Righting structure for repairing cob wall and using method
By building a top frame, interspersed beam, mobile bracket and straightening mechanism, the problem of inconsistent inclination directions of the two ends of the wall is solved, effectively straightening and reinforcement of the earth wall is achieved, and repair efficiency and stability are improved.
Patent Information
- Application Number
- CN202411783904.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-06
- Publication Date
- 2025-03-14
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The prior art is difficult to effectively straighten the inclination directions of both ends of the wall.
A correcting structure for earth wall repair is adopted, including a top frame, interspersed beam, mobile bracket and straightening mechanism built above the earth wall. The driving mechanism adjusts the straightening position to ensure that the straightening mechanism supports both ends of the inclined earth wall.
The straightening support for single and double-sided inclined earth walls is achieved, especially double-sided inclined earth walls, which improves the accuracy and efficiency of straightening, and improves the stability of the earth walls through reinforcement structure.
Smart Images

Figure CN119616248A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of earth wall repair, and in particular to a straightening structure for earth wall repair and a use method thereof. Background Art
[0002] Among the wall structures of some ancient cities or ancient buildings in China, some walls are sandwich walls with bricks on the outside and broken bricks on the inside. The foundation of such walls is shallow, and due to years of disrepair, they will tilt, slant, twist and bulge. These walls have certain historical value, and demolishing and rebuilding them will reduce the historical significance and cultural relic value of the corresponding buildings, so they need to be straightened and repaired.
[0003] After searching, the announcement number CN117988590A discloses a device and method for straightening the earthen wall of an ancient building, including: a mounting mechanism, the mounting mechanism includes a first mounting plate and a second mounting plate, a connecting piece is arranged between the first mounting plate and the second mounting plate, a straightening mechanism is arranged above the first mounting plate, a supporting mechanism is arranged above the second mounting plate, and fixing mechanisms are arranged on the sides of the first mounting plate and the second mounting plate, the straightening mechanism includes a side plate, the side plate is located on the upper surface of the first mounting plate, and the side plate is fixedly connected to the first mounting plate, and two side plates are arranged. The straightening device can understand the local stress condition of the earthen wall according to the value of the pressure sensor, which is convenient for understanding the overall stability of the earthen wall, avoiding damage to the earthen wall caused by excessive local pressure, and can reinforce the earthen wall of the old wall.
[0004] However, the above-mentioned straightening device still has the following problems: in the actual repair process, it was found that due to the relatively large span of the wall, the inclination direction and angle of the two sides of the wall would deviate greatly, forming Fig.10 The twisted state shown is a situation where the inclination directions of the two ends of the wall are inconsistent, and the existing straightening device is difficult to perform straightening work in this situation. Summary of the invention
[0005] The present invention provides a straightening structure for repairing an earth wall and a method for using the structure, which solves the problem in the prior art that the two ends of a wall are difficult to straighten due to inconsistent inclination directions.
[0006] The technical solution of the present invention is as follows: a straightening structure for repairing an earth wall, comprising a top frame built above the earth wall, and an interlaced beam extending from the original building on the inner side of the earth wall, first guide rails are arranged on both sides of the top surface of the top frame, a steel beam is fixed on the top of the top frame, and second guide rails consistent with the direction of the first guide rails are fixed on both sides of the bottom surface of the steel beam, two movable brackets are symmetrically arranged on both sides of the top frame, a first notch and a second notch are opened on the movable bracket, two first guide wheels that can roll along the first guide rail are rotatably arranged in the first notch, and two second guide wheels that can roll along the second guide rail are rotatably arranged in the second notch, and straightening mechanisms respectively located on both sides of the earth wall are arranged at the bottom of the two movable brackets, and a driving mechanism that drives the two straightening mechanisms to move relative to each other through the movable bracket to adjust the straightening position is arranged at the top of the top frame; The two second guide wheels each include two wheel hubs and a wheel groove between the two wheel hubs, and the wheel groove is provided with a marking mechanism for rolling and marking the grouting position of the soil wall after straightening; The outer end of the interlaced beam is provided with a reinforcement structure for further reinforcing the earth wall after straightening.
