Practical operation training examination system and method for high-voltage current collection line terminal tower
By designing a practical training and assessment system for the high-voltage collector line terminal tower, simulating the actual power grid terminal tower and collecting operation timing information, the problem of poor training efficiency and effect of the existing high-voltage transformer drop insurance operation is solved, and the effect of automatic judgment and improving the training efficiency is achieved.
Patent Information
- Application Number
- CN202411691843.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-25
- Publication Date
- 2025-02-28
AI Technical Summary
The practical training efficiency and effect of the drop insurance power outage operation of existing high-voltage transformers is poor, and there is a lack of a training platform composed of a real simulated 35kV transmission line system.
Design a practical training and assessment system for high-voltage collector line terminal towers, including high-voltage collector line terminal towers, data acquisition devices, data analysis devices and result output devices. The system simulates the actual power grid terminal tower, collects and analyzes the opening and closing timing information of the trainees, compares it with the preset timing information, and automatically judges the operation results.
The training efficiency and effect of high-voltage transformer drop insurance power outage operation has been improved, the dependence on on-site assessment personnel has been reduced, and the assessment results of the equipment's own judgment of practical personnel has been achieved.
Smart Images

Figure CN119541296A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of high-voltage power transmission operation, and in particular to a high-voltage collector line terminal tower practical operation training and assessment system and method. Background Art
[0002] At present, the major training institutions in the industry provide training programs for the shutdown and power-on operations of transmission lines, which are single 10kV transformer drop insurance shutdown and power-on operations. The training programs are single and limited by the space of the training institutions. The voltage level of the equipment and the electrical equipment such as hardware fittings and insulators are all lower than the actual operating conditions of the wind power 35kV transmission line.
[0003] The existing practical training platform for power transmission lines cannot truly simulate the composition of a 35kV transmission line system. Due to limited operating space, trainees lack awareness of the safe distance for operating high-voltage equipment and are unable to conduct practical training and identify safety risks in the shoes of the trainees. Practical training has great limitations.
[0004] The existing fall insurance operation training relies on the instructor to judge whether the trainees' operation is correct on the spot. Due to the limited energy of the instructor, manual referees may make misjudgments, and the training efficiency and effect are poor. Summary of the invention
[0005] In order to solve the technical problems in the prior art such as the poor efficiency and effect of practical training on power outage operation of a drop fuse of a high-voltage transformer, the present invention provides a practical training and assessment system and method for a high-voltage collector line terminal tower.
[0006] The technical solution of the present invention to solve the above technical problems is as follows:
[0007] A high-voltage collector line terminal tower practical training and assessment system, comprising a high-voltage collector line training terminal tower, a data acquisition device, a data analysis device and a result output device; the high-voltage collector line training terminal tower is provided with a plurality of drop insurances, the plurality of drop insurances correspond to multi-phase high-voltage lines, and the plurality of drop insurances correspond to the multi-phase high-voltage lines one by one;
[0008] The data analysis device is used to generate training information and generate preset opening and closing timing information according to the training information;
[0009] The result output device is connected to the data analysis device and is used to display the training information;
[0010] The data acquisition device is connected to a plurality of the drop fuses and is used to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation process; wherein the opening and closing operation process is the process of the trainees opening and closing each of the drop fuses according to the training information;
[0011] The data analysis device is connected to the data acquisition device and is also used to integrate the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation into a timing signal to obtain actual opening and closing timing information; compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information;
[0012] The result output device is also used to display the comparison result information.
[0013] The beneficial effects of the present invention are as follows: by building a high-voltage collector line training terminal tower similar to an actual line terminal tower, and setting a drop fuse on the high-voltage collector line training terminal tower, a simulation of a terminal tower in an actual power grid is achieved, and then by setting simulated training information, trainees can operate the drop fuses of each phase through the training information, and record the opening and closing sequence of the trainees' operation of each drop fuse through a data acquisition device, so as to judge whether the trainees' operation is qualified through the opening and closing sequence; compared with traditional practical training and assessment, the present invention does not require on-site assessment personnel to provide on-site guidance and judgment, and can judge the assessment results of the operators by themselves through the equipment, thereby improving the efficiency and effect of the training of the drop fuse power-off operation of the high-voltage transformer.
[0014] Based on the above technical solution, the present invention can also be improved as follows.
