Airtight waterproof process for wire processing and detection method
By adopting airtight waterproofing processes in online material processing, including clamping, cleaning, blow-drying, coating of polyurethane and testing, the problem of wires being damp in humid environments is solved, and insulation performance and equipment safety are improved.
Patent Information
- Application Number
- CN202311213844.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-20
- Publication Date
- 2025-03-25
AI Technical Summary
Existing wires are prone to moisture in humid environments, resulting in degradation of insulation performance and affecting the safety and reliability of electrical equipment.
A wire processing airtight waterproofing process is adopted, including preparing the wire body and installing a connector, and processing the surface of the wire body with clamping components, cleaning components, moving components, scraping components and testing components. The specific steps include cleaning, blow-drying, coating of polyurethane and airtightness detection.
Through this process, the main body of the wire is not easily damp in a humid environment, and the insulation performance remains stable, which improves the safety and reliability of electrical equipment, and ensures the airtightness and waterproof performance of the wire.
Smart Images

Figure CN119694679A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of wire material processing, and in particular to an airtight and waterproof process and a detection method for wire material processing. Background Art
[0002] Wire usually refers to a single or a few wires, which can be bare wires or wires with insulation. Wire can be flexibly bent and arranged, suitable for a variety of simple electrical connections. Wire is often used for simpler electrical connections, such as household circuits, small electronic devices, etc. Wire is generally short in length and can be cut as needed when used.
[0003] When existing wires are used for circuit transmission, traditional wires are easily affected by moisture in a humid environment, resulting in a decrease in the insulation performance of the insulation layer, which in turn affects the safety and reliability of electrical equipment. For example, insulating tapes and heat shrink tubing are used, but these methods have the problems of complex processing, high cost, and poor waterproof effect. Therefore, a wire processing airtight waterproof process and detection method are proposed. Summary of the invention
[0004] The object of the present invention is to provide an airtight and waterproof process and a detection method for wire processing to solve the problems raised in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solution: a wire processing airtight waterproof process, comprising the following steps:
[0006] S1. Prepare the wire body and install connectors on both ends of the wire body;
[0007] S2. Clamping a plurality of wire bodies using a clamping assembly;
[0008] S3, using a cleaning component to clean the outer skins of the plurality of wire bodies;
[0009] S4. Under the action of the moving component, the wire body is moved, and the surface of the wire body is dried by using a blower and an air knife while moving;
[0010] S5, using a scraping component to immerse and coat the surface of the wire body with polyurethane, and scraping off excess polyurethane on the surface of the wire body;
[0011] S6. Use the detection component to perform air tightness detection on the wire body after immersion and coating with polyurethane.
[0012] Preferably, the clamping assembly described in S2 includes two second electric push rods, a second clamping frame is fixed to the push rod end of the second electric push rod, a first clamping frame is provided on the upper side of the second clamping frame, and a plurality of sealing rings which are sleeved on the outside of the connector are bonded to one side of the first clamping frame and the second clamping frame.
[0013] Preferably, the cleaning component described in S3 includes a first motor and a first water tank, the first water tank is rotatably connected to a first rotating shaft and a plurality of second rotating shafts through sealed bearings, one end of the first rotating shaft is fixed to the output shaft end of the first rotating shaft, and a plurality of bristles are fixedly inserted into the outer sides of the first rotating shaft and the second rotating shaft.
[0014] Preferably, a first gear is fixedly sleeved on the outer side of the first rotating shaft, a second gear is fixed at the axis of one end of the second rotating shaft, the first gear is meshed with the second gear, and the second gears are meshed with each other.
[0015] Preferably, the moving component in S4 includes a second motor, a first screw is fixed to the output shaft end of the second motor, the first screw is threadedly connected to a support frame, a first sliding rod is movably passed through one side of the support frame, a first electric push rod is fixed to the bottom of the support frame, and a cross plate is fixed to the push rod end of the first electric push rod.
[0016] Preferably, the scraping assembly in S5 comprises a third motor and a dipping box, the inside of the dipping box is filled with polyurethane, a second screw is fixed to the output shaft end of the third motor, and a connecting frame is threadedly connected to the outer side of the second screw.
[0017] Preferably, a second sliding rod is movably penetrated through one side of the connecting frame, and a scraper slidably connected to the outer side of the wire body is fixed to one side of the bottom of the connecting frame.
