A road and bridge pile foundation efficient slag cleaning device and use method thereof

By designing an efficient slag cleaning equipment combining arc-shaped pads, lifting plates and spiral sheets, the problem of incomplete cleaning of the bottom of the drilling hole in the prior art has been solved, and a more comprehensive cleaning effect and higher engineering quality have been achieved.

CN119507832BActive Publication Date: 2025-04-04YIYANG TRAFFIC PROGRAMMING RECONNAISSANCE DESIGN INST
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202510083656.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2025-01-20
Publication Date
2025-04-04
Estimated Expiration
2045-01-20

AI Technical Summary

Technical Problem

The prior art is ineffective when cleaning slag blocks in the drill hole, especially the slag blocks at the bottom of the drill hole, resulting in incomplete cleaning of the bottom of the drill hole.

Method used

A high-efficiency slag cleaning equipment for road and bridge pile foundations is designed, using multiple arc-shaped pads and lifting plates to match spiral plates. First, the slag blocks at the bottom of the drill hole are moved under the lifting plate. Through the lifting effect of the spiral plates, the slag blocks are collected into the slag loading bucket, and the larger slag blocks are broken through a crushing knife to avoid blockage.

Benefits of technology

A comprehensive cleaning of the bottom of the drill hole is achieved, which avoids adverse effects caused by slag deposition. Through the screening device and hole wall reinforcement device, the cleaning efficiency and engineering quality are further improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119507832B_ABST
    Figure CN119507832B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of road and bridge pile foundation construction, and discloses an efficient slag cleaning device for road and bridge pile foundation and a method of using the same, including: a top seat, the bottom of which is rotatably mounted with an outer gear ring, a side of which is mounted with a motor, and an output end of the motor is connected with a driving gear; a slag cleaning device for collecting slag blocks in a borehole; a screening device for screening slag blocks according to their particle sizes; and a hole wall reinforcement device for reinforcing the hole wall of the borehole to prevent the slag blocks on the hole wall from falling. Through the setting of the slag cleaning device, a plurality of arc-shaped paddles first push the slag blocks at the bottom of the borehole outward, and a plurality of lifting plates then push the slag blocks upward, and the spiral blades lift the slag blocks into a slag bucket for collection by rotating, thereby achieving the effect of cleaning the bottom of the borehole, with a relatively comprehensive cleaning coverage and a better cleaning effect, thereby preventing a large amount of slag blocks from being deposited at the bottom of the borehole and not being effectively cleaned.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road and bridge pile foundation construction, and in particular to a road and bridge pile foundation high-efficiency slag cleaning device and a use method thereof. Background Art

[0002] During the construction of road and bridge pile foundations, drilling operations are required. When the drilling reaches the set depth, slag cleaning equipment is required to clean the borehole to avoid the presence of a large number of slag blocks inside the borehole that affect the pile foundation operation and the quality of the project. The existing slag cleaning method usually uses a spiral excavator to remove the loose slag blocks and slag soil on the inner wall of the borehole through the spiral lifting blade.

[0003] However, the prior art has the following problems:

[0004] The prior art mainly focuses on cleaning the loose slag blocks on the inner wall of the borehole when cleaning the slag blocks in the borehole. However, since the bottom of the spiral excavator is usually pointed, the tip of the bottom of the spiral excavator cannot lift up the slag blocks at the bottom of the borehole when cleaning the slag blocks at the bottom of the borehole, resulting in poor cleaning effect on the bottom of the borehole. Summary of the invention

[0005] The purpose of the present invention is to provide a road and bridge pile foundation efficient slag cleaning equipment and its use method in order to solve the above problems and overcome the defects of the prior art, as described in detail below.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] The present invention provides an efficient slag cleaning device for road and bridge pile foundations, comprising: a top seat, an outer gear ring is rotatably installed at the bottom of the top seat, a motor is installed on the side of the top seat, an output end of the motor is connected to a driving gear, the driving gear is meshed with the outer gear ring, and a connecting flange is arranged on the top of the top seat; a slag cleaning device is used to collect slag blocks in the drill hole; a screening device is used to screen the slag blocks according to their particle size; a hole wall reinforcement device is used to reinforce the hole wall of the drill hole to prevent the slag blocks on the hole wall from falling; the slag cleaning device comprises a connecting frame, the connecting frame is installed at the bottom of the outer gear ring, a drilling barrel is connected to the connecting frame, a plurality of drilling teeth are arranged at the bottom of the drilling barrel, a spiral sheet is connected to the inner wall of the drilling barrel, and the bottom surface of the top seat is connected to There is a connecting column, the bottom of the connecting column is connected to a layer plate, the center position of the bottom surface of the layer plate is connected to a short shaft, the outer wall of the short shaft is rotatably connected to a sun gear, a plurality of planetary gears are rotatably installed on the bottom of the layer plate, the inner wall of the drilling tube is connected to an internal gear ring, the bottom surface of the sun gear is connected to four arc frames, the bottom surfaces of the four arc frames are connected to a second layer plate, the bottom surface of the second layer plate is connected to a fixed column, a slag bucket is installed at the bottom of the fixed column through a bracket, the slag bucket is located inside the drilling tube, a bottom cover is installed at the bottom of the slag bucket through a hinge, a buckle is provided between the bottom cover and the slag bucket, a plurality of arc-shaped shifting plates are connected to the bottom surface of the bottom cover, and a plurality of lifting plates are connected to the outer wall of the slag bucket.

[0008] Preferably, a through hole is provided in the middle of the connecting frame, the connecting column is located in the through hole of the connecting frame, the connecting column does not contact the connecting frame, the multiple planetary gears are arranged in a circular array with the sun gear as the center, the inner gear ring is meshed with the multiple planetary gears, and the multiple planetary gears are all meshed with the sun gear.

[0009] Preferably, the plurality of arc-shaped shifting plates are arranged in a circular array with the center of the bottom cover as the center, the plurality of lifting plates are arranged in a circular array with the center of the bottom cover as the center, the bottoms of the plurality of lifting plates are located outside the plurality of arc-shaped shifting plates, the bottoms of the spiral sheets are located above the tops of the plurality of lifting plates, and the tops of the spiral sheets are located between the top of the slag loading bucket and the bottom surface of the second layer plate.

[0010] Preferably, a plurality of rotating shafts are rotatably mounted on the outer wall of the slag loading bucket, and the plurality of rotating shafts are respectively located between every two adjacent lifting plates. A driven gear is connected to the end of the rotating shaft away from the slag loading bucket. A mounting groove is provided on the inner wall of the drilling barrel, and an annular rack is installed in the mounting groove of the drilling barrel. The plurality of driven gears are meshed with the annular rack, and a plurality of crushing knives are connected to the outer wall of the rotating shaft.

