track; A pair of track control network nodes are arranged on the surface of the crash barrier 40 away from the bridge 30, wherein the distance between the track control network node and the end surface of the bridge 30 is within a set distance range; Repeat the above steps to obtain N track control network nodes, where N is a positive integer greater than or equal to 2; Generate a track control network based on all track control network nodes.
[0066] Specifically, this embodiment provides an implementation method for arranging a track control network along the track.
[0067] Optionally, a track control network is arranged along the track, specifically including: When the bridge 30 is a simply supported beam, obtaining a first length parameter of the simply supported beam; When the distance of the simply supported beams identified by the first length parameter is less than or equal to the first set length, a pair of track control network nodes are set at the distance between every two piers 10; In the case where the distance of the simply supported beam identified by the first length parameter is greater than the first set length, a pair of track control network nodes are set at the distance of each pier 10.
[0068] Specifically, this embodiment provides another implementation method for arranging a track control network along the track.
[0069] Optionally, a track control network is arranged along the track, specifically including: When the bridge 30 is a common continuous beam, a second length parameter of the common continuous beam is obtained; When the length of the common continuous beam identified by the second length parameter is less than or equal to the second set length, the track control network node is arranged at the position of the crash wall 40 corresponding to the fixed support 20 of the bridge 30; When the length of the ordinary continuous beam indicated by the second length parameter is greater than the second set length, the track control network node is arranged at the position of the fixed support 20 of the bridge 30 corresponding to the crash wall 40, and the first supplementary layout points of at least two ordinary continuous beams, and the first supplementary layout points are located between 50m and the second set length, and the second set length is greater than 50m.
[0070] Specifically, this embodiment provides another implementation method for arranging a track control network along the track.
[0071] Optionally, a track control network is arranged along the track, specifically including: When the bridge 30 is a special bridge structure, the structural parameters and the third length parameter of the special bridge structure are obtained, where the structural parameters at least include the structural form, span and material of the special bridge structure, and the special bridge structure at least includes a long-span continuous beam, a suspension bridge, an arch bridge and a cable-stayed bridge; determining a third set length for the particular bridge structure based on the structural parameters; determining the number and positions of the second supplementary arrangement points of the special bridge structure based on the third length parameter and the third set length; Based on the second supplementary layout point, the track control network nodes of the special bridge structure are supplemented and arranged.
[0072] Specifically, this embodiment provides another implementation method for arranging a track control network along the track.
[0073] Optionally, a track control network is arranged along the track, specifically including: When the bridge 30 is within the station area, obtaining the platform eaves of the station area; Based on the bridge 30 and the station area, determine the intersection area of the platform eaves and the crash barrier 40; Based on the intersection area, the track control network nodes arranged on the platform eaves and the crash barrier 40 are determined.
[0074] Specifically, this embodiment also provides an implementation method for arranging a track control network along the track.
[0075] Figure 4 An example of a physical structure diagram of an electronic device is shown in FIG. Figure 4 As shown, the electronic device may include: a processor 810, a communication interface 820, a memory 830 and a communication bus 840, wherein the processor 810, the communication interface 820 and the memory 830 communicate with each other through the communication bus 840. The processor 810 may call the logic instructions in the memory 830 to execute the track control network layout method of the track engineering.
[0076] It should be noted that the electronic device in this embodiment can be a server, a PC, or other devices in specific implementation, as long as its structure includes the following: Figure 4 The processor 810, communication interface 820, memory 830 and communication bus 840 shown in the figure, wherein the processor 810, communication interface 820, memory 830 communicate with each other through the communication bus 840, and the processor 810 can call the logic instructions in the memory 830 to execute the above method. This embodiment does not limit the specific implementation form of the electronic device.
[0077] The server may be a single server or a server group. The server group may be centralized or distributed (for example, the server may be a distributed system).
[0078] In a possible embodiment, the server can be local or remote relative to the terminal. For example, the server can access information stored in the user terminal, database or any combination thereof via a network.
[0079] As another example, the server may be directly connected to at least one of the user terminal and the database to access information and / or data stored therein.
[0080] In a possible embodiment, the server may be implemented on a cloud platform; by way of example only, the cloud platform may include a private cloud, a public cloud, a hybrid cloud, a community cloud, a distributed cloud, an inter-cloud, a multi-cloud, etc., or any combination thereof.
[0081] In a possible embodiment, the server and the user terminal may be implemented on an electronic device having one or more components in the embodiments of the present invention.
[0082] Furthermore, the network may be used for the exchange of information and / or data.
[0083] In a possible embodiment, one or more components in the interactive scenario (eg, a server, a user terminal, and a database) may send information and / or data to other components.
[0084] In possible embodiments, the network may be any type of wired or wireless network, or a combination thereof. As examples only, the network may include a wired network, a wireless network, a fiber optic network, a telecommunications network, an intranet, the Internet, a local area network (LAN), a wide area network (WAN), a wireless local area network (WLAN), a metropolitan area network (MAN), a wide area network (WAN), a public switched telephone network (PSTN), a Bluetooth network, a ZigBee network, or a near field communication (NFC) network, or any combination thereof.
[0085] In a possible embodiment, the network may include one or more network access points. For example, the network may include a wired or wireless network access point, such as a base station and / or a network switching node, through which one or more components of the interactive scene may connect to the network to exchange data and / or information.
[0086] In addition, the logic instructions in the memory 830 described above may be implemented in the form of software functional units and when sold or used as independent products, may be stored in a computer-readable storage medium.
[0087] Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for enabling a computer device (which can be a personal computer, server, or network device, etc.) to perform all or part of the steps of the methods of various embodiments of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., various media that can store program codes.