[0015] Further, the training information includes wind direction information and phase state information;
[0016] The data analysis device is specifically used to generate the wind direction information and the phase state information, and generate the preset opening and closing timing information according to the wind direction information and the phase state information.
[0017] Further, the wind direction information includes upwind direction information and downwind direction information, the phase state information includes normal phase information and phase fault information, the phase fault information includes a plurality of phase fault information, and the plurality of phase fault information corresponds one-to-one to the multi-phase high-voltage lines;
[0018] The data analysis device is also specifically used to generate the preset opening and closing timing information according to the normal information and the upwind direction information when the phase state information is the normal phase information and the wind direction information is the upwind direction information; when the phase state information is the normal phase information and the wind direction information is the downwind direction information, generate the preset opening and closing timing information according to the normal information and the downwind direction information; when the phase state information is the phase fault information and the wind direction information is the upwind direction information, generate any one of the phase fault information among a plurality of the phase fault information, and generate the preset opening and closing timing information according to any one of the phase fault information and the upwind direction information; when the phase state information is the phase fault information and the wind direction information is the downwind direction information, generate any one of the phase fault information among a plurality of the phase fault information, and generate the preset opening and closing timing information according to any one of the phase fault information and the downwind direction information.
[0019] Further, the data acquisition device includes a first data acquisition device, a second data acquisition device and a third data acquisition device; the plurality of drop insurance devices are respectively a first drop insurance device, a second drop insurance device and a third drop insurance device, and the multi-phase high-voltage circuits are respectively an A-phase high-voltage circuit, a B-phase high-voltage circuit and a C-phase high-voltage circuit; wherein the first drop insurance device corresponds to the A-phase high-voltage circuit, the second drop insurance device corresponds to the B-phase high-voltage circuit, and the third drop insurance device corresponds to the C-phase high-voltage circuit;
[0020] The first data collector is connected to the first drop fuse and is used to collect the position information of the fuse tube of the first drop fuse and record the collection time to obtain the first opening and closing discrete time information;
[0021] The second data collector is connected to the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse and record the collection time to obtain the second opening and closing discrete time information;
[0022] The third data collector is connected to the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse and record the collection time to obtain the third opening and closing discrete time information;
[0023] The actual opening and closing timing information includes the first opening and closing discrete time information, the second opening and closing discrete time information and the third opening and closing discrete time information.
[0024] Further, the first data collector includes a first opening position sensor and a first closing position sensor, the second data collector includes a second opening position sensor and a second closing position sensor, and the third data collector includes a third opening position sensor and a third closing position sensor;
[0025] The first opening position sensor is connected to the opening contact of the first drop insurance, and is used to collect the position information and collection time of the fuse tube of the first drop insurance at the opening position when the fuse tube of the first drop insurance is at the opening position, so as to obtain a first opening discrete time signal;
[0026] The first closing position sensor is connected to the closing contact of the first drop fuse, and is used to collect the position information of the first drop fuse in the closing position and record the collection time when the first drop fuse is in the closing position, so as to obtain a first closing discrete time signal; wherein the first opening and closing discrete time information includes the first opening discrete time signal and the first closing discrete time signal;
[0027] The second opening position sensor is connected to the opening contact of the second drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the second drop insurance is at the opening position, so as to obtain a second opening discrete time signal;
[0028] The second closing position sensor is connected to the closing contact of the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse in the closing position and record the collection time when the fuse tube of the second drop fuse is in the closing position, so as to obtain a second closing discrete time signal; wherein the second opening and closing discrete time information includes the second opening discrete time signal and the second closing discrete time signal;
[0029] The third opening position sensor is connected to the opening contact of the third drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the third drop insurance is in the opening position, so as to obtain a third opening discrete time signal;
[0030] The third closing position sensor is connected to the closing contact of the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse in the closing position and record the collection time when the fuse tube of the third drop fuse is in the closing position, so as to obtain a third closing discrete time signal; wherein, the third opening and closing discrete time information includes the third opening discrete time signal and the third closing discrete time signal.
[0031] Further, the data analysis device is connected to the first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor, and is specifically used to integrate the first opening discrete time signal, the first closing discrete time signal, the second opening discrete time signal, the second closing discrete time signal, the third opening discrete time signal and the third closing discrete time signal into a timing signal in the order of recorded time to obtain the actual opening and closing timing information.