[0007] Preferably, the driving mechanism includes a first cylinder and a swivel arm, a rotating shaft rotatably connected to the steel beam is fixed at the middle position of the bottom surface of the swivel arm, an angle plate is fixed at one end of the swivel arm, the end of the first cylinder is hinged to the steel beam, and the output end of the first cylinder is hinged to the angle plate.
[0008] Preferably, the movable bracket includes a top plate, a limiting axis is fixed on the top of the top plate, and side plates are fixed on both sides of the bottom of the top plate.
[0009] Preferably, two waist-shaped grooves are provided on the rotating arm, and the limiting shafts on the two movable brackets are respectively limited in the two waist-shaped grooves.
[0010] Preferably, the straightening mechanism includes a base frame, a second cylinder is fixed to one end of the base frame, a straightening plate is hinged to the other end of the base frame, an inclined support frame is arranged between the angles of the base frame and the straightening plate, hinge seats are fixed on both sides of the straightening plate, sliding grooves are provided on both sides of the base frame, a first hinge shaft hinged to the hinge seat is fixed to one end of the inclined support frame, a second hinge shaft slidingly limited in the sliding groove is fixed to the other end of the inclined support frame, and the output end of the second cylinder is hinged to the second hinge shaft.
[0011] Preferably, an upper conical cavity, a lower conical cavity, and a cylindrical cavity connecting the upper conical cavity with the lower conical cavity are formed on the inner side of the second guide wheel, and a flow channel communicating with the lower conical cavity is formed on one side hub of the second guide wheel.
[0012] Preferably, the flow channels on the two second guide wheels are located on different sides, and the distance between the two second guide wheels is equal to the diameter of the hub.
[0013] Preferably, the punctuation mechanism includes a hollow tube, the outside of which is fixed with a first cone plug respectively arranged in the upper cone cavity and a second cone plug in the lower cone cavity, a spring is arranged outside the hollow tube, one end of the spring abuts against the first cone plug, and the other end of the spring abuts against the bottom wall of the upper cone cavity, a liquid storage cavity is provided on the inner side of the hollow tube, a liquid outlet leading to the cylindrical cavity is provided at the bottom of the liquid storage cavity, the top of the hollow tube passes through the upper cone cavity and extends to the wheel groove, and the portion extending to the wheel groove is filled with a sealing plug.
[0014] Preferably, the reinforcement structure includes an anchor rod connected to the mortise and tenon of the intersecting beam and anchored to the outer end of the intersecting beam, and the outer end of the anchor rod penetrates the earth wall and is fixed with a leech that contacts the outer wall surface of the earth wall.
[0015] Based on the above-mentioned righting structure, the present invention further proposes a method for using the righting structure, comprising the following steps: Step 1: Strengthen the support, build the top frame above the earth wall, and place the two straightening mechanisms on both sides of the earth wall respectively, assemble and fix the mobile bracket and the straightening mechanism, and drive the two mobile brackets to drive the straightening mechanism to adjust the use position according to the inclination direction of the two ends of the earth wall through the driving mechanism, and then fix the straightening mechanism to the foundation, so that the two straightening mechanisms support the two ends of the inclined earth wall; Step 2: Foundation treatment: dig the soil around the earth wall, recompact the foundation, and pour concrete on the foundation; Step 3: Pre-treatment of the earth wall straightening: holes corresponding to the interlaced beams are chiseled on the inner wall surface corresponding to the earth wall straightening to facilitate the installation and fixation of the reinforcement structure; Step 4: Straightening and reinforcing the wall. Two straightening mechanisms work simultaneously, gradually pushing the inclined earth wall on both sides until the wall is straightened to a vertical state. The wall and the interlaced beams extending from the original building are fixed through the reinforcement structure, and the holes on the earth wall around the reinforcement structure are filled and sealed. Step 5: Grouting marking: remove the mobile bracket and the straightening mechanism, so that the two straightening mechanisms can still reinforce and support the earth wall, and drive the two mobile brackets to move back and forth through the driving mechanism again, so that the two second guide wheels on the mobile bracket form two groups of marking points on the earth wall, and take the midpoint of each group of marking points as the grouting point, and perform grouting after drilling holes at the grouting points through the drilling equipment; Step 6: Dismantle the support. First, remove the two mobile brackets and the top frame, then uninstall the two righting mechanisms, and remove the two righting mechanisms from the foundation. Step seven, wall repair, hang wire mesh on the earth wall, cover it with cement mortar, and then level it by plastering.