[0088] In a possible embodiment, the embodiment of the present invention further provides a non-transitory computer-readable storage medium having a computer program stored thereon, which, when executed by a processor, is implemented to execute the track control network layout method for the track engineering provided in the above embodiments.
[0089] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, i.e., they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Those of ordinary skill in the art may understand and implement it without creative effort.
[0090] Through the description of the above implementation modes, those skilled in the art can clearly understand that each implementation mode can be implemented by means of software plus a necessary general hardware platform, or of course by hardware. Based on such an understanding, the above technical solution can essentially or in other words be embodied in the form of a software product that contributes to the prior art. The computer software product can be stored in a computer-readable storage medium, such as ROM / RAM, a magnetic disk, an optical disk, etc., and includes a number of instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods of each embodiment or some parts of the embodiment.
[0091] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for arranging a track control network of a track engineering, characterized in that: include: Establishing a virtual construction environment for the rail engineering project, wherein the virtual construction environment is a simulated construction environment in which the plane control network nodes and the line leveling base points are arranged; Based on the virtual construction environment, evaluating the track control network layout environment; When the evaluation results meet the layout conditions, the track control network is arranged along the track.
2. The method for arranging a track control network of a track engineering according to claim 1, characterized in that: The evaluation of the rail control network layout environment specifically includes: Based on the virtual construction environment, accurate network re-measurement is performed on the arranged plane control network nodes and the line leveling base points; and / or, based on the virtual construction environment, measuring settlement and deformation along the track; And / or, based on the virtual construction environment, re-survey the plane and elevation positions along the track.
3. The method for arranging a track control network of a track engineering according to claim 1 or 2, characterized in that: The arrangement of the track control network along the track specifically includes: Based on the virtual construction environment, obtaining piers (10) arranged along the extension direction of the track; Based on the pier (10), a bridge fixed support (20), a bridge (30) and a crash barrier (40) are determined, the bridge (30) fixed support is connected to the pier (10), the bridge (30) is connected to a side of the bridge (30) fixed support away from the pier (10), and the crash barrier (40) is arranged on the bridge (30) along the extension direction of the track; A pair of track control network nodes are arranged on the surface of the crash barrier (40) on a side away from the bridge (30), wherein the distance between the track control network nodes and the end surface of the bridge (30) is within a set distance range; Repeat the above steps to obtain N track control network nodes, where N is a positive integer greater than or equal to 2; The track control network is generated based on all the track control network nodes.
4. The method for arranging a track control network of a track engineering according to claim 3, characterized in that: The arrangement of the track control network along the track specifically includes: When the bridge (30) is a simply supported beam, obtaining a first length parameter of the simply supported beam; When the distance of the simply supported beams identified by the first length parameter is less than or equal to a first set length, a pair of track control network nodes are arranged at a distance between every two piers (10); When the distance of the simply supported beam indicated by the first length parameter is greater than a first set length, a pair of track control network nodes are arranged at the distance of each pier (10).
5. The method for arranging a track control network of a track engineering according to claim 3, characterized in that: The arrangement of the track control network along the track specifically includes: When the bridge (30) is a common continuous beam, obtaining a second length parameter of the common continuous beam; When the length of the ordinary continuous beam indicated by the second length parameter is less than or equal to a second set length, the track control network node is arranged at a position of the crash barrier (40) corresponding to the bridge fixed support (20); In the case where the length of the ordinary continuous beam indicated by the second length parameter is greater than the second set length, the track control network node is arranged at a position of the crash barrier (40) corresponding to the bridge fixed support (20), and at least two first supplementary arrangement points of the ordinary continuous beam, the first supplementary arrangement points being located between 50m and the second set length, the second set length being greater than 50m.
6. The method for arranging a track control network of a track engineering according to claim 3, characterized in that: The arrangement of the track control network along the track specifically includes: In the case where the bridge (30) is a special bridge structure, obtaining structural parameters and a third length parameter of the special bridge structure, wherein the structural parameters at least include the structural form, span and material of the special bridge structure, and the special bridge structure at least includes a long-span continuous beam, a suspension bridge, an arch bridge and a cable-stayed bridge; determining a third set length of the special bridge structure based on the structural parameters; Determining the number and positions of second supplementary arrangement points of the special bridge structure based on the third length parameter and the third set length; Based on the second supplementary arrangement point, the track control network nodes of the special bridge structure are supplementarily arranged.
7. The method for arranging a track control network of a track engineering according to claim 3, characterized in that: The arrangement of the track control network along the track specifically includes: When the bridge (30) is within the station area, obtaining the platform eaves of the station area; Based on the bridge (30) and the station area, determining the intersection area of the platform eaves and the crash barrier (40); Based on the intersection area, the track control network nodes arranged on the platform eaves and the crash barrier (40) are determined.
8. A track control network arrangement device for a track engineering, characterized in that: include: An environment establishment module (100) is used to establish a virtual construction environment for a rail engineering project, wherein the virtual construction environment is a simulated construction environment in which plane control network nodes and line leveling base points are arranged; An environmental assessment module (200) is used to assess the track control network layout environment based on the virtual construction environment; The arrangement execution module (300) is used to arrange the track control network along the track when the evaluation result meets the arrangement conditions.
9. An electronic device, characterized in that: include: Memory (830) and processor (810); The memory (830) and the processor (810) communicate with each other via a bus; The memory (830) stores computer instructions that can be executed on the processor (810); When the processor (810) calls the computer instruction, it is capable of executing the track control network layout method for track engineering as described in any one of claims 1 to 7 above.
10. A computer program product comprising a non-transitory machine-readable medium storing a computer program, characterized in that: When the computer program is executed by the processor (810), the steps of the method for arranging a track control network for a track engineering project described in any one of claims 1 to 7 are implemented.