[0032] Furthermore, the first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor are all travel switches; and the data analysis device is a programmable logic controller.
[0033] Furthermore, the data analysis device is specifically used to determine whether the actual opening and closing timing information is consistent with the preset opening and closing timing information. If so, the opening and closing operation is determined to be qualified and the training qualified information is output; if not, the opening and closing operation is determined to be unqualified and the training unqualified information is output; wherein the comparison result information is the training qualified information or the training unqualified information.
[0034] Furthermore, the result output device is specifically used to display the qualified training information and output the qualified training voice when the comparison result information is the qualified training information; and to display the unqualified training information and output the unqualified training voice when the comparison result information is the unqualified training information.
[0035] In order to solve the above technical problems, the present invention also provides a high-voltage collector line terminal tower practical training and assessment method, the specific technical contents of which are as follows:
[0036] A high-voltage collector line terminal tower practical training and assessment method, applied to the above-mentioned high-voltage collector line terminal tower practical training and assessment system, comprises the following steps:
[0037] S1. Generate training information using a data analysis device, and generate preset opening and closing timing information according to the training information;
[0038] S2, using a result output device to display the training information;
[0039] S3, using a data acquisition device to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation;
[0040] S4, using a data analysis device to integrate the discrete time signals of the opening and closing of each drop insurance during the opening and closing operation into a timing signal, and obtain the actual opening and closing timing information;
[0041] S5, using a data analysis device to compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information;
[0042] S6. Using a result output device to display the comparison result information. BRIEF DESCRIPTION OF THE DRAWINGS
[0043] Figure 1 A schematic diagram of a high-voltage collector line terminal tower practical training and assessment system according to an embodiment of the present invention Figure 1 ;
[0044] Figure 2 A schematic diagram of a high-voltage collector line terminal tower practical training and assessment system according to an embodiment of the present invention Figure 2 ;
[0045] Figure 3 A schematic diagram of a high-voltage collector line terminal tower practical training and assessment system according to an embodiment of the present invention Figure 3 ;
[0046] Figure 4 It is a flowchart of the qualified process of opening and closing the gate in the embodiment of the present invention. DETAILED DESCRIPTION
[0047] The principles and features of the present invention are described below in conjunction with the accompanying drawings. The examples given are only used to explain the present invention and are not used to limit the scope of the present invention.
[0048] like Figure 1 As shown, this embodiment provides a high-voltage collector line terminal tower practical training and assessment system, including a high-voltage collector line training terminal tower, a data acquisition device, a data analysis device and a result output device; the high-voltage collector line training terminal tower is provided with a plurality of drop insurances, and the plurality of drop insurances correspond to multi-phase high-voltage lines, and the plurality of drop insurances correspond to the multi-phase high-voltage lines one by one;
[0049] The data analysis device is used to generate training information and generate preset opening and closing timing information according to the training information;
[0050] The result output device is connected to the data analysis device and is used to display the training information;
[0051] The data acquisition device is connected to a plurality of the drop fuses and is used to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation process; wherein the opening and closing operation process is the process of the trainees opening and closing each of the drop fuses according to the training information;
[0052] The data analysis device is connected to the data acquisition device and is also used to integrate the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation into a timing signal to obtain actual opening and closing timing information; compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information;
[0053] The result output device is also used to display the comparison result information.
[0054] In some embodiments, the training information includes wind direction information and phase state information;
[0055] The data analysis device is specifically used to generate the wind direction information and the phase state information, and generate the preset opening and closing timing information according to the wind direction information and the phase state information.
[0056] In some embodiments, the wind direction information includes upwind direction information and downwind direction information, the phase state information includes normal phase information and phase fault information, the phase fault information includes a plurality of phase fault information, and the plurality of phase fault information corresponds one-to-one to the multi-phase high-voltage lines;
[0057] The data analysis device is also specifically used to generate the preset opening and closing timing information according to the normal information and the upwind direction information when the phase state information is the normal phase information and the wind direction information is the upwind direction information; when the phase state information is the normal phase information and the wind direction information is the downwind direction information, generate the preset opening and closing timing information according to the normal information and the downwind direction information; when the phase state information is the phase fault information and the wind direction information is the upwind direction information, generate any one of the phase fault information among a plurality of the phase fault information, and generate the preset opening and closing timing information according to any one of the phase fault information and the upwind direction information; when the phase state information is the phase fault information and the wind direction information is the downwind direction information, generate any one of the phase fault information among a plurality of the phase fault information, and generate the preset opening and closing timing information according to any one of the phase fault information and the downwind direction information.