[0011] Preferably, the buckle lock comprises an upper locking block, a lower locking block, a bevel lock buckle and a rebound push block, the upper locking block is connected to the slag loading bucket, the lower locking block is connected to the bottom cover, the bevel lock buckle is slidably installed in the upper locking block by a spring, the rebound push block is slidably installed on the lower locking block by a spring, a buckle is provided on the top of the lower locking block, the buckle of the lower locking block overlaps the top surface of the bevel lock buckle, one end of the rebound push block is located outside the lower locking block, the other end of the rebound push block is located inside the lower locking block, and the end of the rebound push block located inside the lower locking block contacts with the bevel lock buckle.

[0012] Preferably, the screening device includes an upper funnel, which is installed on the inner wall of the slag bucket, and a plurality of short rods are installed on the inner wall of the slag bucket, a screen is connected between the plurality of short rods, and the plurality of short rods are arranged in a circular array with the center of the screen as the center, an inclined funnel is connected to the bottom of the screen, an inclined funnel is connected to the outer wall of the inclined funnel is connected to an inclined guide plate, the outer wall of the inclined guide plate is connected to the inner wall of the slag bucket, and a partition is installed on the inner wall of the slag bucket.

[0013] Preferably, the partition is arranged longitudinally, an outlet is arranged at the bottom of the inclined funnel, the outlet at the bottom of the inclined funnel is located on the right side of the partition, the bottom of the inclined guide plate is located on the left side of the partition, and the bottom of the partition contacts the top surface of the bottom cover.

[0014] Preferably, a sliding rod is slidably installed on the inner wall of the slag loading bucket through a bracket, a spring is arranged between the sliding rod and the inner wall of the slag loading bucket, one end of the sliding rod is connected to an arc block, the other end of the sliding rod is connected to a No. 1 hammer, a sliding groove is opened on the inner wall of the slag loading bucket, the arc block is slidably connected to the sliding groove of the slag loading bucket, the spiral sheet is in sliding contact with the arc block during movement, the No. 1 hammer is in contact with the outer wall of the inclined funnel during movement, a rotating rod is rotatably installed on the bottom surface of the inclined guide plate through the bracket, one end of the rotating rod is connected to a supporting plate, the other end of the rotating rod is connected to a No. 2 hammer, the supporting plate is located in the outlet at the bottom of the inclined funnel, and the No. 2 hammer is in contact with the bottom surface of the inclined guide plate during movement.

[0015] Preferably, the hole wall reinforcement device includes two sliding push rods, which are respectively slidably installed on the inner walls of two of the arc-shaped frames, and the two sliding push rods are mirror-imaged. An elliptical groove is provided on the short axis, and a sliding shaft is installed on the end of the sliding push rod close to the elliptical groove, and the two sliding shafts are slidably connected to the elliptical groove. An arc-shaped push block is connected to the end of the sliding push rod away from the sliding shaft, and two inner sliding seats are connected to the bottom of the inner gear ring, and an outer push plate is slidably connected to the inner wall of the inner sliding seat, and the two outer push plates are mirror-imaged, and a spring is provided inside the connection between the outer push plate and the inner sliding seat, and two square grooves are provided on the drilling tube, and the two outer push plates are respectively slidably connected to the two square grooves of the drilling tube.

[0016] A method for using a high-efficiency slag removal device for a road and bridge pile foundation comprises the following steps:

[0017] Step 1: Connect the sling to the connecting flange on the top seat with bolts;

[0018] Step 2: Fix the sling on the lifting machinery;

[0019] Step 3: Move the lifting machinery so that the drilling tube is directly above the drill hole;

[0020] Step 4: Start the motor, and the drilling tube and the slag bucket begin to rotate;

[0021] Step 5: Control the lifting machinery to lower the drilling tube into the borehole;

[0022] Step 6: As the drilling tube moves downward, the drilling tube knocks down the loose slag blocks on the inner wall of the borehole. After the drilling tube reaches the bottom of the borehole, multiple arc-shaped shifting plates shift the slag blocks at the bottom of the borehole outward, and multiple lifting plates lift the contacted slag blocks upward. The spiral blades lift the slag blocks into the slag bucket by spiral lifting.

[0023] Step seven: control the crane to lift the drilling tube. After the drilling tube leaves the borehole, place the drilling tube on the ground, open the buckle, lift the drilling tube again, open the bottom cover, and the slag blocks in the slag bucket fall to the ground. Move the drilling tube away, and the staff closes the bottom cover and cleans the slag blocks. The slag cleaning operation is completed in one step.

[0024] The beneficial effects are:

[0025] 1. The high-efficiency slag cleaning equipment for road and bridge pile foundations, through the setting of the slag cleaning device, enables multiple arc-shaped plates to first push the slag blocks at the bottom of the borehole outwards, and multiple lifting plates then push the slag blocks upwards, and the spiral pieces lift the slag blocks into the slag bucket for collection through rotation, thereby achieving the effect of cleaning the bottom of the borehole, with a relatively comprehensive cleaning coverage and a better cleaning effect, thereby avoiding a large amount of slag blocks deposited at the bottom of the borehole and not being effectively cleaned; through the setting of multiple crushing knives, the multiple crushing knives can crush the slag blocks they contact by rotating, so that larger slag blocks are crushed when they are flipped upwards through multiple lifting plates, thereby avoiding larger slag blocks from being blocked in the movement path of the slag blocks, thereby affecting the cleaning effect.

[0026] 2. The efficient slag cleaning equipment for road and bridge pile foundations is equipped with a screening device, so that the inclined funnel and the inclined guide plate can cooperate to separate the fine slag blocks with larger particle sizes and the coarse slag blocks with larger particle sizes to both sides of the partition. When the slag blocks are unloaded after cleaning, the fine slag blocks and the coarse slag blocks are divided into two piles and stacked together, which is convenient for the staff to use the slag blocks of different particle sizes and reduces the steps of the staff to screen the slag blocks by themselves; through the setting of the No. 1 hammer and the No. 2 hammer, the No. 1 hammer can repeatedly hit the inclined funnel, and the No. 2 hammer can repeatedly hit the inclined guide plate, which promotes the sliding of the slag blocks on the inclined funnel and the inclined guide plate to avoid blockage.

