Prefabricated energy-saving environment-friendly water-leakage-proof parapet wall convenient to install
By designing a prefabricated wall and an inner and outer splicing installation sealing mechanism, the lack of auxiliary structure and sealing problem during the installation of the wall is solved, and rapid positioning, stable installation and efficient sealing are achieved, and installation convenience and safety are improved.
Patent Information
- Application Number
- CN202411663399.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-20
- Publication Date
- 2025-03-25
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The lack of auxiliary installation splicing structure during the installation process of the daughter wall, which makes it impossible to quickly splice and build walls, and the edges cannot be effectively sealed, resulting in rainwater seepage, reducing installation convenience and sealing effect.
A prefabricated daughter's wall including mounting wall frames, filling walls, strengthening protective nets and waterproof shells is designed, using an inner and outer splicing type mounting sealing mechanism and an outer protective isolation mechanism. Through the mutual cooperation of these components, rapid positioning, stable installation and sealing effects are achieved.
It improves the convenience and stability of the installation and positioning of the daughter wall, enhances the sealing performance, prevents water leakage and seepage, and improves the safety and reliability of use.
Smart Images

Figure CN119686496A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building structures, in particular to a prefabricated energy-saving, environment-friendly and water-proof parapet wall which is easy to install. Background Art
[0002] The parapet is a low wall around the roof of a building. In addition to maintaining safety, it also has waterproof bricks at the bottom to prevent water seepage from the waterproof layer or rainwater from the roof from overflowing. The parapet on the roof is used to protect the safety of personnel and to decorate the facade of the building. The parapet on the roof that is not accessible to people is used to decorate the facade and also to fix the linoleum. For this purpose, a Chinese patent discloses a modular prefabricated parapet panel with application number 201721317469.3. The wall panel in the patent is made of concrete, has high strength and a firm connection effect, and can be disassembled and assembled;
[0003] At the same time, a Chinese patent discloses a modular prefabricated wall panel, application number 201710948260.5. The wall panels in the patent can be spliced to form the entire wall. They are concrete prefabricated wall panels with high strength. The wall panels are connected in a detachable manner through stud bolts and can be freely assembled and disassembled. The wall panels themselves are concrete structures with high strength. They have the advantages of both cast-in-place concrete and prefabricated panel houses.
[0004] However, due to the lack of corresponding auxiliary installation and splicing structures during the use of parapets, the parapets cannot be quickly spliced with the building walls during installation. At the same time, since the edges of the parapets cannot be effectively sealed, rainwater will penetrate into the gaps in the walls, thereby reducing the convenience of parapet installation and the sealing effect. Summary of the invention
[0005] The present invention provides a prefabricated energy-saving, environmentally friendly and leak-proof parapet that is easy to install, which can effectively solve the problem that the parapet proposed in the above background technology lacks a corresponding auxiliary installation splicing structure during use, resulting in the parapet being unable to be quickly spliced with the building wall during installation. At the same time, since the edge of the parapet cannot be effectively sealed, rainwater will penetrate into the gap between the wall, thereby reducing the convenience of parapet installation and the sealing effect.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install, comprising an installation wall frame, a filling wall is embedded and installed in the middle of the inner side of the installation wall frame, and both sides of the filling wall are bonded with a reinforced protective net, and a waterproof shell is bonded to the outer side of the reinforced protective net at a position corresponding to the inner side of the installation wall frame;
[0007] An internal and external splicing installation sealing mechanism is provided inside the installation wall frame, and the internal and external splicing installation sealing mechanism is used to splice and install the parapet wall and seal the gap during the splicing installation process;
[0008] The internal and external splicing installation sealing mechanism includes a splicing rectangular box;
[0009] A splicing rectangular box is installed on the bottom surface of the installation wall frame, a guide special-shaped groove is opened in the middle of the inner side of the splicing rectangular box, a connecting rectangular box is connected to the top of the guide special-shaped groove, a rectangular guide box is installed at the bottom of the inner side of the connecting rectangular box, a puncture glue injection tube is installed in the middle of the top of the rectangular guide box, and material guide rectangular grooves are evenly opened along the circumferential direction at the outer bottom of the puncture glue injection tube and the inner position of the rectangular guide box;
[0010] A fixed capsule is bonded to the middle of the top of the rectangular guide box, a glue injection sheet is embedded in the middle of the bottom of the fixed capsule, a counterweight pressing block is bonded to the top of the fixed capsule, and a limit knob is rotatably installed in the middle of the top of the counterweight pressing block;
[0011] A sealing rubber seat is bonded to the middle of the bottom end of the installation wall frame, a sealing front sheet is bonded to one side of the bottom surface of the sealing rubber seat, and sealing soft rubber strips are embedded and installed on both side edges of the bottom surface of the sealing front sheet.
