Tire base oil immersion device and oil immersion method for modified asphalt waterproof coiled material

By designing the tire-based oil immersion device of the pre-impregnation tank and the main immersion tank, the coverage of two modified asphalts is achieved, which solves the problem of insufficient coverage of modified asphalt in the prior art, improves the performance of the waterproof coil and simplifies the production process.

CN119702334APending Publication Date: 2025-03-28YUNNAN XINCHENG WATERPROOF TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411862438.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-03-28

AI Technical Summary

Technical Problem

The existing tire-based oil-immersion device of modified asphalt waterproof roll cannot complete the processing problem of two different modified asphalt covering the tire-based surface.

Method used

A tire-based oil immersion device including a pre-impregnation tank and a main dipping tank is designed. Through the pre-impregnation and secondary immersion process, two complementary modified bitumen are coated on the tire-based surface, and a compatibilizer is selectively sprayed with a spraying mechanism to ensure the optimal adhesion effect of the modified bitumen.

Benefits of technology

The effective coverage of two modified asphalts is achieved, the performance of waterproof rolls is improved, and the performance requirements of general waterproof rolls are exceeded. At the same time, the production process is simplified and the demand for asphalt modification is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119702334A_ABST
    Figure CN119702334A_ABST
Patent Text Reader

Abstract

The invention discloses a tire base oil immersion device of a modified asphalt waterproof coiled material, which comprises a pre-immersion pool and a main immersion pool which are arranged in sequence, asphalt input ports of the pre-immersion pool and the main immersion pool are respectively connected with a first modified asphalt storage tank and a second modified asphalt storage tank, and the pre-immersion pool and the main immersion pool are respectively arranged in a pre-immersion box body and a main immersion box body. The presoaking box body is communicated with the main soaking box body through a material passing channel, spraying mechanisms are uniformly arranged in the material passing channel, limiting roller type cloth feeding mechanisms are arranged in the presoaking pool and the main soaking pool, a tire base heating roller is arranged at a feeding port of the presoaking pool, and a tire base heating roller is arranged at a discharging port of the main soaking pool. The discharging end of the tire base heating roller is connected with the feeding end of a limiting roller type cloth feeding mechanism in the presoaking pool, and the discharging end of the presoaking pool and the discharging end of the main soaking pool are each provided with a redundant asphalt scraping mechanism. The processing problem that an existing base oil immersion device of the modified asphalt waterproof coiled material cannot cover the surface of a base with two different kinds of modified asphalt is solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of waterproof coiled material processing, in particular to a base oiling device and an oiling method for a modified asphalt waterproof coiled material. Background Art

[0002] When making modified asphalt waterproofing membranes, base and modified asphalt are used. During processing, the modified asphalt needs to be coated on the surface of the base, and then it is subjected to processes such as lamination and embossing to finally prepare the corresponding waterproofing membrane products. In the prior art, soaking the base with modified asphalt is very simple, that is, the base is sent into the asphalt pool so that its surface is soaked with modified asphalt. Such a process is simple, but for those who want to produce waterproofing membranes with better quality, such soaking and covering are not enough, because a single modified asphalt adheres to the surface of the base and there will be more or less certain defects. The prior art generally improves the base as much as possible through modification. There is a way to improve this defect, but there is a method that can skip the complicated modification process, and the performance of the modified asphalt waterproof membrane produced may be better than the further modified asphalt waterproof membrane. This method is to coat two complementary modified asphalts in layers on the surface of the base. At present, this method has not been seen. In order to use this method to make modified asphalt waterproof membranes, it is necessary to transform the existing production line of modified asphalt waterproof membranes. For this reason, this scheme proposes a base oil immersion device for modified asphalt waterproof membranes that can adapt to this method and a method for oil immersion using the same. Summary of the invention

[0003] The purpose of the present invention is to provide a modified asphalt waterproofing membrane base oiling device and oiling method to solve the problem that the existing modified asphalt waterproofing membrane base oiling device cannot complete the processing of covering the base surface with two different modified asphalts.