[0027] 3. The high-efficiency slag cleaning equipment for road and bridge pile foundations is equipped with a hole wall reinforcement device. During the process of cleaning the borehole, the two outer push plates compact the inner wall of the borehole by continuously protruding outward from the outer surface of the drilling tube, and press some loose slag blocks into the soil layer, thereby reinforcing the inner wall of the borehole and preventing some loose slag blocks from falling into the borehole again after cleaning, affecting the quality of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0029] Figure 1 It is a schematic diagram of the appearance of the present invention;

[0030] Figure 2 It is a schematic diagram of the overall structure of the present invention;

[0031] Figure 3 It is a schematic structural diagram of a slag cleaning device of the present invention;

[0032] Figure 4 is a schematic diagram of the sun gear structure of the present invention;

[0033] Figure 5 It is a schematic diagram of the short axis structure of the present invention;

[0034] Figure 6 It is a schematic diagram of the structure of the arc-shaped paddle of the present invention;

[0035] Figure 7 It is a schematic diagram of the spiral plate structure of the present invention;

[0036] Figure 8 It is a schematic diagram of the rotating shaft structure of the present invention;

[0037] Fig. 9 It is a schematic structural diagram of the screening device of the present invention;

[0038] Fig.10 It is a schematic diagram of the buckle lock structure of the present invention;

[0039] Fig.11 It is a schematic diagram of the oblique funnel structure of the present invention;

[0040] Fig.12 It is a schematic diagram of the structure of the inclined guide plate of the present invention;

[0041] Fig.13 It is a schematic structural diagram of the hole wall reinforcement device of the present invention;

[0042] Fig.14 It is a schematic diagram of the push plate structure of the present invention.

[0043] The reference numerals are as follows: 1. top seat; 2. outer gear ring; 3. motor; 4. driving gear; 5. slag cleaning device; 51. connecting frame; 52. drilling tube; 53. inner gear ring; 54. connecting column; 55. first layer plate; 56. short shaft; 57. sun gear; 58. planetary gear; 59. arc frame; 510. second layer plate; 511. fixing column; 512. slag loading bucket; 513. bottom cover; 514. arc-shaped plate; 515. lifting plate; 516. spiral plate; 517. rotating shaft; 518. driven gear; 519. annular rack; 520, crushing knife; 6, screening device; 61, upper funnel; 62, short rod; 63, screen; 64, inclined funnel; 65, inclined guide plate; 66, partition; 67, sliding rod; 68, arc surface block; 69, No. 1 hammer; 610, rotating rod; 611, supporting plate; 612, No. 2 hammer; 7, hole wall reinforcement device; 71, elliptical groove; 72, sliding push rod; 73, sliding shaft; 74, arc push block; 75, inner slide seat; 76, outer push plate; 8, buckle; 81, upper locking block; 82, lower locking block; 83, inclined lock buckle; 84, rebound push block. DETAILED DESCRIPTION

[0044] To make the purpose, technical solution and advantages of the present invention clearer, the technical solution of the present invention will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other implementation methods obtained by ordinary technicians in this field without making creative work belong to the scope of protection of the present invention.

[0045] Example 1: Please refer to Figure 1 - Figure 8, a road and bridge pile foundation efficient slag cleaning equipment, comprising: a top seat 1, the bottom of the top seat 1 is rotatably mounted with an outer gear ring 2, a motor 3 is mounted on the side of the top seat 1, the output end of the motor 3 is connected with a driving gear 4, the driving gear 4 is meshed with the outer gear ring 2, and a connecting flange is arranged on the top of the top seat 1. The staff fixes the top seat 1 on the hanging tool through the connecting flange, and then fixes the hanging tool on the lifting machinery, and lifts the top seat 1 to the top of the borehole through the lifting machinery; a slag cleaning device 5 is used to collect the slag blocks in the borehole;The slag cleaning device 5 includes a connecting frame 51, which is installed at the bottom of the outer gear ring 2, and a drilling tube 52 is connected to the connecting frame 51. The motor 3 drives the driving gear 4 to rotate, and the driving gear 4 drives the outer gear ring 2 to rotate, and the outer gear ring 2 drives the connecting frame 51 to rotate, and the connecting frame 51 drives the drilling tube 52 to rotate. A plurality of drill teeth are arranged at the bottom of the drilling tube 52. The plurality of drill teeth at the bottom of the drilling tube 52 can clean the inner wall of the borehole, so that the loose slag blocks fall to the bottom of the borehole. The inner wall of the drilling tube 52 is connected with a spiral sheet 516, and the bottom surface of the top seat 1 is connected with a connecting column 54, and the bottom of the connecting column 54 is connected with a layer of plate 55. A through hole is arranged in the middle of the connecting frame 51, and the connecting column 54 is located in the through hole of the connecting frame 51. The connecting column 54 is not connected to the connecting frame 5 1 contact, a short shaft 56 is connected to the center of the bottom surface of the first layer plate 55, and the outer wall of the short shaft 56 is rotatably connected to the sun gear 57. A plurality of planetary gears 58 are rotatably installed at the bottom of the first layer plate 55, and an inner gear ring 53 is connected to the inner wall of the drilling tube 52. The plurality of planetary gears 58 are arranged in a circular array with the sun gear 57 as the center. The inner gear ring 53 is meshed with the plurality of planetary gears 58, and the plurality of planetary gears 58 are all meshed with the sun gear 57. When the drilling tube 52 rotates, the inner gear ring 53 is driven to rotate, and the inner gear ring 53 drives the sun gear 57 to rotate through the plurality of planetary gears 58. The bottom surface of the sun gear 57 is connected to four arc frames 59, and the bottom surfaces of the four arc frames 59 are connected to the second layer plate 510, and the bottom surface of the second layer plate 510 is connected to a fixed The bottom of the fixed column 511 is provided with a slag bucket 512 through a bracket, the slag bucket 512 is located inside the drilling tube 52, a bottom cover 513 is provided with a hinge at the bottom of the slag bucket 512, a buckle 8 is provided between the bottom cover 513 and the slag bucket 512, a plurality of arc-shaped shifting plates 514 are connected to the bottom surface of the bottom cover 513, a plurality of lifting plates 515 are connected to the outer wall of the slag bucket 512, a plurality of arc-shaped shifting plates 514 are arranged in a circular array with the center of the bottom cover 513 as the center, a plurality of lifting plates 515 are arranged in a circular array with the center of the bottom cover 513 as the center, the bottom of the plurality of lifting plates 515 are located outside the plurality of arc-shaped shifting plates 514, the bottom of the spiral sheet 516 is located above the top of the plurality of lifting plates 515, and the spiral sheet 51 The top of 6 is located between the top of the slag bucket 512 and the bottom surface of the second layer plate 510. When the drilling tube 52 moves to the bottom of the borehole, multiple arc-shaped prying plates 514 contact the slag blocks. The multiple arc-shaped prying plates 514 rotate to pry the slag blocks from the inside to the outside, so that the slag blocks at the center of the bottom of the borehole move outward to below the multiple lifting plates 515. When the multiple lifting plates 515 rotate, the contacted slag blocks are pushed upward along the inclined surfaces of the multiple lifting plates 515. When the slag blocks move to above the top of the lifting plates 515, the spiral pieces 516 that rotate with the drilling tube 52 contact the slag blocks and lift the slag blocks upward. When the slag blocks are lifted to the top of the spiral pieces 516, they fall into the slag bucket 512. The slag bucket 512 collects the slag blocks, thereby achieving the effect of cleaning the bottom of the borehole.The outer wall of the slag bucket 512 is rotatably installed with multiple rotating shafts 517, and the multiple rotating shafts 517 are respectively located between every two adjacent lifting plates 515. The end of the rotating shaft 517 away from the slag bucket 512 is connected with a driven gear 518. The inner wall of the drilling tube 52 is provided with a mounting groove, and an annular rack 519 is installed in the mounting groove of the drilling tube 52. Multiple driven gears 518 are meshed with the annular rack 519. The outer wall of the rotating shaft 517 is connected with multiple crushing knives 520. When the driven gear 518 revolves, it rotates by meshing with the annular rack 519. When the driven gear 518 rotates, it drives the rotating shaft 517 to rotate, and the rotating shaft 517 drives the multiple crushing knives 520 to rotate. When the slag blocks between two adjacent lifting plates 515 are flipped upward, the multiple crushing knives 520 break the larger slag blocks by rotating. The slag cleaning device 5 is configured to crush the slag blocks at the bottom of the borehole, thereby preventing the larger slag blocks from being stuck on the lifting plate 515 or the spiral piece 516 and causing material blockage. Through the configuration of the slag cleaning device 5, the multiple arc-shaped plates 514 first push the slag blocks at the bottom of the borehole outward, and the multiple lifting plates 515 then push the slag blocks upward. The spiral piece 516 lifts the slag blocks to the slag bucket 512 for collection by rotation, thereby achieving the effect of cleaning the bottom of the borehole. The cleaning coverage is relatively comprehensive, and the cleaning effect is better, thereby preventing the slag blocks deposited on the bottom of the borehole from being effectively cleaned. Through the configuration of the multiple crushing knives 520, the multiple crushing knives 520 can crush the slag blocks they contact by rotating, so that the larger slag blocks are crushed when they are flipped upward by the multiple lifting plates 515, thereby preventing the larger slag blocks from being blocked on the movement path of the slag blocks, thereby affecting the cleaning effect.