[0016] The beneficial effects of the present invention are: The present invention can realize the straightening and supporting of earth walls inclined on one or both sides, especially in the straightening work of earth walls inclined on both sides, by building a top frame above the earth wall, and making two straightening mechanisms respectively located on both sides of the earth wall, assembling and fixing the movable bracket and the straightening mechanism, and driving the two movable brackets to drive the straightening mechanism to adjust the use position according to the inclination direction of the two ends of the earth wall by the driving mechanism, and then fixing the straightening mechanism to the foundation, so that the two straightening mechanisms support the two ends of the inclined earth wall, thereby solving the problem in the prior art that the inclination directions of the two ends of the wall are inconsistent and it is difficult to straighten; In the present invention, the movable bracket and the straightening mechanism can be released from installation, so that the two straightening mechanisms can still reinforce and support the earth wall, and the two movable brackets are driven by the driving mechanism to move back and forth again, and two second guide wheels on the movable bracket form two groups of marking points on the earth wall, and the midpoint of each group of marking points is taken as the grouting point, and the grouting is performed after the grouting point is drilled by the drilling device. Compared with the prior art, the present invention can quickly find the drilling position, facilitate the subsequent grouting work, and improve the efficiency of repairing the earth wall; The present invention makes full use of the interlaced beams to connect and tie with the earth wall during the straightening construction, so that the wooden structure of the interlaced beams and the earth wall form a whole. In this way, the earth wall is no longer an independent structure, which effectively alleviates the wall deflection and improves the seismic resistance of the wall. For some thin wall thicknesses, the earth wall can be reinforced by only using the leech climbing structure to further improve the stability of the earth wall after straightening. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0018] Figure 1 A schematic diagram of a soil wall repair straightening structure proposed by the present invention; Figure 2 A schematic diagram of the top frame structure proposed by the present invention; Figure 3 This is a structural schematic diagram of the top frame proposed by the present invention from another viewing angle; Figure 4 This is a schematic diagram of the driving mechanism structure proposed by the present invention; Figure 5 This is a schematic diagram of the structure of the mobile support proposed by the present invention; Figure 6 This is a schematic diagram of the structure of the righting mechanism proposed by the present invention; Figure 7 This is a schematic diagram of the structure of the second guide wheel proposed by the present invention; Figure 8 A schematic diagram of a half-section structure of one of the second guide wheels proposed in the present invention; Fig. 9A schematic diagram of a half-section structure of another second guide wheel proposed by the present invention; Fig.10 A schematic diagram of a double-sided inclined earth wall proposed by the present invention; Fig.11 This is a schematic diagram of marking points on the earth wall proposed by the present invention; Fig.12 This is a schematic diagram of the distribution of the reinforcement structure and the earth wall after the straightening of the present invention; In the figure: 1, top frame; 11, first guide rail; 12, steel beam; 13, second guide rail; 2, movable bracket; 21, first notch; 22, second notch; 23, top plate; 24, limit shaft; 25, side plate; 3, driving mechanism; 31, first cylinder; 32, rotating arm; 33, rotating shaft; 34, angle plate; 4, first guide wheel; 5, second guide wheel; 51, wheel hub; 52, wheel groove; 53, punctuation mechanism; 531, hollow tube; 532, first cone plug; 533. Second cone plug; 534. Liquid storage chamber; 535. Sealing plug; 536. Liquid outlet; 537. Spring; 54. Upper cone chamber; 55. Lower cone chamber; 56. Cylindrical chamber; 57. Flow channel; 6. Righting mechanism; 61. Base frame; 62. Second cylinder; 63. Diagonal support frame; 64. Righting plate; 65. Hinge seat; 66. First hinge shaft; 67. Second hinge shaft; 7. Reinforcement structure; 71. Wooden frame; 72. Anchor rod; 73. Leech climbing; 8. Interlaced beams. DETAILED DESCRIPTION