[0004] In order to solve the above technical problems, the present invention adopts the following technical solutions: A base oiling device for a modified asphalt waterproofing coiled material comprises a pre-impregnation tank and a main impregnation tank which are arranged in sequence, the asphalt input ports of the pre-impregnation tank and the main impregnation tank being connected to a first modified asphalt storage tank and a second modified asphalt storage tank respectively, the pre-impregnation tank and the main impregnation tank being arranged in a pre-impregnation box and a main impregnation box respectively, the pre-impregnation box and the main impregnation box being connected through a material transfer channel, spraying mechanisms being evenly arranged in the material transfer channel, the pre-impregnation tank and the main impregnation tank being both provided with a limiting roller type cloth feeding mechanism, a base heating roller being provided at the feed port of the pre-impregnation tank, the discharge end of the base heating roller being connected to the feed end of the limiting roller type cloth feeding mechanism in the pre-impregnation tank, and the discharge ends of the pre-impregnation tank and the main impregnation tank being provided with a redundant asphalt scraping mechanism.

[0005] The prepared tire base is sent to the pre-impregnation tank for pre-impregnation. The tire base needs to be heated before pre-impregnation. After the immersion is completed, the initial coating of modified asphalt in the No. 1 modified asphalt storage tank is coated on both sides. The excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. The secondary modified asphalt immersion After the soaking is completed, the excess asphalt scraping mechanism of the main immersion tank is used to scrape off the excess modified asphalt to complete the immersion of the tire base. In this way, two complementary modified asphalts can be coated on the surface of the tire base, so that it can achieve performance that ordinary waterproof membranes cannot achieve. The reason why excess asphalt scraping mechanisms are set at the discharge ends of the pre-immersion tank and the main immersion tank is because they themselves have to be coated with two layers of modified asphalt, so their thickness must be strictly controlled. The main purpose of heating the tire base before pre-immersion is to fully discharge the moisture in the tire base through heating, and to make the adhesion effect between the tire base and the modified asphalt better.

[0006] As a further preferred embodiment of the present invention, a prepreg box body temperature control system and a main impregnation box body temperature control system are respectively provided in the prepreg box body and the main impregnation box body.

[0007] Because different modified asphalts require different temperatures to achieve the best adhesion effect, a pre-impregnation box temperature control system and a main impregnation box temperature control system are set up here. By adjusting the temperature separately, the best adhesion effect can be achieved regardless of whether it is during pre-impregnation or main impregnation.

[0008] As a further preferred embodiment of the present invention, the spray head of the spraying mechanism is connected to the spraying tank through a pumping pipeline.

[0009] Common types of modified asphalt include SBS modified asphalt, SBR modified asphalt, APP modified asphalt, PE modified asphalt and PA modified asphalt. When different types of modified asphalt are mixed, compatibility and mixing ratio need to be considered, because different modified asphalts may repel or split each other. For example, when SBR modified asphalt and SBS modified asphalt are mixed, corresponding compatibilizers need to be selected to ensure that the mixed modified asphalt can meet the expected performance requirements. Therefore, the nozzle of the spraying mechanism can spray the corresponding preparation on the surface of the pre-impregnated modified asphalt after pre-impregnation, so that the material can be well coated with the second modified asphalt after entering the main immersion tank, so that the two modified asphalts can be more harmoniously integrated and used to form complementary performance. The feed channel and the spraying mechanism structure in the feed channel are necessary for the production of this mixed modified asphalt waterproof membrane, and are also unique to it.

[0010] As a further preferred embodiment of the present invention, the spray tank is provided with an electric heating mechanism.

[0011] The temperature of the sprayed preparation can be controlled, which is more conducive to its rapid combination reaction with modified asphalt.

[0012] As a further preferred embodiment of the present invention, a deviation correction mechanism is provided between the tire base heating roller and the limiting roller type cloth feeding mechanism in the prepreg tank and at the discharge port of the material transfer channel.

[0013] It can correct the deviation during production, because sometimes the tire base may shift during movement, and it needs to be corrected to ensure quality. The reason why the correction mechanism is set between the tire base heating roller and the limiting roller feeding mechanism in the pre-impregnation tank is because the correction before pre-impregnation is the most timely, and then a correction mechanism is also set at the discharge port of the feed channel. One is to enable more precise control during the main immersion, and the other is because the discharge port of the feed channel is far away from the pre-impregnation tank. At this time, the asphalt in the pre-impregnation tank has been relatively stably attached to the tire base surface, and it is not easy for the modified asphalt in the pre-impregnation tank to be rubbed off the tire base due to the correction mechanism.