[0046] For further information, see Fig. 9 - Fig.10 The buckle lock 8 includes an upper locking block 81, a lower locking block 82, a bevel lock buckle 83 and a rebound push block 84. The upper locking block 81 is connected to the slag loading bucket 512, and the lower locking block 82 is connected to the bottom cover 513. The bevel lock buckle 83 is slidably installed in the upper locking block 81 through a spring, and the rebound push block 84 is slidably installed on the lower locking block 82 through a spring. A buckle is provided on the top of the lower locking block 82, and the buckle of the lower locking block 82 is overlapped on the top surface of the bevel lock buckle 83. One end of the rebound push block 84 is located outside the lower locking block 82. The rebound push block 84 The other end is located inside the lower locking block 82, and one end of the rebound push block 84 located inside the lower locking block 82 contacts the inclined lock buckle 83. The staff uses a pry bar to penetrate through the gap between the drill teeth at the bottom of the drilling tube 52, resists the rebound push block 84 and pushes it. When the rebound push block 84 moves to the left, the inclined lock buckle 83 is pushed to the left. After the inclined lock buckle 83 moves to the left, it no longer resists the buckle of the lower locking block 82. At this time, the lower locking block 82 is separated from the upper locking block 81. Through the setting of the buckle lock 8, it is convenient for the staff to open the bottom cover 513.

[0047] Further, see Fig. 9 - Fig.12The screening device 6 is used to screen the slag blocks according to the particle size of the slag blocks. The screening device 6 includes an upper funnel 61, which is installed on the inner wall of the slag bucket 512. A plurality of short rods 62 are installed on the inner wall of the slag bucket 512. A screen 63 is connected between the plurality of short rods 62. The plurality of short rods 62 are arranged in a circular array with the center of the screen 63 as the center. An inclined funnel 64 is connected to the bottom of the screen 63. An inclined guide plate 65 is connected to the outer wall of the inclined funnel 64. The outer wall of the inclined guide plate 65 is connected to the inner wall of the slag bucket 512. A partition 66 is installed on the inner wall of the slag bucket 512. The partition 66 is arranged longitudinally. An outlet is provided at the bottom of the inclined funnel 64. The outlet at the bottom of the inclined funnel 64 is located at the partition 66. The bottom of the inclined guide plate 65 is located on the left side of the partition plate 66, and the bottom of the partition plate 66 is in contact with the top surface of the bottom cover 513. The partition plate 66 divides the lower half of the slag barrel 512 into two areas, the right side of the partition plate 66 is the fine slag area, and the left side of the partition plate 66 is the coarse slag area. The slag blocks in the inclined funnel 64 fall into the fine slag area on the right side of the partition plate 66 through the outlet below, and the slag blocks with larger particle sizes move outwards by centrifugal force until they are separated from the screen 63. The slag blocks separated from the screen 63 fall onto the inclined guide plate 65 through the gaps between the multiple short rods 62, and the slag blocks with larger particle sizes slide down the inclined guide plate 65 to the coarse slag area on the left side of the partition plate 66, thereby achieving the effect of classifying and collecting the slag blocks according to their different particle sizes, which is convenient for Subsequent staff used different paths; a sliding rod 67 was slidably installed on the inner wall of the slag bucket 512 through a bracket, a spring was arranged between the sliding rod 67 and the inner wall of the slag bucket 512, one end of the sliding rod 67 was connected to an arc block 68, and the other end of the sliding rod 67 was connected to a No. 1 hammer 69, a sliding groove was provided on the inner wall of the slag bucket 512, the arc block 68 was slidingly connected to the sliding groove of the slag bucket 512, the spiral piece 516 was in sliding contact with the arc block 68 during the movement, the arc block 68 protruded from the outer wall of the slag bucket 512, and the spiral piece 516 was closely attached to the outer wall of the slag bucket 512 and rotated, so that part of the spiral piece 516 would contact the arc block 68 during the rotation, and the No. 1 hammer 69 would be in sliding contact with the arc block 68 during the movement. During the movement, the No. 2 hammer 612 contacts the outer wall of the inclined funnel 64. The No. 1 hammer 69 can hit the outer wall of the inclined funnel 64 with a gentler slope, causing the inclined funnel 64 to vibrate, thereby promoting the slag blocks on the inclined funnel 64 with a gentler slope to slide down. The bottom surface of the inclined guide plate 65 is rotatably mounted with a rotating rod 610 through a bracket. One end of the rotating rod 610 is connected to a supporting plate 611. The other end of the rotating rod 610 is connected to a No. 2 hammer 612. The supporting plate 611 is located in the outlet at the bottom of the inclined funnel 64. The No. 2 hammer 612 contacts the bottom surface of the inclined guide plate 65 during the movement. When the No. 2 hammer 612 moves upward, it can hit the bottom surface of the top of the inclined guide plate 65, causing the inclined guide plate 65 to vibrate, thereby promoting the slag blocks on the inclined guide plate 65 to slide down.Through the setting of the screening device 6, the inclined funnel 64 and the inclined guide plate 65 can cooperate to separate the fine slag blocks with larger particle sizes and the coarse slag blocks with larger particle sizes to the two sides of the partition plate 66. When the slag blocks are unloaded after cleaning, the fine slag blocks and the coarse slag blocks are divided into two piles and stacked together, which is convenient for the staff to use the slag blocks of different particle sizes and reduces the steps of the staff to screen the slag blocks by themselves; through the setting of the No. 1 hammer 69 and the No. 2 hammer 612, the No. 1 hammer 69 can repeatedly hit the inclined funnel 64, and the No. 2 hammer 612 can repeatedly hit the inclined guide plate 65, which promotes the sliding of the slag blocks on the inclined funnel 64 and the inclined guide plate 65 to avoid material blockage. ;