[0019] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0020] See also Figure 1 , Figure 2 and Figure 3The present invention provides a technical solution: a straightening structure for repairing an earth wall, comprising a top frame 1 built above the earth wall, an interlaced beam 8 extending from the original building on the inner side of the earth wall, first guide rails 11 are arranged on both sides of the top surface of the top frame 1, a steel beam 12 is fixed on the top of the top frame 1, and second guide rails 13 consistent with the direction of the first guide rail 11 are fixed on both sides of the bottom surface of the steel beam 12, two movable brackets 2 are symmetrically arranged on both sides of the top frame 1, a first notch 21 and a second notch 22 are opened on the movable bracket 2, two first guide wheels 4 capable of rolling along the first guide rail 11 are rotatably arranged in the first notch 21, and two second guide wheels 5 capable of rolling along the second guide rail 13 are rotatably arranged in the second notch 22, straightening mechanisms 6 respectively located on both sides of the earth wall are arranged at the bottom of the two movable brackets 2, and a driving mechanism 3 for adjusting the straightening position by driving the two straightening mechanisms 6 to move relative to each other through the movable bracket 2 is arranged at the top of the top frame 1.
[0021] See also Figure 7 , Figure 8 The two second guide wheels 5 each include two wheel hubs 51 and a wheel groove 52 between the two wheel hubs 51 , and a marking mechanism 53 for rolling and marking the grouting position of the earth wall after straightening is provided at the wheel groove 52 .
[0022] See also Figure 1 and Figure 4 The driving mechanism 3 includes a first cylinder 31 and a rotating arm 32. A rotating shaft 33 rotatably connected to the steel beam 12 is fixed at the middle position of the bottom surface of the rotating arm 32. An angle plate 34 is fixed at one end of the rotating arm 32. The end of the first cylinder 31 is hinged to the steel beam 12, and the output end of the first cylinder 31 is hinged to the angle plate 34.
[0023] See also Figure 1 and Figure 5 The movable bracket 2 includes a top plate 23, a limiting shaft 24 is fixed on the top of the top plate 23, and side plates 25 are fixed on both sides of the bottom of the top plate 23. Two waist-shaped grooves are provided on the rotating arm 32, and the limiting shafts 24 on the two movable brackets 2 are respectively limited in the two waist-shaped grooves. The first cylinder 31 works to push the angle plate 34, and the rotating arm 32 is driven by the angle plate 34 to rotate around the rotating shaft 33 as the center, and then the limiting shafts 24 of the two movable brackets 2 are limited by the waist-shaped grooves of the rotating arm 32, so as to drive the two movable brackets 2 to move synchronously relative to each other.
[0024] See also Figure 1 and Figure 6The straightening mechanism 6 includes a base frame 61, one end of which is fixed with a second cylinder 62, and the other end of the base frame 61 is hinged with a straightening plate 64, and an inclined support frame 63 is arranged between the angles of the base frame 61 and the straightening plate 64. A hinge seat 65 is fixed on both sides of the straightening plate 64, and a slide groove is provided on both sides of the base frame 61. One end of the inclined support frame 63 is fixed with a first hinge shaft 66 hinged to the hinge seat 65, and the other end of the inclined support frame 63 is fixed with a second hinge shaft 67 whose sliding limit is in the slide groove, and the output end of the second cylinder 62 is hinged to the second hinge shaft 67. When the two straightening mechanisms 6 are moved to the inclined side of the earth wall, the base frame 61 can be fixed to the two sides of the earth wall by bolts and then re-trimmed. The second hinge shaft 67 is pushed by the second cylinder 62, and the diagonal support frame 63 presses down the straightening plate 64, so that the straightening plate 64 gradually pushes the inclined wall until the wall changes from an inclined state to a vertical state.
