Through the intelligent AI computing power system hard equipment assembly planning device, the environmental simulation device and test box are used to detect the heat generation of the server, the problem of mismatch in the existing technology of server heat dissipation is solved, and more reasonable configuration of the heat dissipation equipment and normal operation of the equipment is achieved.
Patent Information
- Application Number
- CN202411637034.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-15
- Publication Date
- 2025-03-14
AI Technical Summary
The server composition of existing intelligent AI computing power systems is high, and there is a problem of mismatch in heat dissipation when the old equipment is improved, resulting in the refrigeration equipment being unable to meet the server's heat dissipation needs and affecting normal operation.
Design an intelligent AI computing power system hardware equipment assembly planning device, including environmental simulation device, test box and refrigeration equipment. Through the environmental simulation device, the external environment is simulated in the test box, the heating capacity of the equipment is detected, and reasonable heat dissipation equipment is configured according to the test results.
It effectively solves the problem of mismatch in server heat dissipation, ensures that the server operates at normal operating temperatures, extends the life of the equipment, and reduces the cost of improvement.
Smart Images

Figure CN119629905A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of equipment assembly planning, and specifically is a hardware equipment assembly planning device for an intelligent AI computing system. Background Art
[0002] Artificial intelligence is an important driving force for the new round of scientific and technological revolution and industrial transformation. It is a new technical science that studies and develops theories, methods, technologies and application systems for simulating, extending and expanding human intelligence.
[0003] Artificial intelligence is an important part of the intelligent discipline. It attempts to understand the essence of intelligence and produce a new intelligent machine that can respond in a similar way to human intelligence. Artificial intelligence is a very broad science, including robotics, language recognition, image recognition, natural language processing, expert systems, machine learning, computer vision, etc.
[0004] With the rapid development of artificial intelligence (AI) technology, the penetration of AI applications in various fields continues to deepen, and the demand for high-performance computing resources is also increasing rapidly.
[0005] The most important part of the intelligent AI computing system hardware equipment is the server.
[0006] The existing patent application publication number is CN110069111 B, and the patent name is an invention patent of an AI computing server. It records that the chassis includes a first area, a second area, and a third area arranged in sequence; a server motherboard arranged in the first area; an AI computing board arranged in parallel with the server motherboard, and the AI computing board is electrically connected to the server motherboard through a PC IE adapter cable; a hard disk array arranged in the third area, and the hard disk array is electrically connected to the server motherboard through a data cable; a first heat dissipation device arranged in the second area, the first heat dissipation device includes a heat sink bracket separating the first area and the third area, the heat sink bracket includes a heat dissipation channel connecting the first area and the third area, and the first heat dissipation device also includes a heat dissipation fan, and the heat dissipation fan is fixed in the heat dissipation channel. It is achieved that multiple AI computing boards can be overlapped and placed horizontally in the narrow space of the server, and the heat dissipation channel forms a good heat dissipation channel between the dense boards in the chassis, ensuring that the chassis always operates within the working temperature.
[0007] However, research has found that the above solution has certain drawbacks when used;
[0008] The cost of the existing intelligent AI computing system servers is relatively high. Therefore, when using them, old equipment is usually improved by combining old parts with new parts, so that some parts in the constructed server are old equipment parts, which makes the actual heat dissipation of the server much greater than the heat dissipation of the new equipment. The refrigeration equipment that meets the requirements of the new equipment may not be able to meet the requirements of the server. Therefore, in order to better ensure the normal operation of the server, it is necessary to conduct corresponding inspections on the server and plan the assembly of the server according to the inspection results;
[0009] In summary, the servers of existing intelligent AI computing systems have certain drawbacks in planning and do not meet people's requirements. To this end, we have developed a hardware equipment assembly planning device for intelligent AI computing systems. Summary of the invention
[0010] In order to overcome the shortcomings of the prior art, an embodiment of the present application provides an intelligent AI computing power system hardware equipment assembly planning device, which is equipped with an environmental simulation device, a test box and a refrigeration device. When in use, the intelligent AI computing power system hardware equipment works in the test box, and the external environment is applied to the test box through the environmental simulation device. The cooling capacity required to maintain the normal operation of the intelligent AI computing power system hardware equipment can be simulated, which provides a basis for the assembly planning of the intelligent AI computing power system hardware equipment, thereby facilitating a more reasonable configuration of the corresponding heat dissipation equipment in the subsequent period, and the overall use effect is good, and it has a good prospect for use.