[0048] For further information, see Fig.13 - Fig.14 The hole wall reinforcement device 7 is used to reinforce the hole wall of the drilled hole to prevent the slag on the hole wall from falling. The hole wall reinforcement device 7 includes two sliding push rods 72, which are respectively slidably installed on the inner walls of two of the arc-shaped frames 59. The two sliding push rods 72 are mirror-imaged. An elliptical groove 71 is provided on the short shaft 56. A sliding shaft 73 is installed at one end of the sliding push rod 72 close to the elliptical groove 71. The two sliding shafts 73 are slidably connected to the elliptical groove 71. When the two sliding shafts 73 slide in the elliptical groove 71, they are repeatedly close to each other. In the process of separating from each other, the two sliding shafts 73 drive the two sliding push rods 72 to perform horizontal reciprocating motion. The end of the sliding push rod 72 away from the sliding shaft 73 is connected to an arcuate push block 74. The two arcuate push blocks 74 perform horizontal reciprocating motion while revolving around the short shaft 56 as the center of the circle. The bottom of the inner gear ring 53 is connected to two inner sliding seats 75. The inner wall of the inner sliding seat 75 is slidably connected to an outer push plate 76. The two outer push plates 76 are mirror-imaged. The two arcuate push blocks 74 will contact each other during the horizontal reciprocating motion. The two outer push plates 76, when the arc push block 74 contacts the outer push plate 76, the arc push block 74 pushes the outer push plate 76 in the direction away from the short shaft 56, and a spring is provided inside the connection between the outer push plate 76 and the inner slide seat 75. Two square grooves are provided on the drilling tube 52, and the two outer push plates 76 are respectively slidably connected with the two square grooves of the drilling tube 52. When the outer push plate 76 moves outward, it protrudes from the square groove of the drilling tube 52 to the outer surface of the drilling tube 52 and contacts the inner wall of the borehole. In the process of the drilling tube 52 moving downward, the two outer The push plate 76 continuously protrudes outward to squeeze the inner wall of the borehole, compacting the inner wall of the borehole to prevent the loose slag blocks on the inner wall of the borehole from falling again during and after the cleaning process; through the arrangement of the hole wall reinforcement device 7, during the process of cleaning the borehole, the two outer push plates 76 compact the inner wall of the borehole by continuously protruding outward from the outer surface of the drilling tube 52, pressing the loose slag blocks into the soil layer, thereby achieving the effect of reinforcing the inner wall of the borehole, and preventing the loose slag blocks from falling into the borehole again after the cleaning is completed, affecting the quality of the project.

[0049] Embodiment 2: A method for using a road and bridge pile foundation efficient slag cleaning device, using the road and bridge pile foundation efficient slag cleaning device in Embodiment 1, further comprising the following steps:

[0050] Step 1: Connect the sling to the connecting flange on the top seat 1 by bolts;

[0051] Step 2: Fix the sling on the lifting machinery;

[0052] Step 3: Move the lifting machinery so that the drilling tube 52 is located directly above the drill hole;

[0053] Step 4: Start the motor 3, and the drilling tube 52 and the slag bucket 512 begin to rotate;

[0054] Step 5: Control the lifting machinery to lower the drilling tube 52 into the borehole;

[0055] Step 6: When the drilling tube 52 moves downward, the drilling tube 52 knocks down the loose slag blocks on the inner wall of the borehole. After the drilling tube 52 reaches the bottom of the borehole, the multiple arc-shaped shifting plates 514 shift the slag blocks at the bottom of the borehole outward, and the multiple lifting plates 515 lift the contacted slag blocks upward, and the spiral pieces 516 lift the slag blocks into the slag bucket 512 by means of spiral lifting;

[0056] Step seven: control the crane to lift the drilling tube 52. After the drilling tube 52 leaves the borehole, place the drilling tube 52 on the ground, open the buckle 8, lift the drilling tube 52 again, open the bottom cover 513, and the slag blocks in the slag bucket 512 fall to the ground. Move the drilling tube 52 away, close the bottom cover 513 and clean the slag blocks, and the slag cleaning operation is completed.