[0012] Preferably, a sealing side convex strip is bonded to the middle of one side of the installation wall frame, an installation inner arc cavity is opened in the middle of the inner side of the sealing side convex strip, an isolation baffle is fixedly installed at a position corresponding to one side of the fixed capsule inside the filling wall, a separation blade is fixedly installed at the middle of the inner side of the isolation baffle, a connecting film is bonded to one side of the counterweight pressing block at a position corresponding to the side of the isolation baffle, and an extrusion slider is bonded to one side of the connecting film at a position corresponding to the side of the isolation baffle;
[0013] An extrusion capsule is bonded to the middle of the bottom surface of the extrusion slider, a liquid-conducting rectangular box is fixedly connected to the middle of the bottom end of the extrusion capsule, a small rubber-conducting tube is fixedly connected to the middle of one side of the liquid-conducting rectangular box, an expansion rubber strip is fixedly connected to the end of the small rubber-conducting tube at a position corresponding to the installation inside the inner arc cavity, and the expansion rubber strip is filled with a supporting sponge strip;
[0014] A splicing side concave strip is bonded to the middle of the other side of the installation wall frame, and reinforcing corner strips are embedded and installed at the two corners inside the splicing side concave strip. A splicing groove is opened in the middle of the side surface of the splicing side concave strip, and splicing circular grooves are opened through the middle of both sides of the sealing side convex strip and the splicing groove, and a limiting clamping strip is inserted into the inside of the splicing circular groove.
[0015] Preferably, the outer side of the waterproof housing is flush with the side of the mounting wall frame, and the bottom end of the spliced rectangular box is connected to the mounting wall frame by bolts.
[0016] Preferably, the outer side of the bottom of the puncture injection tube is tightly slidably fitted with the arc surface of the inner wall of the guide special-shaped groove, the bottom of the puncture injection tube is located inside the guide special-shaped groove, and the inner cavity of the puncture injection tube is connected with the inner cavity of the guide special-shaped groove through the material guide rectangular groove.
[0017] Preferably, the fixed capsule is filled with sealant, the top of the puncture injection tube is aligned with the injection sheet, the length of the limit knob is smaller than the length of the diagonal of the top surface of the counterweight pressing block, and the bottom surface of the limit knob is tightly fitted with the top surface of the installation wall frame.
[0018] Preferably, the side of the isolation baffle is tightly slidably fitted with the side of the counterweight pressing block, the side of the extrusion slider is tightly slidably fitted with the side of the isolation baffle, the connecting film passes through the narrow groove in the middle of the isolation baffle, and the fixed capsule and the extrusion capsule are filled with sealant.
[0019] Preferably, the sealing side convex strip and the splicing groove are correspondingly engaged with each other, the side surface of the sealing side convex strip and the side surface of the splicing groove are tightly fitted, and the inner wall of the splicing circular groove and the outer side of the limiting clamping strip are tightly fitted.
[0020] Preferably, an outer protective isolation mechanism is provided on the top of the installation wall frame, and the outer protective isolation mechanism is used to protect the side and top of the parapet wall and fill the gap between the side of the wall and the building wall;
[0021] The outer protection isolation mechanism includes a sealing top plate;
[0022] A sealing top plate is clamped on the top of the mounting wall frame, connecting bolts are installed through the middle of the top surface of the sealing top plate at both ends, and the tops of the two connecting bolts are fixedly connected to the connecting top plate at positions corresponding to the top of the sealing top plate, and the tops of the two ends of the connecting top plate are fixedly connected to the mounting side plates, and a protective rotating drum is rotatably installed between the two mounting side plates, and a protective inner net is embedded and installed inside the protective rotating drum;
[0023] A central mounting shaft is fixedly installed in the middle of both ends of the protective rotating cylinder, a mounting swivel is evenly sleeved on the outside of the central mounting shaft, a connecting rubber stick is evenly fixedly installed in the middle of the outer side of the mounting swivel along the circumferential direction, a reminder bell is fixedly connected to the end of the connecting rubber stick, and protective side bags are clamped on the sides of the sealing side convex strips and the sides of the splicing side concave strips.
[0024] Preferably, a gap is left between the bottom of the outer side of the protective drum and the top surface of the connecting top plate, and the outer side of the protective inner net is tightly fitted with the inner wall of the protective drum.
[0025] Preferably, a material injection port is provided on the top of the protective side bag, and sealing grooves are evenly opened on the outside of the protective side bag, and the side surfaces of the protective side bag are clamped by independent sealing side convex strips and splicing side concave strips.
[0026] Compared with the prior art, the present invention has the following beneficial effects: the present invention has a scientific and reasonable structure and is safe and convenient to use:
[0027] 1. An internal and external splicing installation sealing mechanism is provided. The mutual cooperation between the internal components of the internal and external splicing installation sealing mechanism optimizes the installation process of the parapet. The cooperation between the splicing rectangular box and the pre-buried installation nails on the roof, and the cooperation between the sealing side convex strips and the splicing side concave strips can quickly position the parapet wall, thereby effectively improving the convenience of the installation and positioning of the parapet. At the same time, the rigid cooperation between the splicing rectangular box and the installation nails makes the installation of the parapet more stable. The elastically deformable structural characteristics of the sealing side convex strips and the splicing side concave strips make the splicing of the side of the parapet faster and more convenient. The bottom surface of the parapet and the edge of the roof are waterproofed and sealed by the sealant seat and the sealing front piece, further improving the overall protective sealing performance of the parapet, effectively preventing the phenomenon of water leakage and water seepage during the use of the parapet after installation, and improving the safety of the use of the parapet.