[0058] like Figure 2As shown, in some embodiments, the data acquisition device includes a first data acquisition device, a second data acquisition device, and a third data acquisition device; the plurality of drop insurance devices are respectively a first drop insurance device, a second drop insurance device, and a third drop insurance device, and the multi-phase high-voltage circuits are respectively an A-phase high-voltage circuit, a B-phase high-voltage circuit, and a C-phase high-voltage circuit; wherein the first drop insurance device corresponds to the A-phase high-voltage circuit, the second drop insurance device corresponds to the B-phase high-voltage circuit, and the third drop insurance device corresponds to the C-phase high-voltage circuit;
[0059] The first data collector is connected to the first drop fuse and is used to collect the position information of the fuse tube of the first drop fuse and record the collection time to obtain the first opening and closing discrete time information;
[0060] The second data collector is connected to the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse and record the collection time to obtain the second opening and closing discrete time information;
[0061] The third data collector is connected to the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse and record the collection time to obtain the third opening and closing discrete time information;
[0062] The actual opening and closing timing information includes the first opening and closing discrete time information, the second opening and closing discrete time information and the third opening and closing discrete time information.
[0063] like Figure 3 As shown, in some embodiments, the first data collector includes a first opening position sensor and a first closing position sensor, the second data collector includes a second opening position sensor and a second closing position sensor, and the third data collector includes a third opening position sensor and a third closing position sensor;
[0064] The first opening position sensor is connected to the opening contact of the first drop insurance, and is used to collect the position information and collection time of the fuse tube of the first drop insurance at the opening position when the fuse tube of the first drop insurance is at the opening position, so as to obtain a first opening discrete time signal;
[0065] The first closing position sensor is connected to the closing contact of the first drop fuse, and is used to collect the position information of the first drop fuse in the closing position and record the collection time when the first drop fuse is in the closing position, so as to obtain a first closing discrete time signal; wherein the first opening and closing discrete time information includes the first opening discrete time signal and the first closing discrete time signal;
[0066] The second opening position sensor is connected to the opening contact of the second drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the second drop insurance is at the opening position, so as to obtain a second opening discrete time signal;
[0067] The second closing position sensor is connected to the closing contact of the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse in the closing position and record the collection time when the fuse tube of the second drop fuse is in the closing position, so as to obtain a second closing discrete time signal; wherein the second opening and closing discrete time information includes the second opening discrete time signal and the second closing discrete time signal;
[0068] The third opening position sensor is connected to the opening contact of the third drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the third drop insurance is in the opening position, so as to obtain a third opening discrete time signal;
[0069] The third closing position sensor is connected to the closing contact of the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse in the closing position and record the collection time when the fuse tube of the third drop fuse is in the closing position, so as to obtain a third closing discrete time signal; wherein, the third opening and closing discrete time information includes the third opening discrete time signal and the third closing discrete time signal.
[0070] By setting a position sensor to monitor the position of the fuse tube of the drop insurance, the opening and closing status of the drop insurance can be quickly determined. Wireless manual observation can understand the opening and closing status of the drop insurance, which improves the efficiency of practical training and assessment.
[0071] Specifically, the first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor are all travel switches; and the data analysis device is a programmable logic controller, i.e., a PLC.
[0072] The data analysis device is connected to the first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor, and is specifically used to integrate the first opening discrete time signal, the first closing discrete time signal, the second opening discrete time signal, the second closing discrete time signal, the third opening discrete time signal and the third closing discrete time signal into a timing signal in the order of recorded time to obtain the actual opening and closing timing information. Wherein, the actual opening and closing timing information and the preset opening and closing timing information are both timing pulse signals.
[0073] like Figure 4 As shown, the multi-phase high-voltage lines are respectively A-phase, B-phase and C-phase high-voltage lines, and the downwind direction indicates that the wind passes through C-phase, B-phase and A-phase in sequence from the direction close to C-phase; the upwind direction indicates that the wind passes through A-phase, B-phase and C-phase in sequence from the direction close to A-phase. Phase fault information includes A-phase fault, B-phase fault and C-phase fault.