[0018] Preferably, the detection component described in S6 includes a second water tank, and a first rubber fixing frame and a second rubber fixing frame are respectively installed on the inner wall of the second water tank, one side of the first rubber fixing frame and the second rubber fixing frame are respectively sleeved on the outside of the connector, one side of the first rubber fixing frame is connected to a pressure gauge through an air pipe, and the air inlet end of the pressure gauge is connected to a compressor through the air pipe.
[0019] Preferably, an operating table is provided on one side of the wire body, the bottoms of the first motor, the first water tank, the fan and the dipping box are fixed to the top of the operating table, the first sliding bar and one side of the second motor are fixed to one side of the top of the operating table, the air inlet end of the wind knife is installed on the air outlet end of the fan, the bottoms of the third motor and the second electric push rod are fixed to the top of the cross plate, and the top of the first clamping frame is fixed to the bottom of the cross plate.
[0020] The present invention also provides a method for detecting the airtight and waterproof process of wire processing, comprising the following steps:
[0021] Step 1: Test preparation: Place the first rubber fixing frame and the second rubber fixing frame on the outside of the second water tank respectively, so that the inner sides of the first rubber fixing frame and the second rubber fixing frame are not in contact with water, start the compressor at the same time, and set the inflation pressure and pressure holding time;
[0022] Step 2: Air tightness test: insert the connectors at both ends of the wire body into the inner sides of the first rubber fixing frame and the second rubber fixing frame respectively, and then place the first rubber fixing frame, the second rubber fixing frame and the wire body into the inner side of the second water tank;
[0023] Step 3: Visual inspection: the high-pressure gas generated by the compressor enters the inside of the first rubber fixing frame. The staff can visually inspect the inside of the second water tank for 2-4 seconds. When there are no bubbles in the second water tank, the wire body can be taken out, proving that the wire body has good air tightness.
[0024] Compared with the prior art, the present invention adopts the above technical scheme and has the following technical effects: the present invention processes the airtight waterproof layer on the surface of the wire body through a cleaning component, a moving component, a scraping component, a clamping component and a detection component, and can immerse and coat the surfaces of multiple wire bodies with polyurethane at one time, thereby avoiding the problem that the wire body is damp in a humid environment and causing the insulation performance of the wire body to decrease, and improving the safety and reliability of the wire body during electrical connection after immersion coating. At the same time, under the action of the polyurethane coating, the airtightness and waterproof performance of the wire body are guaranteed during use. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0026] Figure 1 It is a schematic diagram of the main structure of the present invention;
[0027] Figure 2 It is a schematic diagram of the main cross-sectional structure of the present invention;
[0028] Figure 3 It is a schematic diagram of the cross-sectional structure of the horizontal plate of the present invention;
[0029] Figure 4 It is a schematic diagram of the gear meshing structure of the present invention;
[0030] Figure 5It is a schematic diagram of the front view structure of the first clamping frame of the present invention;
[0031] Figure 6 It is a schematic diagram of the front view structure of the connecting frame of the present invention;
[0032] Figure 7 It is a schematic diagram of the three-dimensional structure of the horizontal plate of the present invention;
[0033] Figure 8 It is a schematic diagram of the cross-sectional structure of the detection component of the present invention.
[0034] Description of reference numerals: 1. operating table; 2. connector; 3. wire body; 4. fan; 5. wind knife; 6. cleaning assembly; 61. first motor; 62. first gear; 63. first rotating shaft; 64. first water tank; 65. bristles; 66. second gear; 67. second rotating shaft; 7. moving assembly; 71. support frame; 72. first slide rod; 73. second motor; 74. first electric push rod; 75. horizontal plate; 76. first screw rod; 8. scraping assembly Parts; 81, the third motor; 82, the dipping box; 83, polyurethane; 84, the connecting frame; 85, the second screw rod; 86, the second sliding rod; 87, the scraper; 9, the clamping assembly; 91, the second electric push rod; 93, the first clamping frame; 94, the second clamping frame; 95, the sealing ring; 10, the detection assembly; 1001, the second water tank; 1002, the first rubber fixing frame; 1003, the second rubber fixing frame; 1004, the compressor; 1005, the barometer. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0036] It should be noted that when an element is referred to as being "fixed on" or "set on" another element, it can be directly on the other element or indirectly set on the other element; when an element is referred to as being "connected to" another element, it can be directly connected to the other element or indirectly connected to the other element.
[0037] It should be understood that the terms "length", "width", "up", "down", "front", "back", "first", "second", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0038] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, "multiple" and "several" mean two or more, unless otherwise clearly and specifically defined.