[0028] At the same time, through the cooperation between the counterweight pressing block and the fixing capsule, the fixing glue can be evenly and quickly injected into the guide special-shaped groove to achieve rapid fixation of the parapet, and the bottom surface of the parapet is sealed by the cooperation between the fixing glue that penetrates into the bottom of the sealant seat and the sealing soft rubber strip, further improving the sealing between the bottom of the parapet and the building wall. At the same time, through the cooperation between the extrusion slider and the extrusion capsule, the expansion of the expansion rubber strip can be used to expand and extrude the sealing side convex strip, thereby improving the tightness of the side installation of the parapet, optimizing the injection process during the installation of the parapet, so that the parapet can be injected from the inside to the outside during the installation process, effectively avoiding the installation gap inside the parapet during the installation process, and further improving the reliability of the parapet installation;
[0029] In addition, through the linkage structural design between the counterweight pressing block and the extrusion slider, after the parapet is installed and positioned and the mechanical fixation between the splicing circular groove and the limit clip is completed, it is only necessary to turn the limit knob to use gravity to cooperate with the counterweight pressing block and the extrusion slider to complete the glue injection process. At the same time, the overall center of gravity of the parapet is driven downward during the sliding of the counterweight pressing block and the extrusion slider, which effectively improves the stability of the parapet after installation.
[0030] 2. An outer protection and isolation mechanism is set up. Through the mutual cooperation between the components inside the outer protection and isolation mechanism, the use process of the parapet after installation is optimized. Through the mutual cooperation between the protection drum and its internal components, the top of the parapet is protected, which effectively prevents the risk of falling when climbing to the top of the parapet during activities on the roof. In addition, the warning bell rings during the rotation of the protection drum to warn people close to the parapet through sound, further improving the safety of the parapet;
[0031] At the same time, the slots on the outside of the protective drum are protected by a protective inner net to prevent users' fingers from being inserted into the inside of the protective drum and causing damage. The side ends of the parapet are sealed and protected by protective side bags, which effectively prevents water seepage at the edges of the parapet during use, further improving the safety and sealing of the parapet.
[0032] To sum up, through the mutual cooperation between the inside and outside splicing installation sealing mechanism and the outside protective isolation mechanism, and through the mutual cooperation between the components inside the filling wall and the components on the top of the installation wall frame, the installation process and use process of the parapet are optimized, so that the parapet can be positioned, installed and fixed more quickly during the installation process. At the same time, by optimizing the fixing process and fixing method during the installation of the parapet, the installation of the parapet is faster and more reliable, and through the mutual cooperation between the protective drum and its internal components, the safety of the parapet during use is effectively improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0034] In the attached picture:
[0035] Figure 1 It is a schematic diagram of the structure of the present invention;
[0036] Figure 2 It is a structural schematic diagram of the installation of the reinforced protection net of the present invention;
[0037] Figure 3 It is a structural schematic diagram of the internal and external splicing installation sealing mechanism of the present invention;
[0038] Figure 4 It is a structural schematic diagram of the installation of the reinforced corner strip of the present invention;
[0039] Figure 5 It is a structural schematic diagram of the installation of the sealant seat of the present invention;
[0040] Figure 6 It is a structural schematic diagram of the installation of the puncture and injection hose of the present invention;
[0041] Figure 7 It is a structural schematic diagram of the installation of the rectangular guide box of the present invention;
[0042] Figure 8 It is a schematic diagram of the structure of the installation of the separation blade of the present invention;
[0043] Fig. 9 It is a structural schematic diagram of the outer protection isolation mechanism of the present invention;
[0044] Fig.10 It is a schematic diagram of the structure of the protective drum installation of the present invention;
[0045] Numbers in the figure: 1. Install wall frame; 2. Fill wall; 3. Strengthen protection net; 4. Waterproof shell;
[0046] 5. Internal and external splicing installation sealing mechanism; 501, splicing rectangular box; 502, guide special-shaped groove; 503, connecting rectangular box; 504, rectangular guide box; 505, puncture injection tube; 506, material guide rectangular groove; 507, fixed capsule; 508, injection sheet; 509, counterweight pressing block; 510, limit knob; 511, sealant seat; 512, sealing front sheet; 513, sealing soft rubber strip; 514, sealant Sealing side convex strip; 515, installing inner arc cavity; 516, isolating baffle; 517, separating blade; 518, connecting film; 519, squeezing slider; 520, squeezing capsule; 521, liquid guiding rectangular box; 522, glue guiding tube; 523, expanding rubber strip; 524, supporting sponge strip; 525, splicing side concave strip; 526, strengthening angle strip; 527, splicing groove; 528, splicing circular groove; 529, limiting card strip;