[0074] When the wind direction information is downwind direction information and the phase fault information is phase A fault, the preset operation steps are, in sequence, pulling the drop insurance corresponding to B, pulling the drop insurance corresponding to C, closing the drop insurance corresponding to C, closing the drop insurance corresponding to A, and closing the drop insurance corresponding to B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the second opening discrete time signal is high and the second closing discrete time signal is low, the third opening discrete time signal is high and the third closing discrete time signal is low, the third opening discrete time signal is low and the third closing discrete time signal is high, the first opening discrete time signal is low and the first closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0075] When the wind direction information is downwind direction information and the phase fault information is B phase fault, the preset operation steps are, in sequence, pulling the corresponding drop insurance of A, pulling the corresponding drop insurance of C, closing the corresponding drop insurance of C, closing the corresponding drop insurance of A, and closing the corresponding drop insurance of B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the first opening discrete time signal is high level and the first closing discrete time signal is low level, the third opening discrete time signal is high level and the third closing discrete time signal is low level, the third opening discrete time signal is low level and the third closing discrete time signal is high level, the first opening discrete time signal is low level and the first closing discrete time signal is high level, the second opening discrete time signal is low level and the second closing discrete time signal is high level.
[0076] When the wind direction information is downwind direction information and the phase fault information is C phase fault, the preset operation steps are, in sequence, pulling the corresponding drop insurance of A, pulling the corresponding drop insurance of B, closing the corresponding drop insurance of C, closing the corresponding drop insurance of A, and closing the corresponding drop insurance of B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the first opening discrete time signal is high level and the first closing discrete time signal is low level, the second opening discrete time signal is high level and the second closing discrete time signal is low level, the third opening discrete time signal is low level and the third closing discrete time signal is high level, the first opening discrete time signal is low level and the first closing discrete time signal is high level, the second opening discrete time signal is low level and the second closing discrete time signal is high level.
[0077] When the wind direction information is downwind direction information and the phase state information is normal phase information, the preset operation steps are, in sequence, pulling the corresponding drop insurance of B, pulling the corresponding drop insurance of A, pulling the corresponding drop insurance of C, closing the corresponding drop insurance of C, closing the corresponding drop insurance of A, and closing the corresponding drop insurance of B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the second opening discrete time signal is high and the second closing discrete time signal is low, the first opening discrete time signal is high and the first closing discrete time signal is low, the third opening discrete time signal is high and the third closing discrete time signal is low, the third opening discrete time signal is low and the third closing discrete time signal is high, the first opening discrete time signal is low and the first closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0078] When the wind direction information is upwind direction information and the phase fault information is phase A fault, the preset operation steps are, in sequence, pulling the drop insurance corresponding to C, pulling the drop insurance corresponding to B, closing the drop insurance corresponding to A, closing the drop insurance corresponding to C, and closing the drop insurance corresponding to B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the third opening discrete time signal is high and the third closing discrete time signal is low, the second opening discrete time signal is high and the second closing discrete time signal is low, the first opening discrete time signal is low and the first closing discrete time signal is high, the third opening discrete time signal is low and the third closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0079] When the wind direction information is upwind direction information and the phase fault information is B phase fault, the preset operation steps are, in sequence, pulling the drop insurance corresponding to C, pulling the drop insurance corresponding to A, closing the drop insurance corresponding to A, closing the drop insurance corresponding to C, and closing the drop insurance corresponding to B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the third opening discrete time signal is high and the third closing discrete time signal is low, the first opening discrete time signal is high and the first closing discrete time signal is low, the first opening discrete time signal is high and the first closing discrete time signal is low, the third opening discrete time signal is low and the third closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0080] When the wind direction information is upwind direction information and the phase fault information is C phase fault, the preset operation steps are, in sequence, pulling the drop insurance corresponding to B, pulling the drop insurance corresponding to A, closing the drop insurance corresponding to A, closing the drop insurance corresponding to C, and closing the drop insurance corresponding to B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the second opening discrete time signal is high and the second closing discrete time signal is low, the first opening discrete time signal is high and the first closing discrete time signal is low, the first opening discrete time signal is low and the first closing discrete time signal is high, the third opening discrete time signal is low and the third closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0081] When the wind direction information is upwind direction information and the phase state information is normal phase information, the preset operation steps are, in sequence, pulling the corresponding drop insurance of B, pulling the corresponding drop insurance of C, pulling the corresponding drop insurance of A, closing the corresponding drop insurance of A, closing the corresponding drop insurance of C, and closing the corresponding drop insurance of B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the second opening discrete time signal is high and the second closing discrete time signal is low, the third opening discrete time signal is high and the third closing discrete time signal is low, the first opening discrete time signal is high and the first closing discrete time signal is low, the first opening discrete time signal is low and the first closing discrete time signal is high, the third opening discrete time signal is low and the third closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high.