[0039] It should be noted that the structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the conditions under which this application can be implemented. Therefore, they have no substantive technical significance. Any structural modification, change in proportional relationship or adjustment of size should still fall within the scope of the technical content disclosed in this application without affecting the effects and purposes that can be achieved by this application.
[0040] Example
[0041] See also Figure 1-8 The present invention provides a technical solution: a wire processing airtight waterproof process, comprising the following steps:
[0042] S1, prepare the wire body 3, and install the connectors 2 at both ends of the wire body 3;
[0043] S2, using the clamping assembly 9 to clamp the plurality of wire bodies 3;
[0044] S3, using the cleaning assembly 6 to clean the outer skins of the plurality of wire bodies 3;
[0045] S4. Under the action of the moving component 7, the wire body 3 is moved, and the fan 4 and the wind knife 5 are used to dry the surface of the wire body 3 during the movement;
[0046] S5, using the scraping assembly 8 to immerse and coat the surface of the wire body 3 with polyurethane 83, and scraping off excess polyurethane 83 on the surface of the wire body 3;
[0047] S6. Use the detection component 10 to perform air tightness detection on the wire body 3 after being immersed in and coated with polyurethane 83 .
[0048] In S2, the clamping assembly 9 includes two second electric push rods 91, and a second clamping frame 94 is fixed to the push rod end of the second electric push rod 91. A first clamping frame 93 is provided on the upper side of the second clamping frame 94. A plurality of sealing rings 95 that are sleeved on the outer side of the connector 2 are bonded to one side of the first clamping frame 93 and the second clamping frame 94. The first clamping frame 93 is attached to one side of the second clamping frame 94, and the outer side of the connector 2 is sealed by the sealing ring 95. At this time, multiple wire bodies 3 can be straightened and clamped and fixed at the bottom of the horizontal plate 75, and multiple wire bodies 3 can be clamped and fixed at one time.
[0049] In S3, the cleaning component 6 includes a first motor 61 and a first water tank 64. The first water tank 64 is rotatably connected to a first rotating shaft 63 and a plurality of second rotating shafts 67 through sealed bearings. One end of the first rotating shaft 63 is fixed to the output shaft end of the first rotating shaft 63. The first rotating shaft 63 drives the first gear 62 to rotate. Under the meshing connection between the first gear 62 and the second gear 66, the plurality of second rotating shafts 67 rotate. A plurality of bristles 65 are fixedly inserted into the outer sides of the first rotating shaft 63 and the second rotating shaft 67. The first rotating shaft 63 is fixedly sleeved with the first gear 62 and the second rotating shaft 67. A second gear 66 is fixed at the axis of one end. The first gear 62 is meshed with the second gear 66. The bristles 65 clean the outer surface of the wire body 3. The power of the first motor 61 drives the plurality of bristles 65 to rotate, so that the bristles 65 clean the surface of the wire body 3, thereby improving the cleanliness of the surface of the wire body 3. The second gears 66 are meshed with each other.
[0050] In S4, the moving component 7 includes a second motor 73, a first screw rod 76 is fixed to the output shaft end of the second motor 73, the first screw rod 76 is threadedly connected to the support frame 71, a first sliding rod 72 is movably penetrated through one side of the support frame 71, a first electric push rod 74 is fixed to the bottom of the support frame 71, and a cross plate 75 is fixed to the push rod end of the first electric push rod 74. During the movement, the fan 4 transports wind to the inner side of the wind knife 5, blows out gas through the wind knife 5, and blows off the water remaining on the surface of the wire body 3.
[0051] In S5, the scraping assembly 8 includes a third motor 81 and a dipping box 82, the inside of the dipping box 82 is filled with polyurethane 83, a second screw 85 is fixed to the output shaft end of the third motor 81, and the outer side of the second screw 85 is threadedly connected to a connecting frame 84, the outer sides of multiple wire bodies 3 at the bottom of the cross plate 75 are immersed in the inner side of the polyurethane 83 inside the dipping box 82 for a certain period of time, so that the polyurethane 83 is fully coated on the outer side of the wire body 3, a second sliding rod 86 is movably penetrated on one side of the connecting frame 84, and a scraper 87 slidably connected to the outer side of the wire body 3 is fixed on one side of the bottom of the connecting frame 84, the push rod end of the first electric push rod 74 is controlled to retract, so that the wire body 3 is located on the upper side of the dipping box 82, and then the third motor 81 is started, so that the output shaft of the third motor 81 drives the second screw 85 to rotate, so that the connecting frame 84 drives the scraper 87 to move back and forth along the second sliding rod 86, and the excess polyurethane 83 at the bottom of the wire body 3 is scraped off.