[0025] See also Figure 7 , Figure 8 and Fig. 9 The inner side of the second guide wheel 5 is provided with an upper cone cavity 54, a lower cone cavity 55, and a cylindrical cavity 56 connecting the upper cone cavity 54 with the lower cone cavity 55. A flow channel 57 communicating with the lower cone cavity 55 is provided on a hub 51 on one side of the second guide wheel 5. The flow channels 57 on the two second guide wheels 5 are respectively located on different sides. The spacing between the two second guide wheels 5 is equal to the diameter of the hub 51. The punctuation mechanism 53 includes a hollow tube 531. The outer side of the hollow tube 531 is fixed with first cones respectively arranged in the upper cone cavity 54 and the lower cone cavity 55. The hollow tube 531 is provided with a spring 537, one end of the spring 537 abuts against the first cone plug 532, and the other end of the spring 537 abuts against the bottom wall of the upper cone cavity 54. The inner side of the hollow tube 531 is provided with a liquid storage cavity 534, and the bottom of the liquid storage cavity 534 is provided with a liquid outlet hole 536 leading to the cylindrical cavity 56. The top of the hollow tube 531 passes through the upper cone cavity 54 and extends to the wheel groove 52, and extends to the position of the wheel groove 52 to fill the liquid storage cavity 534. The top of the hollow tube 531 and the hole in the wheel groove 52 are matched with each other in a clearance, so as to facilitate the entry of air and help the discharge of the marking liquid in the inner cavity of the second guide wheel 5. In the process of slowly driving the two movable brackets 2 to move back and forth by the driving mechanism 3, the two second guide wheels 5 continuously roll on the second guide rail 13. When the hollow tube 531 rolls to contact the second guide rail 13, the hollow tube 531 can overcome the elastic force of the spring 537 and shrink downward under the squeezing of the second guide rail 13, so that the external air enters the inner cavity of the wheel hub 51 through the hole in the wheel groove 52, so that the marking liquid in the inner cavity of the wheel hub 51 can drip out through the flow channel 57. Since the flow channels 57 on the two second guide wheels 5 are respectively on different sides, the spacing between the two second guide wheels 5 is equal to the diameter of the wheel hub 51, so that two sets of marking points can be formed on the top surface of the earth wall below. Fig.11 The location of the small and medium circles, the midpoint of each group of marked points is the grouting point Fig.11 At the location of the middle and large circle, holes are drilled at the grouting points using a drilling device to facilitate the grouting equipment to perform grouting in the holes.
[0026] See also Fig.12 The outer end of the interlaced beam 8 is provided with a reinforcement structure 7 for further reinforcing the earth wall after straightening. The reinforcement structure 7 includes a wooden frame 71 connected to the interlaced beam 8 by mortise and tenon, and an anchor rod 72 anchored to the outer end of the interlaced beam 8. The outer end of the anchor rod 72 penetrates the earth wall and is fixed with a leech climber 73 that abuts against the outer wall surface of the earth wall. During the straightening construction, the interlaced beam 8 is fully utilized to connect and tie with the earth wall, so that the wooden structure of the interlaced beam 8 and the earth wall form a whole. In this way, the earth wall is no longer an independent structure, which effectively alleviates the wall deflection and improves the seismic resistance of the wall. For some cases where the wall thickness is relatively thin, the earth wall can be reinforced by using only the structure of the leech climber 73 to further improve the stability of the earth wall after straightening.
