UHPC building material site construction equipment
By designing the UHPC building materials on-site construction equipment with controlled spraying devices and mixed stirrers, the problems of high unstable and low construction standards of existing equipment during the spraying process are solved, and uniform spraying of UHPC materials and the improvement of construction standards are achieved.
Patent Information
- Application Number
- CN202510249466.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-04
- Publication Date
- 2025-04-01
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing UHPC material on-site construction equipment has problems such as high unstable and low construction standards during the spraying process, resulting in uneven spraying.
A UHPC building materials site construction equipment including a controlled spraying device and a mixing agitator was designed. The lateral displacement and height adjustment of the jet gun is achieved through the drive transmission and electric control rod, and combined with a remote control system, ensuring the efficiency and accuracy of the construction equipment.
The uniform spraying of UHPC materials is achieved, the construction standards are improved, and the construction process is ensured efficient and safe.
Smart Images

Figure CN119737055A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of on-site construction equipment for building materials, in particular to on-site construction equipment for UHPC building materials. Background Art
[0002] UHPC, also known as ultra-high performance concrete, is a new type of cement-based composite material with extremely high mechanical properties and durability. It is widely used in construction, decoration, reinforcement, quick repair and other fields. It is mainly achieved by minimizing the internal pores and micro-cracks of the material through the micro-continuous grading technology, ultra-high efficiency water reducer and fine proportion of fiber, thereby obtaining ultra-high strength and high durability. On-site construction equipment for building materials refers to integrated spraying equipment for mixing UHPC materials, but the prior art has the following deficiencies: the current UHPC materials are mixed on site and then constructed on their building walls, but most of the existing spraying construction equipment uses manual handheld spray guns to complete the spraying of building UHPC materials, which will lead to height factor problems and the pressure generated on the spray gun head and the rear delivery pipeline during the spraying process, causing the operator to resist the pressure generated by the spray head to complete the spraying during the operation, which can easily lead to low construction standards. Summary of the invention
[0003] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or be understood by implementing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the description and other drawings of the description.
[0004] The purpose of the present invention is to overcome the above-mentioned shortcomings and provide an on-site construction equipment for UHPC building materials. During use, the on-site construction equipment prepares the UHPC building materials on-site, and then completes the mixing and pressurized transportation of the UHPC building materials through a mixing agitator. Then, under the control and adjustment of a controlled spraying device, the spray gun fixed between the adapter clamp and the lower connecting card table is driven to move, and the spray gun is adjusted horizontally to complete the on-site UHPC material spraying work on the building body. Compared with the traditional handheld spraying by operators, it not only solves the height problem in the spraying process, but also makes the sprayed UHPC material more uniform and more standardized.
[0005] In order to achieve the above-mentioned object, the present invention is realized by the following technical scheme: a UHPC building material on-site construction equipment, comprising on-site construction equipment, a controlled spraying device is installed on the on-site construction equipment, a lower beam is arranged in the controlled spraying device, fixed columns are installed at both ends of the upper surface of the lower beam, nested columns are nested on the fixed columns, a driving transverse movement assembly is arranged on the top of the nested columns, fixed support blocks are fixed to the outer walls of the fixed columns, lifting connection blocks are fixed to the outer walls of the nested columns, and a first electric control rod is installed between the fixed support block and the lifting connection block; a beam plate is arranged in the driving transverse movement assembly, a through groove is opened on the beam plate, slide rails are arranged on both sides of the through groove, a driving transmission member is installed on the beam plate, a driving motor is fixed to the outer wall of the driving transmission member, a slide table is installed on the slide rail, an even number of second electric control rods are installed on the slide table, a fixed wheel frame is arranged above the slide table, and a connecting frame is connected to the fixed wheel frame. The driving transmission part is mainly driven by a driving motor, so that the built-in belt of the driving transmission part is displaced laterally, and the connected connecting frame assists the slide to displace laterally, thereby realizing the joint movement of the spray gun in the on-site construction equipment to complete the spraying work.
[0006] The present invention is further improved, the ends of the even number of the second electric control rods are connected to an upper connection platform, the upper connection platform is penetrated by an even number of spring rods, the lower surface of the upper connection platform is fixed with an adapting clamp, both sides of the adapting clamp are fixed with wing sleeves, the ends of the spring rods are connected to a lower connection card platform, and the upper surface of the lower connection card platform is fixed with an even number of alignment plugs. The alignment plugs are respectively installed on both sides of the lower connection card platform, and are respectively nested and penetrated with the wing sleeves on both sides of the adapting clamp, so that the two can be accurately aligned when they are subsequently separated and overlapped.