[0082] In some embodiments, the data analysis device is specifically used to determine whether the actual opening and closing timing information is consistent with the preset opening and closing timing information. If so, the opening and closing operation is determined to be qualified and the training qualified information is output; if not, the opening and closing operation is determined to be unqualified and the training unqualified information is output; wherein the comparison result information is the training qualified information or the training unqualified information.
[0083] For example: when the wind direction information is downwind direction information and the phase fault information is phase A fault, if the practical operation steps are, in sequence, pulling the drop fuse corresponding to B, pulling the drop fuse corresponding to C, closing the drop fuse corresponding to C, closing the drop fuse corresponding to A, and closing the drop fuse corresponding to B; then the timing signals in the corresponding practical opening and closing timing information are, in sequence, the second opening discrete time signal is high and the second closing discrete time signal is low, the third opening discrete time signal is high and the third closing discrete time signal is low, the third opening discrete time signal is low and the third closing discrete time signal is high, the first opening discrete time signal is low and the first closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high; it can be seen that the practical opening and closing timing information is consistent with the preset opening and closing timing information, then the opening and closing operation is determined to be qualified and the training qualified information is output.
[0084] When the wind direction information is downwind direction information and the phase fault information is phase A fault, if the actual operation steps are, in sequence, pulling the drop fuse corresponding to C, pulling the drop fuse corresponding to B, closing the drop fuse corresponding to A, closing the drop fuse corresponding to C, and closing the drop fuse corresponding to B; then the timing signals in the corresponding preset opening and closing timing information are, in sequence, the third opening discrete time signal is high and the third closing discrete time signal is low, the second opening discrete time signal is high and the second closing discrete time signal is low, the first opening discrete time signal is low and the first closing discrete time signal is high, the third opening discrete time signal is low and the third closing discrete time signal is high, the second opening discrete time signal is low and the second closing discrete time signal is high; it can be seen that if the actual opening and closing timing information is inconsistent with the preset opening and closing timing information, the opening and closing operation is judged to be unqualified and the training unqualified information is output.
[0085] Through the travel switch installed at the drop insurance, the 35kV terminal tower three-phase drop insurance position switch quantity is introduced into the PLC input contact. After the examiner specifies the on-site wind direction through the control platform, the wind direction information is input into the display screen, the on-site drop insurance information is manually judged to be intact and the status switch quantity information is manually entered. According to the opening sequence of the drop insurance under different faults or normal conditions, the operation sequence logic of the A, B, and C three-phase drop insurances is programmed. If the trainee completes the operation according to the correct process, the voice output is "Congratulations, you passed the test". If a misjudgment occurs during the operation or the operation is not performed according to the standard process, the voice output is "Unfortunately, you failed the test" to terminate the operation. The intelligent drop insurance operation assessment system strengthens the trainees' standardized operation of electrical equipment by solidifying the operation process to prevent electrical misoperation incidents.
[0086] The embodiment of the present invention realizes the simulation of the terminal tower in the actual power grid by building a high-voltage collector line training terminal tower similar to the actual line terminal tower and setting a drop fuse on the high-voltage collector line training terminal tower. Then, by setting the simulated training information, the trainees can operate the drop fuses of each phase through the training information, and record the opening and closing sequence of the trainees' operation of each drop fuse through the data acquisition device, so as to judge whether the trainees' operation is qualified through the opening and closing sequence. Compared with traditional practical training and assessment, the present invention does not require on-site assessment personnel to provide on-site guidance and judgment, and can judge the assessment results of the operators by themselves through the equipment, thereby improving the efficiency and effect of the training of the drop fuse power outage operation of the high-voltage transformer.
[0087] Furthermore, the result output device is specifically used to display the qualified training information and output the qualified training voice when the comparison result information is the qualified training information; and to display the unqualified training information and output the unqualified training voice when the comparison result information is the unqualified training information.