[0052] In S6, the detection component 10 includes a second water tank 1001, and the inner wall of the second water tank 1001 is respectively installed with a first rubber fixing frame 1002 and a second rubber fixing frame 1003, one side of the first rubber fixing frame 1002 and the second rubber fixing frame 1003 are respectively sleeved on the outside of the connector 2, one side of the first rubber fixing frame 1002 is connected to a pressure gauge 1005 through an air pipe, and the air inlet end of the pressure gauge 1005 is connected to a compressor 1004 through an air pipe. The staff visually observes the inside of the second water tank 1001 for 3 seconds, and uses the pressure difference to detect whether the wire body 3 has a leak, please refer to Figure 8 When there are no bubbles on the outside of the wire body 3, the wire body 3 can be taken out, and the air tightness of the wire body 3 can be determined to be qualified. An operating table 1 is provided on one side of the wire body 3, and the bottoms of the first motor 61, the first water tank 64, the fan 4 and the dipping box 82 are fixed to the top of the operating table 1, and one side of the first sliding bar 72 and the second motor 73 are fixed to one side of the top of the operating table 1. The air inlet end of the wind knife 5 is installed on the air outlet end of the fan 4, the bottoms of the third motor 81 and the second electric push rod 91 are fixed to the top of the cross plate 75, and the top of the first clamping frame 93 is fixed to the bottom of the cross plate 75. By installing multiple components on the top of the operating table 1, it is more convenient to carry out airtight waterproof layer processing on the wire body 3.
[0053] Working principle: when it is necessary to process the waterproof layer on the outside of the wire body 3, first prepare a plurality of wire bodies 3, place the connectors 2 at both ends of the plurality of wire bodies 3 on the inner side of the second clamping frame 94 respectively, then control the push rod end of the second electric push rod 91 to retract, so that the first clamping frame 93 is attached to one side of the second clamping frame 94, and the outer side of the connector 2 is sealed by the sealing ring 95, at this time, the plurality of wire bodies 3 can be straightened and clamped and fixed at the bottom of the horizontal plate 75, and the plurality of wire bodies 3 can be clamped and fixed at one time;
[0054] Then, the push rod end of the first electric push rod 74 is controlled to push the cross plate 75 downward, so that the outer sides of the plurality of wire bodies 3 enter the first water tank 64. A certain amount of water is injected into the first water tank 64 in advance. The output shaft of the first motor 61 is controlled to drive the first rotating shaft 63 to rotate. At the same time, the first rotating shaft 63 drives the first gear 62 to rotate. Under the meshing connection between the first gear 62 and the second gear 66, the plurality of second rotating shafts 67 rotate. At this time, the first rotating shaft 63 and the second rotating shaft 67 drive the plurality of bristles 65 to rotate. When the bristles 65 contact the wire body 3, the bristles 65 clean the outer surface of the wire body 3. The power of the first motor 61 drives the plurality of bristles 65 to rotate, so that the bristles 65 clean the surface of the wire body 3, thereby improving the cleanliness of the surface of the wire body 3 and preventing the dirt on the surface of the wire body 3 from affecting the processing of the airtight waterproof layer.
[0055] When the outer side of the wire body 3 is cleaned, the output shaft of the second motor 73 drives the first screw rod 76 to rotate, so that the support frame 71 moves to the right along the first slide bar 72, and finally the multiple wire bodies 3 move to the upper side of the dipping box 82. During the movement, the fan 4 delivers wind to the inner side of the wind knife 5, and the wind knife 5 blows out gas to blow off the water remaining on the surface of the wire body 3, so as to avoid the water remaining on the surface of the wire body 3 after cleaning, which affects the effect of the subsequent immersion coating of the wire body 3;
[0056] The push rod end of the first electric push rod 74 is controlled to extend, so that the outer sides of the plurality of wire bodies 3 at the bottom of the cross plate 75 are immersed in the inner side of the polyurethane 83 inside the dipping box 82 for a certain period of time, so that the polyurethane 83 is fully coated on the outer sides of the wire bodies 3, and then the push rod end of the first electric push rod 74 is controlled to retract, so that the wire bodies 3 are located on the upper side of the dipping box 82, and then the third motor 81 is started, so that the output shaft of the third motor 81 drives the second screw rod 85 to rotate, so that the connecting frame 84 drives the scraper 87 to reciprocate along the second slide bar 86, and the excess polyurethane 83 at the bottom of the wire bodies 3 is scraped off, and after the polyurethane 83 is dried, the push rod end of the second electric push rod 91 is controlled to extend, and then the wire bodies 3 are removed;
[0057] Insert the connectors 2 at both ends of the wire body 3 into one side of the first rubber fixing frame 1002 and the second rubber fixing frame 1003 respectively, then start the compressor 1004, and control the gas pressure of the compressor 1004 through the pressure gauge 1005. The staff visually observes the inside of the second water tank 1001 for 3 seconds and uses the pressure difference to detect whether there is any leakage in the wire body 3. When there are no bubbles on the outside of the wire body 3, the wire body 3 can be taken out, and the air tightness of the wire body 3 can be determined to be qualified.