[0011] The technical solution adopted by the embodiment of the present application to solve the technical problem is:
[0012] An intelligent AI computing system hardware equipment assembly planning device, comprising a device body, a test box and a refrigeration device;
[0013] The interior of the device body includes a refrigeration area and a testing area;
[0014] A test box used to detect the heat generated by the hardware equipment of the intelligent AI computing system. The test box is installed inside the test area;
[0015] The refrigeration equipment is installed in the refrigeration area to deliver cold air to the interior of the test box;
[0016] Wherein, an environmental simulation device for changing the external temperature of the test box is installed inside the test area and outside the test area.
[0017] The present invention records an assembly planning device for hardware equipment of an intelligent AI computing power system, in which an environmental simulation device, a test box and a refrigeration device are provided. When in use, the hardware equipment of the intelligent AI computing power system works in the test box, and the external environment is applied to the test box through the environmental simulation device, so as to simulate the refrigeration capacity required to maintain the normal operation of the hardware equipment of the intelligent AI computing power system, thereby providing a basis for the assembly planning of the hardware equipment of the intelligent AI computing power system, thereby facilitating a more reasonable configuration of the corresponding heat dissipation equipment in the subsequent process, and having a good overall use effect and a good prospect for use.
[0018] Preferably, the environmental simulation device comprises a heating rod and a temperature monitor;
[0019] The number of heating rods is several groups, and the heating rods are installed above or below the test box;
[0020] A temperature monitor for monitoring the temperature inside the test area, the temperature monitor is installed on the side wall of the test area;
[0021] Wherein, the temperature monitor is electrically connected to the heating rod.
[0022] Preferably, a partition plate is provided inside the test box, and the partition plate divides the inside of the test area into two groups of detection areas. The number of the refrigeration equipment is two groups, and the cold air outlet of the refrigeration equipment is connected to the detection area through a pipeline.
[0023] Preferably, a plurality of groups of support bars are fixedly mounted on the inner side wall of the test box, and the interval between two adjacent groups of support bars is the same as the thickness of the partition plate.
[0024] Preferably, the upper end position and the lower end position of the front end surface of the support bar are both inclined, and the interior of the detection area is equipped with a power connection component near the upper end position.
[0025] Preferably, the power connection assembly includes a mounting seat and a movable seat;
[0026] The mounting base is fixedly mounted on the inner wall of the detection area;
[0027] The movable seat is movably mounted on the mounting seat;
[0028] Among them, the movable seat is embedded with an interface component for powering the hardware equipment of the intelligent AI computing system.
[0029] Preferably, a cavity is provided inside the mounting seat, a strip opening connected to the cavity is provided on the side end surface of the mounting seat facing the movable seat, a moving part is arranged inside the cavity, and a connecting block connected to the moving part is arranged in the middle of the movable seat.
[0030] The present invention records an assembly planning device for hardware equipment of an intelligent AI computing power system, which records a test box. The internal partitions of the test box are arranged, and the internal space is adjustable. Combined with an environmental simulation device, it can better simulate the working environment of the hardware equipment of the intelligent AI computing power system. In addition, a power connection component is installed inside the test box. The position of the movable seat in the power connection component is adjustable, and the power connection of the hardware equipment of the intelligent AI computing power system can be completed outside the test box. The line connection is not affected by the internal space of the test box. It is convenient to use, has a good use effect, and has a good use prospect.
[0031] Preferably, the moving member includes a limit plate and a wire reel;
[0032] The limiting plate is arranged inside the cavity, and the connecting block is fixedly connected to one side of the limiting plate;
[0033] The cord reel is wound with an electric wire, and two ends of the electric wire are respectively connected with a power supply device and an interface component on the device body.
[0034] Preferably, a magnetic plate is provided at the rear end of the mounting seat, a metal plate magnetically attracted to the magnetic plate is installed at the rear end of the movable seat, a groove is provided on the front end surface of the magnetic plate, and an insertion block plugged into the groove is provided on the rear end surface of the movable seat, and after the reel is wound, the insertion block is inserted into the groove.
[0035] In summary, the present invention includes at least one of the following beneficial technical effects:
[0036] First, the present invention records an intelligent AI computing power system hardware equipment assembly planning device, which is provided with an environmental simulation device, a test box and a refrigeration device. When in use, the intelligent AI computing power system hardware equipment works in the test box, and the external environment is applied to the test box through the environmental simulation device, which can simulate the cooling capacity required to maintain the normal operation of the intelligent AI computing power system hardware equipment, and provide a basis for the assembly planning of the intelligent AI computing power system hardware equipment, so as to facilitate the subsequent more reasonable configuration of the corresponding heat dissipation equipment, and the overall use effect is good, and it has a good prospect for use.