[0027] Based on the righting structure in the above embodiment, the present invention further provides a method for using the righting structure, comprising the following steps: Step 1: Strengthen the support, build the top frame 1 above the earth wall, and place the two straightening mechanisms 6 on both sides of the earth wall respectively, assemble and fix the mobile bracket 2 and the straightening mechanism 6, and drive the two mobile brackets 2 to drive the straightening mechanism 6 to adjust the use position according to the inclination direction of the two ends of the earth wall through the driving mechanism 3, and then fix the straightening mechanism 6 to the foundation, so that the two straightening mechanisms 6 support the two ends of the inclined earth wall; Step 2: Foundation treatment: dig the soil around the earth wall, recompact the foundation, and pour concrete on the foundation; Step three, pre-treatment of the earth wall straightening, chiseling holes corresponding to the interlaced beams 8 on the inner wall surface corresponding to the earth wall straightening, so as to facilitate the installation and fixation of the reinforcement structure 7.
[0028] Step 4: straightening and reinforcing the wall. The two straightening mechanisms 6 work simultaneously to gradually push the inclined earth wall on both sides until the wall is straightened to a vertical state. The wall and the interlaced beams 8 extending from the original building are fixed by the reinforcement structure 7, and the holes on the earth wall around the reinforcement structure 7 are filled and sealed. Step 5: Grouting marking. The mobile bracket 2 and the straightening mechanism 6 are unmounted so that the two straightening mechanisms 6 can still reinforce and support the earth wall. The two mobile brackets 2 are driven to move back and forth by the driving mechanism 3 again. Two sets of marking points are formed on the earth wall by the two second guide wheels 5 on the mobile bracket 2. The midpoint of each set of marking points is taken as the grouting point. The grouting is performed after drilling holes at the grouting points by the punching equipment. Step 6: dismantle the support, first dismantle the two mobile brackets 2 and the top frame 1, then unload the two straightening mechanisms 6, and remove the two straightening mechanisms 6 from the foundation; Step seven, wall repair, hang wire mesh on the earth wall, cover it with cement mortar, and then level it by plastering.
[0029] The working principle and use process of the present invention are as follows: when straightening a single-sided inclined earth wall, the two straightening mechanisms 6 can be moved to the inclined side of the earth wall, and the two straightening mechanisms 6 work together to straighten the single-sided inclined earth wall. Fig.10 The double-sided inclined earth wall shown in the figure is straightened, and the specific operation is as follows: the first cylinder 31 works to push the angle plate 34, and the angle plate 34 drives the rotating arm 32 to rotate around the rotating shaft 33, and then the waist-shaped groove of the rotating arm 32 limits the limit shafts 24 of the two movable brackets 2, and drives the two movable brackets 2 to move synchronously relative to each other, so that the two straightening mechanisms 6 can be moved to the inclined sides of the two ends of the earth wall, and then the base frame 61 is fixed to the two sides of the earth wall by bolts. The second hinge shaft 67 is pushed by the second cylinder 62, and the diagonal support frame 63 presses the straightening plate 64 downward, so that the straightening plate 64 gradually pushes the inclined wall until the wall changes from an inclined state to a vertical state; When the earth wall needs to be marked with grouting, the foot bolts of the side plate 25 are removed from the base frame 61, and the sealing plug 535 on the top of the hollow tube 531 is removed. The marking liquid is injected into the liquid storage chamber 534 and then the sealing plug 535 is filled. Finally, the sealing plug 535 at the bottom of the flow channel 57 is removed, and the two movable brackets 2 are slowly driven to move back and forth by the driving mechanism 3 again. During this process, the two second guide wheels 5 continue to roll on the second guide rail 13. When the hollow tube 531 rolls to the first When the two guide rails 13 are in contact, the hollow tube 531 can be squeezed by the second guide rail 13 to overcome the elastic force of the spring 537 and shrink downward, so that the external air enters the inner cavity of the hub 51 through the hole in the wheel groove 52, so that the marking liquid in the inner cavity of the hub 51 can drip out through the flow channel 57. Since the flow channels 57 on the two second guide wheels 5 are respectively on different sides, the distance between the two second guide wheels 5 is equal to the diameter of the hub 51, so that two sets of marking points can be formed on the top surface of the earth wall below. Fig.11 The location of the small and medium circles, the midpoint of each group of marked points is the grouting point Fig.11 At the location of the middle and large circle, holes are drilled at the grouting points using a drilling device to facilitate the grouting equipment to perform grouting in the holes.