[0014] As a further preferred embodiment of the present invention, the correcting mechanism includes a main support roller and a correcting roller. The correcting roller is obliquely arranged at the two ends of the main support roller, and the correcting roller is inclined upward from the inside to the outside. The two ends of the rotating shaft of the correcting roller are connected to the correcting roller base through a rotating seat, one end of the correcting roller base is rotatably connected to the fixed surface of the correcting mechanism, and the bottom surface of the other end of the correcting seat is hinged to the top of the telescopic rod of the hydraulic cylinder, and the hydraulic cylinder is hinged to the fixed surface of the correcting mechanism.

[0015] The inclination angle of the deviation correction roller can be adjusted through the telescopic rod of the hydraulic cylinder, so that it can better adapt to the tire base and better complete the deviation correction work.

[0016] As a further preferred embodiment of the present invention, the excess asphalt scraping mechanism includes an extrusion scraping roller and a scraping roller cleaning mechanism, the extrusion scraping roller includes an upper movable extrusion roller and a lower fixed extrusion roller, the upper movable extrusion roller can move in a vertical direction, and an excess asphalt scraping channel is left between the upper movable extrusion roller and the lower fixed extrusion roller, the scraping roller cleaning mechanism includes an upper cleaning rubber scraper and a lower cleaning rubber scraper, and the upper cleaning rubber scraper and the lower cleaning rubber scraper are respectively arranged close to the upper movable extrusion roller and the lower fixed extrusion roller.

[0017] The scraping thickness can be adjusted by adjusting the distance between the upper movable squeezing roller and the lower fixed squeezing roller, and the upper cleaning rubber scraper and the lower cleaning rubber scraper can keep the surfaces of the upper movable squeezing roller and the lower fixed squeezing roller clean.

[0018] As a further preferred embodiment of the present invention, the material transfer channel is "U"-shaped, and guide rollers are provided at the turning points in the middle of the material transfer channel.

[0019] The "U"-shaped material transfer channel not only serves to isolate the heat transfer between the prepreg box and the main prepreg box, but also avoids the problem that when feeding horizontally, the preparation sprayed by the spraying mechanism at the bottom cannot be well combined with the modified asphalt due to the effect of gravity. The material transfer channel adopts a "U"-shaped structure, so during transportation, the tire base is in a vertical state most of the time. At this time, the spraying mechanism is located on both sides of the material, and the sprayed preparation can be well combined with the modified asphalt on the surface of the material.

[0020] The method for oiling the base of the modified asphalt waterproofing membrane described in any one of the above-mentioned items comprises the following steps: A. sending the prepared base to a pre-impregnation tank for pre-impregnation, and the base needs to be heated before pre-impregnation; B. after the immersion is completed, the initial coating of the modified asphalt in the No. 1 modified asphalt storage tank is coated on both sides, and the excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank, and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank; C. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. After the secondary modified asphalt immersion is completed, the excess modified asphalt is scraped off by the excess asphalt scraping mechanism in the main immersion tank to complete the base immersion work.

[0021] It is a new method for producing modified asphalt waterproofing membrane. The modified asphalt waterproofing membrane produced by this method does not require excessive modification of the asphalt, is simpler, and uses improved production equipment for production. The modified asphalt waterproofing membrane produced is of high quality and good performance.

[0022] Compared with the prior art, the present invention can achieve at least one of the following beneficial effects: 1. Send the prepared tire base into the pre-impregnation tank for pre-impregnation. The tire base needs to be heated before pre-impregnation. After the immersion is completed, the initial coating of modified asphalt in the No. 1 modified asphalt storage tank is coated on both sides. The excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. The secondary modified asphalt After the soaking is completed, the excess asphalt scraping mechanism of the main soaking tank is used to scrape off the excess modified asphalt to complete the tire base soaking work. In this way, two complementary modified asphalts can be coated on the tire base surface, so that it can achieve performance that ordinary waterproof membranes cannot achieve. The reason why excess asphalt scraping mechanisms are set at the discharge ends of the pre-immersion tank and the main soaking tank is because they themselves have to be coated with two layers of modified asphalt, so their thickness must be strictly controlled. The main purpose of heating the tire base before pre-immersion is to fully discharge the moisture in the tire base through heating, and to make the adhesion effect between the tire base and the modified asphalt better.