[0037] Second, the present invention records an intelligent AI computing system hardware equipment assembly planning device, which records a test box. The internal partitions of the test box are set, and the internal space is adjustable. Combined with the environmental simulation device, it can better simulate the working environment of the intelligent AI computing system hardware equipment. In addition, a power connection component is installed inside the test box. The position of the movable seat in the power connection component is adjustable, and the power connection of the intelligent AI computing system hardware equipment can be completed outside the test box. The line connection is not affected by the internal space of the test box. It is convenient to use, the use effect is good, and it has a good prospect for use. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0039] Figure 2 This is the overall structural diagram of the present invention in the door-opening state;
[0040] Figure 3 It is a local structural diagram of the present invention;
[0041] Figure 4 It is a partial structural diagram of other angles in the present invention;
[0042] Figure 5 It is a partial internal structure diagram of the test box in the present invention;
[0043] Figure 6 It is a partial structural diagram of the power connection component in the present invention;
[0044] Figure 7 It is a structural diagram of the power connection component in the present invention in a pulled-out state;
[0045] Figure 8 It is a structural diagram of the movable seat in the present invention.
[0046] Figure numerals: 1. Device body; 2. Test box; 3. Refrigeration equipment; 4. Heating rod; 5. Temperature monitor; 6. Partition plate; 7. Mounting seat; 8. Movable seat; 9. Interface assembly; 10. Connecting block; 11. Limiting plate; 12. Cable reel; 13. Magnetic plate; 14. Strip mouth; 15. Support bar. DETAILED DESCRIPTION
[0047] The embodiment of the present application provides an intelligent AI computing system hardware equipment assembly planning device to solve the problem that the construction cost of the server of the existing intelligent AI computing system is relatively high. Therefore, when in use, old equipment is usually improved and old components are combined with new components, so that some parts of the constructed server are parts of old equipment, which makes the actual heat dissipation of the server much greater than the heat dissipation of the new equipment. The refrigeration equipment that meets the new equipment may not be able to meet the needs of the server, causing equipment damage.
[0048] Embodiment 1:
[0049] An intelligent AI computing system hardware equipment assembly planning device, such as Figure 1-5 As shown, it includes a device body 1, a test box 2 and a refrigeration device 3;
[0050] The interior of the device body 1 includes a refrigeration area and a testing area;
[0051] A test box 2 for detecting the working heat generation of the hardware equipment of the intelligent AI computing system, and the test box 2 is installed inside the test area;
[0052] The refrigeration device 3 is installed in the refrigeration area and is used to deliver cold air to the interior of the test box 2. The refrigeration device 3 uses existing refrigeration equipment, such as an air cooler, an air conditioner, etc. Since it is an existing device, it will not be described in detail here.
[0053] Among them, an environmental simulation device for changing the external temperature of the test box 2 is installed inside the test area and outside the test area. The external temperature of the test box 2 can be adjusted so that the inside of the test box 2 is close to the high temperature in summer, so the measurement is more accurate.
[0054] A controller is fixedly installed on the side end face of the device body 1. The controller is connected to the electronic equipment inside the device body 1, receives and processes data transmitted by the electronic equipment, and the cooling capacity of the refrigeration equipment 3 and the simulation temperature of the environmental simulation device can be set through the controller.
[0055] This controller applies the basic functions of existing controllers and is used in conjunction with an industrial computer. It belongs to the existing technology. This patent does not improve its structure, but only directly applies it. Therefore, no excessive description is given.
[0056] The present invention records an assembly planning device for hardware equipment of an intelligent AI computing power system, in which an environmental simulation device, a test box 2 and a refrigeration device 3 are provided. When in use, the hardware equipment of the intelligent AI computing power system works in the test box 2. The external environment is applied to the test box 2 through the environmental simulation device, which can simulate the refrigeration capacity required to maintain the normal operation of the hardware equipment of the intelligent AI computing power system, thereby providing a basis for the assembly planning of the hardware equipment of the intelligent AI computing power system, thereby facilitating a more reasonable configuration of the corresponding heat dissipation equipment in the subsequent process, and having a good overall use effect and a good prospect for use.
[0057] A temperature sensor is installed inside the test box 2 to monitor the temperature inside the test box 2 .
[0058] When in use, the intelligent AI computing power system hardware equipment is placed inside the test box 2, the relevant lines are connected, the environmental simulation device is started through the controller, the heating rod 4 in the environmental simulation device is started, the heating rod 4 works to generate temperature, and the outside of the test box 2 is heated up. At the same time, the temperature sensor is started to monitor the temperature inside the test box 2. When the temperature inside the test box 2 reaches the set temperature, the value of the temperature monitor 5 is recorded, and then the heating rod 4 is started intermittently to maintain the external temperature of the test box 2 constant. At this time, the intelligent AI computing power system hardware equipment is started and runs at full power. During the operation, the refrigeration equipment 3 is started to maintain the intelligent AI computing power system hardware equipment at a normal working temperature. The normal working heat generation of the intelligent AI computing power system hardware equipment can be fed back through the cooling capacity, thereby helping designers to better plan the specifications of the heat dissipation equipment.