[0030] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A straightening structure for repairing an earth wall, comprising a top frame (1) built on the top of the earth wall, and a through beam (8) extending from an original building on the inner side of the earth wall, characterized in that: First guide rails (11) are provided on both sides of the top surface of the top frame (1); a steel beam (12) is fixed on the top of the top frame (1); second guide rails (13) in the same direction as the first guide rails (11) are fixed on both sides of the bottom surface of the steel beam (12); two movable brackets (2) are symmetrically provided on both sides of the top frame (1); a first notch (21) and a second notch (22) are provided on the movable bracket (2); two first guide wheels (4) capable of rolling along the first guide rail (11) are rotatably provided in the first notch (21); two second guide wheels (5) capable of rolling along the second guide rail (13) are rotatably provided in the second notch (22); straightening mechanisms (6) are provided at the bottom of the two movable brackets (2) and are located on both sides of the earth wall respectively; and a driving mechanism (3) is provided at the top of the top frame (1) for adjusting the straightening position by driving the two straightening mechanisms (6) to move relative to each other through the movable bracket (2); The two second guide wheels (5) each comprise two wheel hubs (51) and a wheel groove (52) located between the two wheel hubs (51); the wheel groove (52) is provided with a marking mechanism (53) for rolling and marking a grouting position for the earth wall after straightening; The outer end of the interlaced beam (8) is provided with a reinforcement structure (7) for further reinforcing the earth wall after straightening.
2. The soil wall repairing structure according to claim 1, characterized in that: The driving mechanism (3) comprises a first cylinder (31) and a rotating arm (32); a rotating shaft (33) rotatably connected to the steel beam (12) is fixed at the middle position of the bottom surface of the rotating arm (32); an angle plate (34) is fixed to one end of the rotating arm (32); the end of the first cylinder (31) is hinged to the steel beam (12); and the output end of the first cylinder (31) is hinged to the angle plate (34).
3. The soil wall repairing structure according to claim 2, characterized in that: The movable bracket (2) comprises a top plate (23), a limiting axis (24) is fixed on the top of the top plate (23), and side plates (25) are fixed on both sides of the bottom of the top plate (23).
4. The soil wall repairing structure according to claim 3, characterized in that: The rotating arm (32) is provided with two waist-shaped grooves, and the limiting shafts (24) on the two movable brackets (2) are respectively limited in the two waist-shaped grooves.
5. The earth wall repairing structure according to claim 3, characterized in that: The straightening mechanism (6) comprises a base frame (61), a second cylinder (62) is fixed to one end of the base frame (61), a straightening plate (64) is hinged to the other end of the base frame (61), an inclined support frame (63) is arranged between the base frame (61) and the straightening plate (64) at an angle, hinge seats (65) are fixed to both sides of the straightening plate (64), sliding grooves are provided on both sides of the base frame (61), a first hinge shaft (66) hinged to the hinge seat (65) is fixed to one end of the inclined support frame (63), a second hinge shaft (67) slidably limited in the sliding groove is fixed to the other end of the inclined support frame (63), and an output end of the second cylinder (62) is hinged to the second hinge shaft (67).
6. The soil wall repairing straightening structure according to claim 1, characterized in that: An upper conical cavity (54), a lower conical cavity (55), and a cylindrical cavity (56) connecting the upper conical cavity (54) and the lower conical cavity (55) are formed on the inner side of the second guide wheel (5), and a flow channel (57) communicating with the lower conical cavity (55) is formed on a wheel hub (51) on one side of the second guide wheel (5).