[0047] 6. Outer protective isolation mechanism; 601. Sealing top plate; 602. Connecting bolts; 603. Connecting top plate; 604. Installing side plates; 605. Protective rotating drum; 606. Protective inner net; 607. Center mounting shaft; 608. Installing swivel seat; 609. Connecting rubber stick; 610. Reminder bell; 611. Protective side bag. DETAILED DESCRIPTION
[0048] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0049] Example: Figure 1-10 As shown, the present invention provides a technical solution, a prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install, comprising an installation wall frame 1, a filling wall 2 is embedded and installed in the middle of the inner side of the installation wall frame 1, and a reinforced protective net 3 is bonded to both sides of the filling wall 2, and a waterproof shell 4 is bonded to the outer side of the reinforced protective net 3 at a position corresponding to the inner side of the installation wall frame 1;
[0050] An internal and external splicing installation sealing mechanism 5 is provided inside the installation wall frame 1, and the internal and external splicing installation sealing mechanism 5 is used to splice and install the parapet wall and seal the gap during the splicing installation process;
[0051] The internal and external splicing installation sealing mechanism 5 includes a splicing rectangular box 501, a guide special-shaped groove 502, a connecting rectangular box 503, a rectangular guide box 504, a puncture glue injection tube 505, a material guide rectangular groove 506, a fixing capsule 507, a glue injection sheet 508, a counterweight pressing block 509, a limit knob 510, a sealant seat 511, a sealing front sheet 512, a sealing soft rubber strip 513, a sealing side convex strip 514, an installation inner arc cavity 515, an isolation baffle 516, a separation blade 517, a connecting film 518, an extrusion slider 519, an extrusion capsule 520, a liquid guide rectangular box 521, a glue guide tube 522, an expansion rubber strip 523, a support sponge strip 524, a splicing side concave strip 525, a reinforcing angle strip 526, a splicing groove 527, a splicing circular groove 528 and a limit card strip 529;
[0052] A splicing rectangular box 501 is embedded and installed at a position corresponding to the inner part of the filling wall 2 on the bottom surface of the installation wall frame 1, the outer side of the waterproof shell 4 is flush with the side surface of the installation wall frame 1, and the bottom end of the splicing rectangular box 501 is connected to the installation wall frame 1 through bolts;
[0053] A guide special-shaped groove 502 is provided through the middle of the inner side of the splicing rectangular box 501, and a connecting rectangular box 503 is fixedly connected at the top of the guiding special-shaped groove 502 corresponding to the internal position of the filling wall 2, and a rectangular guide box 504 is slidably embedded and installed at the bottom of the inner side of the connecting rectangular box 503, and a puncture glue injection tube 505 is embedded and installed at the middle of the top of the rectangular guide box 504, and a material guiding rectangular groove 506 is evenly provided along the circumferential direction at the bottom of the outer side of the puncture glue injection tube 505 and the inner position of the rectangular guide box 504, and the outer side of the bottom of the puncture glue injection tube 505 is tightly slidably fitted with the arc surface of the inner wall of the guiding special-shaped groove 502, and the bottom of the puncture glue injection tube 505 is located inside the guiding special-shaped groove 502, and the inner cavity of the puncture glue injection tube 505 is connected with the inner cavity of the guiding special-shaped groove 502 through the material guiding rectangular groove 506;
[0054] A fixed capsule 507 is bonded to the middle of the top of the rectangular guide box 504, and a glue injection sheet 508 is embedded in the middle of the bottom of the fixed capsule 507. A counterweight pressing block 509 is bonded to the top of the fixed capsule 507 corresponding to the internal position of the filling wall 2. A limit knob 510 is rotatably installed in the middle of the top of the counterweight pressing block 509. The fixed capsule 507 is filled with sealant. The top of the puncture glue injection tube 505 is aligned with the glue injection sheet 508. The length of the limit knob 510 is less than the length of the diagonal line of the top surface of the counterweight pressing block 509. The bottom surface of the limit knob 510 is tightly fitted with the top surface of the installation wall frame 1.
[0055] A sealing rubber seat 511 is bonded to the middle of the bottom end of the installation wall frame 1, a sealing front sheet 512 is bonded to one side of the bottom surface of the sealing rubber seat 511, and sealing soft rubber strips 513 are embedded and installed on both sides of the bottom surface of the sealing front sheet 512;
[0056] A sealing side convex strip 514 is bonded to the middle of one side of the installation wall frame 1, and an installation inner arc cavity 515 is opened in the middle of the inner side of the sealing side convex strip 514. An isolation baffle 516 is fixedly installed at a position corresponding to one side of the fixed capsule 507 inside the filling wall 2, and a separation blade 517 is fixedly installed at the middle of the inner side of the isolation baffle 516. A connecting film 518 is bonded to one side of the counterweight pressing block 509 at a position corresponding to the side of the isolation baffle 516, and an extrusion slider 519 is bonded to one side of the connecting film 518 at a position corresponding to the side of the isolation baffle 516.