[0059] Embodiment 2:
[0060] On the basis of Example 1, Figure 1-8 As shown, it also includes the following:
[0061] The environmental simulation device includes a heating rod 4 and a temperature monitor 5; the heating rod 4 is an electric heating rod;
[0062] The number of heating rods 4 is several groups, and the heating rods 4 are installed above or below the test box 2; the heating rods 4 heat, and the temperature monitor 5 monitors the temperature inside the test area to ensure that the temperature inside the test area is constant (representing the continuous temperature of the outside world, which is a fluctuation range) during subsequent testing. In this case, the measured data is more accurate;
[0063] A temperature monitor 5 for monitoring the internal temperature of the test area, the temperature monitor 5 is installed on the side wall of the test area;
[0064] Among them, the temperature monitor 5 is electrically connected to the heating rod 4. When the temperature monitored by the temperature monitor 5 is lower than the set lower limit value, a signal is sent to start the heating rod 4. When the temperature reaches the set upper limit value, a signal is sent to turn off the heating rod 4 to maintain the temperature in a relatively constant range.
[0065] A partition plate 6 is provided inside the test box 2, and the partition plate 6 divides the inside of the test area into two groups of detection areas. The number of refrigeration equipment 3 is two groups, and the cold air outlet of the refrigeration equipment 3 is connected with the detection area through a pipeline.
[0066] When in use, the refrigeration device 3 is connected to the detection area alone, and can measure two groups of intelligent AI computing system hardware devices at the same time.
[0067] The partition plate 6 is an insulation plate. Although the test box 2 will conduct temperature and there will be certain interference when measuring two sets of intelligent AI computing system hardware equipment at the same time, this part of the interference is small and the detected data deviation is small, so it has no impact.
[0068] A plurality of groups of support bars 15 are fixedly mounted on the inner wall of the test box 2 , and the interval between two adjacent groups of support bars 15 is the same as the thickness of the partition plate 6 .
[0069] Therefore, after the partition plate 6 is inserted between the support bars 15, it is fixed as a whole without being loose, and has high stability.
[0070] The upper end and the lower end of the front end surface of the support bar 15 are both inclined, which can facilitate the insertion of the partition plate 6. The interior of the detection area is installed near the upper end with power connection components to ensure the stable operation of the intelligent AI computing system hardware equipment.
[0071] The power connection assembly includes a mounting seat 7 and a movable seat 8;
[0072] The mounting seat 7 is fixedly mounted on the inner wall of the detection area; the movable seat 8 is movably mounted on the mounting seat 7;
[0073] Among them, an interface component 9 for powering the hardware equipment of the intelligent AI computing system is embedded on the movable seat 8.
[0074] The movable seat 8 is designed to be movable, so it is convenient to remove it, which is convenient for relevant technical personnel to connect lines in the outside.
[0075] A cavity is provided inside the mounting seat 7, a strip opening 14 connected to the cavity is provided on the side end surface of the mounting seat 7 facing the movable seat 8, a moving part is provided inside the cavity, and a connecting block 10 connected to the moving part is provided in the middle of the movable seat 8.
[0076] The connecting block 10 moves along the strip-shaped opening 14 , and the strip-shaped opening 14 has the effect of limiting the pay-off.
[0077] The present invention records an assembly planning device for hardware equipment of an intelligent AI computing power system, which records a test box 2. The internal partitions of the test box 2 are arranged, and the internal space is adjustable. Combined with an environmental simulation device, it can better simulate the working environment of the hardware equipment of the intelligent AI computing power system. In addition, a power connection component is installed inside the test box 2. The position of the movable seat 8 in the power connection component is adjustable, and the power connection of the hardware equipment of the intelligent AI computing power system can be completed outside the test box 2. The line connection is not affected by the internal space of the test box 2. It is convenient to use, has a good use effect, and has a good use prospect.
[0078] The moving part includes a limit plate 11 and a wire reel 12;
[0079] The limiting plate 11 is arranged inside the cavity, and the connecting block 10 is fixedly connected to one side of the limiting plate 11;
[0080] An electric wire is wound in the wire reel 12 , and two ends of the electric wire are respectively connected to a power supply device and an interface component 9 on the device body 1 .