[0058] The surface of the wire body 3 is processed with an airtight waterproof layer through the cleaning component 6, the moving component 7, the scraping component 8, the clamping component 9 and the detection component 10, and the surfaces of multiple wire bodies 3 can be immersed in polyurethane 83 at one time to prevent the wire body 3 from getting damp in a humid environment, which causes the insulation performance of the wire body 3 to decrease. The safety and reliability of the wire body 3 during electrical connection after immersion coating are improved. At the same time, under the action of the polyurethane 83 coating, the airtightness and waterproof performance of the wire body 3 during use are guaranteed.
[0059] The present invention also provides a method for detecting the airtight and waterproof process of wire processing, comprising the following steps:
[0060] Step 1: Test preparation: Place the first rubber fixing frame 1002 and the second rubber fixing frame 1003 on the outside of the second water tank 1001 respectively, so that the inner sides of the first rubber fixing frame 1002 and the second rubber fixing frame 1003 are not in contact with water, and start the compressor 1004 at the same time, and set the inflation pressure and pressure holding time;
[0061] Step 2: Air tightness test: insert the connectors 2 at both ends of the wire body 3 into the inner sides of the first rubber fixing frame 1002 and the second rubber fixing frame 1003 respectively, and then place the first rubber fixing frame 1002, the second rubber fixing frame 1003 and the wire body 3 inside the second water tank 1001;
[0062] Step 3: Visual inspection: the high-pressure gas generated by the compressor 1004 enters the inside of the first rubber fixing frame 1002. The staff can visually inspect the inside of the second water tank 1001 for 3 seconds. When there are no bubbles in the second water tank 1001, the wire body 3 can be taken out, which proves that the wire body 3 has good air tightness.
[0063] So far, the embodiments of the present invention have been described in detail in conjunction with the accompanying drawings. It should be noted that the implementation methods not shown or described in the drawings or the body of the specification are all forms known to ordinary technicians in the relevant technical field and are not described in detail. In addition, the above definitions of each component are not limited to the various specific structures, shapes or methods mentioned in the embodiments, and ordinary technicians in the field can simply change or replace them.
[0064] It will be appreciated by those skilled in the art that the features described in the various embodiments and / or claims of the present invention may be combined and / or combined in various ways, even if such combinations and / or combinations are not explicitly described in the present invention. In particular, the features described in the various embodiments and / or claims of the present invention may be combined and / or combined in various ways without departing from the spirit and teachings of the present invention. All of these combinations and / or combinations fall within the scope of the present invention.
[0065] The specific embodiments described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a specific embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A wire processing airtight waterproof process, characterized in that: The steps include: S1. Prepare a wire body (3), and install connectors (2) on both ends of the wire body (3); S2, using a clamping assembly (9) to clamp the plurality of wire bodies (3); S3, using a cleaning component (6) to clean the outer skins of the plurality of wire bodies (3); S4. Under the action of the moving component (7), the wire body (3) is moved, and the fan (4) and the wind knife (5) are used to dry the surface of the wire body (3) while the wire body (3) is moved; S5, using a scraping assembly (8) to immerse and coat the surface of the wire body (3) with polyurethane (83), and scraping off excess polyurethane (83) on the surface of the wire body (3); S6. Use the detection component (10) to perform air tightness detection on the wire body (3) after being immersed in the polyurethane coating (83).
2. The wire processing airtight and waterproof process according to claim 1, characterized in that: In S2, the clamping assembly (9) includes two second electric push rods (91), a second clamping frame (94) is fixed to the push rod end of the second electric push rod (91), a first clamping frame (93) is provided on the upper side of the second clamping frame (94), and a plurality of sealing rings (95) which are sleeved on the outer side of the connector (2) are bonded to one side of the first clamping frame (93) and the second clamping frame (94).