[0057] An extrusion capsule 520 is bonded to the middle of the bottom surface of the extrusion slider 519, a liquid-conducting rectangular box 521 is fixedly connected to the middle of the bottom end of the extrusion capsule 520, a small glue-conducting tube 522 is fixedly connected to the middle of one side of the liquid-conducting rectangular box 521, an expansion rubber strip 523 is fixedly connected to the end of the small glue-conducting tube 522 at a position corresponding to the installation inside the inner arc cavity 515, and the expansion rubber strip 523 is filled with a supporting sponge strip 524, the side of the isolation baffle 516 and the side of the counterweight pressing block 509 are tightly slidably fitted, the side of the extrusion slider 519 and the side of the isolation baffle 516 are tightly slidably fitted, the connecting film 518 runs through the narrow groove in the middle of the isolation baffle 516, and the fixed capsule 507 and the extrusion capsule 520 are both filled with sealant;
[0058] A splicing side groove strip 525 is bonded to the middle of the other side of the installation wall frame 1, and reinforcing corner strips 526 are embedded and installed at the two corners of the splicing side groove strip 525. A splicing groove 527 is opened in the middle of the side of the splicing side groove strip 525, and a splicing circular groove 528 is penetrated in the middle of both sides of the sealing side convex strip 514 and the splicing groove 527. A limiting clamping strip 529 is penetrated and clamped inside the splicing circular groove 528. The sealing side convex strip 514 and the splicing groove 527 are correspondingly clamped with each other, and the side of the sealing side convex strip 514 is tightly fitted with the side of the splicing groove 527, and the inner wall of the splicing circular groove 528 is tightly fitted with the outer side of the limiting clamping strip 529. The mutual cooperation between the internal components of the sealing mechanism 5 for internal and external splicing is optimized, and the installation process of the parapet is optimized by splicing the rectangular box 501 The cooperation with the pre-buried installation nails on the roof, and the cooperation between the sealing side convex strips 514 and the splicing side concave strips 525 can quickly position the parapet wall, thereby effectively improving the convenience of parapet installation and positioning. At the same time, the rigid cooperation between the splicing rectangular box 501 and the installation nails makes the parapet installation more stable. The elastically deformable structural characteristics of the sealing side convex strips 514 and the splicing side concave strips 525 make the splicing of the side of the parapet faster and more convenient. The bottom surface of the parapet and the edge of the roof are waterproofed by the sealing rubber seat 511 and the sealing front sheet 512, further improving the overall protective sealing performance of the parapet, effectively preventing the phenomenon of water leakage and seepage during the use of the parapet after installation, and improving the safety of the use of the parapet.
[0059] At the same time, through the mutual cooperation between the counterweight pressing block 509 and the fixing capsule 507, the fixing glue can be evenly and quickly injected into the guide special-shaped groove 502 to achieve rapid fixation of the parapet, and the bottom surface of the parapet is sealed by the mutual cooperation between the fixing glue infiltrated into the bottom of the sealing glue seat 511 and the sealing soft rubber strip 513, further improving the sealing between the bottom of the parapet and the building wall. At the same time, through the mutual cooperation between the extrusion slider 519 and the extrusion capsule 520, the expansion of the expansion rubber strip 523 can be used to expand and squeeze the sealing side convex strip 514, further improving the tightness of the side installation of the parapet, optimizing the injection process during the installation of the parapet, so that the parapet can be injected from the inside to the outside during the installation process, effectively avoiding the installation gap inside the parapet during the installation process, and further improving the reliability of the parapet installation.
[0060] And through the linkage structure design between the counterweight pressing block 509 and the extrusion slider 519, after the parapet is installed and positioned and the mechanical fixation between the splicing circular groove 528 and the limit clamping strip 529 is completed, it is only necessary to turn the limit knob 510 to use gravity to cooperate with the counterweight pressing block 509 and the extrusion slider 519 to complete the glue injection process. At the same time, the overall center of gravity of the parapet is moved downward during the sliding of the counterweight pressing block 509 and the extrusion slider 519, which effectively improves the stability of the parapet after installation.