[0081] A magnetic plate 13 is provided at the rear end of the mounting seat 7, a metal plate magnetically attracted to the magnetic plate 13 is installed at the rear end of the movable seat 8, a groove is provided on the front end surface of the magnetic plate 13, and an insert block plugged into the groove is provided on the rear end surface of the movable seat 8. After the reel 12 is wound, the insert block is plugged into the groove.
[0082] The wire reel 12 adopts the existing spiral spring structure, so the movable seat 8 can be pulled out. At this time, the wire is pulled out from the wire reel 12. After being released, the spiral spring resets, driving the movable seat 8 to move, so that the plug block on the rear end face of the movable seat 8 is inserted into the groove.
[0083] The structures of the magnetic plate 13, the insert block and the groove can ensure the stability of the movable seat 8, and the use effect is good.
[0084] When in use, pull out the movable seat 8, connect the line of the intelligent AI computing system hardware device to the interface component 9, and then place the intelligent AI computing system hardware device inside the test box 2 for testing.
[0085] Finally, it should be noted that: Obviously, the above embodiments are only examples for clearly explaining the present invention, and are not intended to limit the implementation methods. For ordinary technicians in the relevant field, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the scope of protection of the present invention.
Claims
1. An intelligent AI computing system hardware equipment assembly planning device, characterized in that: include: The device body (1) includes a refrigeration area and a testing area; A test box (2) for detecting the heat generated by the hardware equipment of the intelligent AI computing system, which is installed inside the test area; A refrigeration device (3), which is installed in the refrigeration zone and is used to deliver cold air to the interior of the test box (2); Wherein, an environmental simulation device for changing the external temperature of the test box (2) is installed inside the test area and outside the test area.
2. The intelligent AI computing system hardware equipment assembly planning device according to claim 1, characterized in that: The environmental simulation device comprises: Heating rods (4), which are provided in several groups and are installed above or below the test box (2); A temperature monitor (5) for monitoring the temperature inside the test area, which is installed on the side wall of the test area; Wherein, the temperature monitor (5) is electrically connected to the heating rod (4).
3. The intelligent AI computing system hardware equipment assembly planning device according to claim 2, characterized in that: The test box (2) is provided with a partition plate (6) inside, and the partition plate (6) divides the inside of the test area into two groups of detection areas. The number of the refrigeration equipment (3) is two groups, and the cold air outlet of the refrigeration equipment (3) is connected to the detection area through a pipeline.
4. The intelligent AI computing system hardware equipment assembly planning device according to claim 3, characterized in that: A plurality of groups of support bars (15) are fixedly mounted on the inner side wall of the test box (2), and the interval between two adjacent groups of support bars (15) is the same as the thickness of the partition plate (6).
5. The intelligent AI computing system hardware equipment assembly planning device according to claim 4, characterized in that: The upper end position and the lower end position of the front end surface of the support bar (15) are both inclined, and the interior of the detection area near the upper end position is equipped with an electrical connection component.
6. The intelligent AI computing system hardware equipment assembly planning device according to claim 5, characterized in that: The power connection assembly comprises: A mounting seat (7) fixedly mounted on the inner wall of the detection area; A movable seat (8) movably mounted on the mounting seat (7); Wherein, an interface component (9) for supplying power to the hardware device of the intelligent AI computing system is embedded on the movable seat (8).
7. The intelligent AI computing system hardware equipment assembly planning device according to claim 6, characterized in that: A cavity is provided inside the mounting seat (7), a strip-shaped opening (14) connected to the cavity is provided on the side end surface of the mounting seat (7) facing the movable seat (8), a moving part is provided inside the cavity, and a connecting block (10) connected to the moving part is provided in the middle of the movable seat (8).
8. The intelligent AI computing system hardware equipment assembly planning device according to claim 1, characterized in that: The moving part comprises: A limiting plate (11) is arranged inside the cavity, and the connecting block (10) is fixedly connected to a side surface of the limiting plate (11); A cord reel (12) is provided in which a cord is wound, and two ends of the cord are respectively connected to a power supply device and an interface component (9) on a device body (1).
9. The intelligent AI computing system hardware equipment assembly planning device according to claim 8, characterized in that: A magnetic attraction plate (13) is arranged at the rear end of the mounting seat (7), a metal plate magnetically attracted to the magnetic attraction plate (13) is installed at the rear end of the movable seat (8), a groove is provided on the front end surface of the magnetic attraction plate (13), and an insert block plugged into the groove is arranged on the rear end surface of the movable seat (8), and after the winding device (12) is wound, the insert block is plugged into the groove.
Citation Information
Patent Citations
An AI computing server
CN110069111B