[0023] 2. Because different modified asphalts require different temperatures to achieve the best adhesion effect, a pre-impregnation box temperature control system and a main impregnation box temperature control system are set up here. By adjusting the temperature separately, the best adhesion effect can be achieved regardless of whether it is during pre-impregnation or main impregnation.

[0024] 3. The temperature of the sprayed preparation can be controlled, which is more conducive to its rapid combination reaction with modified asphalt.

[0025] 4. It can correct the deviation during production, because sometimes the tire base may shift during movement. In order to ensure quality, it needs to be corrected. The reason why the correction mechanism is set between the tire base heating roller and the limiting roller feeding mechanism in the pre-impregnation tank is because the correction before pre-impregnation is the most timely. Then a correction mechanism is also set at the discharge port of the feed channel. One is to enable more precise control during the main immersion, and the other is because the discharge port of the feed channel is far away from the pre-impregnation tank. At this time, the asphalt in the pre-impregnation tank has been relatively stably attached to the tire base surface, and it is not easy to rub the modified asphalt in the pre-impregnation tank off the tire base due to the correction mechanism.

[0026] 5. The inclination angle of the correction roller can be adjusted through the telescopic rod of the hydraulic cylinder, which can better adapt to the tire base and better complete the correction work.

[0027] 6. The scraping thickness can be adjusted by adjusting the distance between the upper movable squeezing roller and the lower fixed squeezing roller. The upper cleaning rubber scraper and the lower cleaning rubber scraper can keep the surface of the upper movable squeezing roller and the lower fixed squeezing roller clean.

[0028] 7. The U-shaped material transfer channel not only isolates the heat transfer between the prepreg box and the main impregnation box, but also avoids the problem that when feeding horizontally, the preparation sprayed by the spraying mechanism at the bottom cannot be well combined with the modified asphalt due to gravity. The material transfer channel adopts a "U"-shaped structure, so during transportation, the tire base is in a vertical state most of the time. At this time, the spraying mechanism is located on both sides of the material, and the sprayed preparation can be well combined with the modified asphalt on the surface of the material.

[0029] 8. It is a new method for producing modified asphalt waterproofing membrane. The modified asphalt waterproofing membrane produced by this method does not need to modify the asphalt excessively, which is simpler. In addition, it uses improved production equipment for production. The modified asphalt waterproofing membrane produced is of high quality and good performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1 It is a structural schematic diagram of the present invention.

[0031] Figure 2 It is a schematic structural diagram of the material transfer channel of the present invention.

[0032] Figure 3 It is a structural schematic diagram of the deviation correction mechanism of the present invention. DETAILED DESCRIPTION

[0033] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0034] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features of the embodiments may be combined with each other.

[0036] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0037] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the invention is usually placed when in use, or the positions or positional relationships commonly understood by those skilled in the art, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0038] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. Specific embodiment 1: Figure 1 , Figure 2 , Figure 3 A base oil impregnation device for a modified asphalt waterproofing membrane is shown, comprising a pre-impregnation tank 1 and a main impregnation tank 2 which are arranged in sequence, the asphalt input ports of the pre-impregnation tank 1 and the main impregnation tank 2 are respectively connected to a first modified asphalt storage tank and a second modified asphalt storage tank, the pre-impregnation tank 1 and the main impregnation tank 2 are respectively arranged in a pre-impregnation box 3 and a main impregnation box 4, the pre-impregnation box 3 and the main impregnation box 4 are connected through a feed passage 5, a spraying mechanism 6 is evenly arranged in the feed passage 5, a limiting roller feeding mechanism is provided in the pre-impregnation tank 1 and the main impregnation tank 2, a base heating roller 7 is provided at the feed port of the pre-impregnation tank 1, the discharge end of the base heating roller 7 is connected to the feed end of the limiting roller feeding mechanism in the pre-impregnation tank 1, and an excess asphalt scraping mechanism 8 is also provided at the discharge end of the pre-impregnation tank 1 and the main impregnation tank 2.

