Building collaborative jacking control method and system
By collecting data during the building deviation correction process to generate a three-dimensional model and adjusting the lifting strategy in real time, the problems of incomplete building deviation correction and stress concentration are solved, and efficient and safe building lifting control is achieved.
Patent Information
- Application Number
- CN202411520881.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-29
- Publication Date
- 2025-03-28
AI Technical Summary
During the clamping process, existing building deviation correction methods may cause the building to be unable to be completely corrected due to building deformation and other reasons, which may affect work efficiency. In addition, aging buildings may lead to structural stress concentration or even partial collapse when synchronous clamping is raised.
A coordinated building lift control method is proposed. By collecting building appearance dimension data and inclination angle data, a three-dimensional building model is generated, a lifting strategy is designed, and displacement data is collected in real time during the lifting process, a real building model is fitted and the lifting strategy is dynamically adjusted to reduce errors.
It realizes timely detection of deviations during the hoisting process, dynamically adjusting the hoisting strategy, reducing rework, improving work efficiency, and by uniformly dividing the hoisting height and forming multiple hoisting sub-strategy, the controllability and safety of the hoisting process are improved and the stress concentration of the building structure is prevented.
Smart Images

Figure CN119720321A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of building jacking, and in particular relates to a building collaborative jacking control method and system. Background Art
[0002] Masonry buildings with brick masonry as the main load-bearing material are increasingly suffering from problems such as uneven settlement, tilting or cracking due to improper operation and maintenance measures in the later stage, changes in load and foundation conditions, and the masonry structure's own sensitivity to deformation. The current main solution is to take countermeasures such as correction and reinforcement.
[0003] In the current correction method, hydraulic cylinders are used to gradually lift the jacking positions. This method has the following problems during operation: First, due to building deformation and other reasons, multiple jacking positions may not be completely corrected according to the originally specified jacking strategy, and rework may affect work efficiency; second, some buildings are seriously aged. If they cannot be lifted synchronously, it will cause stress concentration inside the building structure, and in severe cases it may even cause partial collapse of the building. Summary of the invention
[0004] In view of this, the present invention aims to propose a building collaborative jacking control method and system, in order to solve at least one of the above-mentioned technical problems.
[0005] To achieve the above object, the technical solution of the present invention is achieved as follows:
[0006] A first aspect of the present invention provides a building collaborative jacking control method, comprising the following steps:
[0007] S1. Collect the building's external dimensions and inclination angle data;
[0008] S2, making a three-dimensional building model based on the data collected in S1, and designing a jacking strategy based on the three-dimensional building model;
[0009] S3, collecting displacement data of the building during the lifting process, and fitting the displacement data with the building three-dimensional model to generate a real building model;
[0010] S4, generating an ideal building model by moving the building three-dimensional model according to the jacking strategy;
[0011] S5. Compare the error between the ideal building model and the real building model. If the error exceeds a set threshold, modify the jacking strategy.
[0012] Furthermore, in S1, the building's external dimension data and inclination angle data are obtained by measuring with a total station, and in S2, the building's plan drawings, the building's external dimension data and inclination angle data are used to produce a three-dimensional model of the building.
[0013] Furthermore, the steps of designing a jacking strategy according to the building three-dimensional model in S2 are as follows:
[0014] S21. The center of gravity of the building is obtained by calculating the three-dimensional building model. The projection of the center of gravity of the building on the ground along the inclined direction is the axis, and the jacking positions are set on both sides of the axis;
[0015] S22, calculating the weight of the building through the three-dimensional model of the building, calculating the theoretical lifting force according to the finite element force analysis, and selecting the corresponding lifting component according to the theoretical lifting force;
[0016] S23, obtaining the total lifting height of each lifting position by comparing the building three-dimensional model with the corrected building three-dimensional model;
[0017] S24, evenly dividing the total lifting height into a plurality of sub-lifting heights, and dividing the lifting strategy into a plurality of lifting sub-strategies according to the sub-lifting heights.
[0018] Furthermore, in said S3, after the building is lifted according to the sub-lifting strategy, the phase displacement data of the building is collected, and the phase displacement data is fitted with the building three-dimensional model to generate a phase real building model;
[0019] In S4, the three-dimensional building model is moved according to the jacking sub-strategy to generate multiple stages of ideal building models.
[0020] Furthermore, in S24, the maximum total lifting height is calculated, the maximum total lifting height is evenly divided into multiple sub-lifting heights, the number of lifting sub-strategies is calculated, and the sub-lifting heights of each lifting position are calculated according to the number of lifting sub-strategies, and each sub-lifting height is not greater than 10 mm.
[0021] Furthermore, in S5, the error between the actual building model of the stage and the ideal building model of the corresponding stage is compared, and if the error exceeds a set threshold, the jacking height of the corresponding jacking position of the next jacking sub-strategy is adjusted.