[0088] In some other embodiments, a high-voltage collector line terminal tower practical training and assessment method is also provided, which is applied to the above-mentioned high-voltage collector line terminal tower practical training and assessment system, and includes the following steps:
[0089] S1. Generate training information using a data analysis device, and generate preset opening and closing timing information according to the training information;
[0090] S2, using a result output device to display the training information;
[0091] S3, using a data acquisition device to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation;
[0092] S4, using a data analysis device to integrate the discrete time signals of the opening and closing of each drop insurance during the opening and closing operation into a timing signal, and obtain the actual opening and closing timing information;
[0093] S5, using a data analysis device to compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information;
[0094] S6. Using a result output device to display the comparison result information.
[0095] In this embodiment, the practical training and assessment method for the high-voltage collector line terminal tower solidifies the operation logic by inputting the drop insurance information under different wind directions and different states into the PLC, i.e., the above-mentioned data analysis device, so as to combine the practical training with digitization and intelligence, strengthen the trainees' standardized operation of electrical equipment, and improve the efficiency and effect of practical training.
[0096] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the concept and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A high-voltage collector line terminal tower practical training and assessment system, characterized in that: It includes a high-voltage collector line training terminal tower, a data acquisition device, a data analysis device and a result output device; the high-voltage collector line training terminal tower is provided with a plurality of drop insurances, the plurality of drop insurances correspond to multi-phase high-voltage lines, and the plurality of drop insurances correspond to the multi-phase high-voltage lines one by one; The data analysis device is used to generate training information and generate preset opening and closing timing information according to the training information; The result output device is connected to the data analysis device and is used to display the training information; The data acquisition device is connected to a plurality of the drop fuses and is used to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation process; wherein the opening and closing operation process is the process of the trainees opening and closing each of the drop fuses according to the training information; The data analysis device is connected to the data acquisition device and is also used to integrate the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation into a timing signal to obtain actual opening and closing timing information; compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information; The result output device is also used to display the comparison result information.
2. The high-voltage collector line terminal tower practical training and assessment system according to claim 1 is characterized in that: The training information includes wind direction information and phase state information; The data analysis device is specifically used to generate the wind direction information and the phase state information, and generate the preset opening and closing timing information according to the wind direction information and the phase state information.
3. The high-voltage collector line terminal tower practical training and assessment system according to claim 2 is characterized in that: The wind direction information includes upwind direction information and downwind direction information, the phase state information includes normal phase information and phase fault information, the phase fault information includes a plurality of phase fault information, and the plurality of phase fault information corresponds one-to-one to the multi-phase high-voltage lines; The data analysis device is also specifically used to generate the preset switch opening and closing timing information according to the normal information and the upwind direction information when the phase state information is the normal phase information and the wind direction information is the upwind direction information; generate the preset switch opening and closing timing information according to the normal information and the downwind direction information when the phase state information is the normal phase information and the wind direction information is the downwind direction information; generate any one of the phase fault information among the multiple phase fault information when the phase state information is the phase fault information and the wind direction information is the upwind direction information, and generate the preset switch opening and closing timing information according to any one of the phase fault information and the upwind direction information; When the phase state information is the phase fault information and the wind direction information is the downwind direction information, any one of the multiple phase fault information is generated, and the preset opening and closing timing information is generated according to any one of the phase fault information and the downwind direction information.
4. The high-voltage collector line terminal tower practical training and assessment system according to claim 2 is characterized in that: The data acquisition device includes a first data acquisition device, a second data acquisition device and a third data acquisition device; the plurality of drop insurance devices are respectively a first drop insurance device, a second drop insurance device and a third drop insurance device, and the multi-phase high-voltage circuits are respectively an A-phase high-voltage circuit, a B-phase high-voltage circuit and a C-phase high-voltage circuit; wherein the first drop insurance device corresponds to the A-phase high-voltage circuit, the second drop insurance device corresponds to the B-phase high-voltage circuit, and the third drop insurance device corresponds to the C-phase high-voltage circuit; The first data collector is connected to the first drop fuse and is used to collect the position information of the fuse tube of the first drop fuse and record the collection time to obtain the first opening and closing discrete time information; The second data collector is connected to the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse and record the collection time to obtain the second opening and closing discrete time information; The third data collector is connected to the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse and record the collection time to obtain the third opening and closing discrete time information; The actual opening and closing timing information includes the first opening and closing discrete time information, the second opening and closing discrete time information and the third opening and closing discrete time information.