[0057] With the above structure, the working principle of this case is that the staff fixes the top seat 1 on the hanger through the connecting flange, and then fixes the hanger on the lifting machinery, and lifts the top seat 1 to the top of the borehole through the lifting machinery, and turns on the motor 3, the motor 3 drives the driving gear 4 to rotate, the driving gear 4 drives the outer gear ring 2 to rotate, the outer gear ring 2 drives the connecting frame 51 to rotate, the connecting frame 51 drives the drilling tube 52 to rotate, and the top seat 1 is driven downward by the starter, and the drilling tube 52 moves downward accordingly. When the drilling tube 52 moves downward, the multiple drill teeth at the bottom of the drilling tube 52 can clean the inner wall of the borehole, so that the loose slag blocks fall to the bottom of the borehole. When the drilling tube 52 rotates, the top seat 1, the connecting column 54, the layer plate 55 and the short shaft 56 do not rotate, and the drilling tube 52 When the inner gear ring 53 rotates, the inner gear ring 53 drives the sun gear 57 to rotate through a plurality of planetary gears 58. The sun gear 57 drives the second layer plate 510 to rotate through four arc frames 59. The second layer plate 510 drives the slag bucket 512 to rotate through the fixed column 511. The rotation direction of the slag bucket 512 is opposite to that of the drilling tube 52. When the slag bucket 512 rotates, it drives the bottom cover 513 and a plurality of lifting plates 515 to rotate. The bottom cover 513 drives a plurality of arc-shaped shifting plates 514 to rotate. When the drilling tube 52 moves to the bottom of the borehole, the plurality of arc-shaped shifting plates 514 contact the slag blocks. The plurality of arc-shaped shifting plates 514 rotate to shift the slag blocks from the inside to the outside, so that the slag blocks at the center of the bottom of the borehole move outward to the plurality of lifting plates 515. At the bottom, when the multiple lifting plates 515 rotate, the slag blocks they contact are pushed upward along the inclined surfaces of the multiple lifting plates 515. When the slag blocks move to above the top of the lifting plates 515, the spiral pieces 516 rotating along with the drilling tube 52 contact the slag blocks and lift the slag blocks upward. When the slag blocks are lifted to the top of the spiral pieces 516, they fall into the slag bucket 512. The slag bucket 512 collects the slag blocks, thereby achieving the effect of cleaning the bottom of the borehole; while the slag bucket 512 rotates, the slag bucket 512 drives the multiple rotating shafts 517 to rotate. When the rotating shafts 517 rotate, they drive the driven gears 518 to revolve around the slag bucket 512 as the center of the circle. When the driven gears 518 revolve, they rotate by meshing with the annular rack 519. When rotating, it drives the rotating shaft 517 to rotate, and the rotating shaft 517 drives the multiple crushing knives 520 to rotate. When the slag blocks between two adjacent lifting plates 515 flip upward, the multiple crushing knives 520 crush the larger slag blocks by rotating, so as to prevent the larger slag blocks from being stuck on the lifting plate 515 or the spiral piece 516 and causing material blockage. By setting the slag cleaning device 5, the multiple arc-shaped paddles 514 first pry the slag blocks at the bottom of the borehole outward, and the multiple lifting plates 515 then pry the slag blocks upward, and the spiral piece 516 lifts the slag blocks into the slag bucket 512 for collection by rotating, so as to achieve the effect of cleaning the bottom of the borehole, the cleaning coverage is relatively comprehensive, the cleaning effect is better, and it is avoided that a large amount of slag blocks are deposited at the bottom of the borehole and cannot be effectively cleaned;Through the arrangement of multiple crushing knives 520, the multiple crushing knives 520 can crush the slag blocks they come into contact with by rotating, so that larger slag blocks are crushed when they are turned upward through the multiple lifting plates 515, thereby preventing larger slag blocks from being blocked in the movement path of the slag blocks, thereby affecting the cleaning effect. ;

[0058] During the construction process, the slag blocks can be utilized, and the slag blocks of different particle sizes are utilized in different ways. The slag blocks falling into the slag bucket 512 first fall on the upper funnel 61, and then fall on the center of the screen 63 through the outlet at the bottom of the upper funnel 61. As the slag bucket 512 rotates, the upper funnel 61 and the screen 63 are driven to rotate synchronously, so that the slag blocks on the screen 63 generate centrifugal force and roll outward. The slag blocks with smaller particle sizes on the screen 63 pass through the screen 63 and fall into the inclined funnel 64. The partition 66 divides the lower half of the slag bucket 512 into two areas. The partition 66 The right side of the partition 66 is the fine slag area, and the left side of the partition 66 is the coarse slag area. The slag blocks in the inclined funnel 64 fall into the fine slag area on the right side of the partition 66 through the outlet at the bottom, and the slag blocks with larger particle sizes move outwards due to centrifugal force until they are separated from the screen 63. The slag blocks separated from the screen 63 fall onto the inclined guide plate 65 through the gaps between the multiple short rods 62, and the slag blocks with larger particle sizes slide down the inclined guide plate 65 to the coarse slag area on the left side of the partition 66, achieving the effect of classifying and collecting the slag blocks according to different particle sizes, which is convenient for subsequent staff to use them in different paths; the bottom outlet of the inclined funnel 64 is the inclined The center is set so that the slope of the right half of the inclined funnel 64 is larger, and the slope of the left half is gentler. Since the arc block 68 protrudes from the outer wall of the slag bucket 512, and the spiral piece 516 rotates closely against the outer wall of the slag bucket 512, a part of the spiral piece 516 will contact the arc block 68 during rotation. When the spiral piece 516 contacts the arc block 68, the spiral piece 516 pushes the arc block 68 toward the inclined funnel 64. The arc block 68 drives the first hammer 69 to move toward the inclined funnel 64 through the sliding rod 67, so that the first hammer 69 hits the inclined funnel. The outer wall of the side with a gentler slope 64 makes the inclined funnel 64 vibrate, promoting the slag blocks at the gentler slope of the inclined funnel 64 to slide down, avoiding local blockage. When the slag blocks in the inclined funnel 64 fall through the outlet, some of the slag blocks will hit the supporting plate 611, so that the supporting plate 611 pushes the left end of the rotating rod 610 downward, so that the rotating rod 610 drives the second hammer 612 to move upward through the lever principle. When the second hammer 612 moves upward, it hits the bottom surface of the top of the inclined guide plate 65, causing the inclined guide plate 65 to vibrate, promoting the slag blocks on the inclined guide plate 65 to slide down.When the cleaning is completed, the drilling tube 52 is placed on the ground by a lifting machine, and the staff uses a pry bar to penetrate through the gap between the drill teeth at the bottom of the drilling tube 52, press against the rebound push block 84 and push it, so that when the rebound push block 84 moves to the left, the inclined surface lock buckle 83 is pushed to the left, and the inclined surface lock buckle 83 no longer presses against the buckle of the lower locking block 82 after moving to the left. At this time, the lower locking block 82 is separated from the upper locking block 81, and the lifting machine lifts the top seat 1 again, and the slag bucket 512 moves upward, and the slag blocks inside it open the bottom cover 513 by gravity, and the slag blocks inside the slag bucket 512 fall to the ground, and the coarse slag blocks and the fine slag blocks are divided into two piles and stacked together. After the slag bucket 512 is empty, the lifting machine puts the drilling tube 52 on the ground again, presses against the bottom cover 513 through the ground, so that the lower locking block 82 and the upper locking block 81 fit together again, and the inclined surface lock buckle 83 The buckle 83 uses its own inclined surface and the elastic force of the spring to slide into the buckle bottom of the lower locking block 82 to achieve the locking effect. The setting of the buckle lock 8 makes it easy for the staff to open the bottom cover 513; through the setting of the screening device 6, the inclined funnel 64 and the inclined guide plate 65 can separate the fine slag blocks with larger particle sizes and the coarse slag blocks with larger particle sizes to the two sides of the partition 66. When the slag blocks are unloaded after cleaning, the fine slag blocks and the coarse slag blocks are divided into two piles and stacked together, which is convenient for the staff to use the slag blocks of different particle sizes, reducing the steps of the staff to screen the slag blocks by themselves; through the setting of the No. 1 hammer 69 and the No. 2 hammer 612, the No. 1 hammer 69 can repeatedly hit the inclined funnel 64, and the No. 2 hammer 612 can repeatedly hit the inclined guide plate 65, which promotes the sliding of the slag blocks on the inclined funnel 64 and the inclined guide plate 65 to avoid material blockage. ;