[0022] A second aspect of the present invention provides a building collaborative jacking control system, comprising:
[0023] A building data collection module, which is configured to collect building shape dimension data and inclination angle data;
[0024] A model generation module, which is configured to make a three-dimensional building model according to the data collected by the building data collection module, and design a jacking strategy according to the three-dimensional building model;
[0025] A displacement data acquisition module, which is configured to acquire displacement data of the building during the jacking process;
[0026] A model simulation module is configured to fit the displacement data with the building three-dimensional model to generate a real building model; and to move the building three-dimensional model according to the jacking strategy to generate an ideal building model;
[0027] A control module, which is configured to compare the error between the ideal building model and the real building model, and modify the lifting strategy of the lifting component if the error exceeds a set threshold;
[0028] A jacking assembly is equipped for jacking up a building foundation.
[0029] A third aspect of the present invention provides an electronic device, comprising a processor and a memory that is communicatively connected to the processor and is used to store instructions executable by the processor, wherein the processor is used to execute the method described in the first aspect above.
[0030] The fourth aspect of the present invention provides a server, comprising at least one processor, and a memory communicatively connected to the processor, the memory storing instructions executable by the at least one processor, the instructions being executed by the processor so that the at least one processor executes the method described in the first aspect.
[0031] A fifth aspect of the present invention provides a computer-readable storage medium storing a computer program, which implements the method described in the first aspect when executed by a processor.
[0032] Compared with the prior art, the building collaborative lifting control method and system described in the present invention have the following beneficial effects:
[0033] (1) The method for controlling collaborative building jacking described in the present invention generates a real building model by detecting the displacement of the building during the jacking process, and compares the real building model with the ideal building model. It can timely discover the deviations in the jacking process and dynamically adjust the jacking strategy in a timely manner, thereby reducing rework and improving work efficiency.
[0034] (2) The collaborative building jacking control method described in the present invention evenly divides the total jacking height into multiple sub-jacking heights and forms multiple jacking sub-strategies, thereby improving the controllability and safety of the jacking process. The real building model of each stage is generated by fitting the stage displacement data, which helps to more accurately reflect the real-time status of the building and effectively prevent the problem of stress concentration in the building structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:
[0036] Figure 1It is a schematic flow chart of the jacking control method according to an embodiment of the present invention;
[0037] Figure 2 It is a schematic diagram of the planar structure of the building jacking position according to an embodiment of the present invention.
[0038] Description of reference numerals: DETAILED DESCRIPTION
[0039] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments may be combined with each other.
[0040] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.
[0041] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.
[0042] The present invention will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.
[0043] Embodiment 1:
[0044] like Figure 1 As shown, a building collaborative jacking control method includes the following steps:
[0045] S1, collecting the building's external dimension data and inclination angle data; In S1, the building's external dimension data and inclination angle data are obtained by measuring with a total station;
[0046] S2, making a three-dimensional building model according to the data collected in S1, using the building plan drawings, the building's external dimensions data and the inclination angle data to make the building three-dimensional model, and designing a jacking strategy according to the building three-dimensional model;
[0047] The steps to design a jacking strategy based on the building 3D model are as follows:
[0048] S21. The center of gravity of the building is obtained by calculating the three-dimensional building model. The projection of the center of gravity of the building on the ground along the inclined direction is the axis, and the jacking positions are set on both sides of the axis;
[0049] S22, calculating the weight of the building through the three-dimensional model of the building, calculating the theoretical lifting force according to the finite element force analysis, and selecting the corresponding lifting component according to the theoretical lifting force;
[0050] S23, obtaining the total lifting height of each lifting position by comparing the building three-dimensional model with the corrected building three-dimensional model;
[0051] S24, evenly dividing the total lifting height into a plurality of sub-lifting heights, and dividing the lifting strategy into a plurality of lifting sub-strategies according to the sub-lifting heights.
[0052] In S24, the maximum total lifting height is calculated, the maximum total lifting height is evenly divided into a plurality of sub-lifting heights, the number of lifting sub-strategies is calculated, and the sub-lifting heights of each lifting position are calculated according to the number of lifting sub-strategies, and each sub-lifting height is not greater than 10 mm.
[0053] like Figure 2 As shown, point O is the projection of the building's center of gravity on the ground, the arrow direction is the building's tilt direction, the total lifting height of the lifting position H1 is 449mm, 441mm is divided into 50 sections, the height of each of the first 49 sections is 9mm, the height of the last section is 8mm, and the remaining lifting positions are divided into 50 sections according to this ratio. Each lifting sub-strategy contains the lifting height of the corresponding section of each lifting position. The lifting process of each lifting position starts and ends at the same time, and the lifting time of each lifting sub-strategy is 2 minutes.