[0061] The top of the installation wall frame 1 is provided with an outer protective isolation mechanism 6, which is used to protect the side and top of the parapet wall and fill the gap between the side of the wall and the building wall;
[0062] The outer protection isolation mechanism 6 includes a sealing top plate 601, a connecting bolt 602, a connecting top plate 603, a mounting side plate 604, a protection rotating cylinder 605, a protection inner net 606, a central mounting shaft 607, a mounting rotating seat 608, a connecting glue stick 609, a reminder bell 610 and a protection side bag 611;
[0063] A sealing top plate 601 is clamped on the top of the installation wall frame 1, and connecting bolts 602 are installed through the middle of the top of the sealing top plate 601 at both ends. A connecting top plate 603 is fixedly connected to the top of the two connecting bolts 602 corresponding to the top of the sealing top plate 601. The tops of the two ends of the connecting top plate 603 are fixedly connected to the tops of the two mounting side plates 604. A protective rotating cylinder 605 is rotatably installed between the two mounting side plates 604. A protective inner net 606 is embedded and installed inside the protective rotating cylinder 605. A gap is left between the bottom of the outer side of the protective rotating cylinder 605 and the top of the connecting top plate 603, and the outer side of the protective inner net 606 is tightly fitted with the inner wall of the protective rotating cylinder 605.
[0064] A central mounting shaft 607 is fixedly installed in the middle of both ends of the protective rotating cylinder 605, and a mounting rotating seat 608 is evenly sleeved on the outside of the central mounting shaft 607, and a connecting glue stick 609 is evenly fixedly installed in the middle of the outside of the mounting rotating seat 608 along the circumferential direction, and a reminder bell 610 is fixedly connected to the end of the connecting glue stick 609. The side of the sealing side convex strip 514 and the side of the splicing side concave strip 525 are both clamped with a protective side bag 611, and a material injection port is provided on the top of the protective side bag 611, and a sealing groove is evenly opened on the outside of the protective side bag 611. The side of the protective side bag 611 is connected by an independent The sealing side convex strip 514 and the splicing side concave strip 525 are clamped together, and the use process of the parapet after installation is optimized through the mutual cooperation between the internal components of the outer protective isolation mechanism 6. The top of the parapet is protected by the mutual cooperation between the protective rotating drum 605 and the internal components, which effectively prevents the risk of falling when climbing to the top of the parapet during activities on the roof. In addition, the warning bell 610 is driven to ring during the rotation of the protective rotating drum 605, so as to warn people close to the parapet through sound, thereby further improving the safety of the parapet.
[0065] At the same time, the slots on the outside of the protective drum 605 are protected by the protective inner net 606 to prevent the user's fingers from being inserted into the inside of the protective drum 605 and causing damage, and the side surfaces of the end of the parapet are sealed and protected by the protective side bags 611, which effectively prevents water seepage at the edges of the parapet during use, further improving the safety and sealing of the parapet.
[0066] Working principle and use process of the present invention: In the actual application process of the present invention, when using the parapet, it is necessary to first embed the installation nails on the top of the installation wall, fill the inside of the installation wall frame 1 through the filling wall 2, and then protect the outside of the filling wall 2 through the strengthening protection net 3 and the waterproof shell 4, so as to improve the overall structural strength of the parapet;
[0067] When the parapet needs to be installed on the roof of the building, it is necessary to first align the guide special-shaped groove 502 at the bottom of the splicing rectangular box 501 with the top of the embedded installation nail, and then put the splicing rectangular box 501 on the outside of the installation nail. As the installation nail is inserted into the guide special-shaped groove 502, when the top of the installation nail contacts the bottom of the puncture injection tube 505 inside the connecting rectangular box 503, the puncture injection tube 505 is guided by the rectangular guide box 504 so that the top of the puncture injection tube 505 can penetrate the injection sheet 508 and be inserted into the fixed capsule 507, so that the fixing glue inside the fixed capsule 507 can flow into the guide special-shaped groove 502 through the guide rectangular groove 506.
[0068] When it is necessary to squeeze out the fixing glue inside the fixing capsule 507, the limit on the top of the counterweight pressing block 509 is canceled by turning the limit knob 510, and then the counterweight pressing block 509 is gradually slid downward under the action of gravity, and then the fixing glue inside the fixing capsule 507 is evenly squeezed into the guide special-shaped groove 502 by the descent of the counterweight pressing block 509, and the gap between the installation nail and the guide special-shaped groove 502 is filled, and after the fixing glue solidifies, the splicing rectangular box 501 is fixedly connected to the installation nail;
[0069] After the fixing glue completely fills the inside of the guide special-shaped groove 502, some glue will overflow from the bottom thereof. The fixing glue overflowing from the bottom of the guide special-shaped groove 502 gradually fills the gap between the bottom surface of the sealing glue seat 511 and the top surface of the building wall, and at the same time seals the gap between the side surface of the sealing front sheet 512 and the building wall, thereby achieving sealing of the bottom of the parapet.