[0040] The prepared tire base is sent to the pre-impregnation tank for pre-impregnation. The tire base needs to be heated before pre-impregnation. After the immersion is completed, the initial coating of modified asphalt in the No. 1 modified asphalt storage tank is coated on both sides. The excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. The secondary modified asphalt immersion After the soaking is completed, the excess asphalt scraping mechanism of the main immersion tank is used to scrape off the excess modified asphalt to complete the immersion of the tire base. In this way, two complementary modified asphalts can be coated on the surface of the tire base, so that it can achieve performance that ordinary waterproof membranes cannot achieve. The reason why excess asphalt scraping mechanisms are set at the discharge ends of the pre-immersion tank and the main immersion tank is because they themselves have to be coated with two layers of modified asphalt, so their thickness must be strictly controlled. The main purpose of heating the tire base before pre-immersion is to fully discharge the moisture in the tire base through heating, and to make the adhesion effect between the tire base and the modified asphalt better. Specific embodiment 2: This embodiment further describes the prepreg box and the main impregnation box on the basis of the specific embodiment 1. The prepreg box 3 and the main impregnation box 4 are respectively provided with a prepreg box temperature control system and a main impregnation box temperature control system.

[0042] Because different modified asphalts require different temperatures to achieve the best adhesion effect, a pre-impregnation box temperature control system and a main impregnation box temperature control system are set up here. By adjusting the temperature separately, the best adhesion effect can be achieved regardless of whether it is during pre-impregnation or main impregnation. Specific embodiment 3: This embodiment further illustrates the spraying mechanism on the basis of the specific embodiment 1. The spray head of the spraying mechanism 6 is connected to the spraying tank through a pumping pipeline.

[0044] Common types of modified asphalt include SBS modified asphalt, SBR modified asphalt, APP modified asphalt, PE modified asphalt and PA modified asphalt. When different types of modified asphalt are mixed, compatibility and mixing ratio need to be considered, because different modified asphalts may repel or split each other. For example, when SBR modified asphalt and SBS modified asphalt are mixed, corresponding compatibilizers need to be selected to ensure that the mixed modified asphalt can meet the expected performance requirements. Therefore, the nozzle of the spraying mechanism can spray the corresponding preparation on the surface of the pre-impregnated modified asphalt after pre-impregnation, so that the material can be well coated with the second modified asphalt after entering the main immersion tank, so that the two modified asphalts can be more harmoniously integrated and used to form complementary performance. The feed channel and the spraying mechanism structure in the feed channel are necessary for the production of this mixed modified asphalt waterproof membrane, and are also unique to it. Specific embodiment 4: This embodiment further illustrates the spray tank based on the specific embodiment 3, and the spray tank is provided with an electric heating mechanism.

[0046] The temperature of the sprayed preparation can be controlled, which is more conducive to its rapid combination reaction with modified asphalt. Specific embodiment 5: This embodiment is based on the specific embodiment 1 and is provided with a correction mechanism. A correction mechanism 9 is provided between the tire base heating roller 7 and the limiting roller type cloth feeding mechanism in the prepreg tank 1 and at the discharge port of the material transfer channel 5.

[0048] It can correct the deviation during production, because sometimes the tire base may shift during movement, and it needs to be corrected to ensure quality. The reason why the correction mechanism is set between the tire base heating roller and the limiting roller feeding mechanism in the pre-impregnation tank is because the correction before pre-impregnation is the most timely, and then a correction mechanism is also set at the discharge port of the feed channel. One is to enable more precise control during the main immersion, and the other is because the discharge port of the feed channel is far away from the pre-impregnation tank. At this time, the asphalt in the pre-impregnation tank has been relatively stably attached to the tire base surface, and it is not easy for the modified asphalt in the pre-impregnation tank to be rubbed off the tire base due to the correction mechanism. Specific embodiment 6: This embodiment further illustrates the correcting mechanism on the basis of the specific embodiment 5, the correcting mechanism 9 comprises a main support roller 91 and a correcting roller 92, the correcting roller 92 is tiltedly arranged at the two ends of the main support roller 91, the correcting roller 92 is tilted upward from the inside to the outside, the two ends of the rotating shaft of the correcting roller 92 are connected to the correcting roller base 93 through a rotating seat, one end of the correcting roller base 93 is rotatably connected to the fixed surface of the correcting mechanism 9, the bottom surface of the other end of the correcting roller base 93 is hinged to the top end of the telescopic rod of the hydraulic cylinder 10, and the hydraulic cylinder 10 is hinged to the fixed surface of the correcting mechanism 9.