[0054] S3, during the lifting process, displacement data of the building is collected, and the displacement data is fitted with the three-dimensional model of the building to generate a real building model; in S3, after the building is lifted according to the sub-lifting strategy, the stage displacement data of the building is collected, and the stage displacement data is fitted with the three-dimensional model of the building to generate a stage real building model;
[0055] S4, moving the building three-dimensional model according to the jacking strategy to generate an ideal building model; in S4, moving the building three-dimensional model according to the jacking sub-strategy to generate multiple stages of ideal building models.
[0056] S5. Compare the error between the ideal building model and the real building model. If the error exceeds a set threshold, modify the jacking strategy.
[0057] In S5, the error between the actual building model of the stage and the ideal building model of the corresponding stage is compared. If the error exceeds a set threshold, the jacking height of the corresponding jacking position of the next jacking sub-strategy is adjusted.
[0058] The error calculation process between the real building model in the comparison stage and the ideal building model in the corresponding stage is as follows:
[0059] The distance between the outer side of the real building model of this stage and the outer side of the ideal building model of the corresponding stage is calculated as the first distance.
[0060] The distance between the outer side of the ideal building model in this stage and the outer side of the ideal building model in the previous stage is calculated as the second distance.
[0061] The ratio of the first spacing to the second spacing is an error.
[0062] Set the threshold to 10%-30%.
[0063] If the real building model of this stage is located inside the ideal building model of the corresponding stage, the jacking height of the corresponding jacking position and the adjacent jacking position of the next jacking sub-strategy is reduced.
[0064] If the actual building model of a stage is located inside the ideal building model of the corresponding stage, it means that the actual lifting height is lower than the expected height. The lifting height of the corresponding lifting position and the adjacent lifting position in the next lifting sub-strategy needs to be reduced. The height of the adjacent lifting position is reduced to maintain the overall balance of the building and avoid new deviations caused by the height adjustment of a single position.
[0065] If the real building model of this stage is located outside the ideal building model of the corresponding stage, the jacking height of the corresponding jacking position of the next jacking sub-strategy is increased, and the jacking height of the adjacent jacking position is reduced in the next jacking sub-strategy.
[0066] Outer deviation adjustment: If the actual building model of a stage is located inside or outside the ideal building model of the corresponding stage, this indicates that the actual jacking height is higher than the expected height or there is uneven jacking. In order to correct this deviation, the height of the corresponding jacking position in the next jacking sub-strategy needs to be increased. In order to maintain balance and avoid excessive jacking, the height of the adjacent jacking position needs to be reduced in the next jacking sub-strategy, so that the building gradually returns to the predetermined jacking path and alleviates the stress concentration of the building structure.
[0067] The increased lifting height ratio is directly proportional to the error.
[0068] A building collaborative lifting control system, comprising:
[0069] A building data collection module, which is configured to collect building shape dimension data and inclination angle data;
[0070] The building data acquisition module adopts but is not limited to one of the existing laser scanners and total stations or a combination of the two.
[0071] The model generation module is configured to make a three-dimensional building model according to the data collected by the building data collection module, and design a jacking strategy according to the three-dimensional building model; the model generation module adopts existing three-dimensional modeling software.
[0072] A displacement data acquisition module, which is configured to acquire displacement data of the building during the jacking process;
[0073] The displacement data acquisition module adopts but is not limited to one of the existing displacement sensors and total stations, and detects the displacement data of key points of the building.
[0074] A model simulation module is configured to fit the displacement data with the building three-dimensional model to generate a real building model; and to move the building three-dimensional model according to the jacking strategy to generate an ideal building model;
[0075] A control module, which is configured to compare the error between the ideal building model and the real building model, and modify the lifting strategy of the lifting component if the error exceeds a set threshold;
[0076] The jacking component is equipped for jacking up the building base, and the jacking component adopts but is not limited to the existing hydraulic cylinder.
[0077] By detecting the displacement of the building during the jacking process to generate a real building model, and comparing the real building model with the ideal building model, deviations in the jacking process can be discovered in a timely manner, and the jacking strategy can be adjusted in a timely and dynamic manner to reduce rework and improve work efficiency.
[0078] The total lifting height is evenly divided into multiple sub-lifting heights, and multiple lifting sub-strategies are formed, which improves the controllability and safety of the lifting process. The real building model of the stage is generated according to the stage displacement data fitting, which helps to more accurately reflect the real-time status of the building and effectively prevent the problem of stress concentration in the building structure.
[0079] Adjusting the jacking height of the corresponding jacking position in the next jacking sub-strategy by adjusting the jacking strategy in real time requires a high degree of expertise and advanced control systems.
[0080] By using a total station to accurately measure the building's dimensions and inclination angles, a high-precision three-dimensional model can be produced, providing an accurate data basis for subsequent jacking strategy design.