[0059] When the arc frame 59 rotates following the sun gear 57, the short shaft 56 does not rotate. When the two arc frames 59 with sliding push rods 72 rotate, they drive the two sliding push rods 72 to rotate. The two sliding push rods 72 drive the two sliding shafts 73 to rotate along the elliptical groove 71. When the two sliding shafts 73 slide in the elliptical groove 71, they constantly repeat the process of approaching and separating from each other, so that the two sliding shafts 73 drive the two sliding push rods 72 to perform horizontal reciprocating motion. The two sliding push rods 72 drive the two arc push blocks 74 to perform horizontal reciprocating motion. The two arc push blocks 74 perform horizontal reciprocating motion while revolving around the short shaft 56 as the center of the circle. The two arc push blocks 74 will contact the two outer push plates 76 during the horizontal reciprocating motion. When the arc push blocks 74 contact the outer push plates 76, the arc push blocks 74 push the outer push plates 76 in the direction away from the short shaft 56. When the arc push blocks When the outer push plate 74 is not in contact with the outer push plate 76, the outer push plate 76 is reset by the spring between the inner slide seat 75, so that the two outer push plates 76 can move outward periodically. When the outer push plate 76 moves outward, it will protrude from the square groove of the drilling tube 52 to the outer surface of the drilling tube 52 and contact the inner wall of the borehole. In the process of the drilling tube 52 moving downward, the two outer push plates 76 continuously protrude outward to squeeze the inner wall of the borehole, compacting the inner wall of the borehole, and preventing the loose slag blocks on the inner wall of the borehole from falling again during and after the cleaning process; through the setting of the hole wall reinforcement device 7, in the process of cleaning the borehole, the two outer push plates 76 compact the inner wall of the borehole by continuously protruding outward from the outer surface of the drilling tube 52, pressing the loose slag blocks into the soil layer, thereby strengthening the inner wall of the borehole, and preventing the loose slag blocks from falling into the borehole again after the cleaning is completed, affecting the quality of the project.

[0060] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any person skilled in the art can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. A road and bridge pile foundation efficient slag removal equipment, characterized in that: include: A top seat (1), wherein an outer gear ring (2) is rotatably mounted on the bottom of the top seat (1), a motor (3) is mounted on the side of the top seat (1), an output end of the motor (3) is connected to a drive gear (4), the drive gear (4) is meshed with the outer gear ring (2), and a connecting flange is arranged on the top of the top seat (1); A slag cleaning device (5) for collecting slag blocks in the drill hole; A screening device (6) is used to screen the slag according to its particle size; A hole wall reinforcement device (7) is used to reinforce the hole wall of the drilled hole to prevent slag blocks on the hole wall from falling off; The slag cleaning device (5) comprises a connecting frame (51), the connecting frame (51) being mounted on the bottom of the outer gear ring (2), a drilling tube (52) being connected to the connecting frame (51), a plurality of drilling teeth being arranged at the bottom of the drilling tube (52), a spiral sheet (516) being connected to the inner wall of the drilling tube (52), a connecting column (54) being connected to the bottom surface of the top seat (1), a layer plate (55) being connected to the bottom of the connecting column (54), a short shaft (56) being connected to the center position of the bottom surface of the layer plate (55), an outer wall of the short shaft (56) being rotatably connected to a sun gear (57), a plurality of planetary gears (58) being rotatably mounted on the bottom of the layer plate (55), an inner gear being connected to the inner wall of the drilling tube (52), and a plurality of planetary gears (58) being rotatably mounted on the inner wall of the drilling tube (52). The sun gear (57) is provided with a ring (53), the bottom surface of the sun gear (57) is connected to four arc frames (59), the bottom surfaces of the four arc frames (59) are connected to a second-layer plate (510), the bottom surface of the second-layer plate (510) is connected to a fixing column (511), a slag bucket (512) is installed at the bottom of the fixing column (511) via a bracket, the slag bucket (512) is located inside the drilling tube (52), a bottom cover (513) is installed at the bottom of the slag bucket (512) via a hinge, a buckle (8) is provided between the bottom cover (513) and the slag bucket (512), a plurality of arc-shaped shifting plates (514) are connected to the bottom surface of the bottom cover (513), and a plurality of lifting plates (515) are connected to the outer wall of the slag bucket (512).

2. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 1 is characterized by: A through hole is provided in the middle of the connecting frame (51), the connecting column (54) is located in the through hole of the connecting frame (51), the connecting column (54) does not contact the connecting frame (51), the plurality of planetary gears (58) are arranged in a circular array with the sun gear (57) as the center, the inner gear ring (53) meshes with the plurality of planetary gears (58), and the plurality of planetary gears (58) all mesh with the sun gear (57).

3. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 2 is characterized by: The plurality of arc-shaped shifting plates (514) are arranged in a circular array with the center of the bottom cover (513) as the center of the circle, and the plurality of lifting plates (515) are arranged in a circular array with the center of the bottom cover (513) as the center of the circle, the bottoms of the plurality of lifting plates (515) are located outside the plurality of arc-shaped shifting plates (514), the bottoms of the spiral plates (516) are located above the tops of the plurality of lifting plates (515), and the tops of the spiral plates (516) are located between the top of the slag loading bucket (512) and the bottom surface of the second layer plate (510).

4. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 3 is characterized by: The outer wall of the slag loading bucket (512) is rotatably mounted with a plurality of rotating shafts (517), the plurality of rotating shafts (517) being respectively located between every two adjacent lifting plates (515), one end of the rotating shaft (517) away from the slag loading bucket (512) being connected to a driven gear (518), the inner wall of the drilling tube (52) being provided with a mounting groove, an annular rack (519) being mounted in the mounting groove of the drilling tube (52), the plurality of driven gears (518) being meshed with the annular rack (519), and the outer wall of the rotating shaft (517) being connected to a plurality of crushing knives (520).

5. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 4 is characterized by: The buckle lock (8) comprises an upper locking block (81), a lower locking block (82), an inclined locking buckle (83) and a rebound push block (84); the upper locking block (81) is connected to the slag loading bucket (512); the lower locking block (82) is connected to the bottom cover (513); the inclined locking buckle (83) is slidably mounted in the upper locking block (81) by a spring; the rebound push block (84) is slidably mounted on the lower locking block (82) by a spring; a buckle is provided on the top of the lower locking block (82); the buckle of the lower locking block (82) overlaps the top surface of the inclined locking buckle (83); one end of the rebound push block (84) is located outside the lower locking block (82); the other end of the rebound push block (84) is located inside the lower locking block (82); and one end of the rebound push block (84) located inside the lower locking block (82) contacts the inclined locking buckle (83).

6. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 5 is characterized by: The screening device (6) comprises an upper funnel (61), the upper funnel (61) being mounted on the inner wall of a slag bucket (512), a plurality of short rods (62) being mounted on the inner wall of the slag bucket (512), a screen (63) being connected between the plurality of short rods (62), the plurality of short rods (62) being arranged in a circular array with the center of the screen (63) as the center, an inclined funnel (64) being connected to the bottom of the screen (63), an inclined guide plate (65) being connected to the outer wall of the inclined funnel (64), the outer wall of the inclined guide plate (65) being connected to the inner wall of the slag bucket (512), and a partition plate (66) being mounted on the inner wall of the slag bucket (512).

7. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 6 is characterized by: The partition (66) is arranged longitudinally, and an outlet is arranged at the bottom of the inclined funnel (64). The outlet at the bottom of the inclined funnel (64) is located on the right side of the partition (66). The bottom of the inclined guide plate (65) is located on the left side of the partition (66). The bottom of the partition (66) contacts the top surface of the bottom cover (513).

8. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 7 is characterized by: The inner wall of the slag loading bucket (512) is slidably mounted with a slide bar (67) through a bracket, a spring is arranged between the slide bar (67) and the inner wall of the slag loading bucket (512), one end of the slide bar (67) is connected to an arc surface block (68), and the other end of the slide bar (67) is connected to a first hammer (69), a slide groove is provided on the inner wall of the slag loading bucket (512), the arc surface block (68) is slidably connected to the slide groove of the slag loading bucket (512), and the spiral piece (516) is in contact with the arc surface block (68) during the movement. 8) Sliding contact, the first hammer (69) contacts the outer wall of the inclined funnel (64) during movement, the bottom surface of the inclined guide plate (65) is rotatably mounted with a rotating rod (610) through a bracket, one end of the rotating rod (610) is connected to a supporting plate (611), and the other end of the rotating rod (610) is connected to a second hammer (612), the supporting plate (611) is located in the outlet at the bottom of the inclined funnel (64), and the second hammer (612) contacts the bottom surface of the inclined guide plate (65) during movement.

9. The high-efficiency slag removal equipment for road and bridge pile foundation according to claim 8, characterized in that: The hole wall reinforcement device (7) comprises two sliding push rods (72), the two sliding push rods (72) are respectively slidably mounted on the inner walls of two of the arc-shaped frames (59), the two sliding push rods (72) are arranged in a mirror image, an elliptical groove (71) is provided on the short shaft (56), a sliding shaft (73) is mounted on one end of the sliding push rod (72) close to the elliptical groove (71), the two sliding shafts (73) are both slidably connected to the elliptical groove (71), and the sliding push rod (72) is away from the sliding groove (71). One end of the shaft (73) is connected to an arc-shaped push block (74), the bottom of the inner gear ring (53) is connected to two inner slide seats (75), the inner wall of the inner slide seat (75) is slidably connected to an outer push plate (76), the two outer push plates (76) are arranged in a mirror image, and a spring is arranged inside the connection between the outer push plate (76) and the inner slide seat (75), and two square grooves are provided on the drilling tube (52), and the two outer push plates (76) are respectively slidably connected to the two square grooves of the drilling tube (52).

10. A method for using a high-efficiency slag removal device for road and bridge pile foundations, characterized in that: The high-efficiency slag cleaning equipment for road and bridge pile foundations according to any one of claims 1 to 9 further comprises the following steps: Step 1: Connect the sling to the connecting flange on the top seat (1) by bolts; Step 2: Fix the sling on the lifting machinery; Step 3: Move the lifting machinery so that the drilling tube (52) is located directly above the drill hole; Step 4: Start the motor (3), and the drilling tube (52) and the slag bucket (512) begin to rotate; Step 5: Control the lifting machinery to lower the drilling tube (52) into the borehole; Step 6: When the drilling tube (52) moves downward, the drilling tube (52) knocks down loose slag blocks on the inner wall of the borehole. After the drilling tube (52) reaches the bottom of the borehole, the plurality of arc-shaped shifting plates (514) shift the slag blocks at the bottom of the borehole outward, the plurality of lifting plates (515) lift the slag blocks that they have contact with upward, and the spiral blades (516) lift the slag blocks into the slag loading bucket (512) by means of spiral lifting. Step seven: Control the crane to lift the drilling tube (52). After the drilling tube (52) leaves the borehole, place the drilling tube (52) on the ground, open the buckle (8), lift the drilling tube (52) again, open the bottom cover (513), and the slag blocks in the slag bucket (512) fall to the ground. Move the drilling tube (52) away, close the bottom cover (513) and clean the slag blocks, and the slag cleaning operation is completed.

Citation Information

Patent Citations

  • Sediment treatment device for large-diameter pile foundation construction

    CN114233228A

  • Punching and slag removing device for hydraulic tunnel engineering

    CN211924082U