7. The soil wall repairing straightening structure according to claim 1, characterized in that: An upper conical cavity (54), a lower conical cavity (55), and a cylindrical cavity (56) connecting the upper conical cavity (54) and the lower conical cavity (55) are formed on the inner side of the second guide wheel (5), and a flow channel (57) communicating with the lower conical cavity (55) is formed on a wheel hub (51) on one side of the second guide wheel (5).
8. The soil wall repairing straightening structure according to claim 6, characterized in that: The punctuation mechanism (53) comprises a hollow tube (531), the outer side of which is fixed with a first cone plug (532) arranged in the upper cone cavity (54) and a second cone plug (533) arranged in the lower cone cavity (55), respectively; a spring (537) is provided on the outer sleeve of the hollow tube (531), one end of the spring (537) abuts against the first cone plug (532), and the other end of the spring (537) abuts against the bottom wall of the upper cone cavity (54); a liquid storage cavity (534) is provided on the inner side of the hollow tube (531), and a liquid outlet hole (536) leading to the columnar cavity (56) is provided at the bottom of the liquid storage cavity (534); the top of the hollow tube (531) passes through the upper cone cavity (54) and extends to the wheel groove (52), and a sealing plug (535) is filled at the portion extending to the wheel groove (52).
9. The soil wall repairing structure according to claim 8, characterized in that: The reinforcement structure (7) comprises a mortise and tenon connection (71) with the inserted beam (8), and an anchor rod (72) anchored to the outer end of the inserted beam (8), wherein the outer end of the anchor rod (72) penetrates the earth wall and is fixed with a leech (73) that contacts the outer wall surface of the earth wall.
10. A method for using a straightening structure, according to the straightening structure for repairing earth walls according to claim 1, characterized in that: The following steps are involved: Step 1: Strengthen the support, build the top frame (1) above the earth wall, and place the two straightening mechanisms (6) on both sides of the earth wall respectively, assemble and fix the movable bracket (2) and the straightening mechanism (6), and drive the two movable brackets (2) to drive the straightening mechanism (6) to adjust the use position according to the inclination direction of the two ends of the earth wall through the driving mechanism (3), and then fix the straightening mechanism (6) to the foundation, so that the two straightening mechanisms (6) support the two ends of the inclined earth wall; Step 2: Foundation treatment: dig the soil around the earth wall, recompact the foundation, and pour concrete on the foundation; Step 3: Pre-treatment of the earth wall straightening: holes corresponding to the interlaced beams (8) are chiseled on the inner wall surface corresponding to the earth wall straightening to facilitate the installation and fixation of the reinforcement structure (7); Step 4: straightening and reinforcing the wall. The two straightening mechanisms (6) work simultaneously to gradually push the inclined earth wall on both sides until the wall is straightened to a vertical state. The wall is fixed to the interlaced beams (8) extending from the original building through the reinforcement structure (7), and the holes on the earth wall around the reinforcement structure (7) are filled and sealed. Step 5: grouting marking. The movable bracket (2) and the straightening mechanism (6) are disassembled so that the two straightening mechanisms (6) can still reinforce and support the earth wall. The two movable brackets (2) are driven to move back and forth by the driving mechanism (3) again. Two second guide wheels (5) on the movable bracket (2) form two groups of marking points on the earth wall. The midpoint of each group of marking points is taken as the grouting point. The grouting is performed after drilling holes at the grouting points by the drilling equipment. Step 6: dismantle the support, first dismantle the two movable brackets (2) and the top frame (1), then uninstall the two righting mechanisms (6), and remove the two righting mechanisms (6) from the foundation; Step seven, wall repair, hang wire mesh on the earth wall, cover it with cement mortar, and then level it by plastering.
Citation Information
Patent Citations
Ancient building cob wall righting device and method thereof
CN117988590A