[0070] When the side of the parapet needs to be spliced and installed, the sealing side convex strip 514 on the side of the adjacent installation wall frame 1 can be inserted into the installed splicing side concave strip 525, and the side of the sealing side convex strip 514 is tightly fitted with the inner wall of the splicing groove 527, and the corners of the splicing side concave strip 525 are strengthened by reinforcing the corner strip 526 to improve the overall structural strength of the splicing side concave strip 525, and then the limiting card strip 529 is inserted into the splicing circular groove 528, thereby realizing the limiting between the sealing side convex strip 514 and the splicing side concave strip 525;
[0071] In the process of the counterweight pressing block 509 sliding down, the connecting film 518 drives the extrusion slider 519 to move downward synchronously, and the connecting film 518 is cut off by the separation blade 517 inside the isolation baffle 516 during the downward movement of the extrusion slider 519, and after the connecting film 518 is completely cut off, the extrusion slider 519 continues to fall under the action of gravity, and squeezes the extrusion capsule 520 downward, so that the fixing glue inside the extrusion capsule 520 is introduced into the liquid guiding rectangular box 521, and then The fixing glue in the liquid-guiding rectangular box 521 is introduced into the expansion rubber strip 523 through the rubber guiding tube 522, and the expansion rubber strip 523 is driven to expand and increase after the pressure inside the expansion rubber strip 523 increases. At the same time, the expansion rubber strip 523 is supported by the supporting sponge strip 524. After the expansion rubber strip 523 expands, the sealing side convex strip 514 is driven to expand outward, so that the sealing side convex strip 514 and the inner wall of the splicing side concave strip 525 are more closely fitted, further improving the sealing performance of the side connection of the parapet wall;
[0072] When the top and side connections of the parapet need to be sealed, the connecting top plate 603 and the components thereon are installed to the top of the installation wall frame 1 through the sealing top plate 601 and the connecting bolts 602, and then the side of the protective rotating drum 605 is limited by the installation side plate 604, so that when a person standing next to the parapet touches the top of the wall, the protective rotating drum 605 can be directly driven to rotate, and the side gap of the protective rotating drum 605 is protected by the protective inner net 606 to prevent external debris from entering the inside of the protective rotating drum 605;
[0073] And during the rotation of the protective drum 605, the central installation shaft 607 can be driven to rotate synchronously, and during the rotation of the central installation shaft 607, the installation swivel seat 608 and the connecting glue stick 609 can be driven to rotate synchronously, and during the rotation of the connecting glue stick 609, the reminder bell 610 can be driven to shake and make a sound, thereby reminding people near the wall through the sound of the reminder bell 610, and at the same time, the ends of the two sides of the installation wall frame 1 are protected by the spliced and installed protective side bags 611, so that the side of the parapet fits more closely with the protective iron sheet of the roof or the end wall, so as to improve the waterproof performance of the end side of the installation wall frame 1.
[0074] Finally, it should be noted that the above description is only a preferred example of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A prefabricated energy-saving, environmentally friendly and water-proof parapet that is easy to install, comprising an installation wall frame (1), characterized in that: A filling wall (2) is embedded and installed in the middle of the inner side of the installation wall frame (1), and a reinforced protection net (3) is bonded to both sides of the filling wall (2), and a waterproof shell (4) is bonded to the outer side of the reinforced protection net (3) at a position corresponding to the inner side of the installation wall frame (1); The installation wall frame (1) is provided with an internal and external splicing installation sealing mechanism (5), and the internal and external splicing installation sealing mechanism (5) is used to splice and install the parapet wall and seal the gap during the splicing installation process; The inner and outer splicing installation sealing mechanism (5) comprises a splicing rectangular box (501); A splicing rectangular box (501) is installed on the bottom surface of the installation wall frame (1), a guide special-shaped groove (502) is opened in the middle of the inner side of the splicing rectangular box (501), a connecting rectangular box (503) is connected to the top of the guide special-shaped groove (502), a rectangular guide box (504) is installed at the bottom of the inner side of the connecting rectangular box (503), a puncture glue injection tube (505) is installed in the middle of the top of the rectangular guide box (504), and material guiding rectangular grooves (506) are evenly opened along the circumferential direction at the outer bottom of the puncture glue injection tube (505) and the inner position of the rectangular guide box (504); A fixed capsule (507) is bonded to the middle of the top end of the rectangular guide box (504), a glue injection sheet (508) is embedded and installed in the middle of the bottom end of the fixed capsule (507), a counterweight pressing block (509) is bonded to the top end of the fixed capsule (507), and a limit knob (510) is rotatably installed in the middle of the top end of the counterweight pressing block (509); A sealing rubber seat (511) is bonded to the middle of the bottom end of the installation wall frame (1), a sealing front plate (512) is bonded to one side of the bottom surface of the sealing rubber seat (511), and sealing soft rubber strips (513) are embedded and installed on both side edges of the bottom surface of the sealing front plate (512).
2. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 1 is characterized in that: A sealing side convex strip (514) is bonded to the middle of one side of the installation wall frame (1), and an installation inner arc cavity (515) is provided in the middle of the inner side of the sealing side convex strip (514); an isolation baffle (516) is fixedly installed at a position corresponding to one side of the fixed capsule (507) inside the filling wall (2); a separation blade (517) is fixedly installed at the middle of the inner side of the isolation baffle (516); a connecting film (518) is bonded to one side of the counterweight pressing block (509) at a position corresponding to the side of the isolation baffle (516); and an extrusion slider (519) is bonded to one side of the connecting film (518) at a position corresponding to the side of the isolation baffle (516); A squeezing capsule (520) is bonded to the middle of the bottom surface of the squeezing slider (519), a liquid-conducting rectangular box (521) is fixedly connected to the middle of the bottom end of the squeezing capsule (520), a small rubber-conducting tube (522) is fixedly connected to the middle of one side of the liquid-conducting rectangular box (521), an expansion rubber strip (523) is fixedly connected to the end of the small rubber-conducting tube (522) at a position corresponding to the internal installation position of the inner arc cavity (515), and the expansion rubber strip (523) is filled with a supporting sponge strip (524); A splicing side groove strip (525) is bonded to the middle of the other side of the installation wall frame (1), and reinforcing corner strips (526) are embedded and installed at both corners of the splicing side groove strip (525). A splicing groove (527) is provided in the middle of the side surface of the splicing side groove strip (525), and splicing circular grooves (528) are provided through the middle of both sides of the sealing side convex strip (514) and the splicing groove (527), and a limiting clamping strip (529) is inserted and clamped inside the splicing circular groove (528).
3. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 1 is characterized in that: The outer side of the waterproof housing (4) is flush with the side of the mounting wall frame (1), and the bottom end of the spliced rectangular box (501) is connected to the mounting wall frame (1) via bolts.
4. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 1 is characterized in that: The outer side of the bottom of the puncture injection tube (505) is tightly slidably fitted with the arc surface of the inner wall of the guide special-shaped groove (502), the bottom of the puncture injection tube (505) is located inside the guide special-shaped groove (502), and the inner cavity of the puncture injection tube (505) is connected to the inner cavity of the guide special-shaped groove (502) through the material guiding rectangular groove (506).
5. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 1 is characterized in that: The fixing capsule (507) is filled with sealant, the top end of the puncture injection tube (505) and the injection sheet (508) are aligned with each other, the length of the limit knob (510) is less than the length of the diagonal line of the top surface of the counterweight pressing block (509), and the bottom surface of the limit knob (510) is tightly fitted with the top surface of the installation wall frame (1).
6. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 2 is characterized in that: The side of the isolation baffle (516) is tightly slidably fitted with the side of the counterweight pressing block (509), and the side of the extrusion slider (519) is tightly slidably fitted with the side of the isolation baffle (516). The connecting film (518) passes through the narrow groove in the middle of the isolation baffle (516), and the interior of the fixing capsule (507) and the extrusion capsule (520) are both filled with sealant.
7. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 2 is characterized in that: The sealing side convex strip (514) and the splicing groove (527) are correspondingly engaged with each other, the side surface of the sealing side convex strip (514) and the side surface of the splicing groove (527) are tightly fitted, and the inner wall of the splicing circular groove (528) and the outer side of the limiting clamping strip (529) are tightly fitted.
8. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 1 is characterized in that: An outer protective isolation mechanism (6) is arranged on the top of the installation wall frame (1), and the outer protective isolation mechanism (6) is used to protect the side and top of the parapet wall and fill the gap between the side of the wall and the building wall; The outer protective isolation mechanism (6) comprises a sealing top plate (601); The top of the installation wall frame (1) is clamped with a sealing top plate (601), and connecting bolts (602) are installed through the middle of the top surface of the sealing top plate (601) at both ends. The tops of the two connecting bolts (602) are fixedly connected with a connecting top plate (603) at positions corresponding to the tops of the sealing top plate (601), and the tops of the two ends of the connecting top plate (603) are fixedly connected with mounting side plates (604), and a protective rotating drum (605) is rotatably installed between the two mounting side plates (604), and a protective inner net (606) is embedded and installed inside the protective rotating drum (605); A central installation shaft (607) is fixedly installed in the middle of both ends of the protective rotating cylinder (605), and a mounting rotating seat (608) is evenly and equidistantly sleeved on the outside of the central installation shaft (607). A connecting rubber stick (609) is evenly and equidistantly fixedly installed in the middle of the outside of the mounting rotating seat (608) along the circumferential direction, and a reminder bell (610) is fixedly connected to the end of the connecting rubber stick (609). The side of the sealing side convex strip (514) and the side of the splicing side concave strip (525) are both clamped with a protective side bag (611).
9. The prefabricated energy-saving and environmentally friendly water-proof parapet that is easy to install according to claim 8, characterized in that: A gap is left between the outer bottom of the protective rotating cylinder (605) and the top surface of the connecting top plate (603), and the outer side of the protective inner net (606) is tightly fitted to the inner wall of the protective rotating cylinder (605).
10. The prefabricated energy-saving and environment-friendly water-proof parapet that is easy to install according to claim 8, characterized in that: The top of the protective side bag (611) is provided with a material injection port, and the outer side of the protective side bag (611) is evenly provided with sealing grooves, and the side of the protective side bag (611) is clamped by an independent sealing side convex strip (514) and a splicing side concave strip (525).
Citation Information
Cited By
Heat-preservation and energy-saving building component
CN120401730A