[0081] The center of gravity, weight and lifting force of the building are calculated based on the three-dimensional model, and the lifting strategy is determined through finite element analysis, ensuring the scientificity and rationality of the lifting process.
[0082] The total lifting height is evenly divided into multiple sub-lifting heights to form multiple lifting sub-strategies, making the lifting process more controllable and reducing overall risks.
[0083] Dynamic error correction: By comparing the error between the ideal model and the real model and setting the error threshold, the lifting height can be adjusted dynamically to ensure the accuracy of the lifting process.
[0084] Embodiment 2:
[0085] An electronic device includes a processor and a memory connected to the processor for storing instructions executable by the processor, wherein the processor is used to execute the method of the first embodiment.
[0086] Embodiment three:
[0087] A server includes at least one processor and a memory connected to the processor in communication, wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the processor so that the at least one processor executes the method of the first embodiment.
[0088] Embodiment 4:
[0089] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the method of embodiment 1 is implemented.
[0090] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. These modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention, and they should all be included in the scope of the claims and specification of the present invention.
[0091] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A building collaborative lifting control method, characterized in that: The following steps are involved: S1. Collect the building's external dimensions and inclination angle data; S2, making a three-dimensional building model based on the data collected in S1, and designing a jacking strategy based on the three-dimensional building model; S3, collecting displacement data of the building during the lifting process, and fitting the displacement data with the building three-dimensional model to generate a real building model; S4, generating an ideal building model by moving the building three-dimensional model according to the jacking strategy; S5. Compare the error between the ideal building model and the real building model. If the error exceeds a set threshold, modify the jacking strategy.
2. A building collaborative lifting control method according to claim 1, characterized in that: In S1, the building's external dimension data and inclination angle data are obtained by measuring with a total station, and in S2, the building's plan drawings, the building's external dimension data and inclination angle data are used to produce a three-dimensional model of the building.
3. A building collaborative lifting control method according to claim 1, characterized in that: The steps of designing the jacking strategy according to the building three-dimensional model in S2 are as follows: S21. The center of gravity of the building is obtained by calculating the three-dimensional building model. The projection of the center of gravity of the building on the ground along the inclined direction is the axis, and the jacking positions are set on both sides of the axis; S22, calculating the weight of the building through the three-dimensional model of the building, calculating the theoretical lifting force according to the finite element force analysis, and selecting the corresponding lifting component according to the theoretical lifting force; S23, obtaining the total lifting height of each lifting position by comparing the building three-dimensional model with the corrected building three-dimensional model; S24, evenly dividing the total lifting height into a plurality of sub-lifting heights, and dividing the lifting strategy into a plurality of lifting sub-strategies according to the sub-lifting heights.
4. A building collaborative lifting control method according to claim 3, characterized in that: In S3, after the building is lifted according to the sub-lifting strategy, stage displacement data of the building is collected, and the stage displacement data is fitted with the building three-dimensional model to generate a stage real building model; In S4, the three-dimensional building model is moved according to the jacking sub-strategy to generate multiple stages of ideal building models.
5. A building collaborative lifting control method according to claim 3, characterized in that: In S24, the maximum total lifting height is calculated, the maximum total lifting height is evenly divided into a plurality of sub-lifting heights, the number of lifting sub-strategies is calculated, and the sub-lifting heights of each lifting position are calculated according to the number of lifting sub-strategies, and each sub-lifting height is not greater than 10 mm.
6. A building collaborative lifting control method according to claim 4, characterized in that: In S5, the error between the real building model of the stage and the ideal building model of the corresponding stage is compared, and if the error exceeds a set threshold, the jacking height of the corresponding jacking position of the next jacking sub-strategy is adjusted.
7. A building collaborative lifting control system, characterized in that: include: A building data collection module, which is configured to collect building shape dimension data and inclination angle data; A model generation module, which is configured to make a three-dimensional building model according to the data collected by the building data collection module, and design a jacking strategy according to the three-dimensional building model; A displacement data acquisition module, which is configured to acquire displacement data of the building during the jacking process; A model simulation module, which is configured to fit the displacement data with the building three-dimensional model to generate a real building model; According to the lifting strategy, the 3D model of the building is moved to generate an ideal building model; A control module, which is configured to compare the error between the ideal building model and the real building model, and modify the lifting strategy of the lifting component if the error exceeds a set threshold; A jacking assembly is equipped for jacking up a building foundation.
8. An electronic device, comprising a processor and a memory connected to the processor for storing instructions executable by the processor, characterized in that: The processor is used to execute the method described in any one of claims 1 to 6.
9. A server, characterized in that: It includes at least one processor and a memory communicatively connected to the processor, wherein the memory stores instructions executable by the at least one processor, and the instructions are executed by the processor so that the at least one processor executes the method according to any one of claims 1-6.
10. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the method according to any one of claims 1 to 6 is implemented.