3. The wire processing airtight and waterproof process according to claim 2, characterized in that: In S3, the cleaning component (6) includes a first motor (61) and a first water tank (64); the first water tank (64) is rotatably connected to a first rotating shaft (63) and a plurality of second rotating shafts (67) through sealed bearings; one end of the first rotating shaft (63) is fixed to the output shaft end of the first rotating shaft (63); and a plurality of bristles (65) are fixedly inserted into the outer sides of the first rotating shaft (63) and the second rotating shaft (67).
4. The wire processing airtight and waterproof process according to claim 3, characterized in that: A first gear (62) is fixedly sleeved on the outer side of the first rotating shaft (63); a second gear (66) is fixed at the axis of one end of the second rotating shaft (67); the first gear (62) is meshedly connected with the second gear (66); and the second gears (66) are meshedly connected with each other.
5. The wire processing airtight and waterproof process according to claim 3, characterized in that: In S4, the moving component (7) includes a second motor (73), a first screw rod (76) is fixed to the output shaft end of the second motor (73), the first screw rod (76) is threadedly connected to a support frame (71), a first sliding rod (72) is movably passed through one side of the support frame (71), a first electric push rod (74) is fixed to the bottom of the support frame (71), and a cross plate (75) is fixed to the push rod end of the first electric push rod (74).
6. The wire processing airtight and waterproof process according to claim 5, characterized in that: In S5, the scraping assembly (8) includes a third motor (81) and a dipping box (82), the inside of the dipping box (82) is filled with polyurethane (83), a second screw rod (85) is fixed to the output shaft end of the third motor (81), and the outer side of the second screw rod (85) is threadedly connected to a connecting frame (84).
7. The wire processing airtight and waterproof process according to claim 6, characterized in that: A second sliding rod (86) is movably penetrated through one side of the connecting frame (84), and a scraper (87) is fixed on one side of the bottom of the connecting frame (84) and is slidably connected to the outside of the wire body (3).
8. The wire material processing airtight and waterproof process according to claim 6, characterized in that: In S6, the detection component (10) comprises a second water tank (1001), the inner wall of the second water tank (1001) is respectively mounted with a first rubber fixing frame (1002) and a second rubber fixing frame (1003), one side of the first rubber fixing frame (1002) and the second rubber fixing frame (1003) are respectively sleeved on the outer side of the connector (2), one side of the first rubber fixing frame (1002) is connected to a pressure gauge (1005) via an air pipe, and an air inlet end of the pressure gauge (1005) is connected to a compressor (1004) via an air pipe.
9. The wire processing airtight and waterproof process according to claim 8, characterized in that: An operating table (1) is provided on one side of the wire body (3); the bottoms of the first motor (61), the first water tank (64), the fan (4) and the dipping box (82) are fixed to the top of the operating table (1); one side of the first sliding bar (72) and the second motor (73) are fixed to one side of the top of the operating table (1); the air inlet end of the air knife (5) is installed on the air outlet end of the fan (4); the bottoms of the third motor (81) and the second electric push rod (91) are fixed to the top of the cross plate (75); and the top of the first clamping frame (93) is fixed to the bottom of the cross plate (75).
10. A method for detecting the airtight and waterproof process of wire processing according to any one of claims 1 to 9, characterized in that: The steps include: Step 1: Test preparation: Place the first rubber fixing frame (1002) and the second rubber fixing frame (1003) on the outside of the second water tank (1001) respectively, so that the inside of the first rubber fixing frame (1002) and the second rubber fixing frame (1003) are not in contact with water, and start the compressor (1004) at the same time, and set the inflation pressure and pressure holding time; Step 2: Air tightness test: insert the connectors (2) at both ends of the wire body (3) into the inner sides of the first rubber fixing frame (1002) and the second rubber fixing frame (1003), respectively, and then place the first rubber fixing frame (1002), the second rubber fixing frame (1003) and the wire body (3) into the inner side of the second water tank (1001); Step 3: Visual inspection: the high-pressure gas generated by the compressor (1004) enters the inside of the first rubber fixing frame (1002). The staff can visually inspect the inside of the second water tank (1001) for 2-4 seconds. When there are no bubbles in the second water tank (1001), the wire body (3) can be taken out, which proves that the wire body (3) has good air tightness.
Citation Information
Cited By
Waterproof connector airtightness detection method and system
CN122217559A