[0050] The inclination angle of the deviation correction roller can be adjusted through the telescopic rod of the hydraulic cylinder, so that it can better adapt to the tire base and better complete the deviation correction work. Specific embodiment 7: This embodiment further illustrates the excess asphalt scraping mechanism on the basis of the specific embodiment 1. The excess asphalt scraping mechanism 8 includes an extrusion scraping roller 81 and a scraping roller cleaning mechanism 82. The extrusion scraping roller 81 includes an upper movable extrusion roller and a lower fixed extrusion roller. The upper movable extrusion roller can move in a vertical direction. An excess asphalt scraping channel is left between the upper movable extrusion roller and the lower fixed extrusion roller. The scraping roller cleaning mechanism 82 includes an upper cleaning rubber scraper and a lower cleaning rubber scraper. The upper cleaning rubber scraper and the lower cleaning rubber scraper are respectively arranged close to the upper movable extrusion roller and the lower fixed extrusion roller.

[0052] The scraping thickness can be adjusted by adjusting the distance between the upper movable squeezing roller and the lower fixed squeezing roller, and the upper cleaning rubber scraper and the lower cleaning rubber scraper can keep the surfaces of the upper movable squeezing roller and the lower fixed squeezing roller clean. Specific embodiment 8: This embodiment further illustrates the material transfer channel based on the specific embodiment 1. The material transfer channel 5 is "U"-shaped, and guide rollers 51 are provided at the turning points in the middle of the material transfer channel 5.

[0054] The "U"-shaped material transfer channel not only serves to isolate the heat transfer between the prepreg box and the main prepreg box, but also avoids the problem that when feeding horizontally, the preparation sprayed by the spraying mechanism at the bottom cannot be well combined with the modified asphalt due to the effect of gravity. The material transfer channel adopts a "U"-shaped structure, so during transportation, the tire base is in a vertical state most of the time. At this time, the spraying mechanism is located on both sides of the material, and the sprayed preparation can be well combined with the modified asphalt on the surface of the material. Specific embodiment 9: The method for oiling the base of the modified asphalt waterproofing membrane described in any one of the above-mentioned items comprises the following steps: A. sending the prepared base to a pre-impregnation tank for pre-impregnation, and the base needs to be heated before pre-impregnation; B. after the immersion is completed, the initial coating of the modified asphalt in the No. 1 modified asphalt storage tank is coated on both sides, and the excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank, and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank; C. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. After the secondary modified asphalt immersion is completed, the excess modified asphalt is scraped off by the excess asphalt scraping mechanism in the main immersion tank to complete the base immersion work.

[0056] It is a new method for producing modified asphalt waterproofing membrane. The modified asphalt waterproofing membrane produced by this method does not require excessive modification of the asphalt, is simpler, and uses improved production equipment for production. The modified asphalt waterproofing membrane produced is of high quality and good performance.

[0057] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A modified asphalt waterproofing coiled material base oiling device, characterized in that: The invention comprises a pre-impregnation tank (1) and a main impregnation tank (2) which are arranged in sequence, wherein the asphalt input ports of the pre-impregnation tank (1) and the main impregnation tank (2) are connected to a first modified asphalt storage tank and a second modified asphalt storage tank respectively, the pre-impregnation tank (1) and the main impregnation tank (2) are arranged in a pre-impregnation box (3) and a main impregnation box (4) respectively, the pre-impregnation box (3) and the main impregnation box (4) are connected through a material transfer channel (5), and a spraying mechanism (6) is evenly arranged in the material transfer channel (5), the pre-impregnation tank (1) and the main impregnation tank (2) are both provided with a limit roller type cloth feeding mechanism, a tire base heating roller (7) is provided at the feed port of the pre-impregnation tank (1), and the discharge end of the tire base heating roller (7) is connected to the feed end of the limit roller type cloth feeding mechanism in the pre-impregnation tank (1), and the discharge end of the pre-impregnation tank (1) and the main impregnation tank (2) are also provided with an excess asphalt scraping mechanism (8).