5. The high-voltage collector line terminal tower practical training and assessment system according to claim 4 is characterized in that: The first data collector includes a first opening position sensor and a first closing position sensor, the second data collector includes a second opening position sensor and a second closing position sensor, and the third data collector includes a third opening position sensor and a third closing position sensor; The first opening position sensor is connected to the opening contact of the first drop insurance, and is used to collect the position information and collection time of the fuse tube of the first drop insurance at the opening position when the fuse tube of the first drop insurance is at the opening position, so as to obtain a first opening discrete time signal; The first closing position sensor is connected to the closing contact of the first drop fuse, and is used to collect the position information of the first drop fuse in the closing position and record the collection time when the first drop fuse is in the closing position, so as to obtain a first closing discrete time signal; wherein the first opening and closing discrete time information includes the first opening discrete time signal and the first closing discrete time signal; The second opening position sensor is connected to the opening contact of the second drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the second drop insurance is at the opening position, so as to obtain a second opening discrete time signal; The second closing position sensor is connected to the closing contact of the second drop fuse, and is used to collect the position information of the fuse tube of the second drop fuse in the closing position and record the collection time when the fuse tube of the second drop fuse is in the closing position, so as to obtain a second closing discrete time signal; wherein the second opening and closing discrete time information includes the second opening discrete time signal and the second closing discrete time signal; The third opening position sensor is connected to the opening contact of the third drop insurance, and is used to collect the position information of the fuse tube of the second drop insurance at the opening position and record the collection time when the fuse tube of the third drop insurance is in the opening position, so as to obtain a third opening discrete time signal; The third closing position sensor is connected to the closing contact of the third drop fuse, and is used to collect the position information of the fuse tube of the third drop fuse in the closing position and record the collection time when the fuse tube of the third drop fuse is in the closing position, so as to obtain a third closing discrete time signal; wherein, the third opening and closing discrete time information includes the third opening discrete time signal and the third closing discrete time signal.
6. The high-voltage collector line terminal tower practical training and assessment system according to claim 5 is characterized in that: The data analysis device is connected to the first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor, and is specifically used to integrate the first opening discrete time signal, the first closing discrete time signal, the second opening discrete time signal, the second closing discrete time signal, the third opening discrete time signal and the third closing discrete time signal into a timing signal in the order of recorded time to obtain the actual opening and closing timing information.
7. The high-voltage collector line terminal tower practical training and assessment system according to claim 6 is characterized in that: The first opening position sensor, the first closing position sensor, the second opening position sensor, the second closing position sensor, the third opening position sensor and the third closing position sensor are all travel switches; and the data analysis device is a programmable logic controller.
8. The high-voltage collector line terminal tower practical training and assessment system according to claim 1 is characterized in that: The data analysis device is specifically used to determine whether the actual opening and closing timing information is consistent with the preset opening and closing timing information. If so, the opening and closing operation is determined to be qualified and the training qualified information is output; if not, the opening and closing operation is determined to be unqualified and the training unqualified information is output; wherein the comparison result information is the training qualified information or the training unqualified information.
9. The high-voltage collector line terminal tower practical training and assessment system according to claim 8 is characterized in that: The result output device is specifically used for displaying the qualified training information and outputting the qualified training voice when the comparison result information is the qualified training information; and for displaying the unqualified training information and outputting the unqualified training voice when the comparison result information is the unqualified training information.
10. A practical training and assessment method for high-voltage collector line terminal tower, characterized in that: The high-voltage collector line terminal tower practical training and assessment system as claimed in any one of claims 1 to 9 comprises the following steps: S1. Generate training information using a data analysis device, and generate preset opening and closing timing information according to the training information; S2, using a result output device to display the training information; S3, using a data acquisition device to collect the discrete time signals of the opening and closing of each of the drop fuses during the opening and closing operation; S4, using a data analysis device to integrate the discrete time signals of the opening and closing of each drop insurance during the opening and closing operation into a timing signal, and obtain the actual opening and closing timing information; S5, using a data analysis device to compare the actual opening and closing timing information with the preset opening and closing timing information to obtain comparison result information; S6. Using a result output device to display the comparison result information.