2. The base oil immersion device of the modified asphalt waterproofing coiled material according to claim 1 is characterized by: The prepreg box (3) and the main prepreg box (4) are respectively provided with a prepreg box temperature control system and a main prepreg box temperature control system.

3. The base oil immersion device of the modified asphalt waterproofing coiled material according to claim 1 is characterized by: The spray head of the spray mechanism (6) is connected to the spray tank via a pumping pipeline.

4. The base oiling device of the modified asphalt waterproofing coiled material according to claim 3 is characterized by: The spraying tank is provided with an electric heating mechanism.

5. The base oil immersion device of the modified asphalt waterproofing coiled material according to claim 1, characterized in that: A deviation correction mechanism (9) is provided between the tire base heating roller (7) and the limiting roller type cloth feeding mechanism in the prepreg tank (1) and at the outlet of the material transfer channel (5).

6. The base oiling device of the modified asphalt waterproofing coiled material according to claim 5, characterized in that: The deflection correction mechanism (9) comprises a main support roller (91) and a deflection correction roller (92), wherein the deflection correction roller (92) is arranged obliquely at both ends of the main support roller (91), and the deflection correction roller (92) is arranged obliquely upward from the inside to the outside, and both ends of the rotating shaft of the deflection correction roller (92) are connected to a deflection correction roller base (93) through a rotating seat, and one end of the deflection correction roller base (93) is rotatably connected to a fixed surface of the deflection correction mechanism (9), and the bottom surface of the other end of the deflection correction roller base (93) is hinged to the top end of the telescopic rod of the hydraulic cylinder (10), and the hydraulic cylinder (10) is hinged to the fixed surface of the deflection correction mechanism (9).

7. The base oiling device of modified asphalt waterproofing coiled material according to claim 1, characterized in that: The excess asphalt scraping mechanism (8) comprises an extrusion scraping roller (81) and a scraping roller cleaning mechanism (82), wherein the extrusion scraping roller (81) comprises an upper movable extrusion roller and a lower fixed extrusion roller, wherein the upper movable extrusion roller is movable in a vertical direction, and an excess asphalt scraping channel is left between the upper movable extrusion roller and the lower fixed extrusion roller, and the scraping roller cleaning mechanism (82) comprises an upper cleaning rubber scraper and a lower cleaning rubber scraper, wherein the upper cleaning rubber scraper and the lower cleaning rubber scraper are respectively arranged in close contact with the upper movable extrusion roller and the lower fixed extrusion roller.

8. The base oiling device of the modified asphalt waterproofing coiled material according to claim 1, characterized in that: The material transfer channel (5) is in a "U" shape, and guide rollers (51) are provided at the turning points in the middle of the material transfer channel (5).

9. A method for oiling a modified asphalt waterproofing membrane according to any one of claims 1 to 8, characterized in that: The method comprises the following steps: A. sending the prepared tire base into the pre-impregnation tank for pre-impregnation, and the tire base needs to be heated before pre-impregnation; B. after the pre-impregnation is completed, the initial coating of the modified asphalt in the No. 1 modified asphalt storage tank is fully coated on both sides, and the excess asphalt is scraped off by the excess asphalt scraping mechanism in the pre-impregnation tank and then sent to the material transfer channel. When the initial coating passes through the material transfer channel, the spraying mechanism will selectively spray the compatibilizer according to the modified asphalt in the No. 1 modified asphalt storage tank and the modified asphalt in the No. 2 modified asphalt storage tank; C. After the initial coating passes through the material transfer channel, it enters the main immersion tank for secondary modified asphalt immersion. After the secondary modified asphalt immersion is completed, the excess modified asphalt is scraped off using the excess asphalt scraping mechanism of the main immersion tank to complete the tire base immersion work.

Citation Information

Patent Citations

  • Asphalt waterproof coiled material and preparation method thereof

    CN115353820A

  • Vertical strip steel cleaning device

    CN202174114U

  • Modified asphalt waterproofing membrane defoaming former

    CN208592010U

  • Automatic deviation rectifying device for fabric

    CN220078062U

  • Asphalt waterproof sheet manufacturing equipment

    KR101811182B1