[0007] The present invention is further improved, the alignment plug block is nested in the wing sleeve block, the lower connection card platform is matched with the adapter clamp block and is engaged, the top of the upper connection platform is connected to the end of the second electric control rod, the lower connection card platform is penetrated and fixed by the spring rod, the second electric control rod slides horizontally between the penetration grooves, and the second electric control rod is fixed and penetrates the slide. The lower connection card platform is connected through the connected, penetrated and fixed spring rod, and the spring on the spring rod forms an alignment top fixation with the adapter clamp block under the top fit, completing the rapid and tight installation of the spray gun.
[0008] The present invention is further improved, the connecting frame is connected to the driving transmission member, the driving transmission member cooperates with the driving motor, the roller on the fixed wheel frame is slidably matched with the slide rail, the lower surfaces of both ends of the beam plate are fixed to the top of the nested column, and the lower beam is connected to the on-site construction equipment. The fixed wheel frame is provided with rollers, so that the rollers are fitted to the side walls of the slide rail for sliding cooperation, so that under the auxiliary cooperation of the connecting frame, the driving transmission member and its slide table are slidably displaced, driving the second electric control rod end structure installed in the slide table to complete the lateral position adjustment.
[0009] In a further improvement of the present invention, the second electric control rod, the drive motor, the first electric control rod and the on-site construction equipment can all be remotely controlled. The second electric control rod, the drive motor, the first electric control rod and the on-site construction equipment can all be remotely controlled, so that during on-site construction work, personnel can stand around the equipment to perform remote control and complete the construction from a safe distance.
[0010] The present invention is further improved, the on-site construction equipment is provided with a frame, the left and right ends of the frame are equipped with shock-absorbing moving wheels, the upper surface of the frame is provided with an equipment box, the equipment box is equipped with a mixer, the lower part of the mixer is connected with a material conveying pipe, the end of the material conveying pipe is connected with a spray gun, the side wall of the equipment box is provided with a water supply pipe, the lower part of the water supply pipe is provided with a feed pipe, the bottom of the frame is provided with a mounting beam, and the upper surface of the frame is provided with an even number of stable support platforms on both sides of the equipment box. One of the shock-absorbing moving wheels installed at both ends of the frame is a universal wheel, and can be towed so as to make corresponding displacements when the construction position changes, so that it can complete corresponding adjustments as the construction orientation of the building changes.
[0011] The present invention is further improved, the mixing agitator is provided with an agitator mounting seat, a mixing drum is installed above the agitator mounting seat, a windproof and splashproof cover is installed on the top of the mixing drum, a vibrator is installed on the outer surface of the mixing drum, a conveying bucket is installed on the mixing drum, an even number of top fixed rotating rods are installed on both sides of the conveying bucket, one of the top fixed rotating rods is provided with a side fixed rotating rod, a clamping block is installed on the top of the side fixed rotating rod, and a built-in mixing impeller is installed in the mixing drum. The windproof and splashproof cover mainly serves to isolate and splash-proof the external input raw materials, ensuring that all the external input raw materials fall into the mixing drum, and the on-site manufacturing of the UHPC material meets the use standards under the cooperation of the vibrator and the built-in mixing impeller.
[0012] The present invention is further improved, the built-in stirring impeller is used to stir the UHPC raw materials in the mixing drum, the stirrer mounting seat is installed above the equipment box, the mixing drum is connected to the water supply pipe and the agent supply pipe respectively, the bottom of the mixing drum is connected to the material conveying pipe, the spray gun is clamped between the adapter clamp and the lower connecting card platform, and the spray gun is moved by the slide. The end of the spray gun is connected to the logistics conveying pipe, and the end of the logistics conveying pipe is supplied by the mixing drum, and UHPC is continuously provided to the spray gun, and the spray gun is fastened with the assistance of the adapter clamp and the lower connecting card platform, and the slide assists it to complete the corresponding construction position movement and transformation.
[0013] The present invention is further improved, the stable support platform is provided with a support column platform, the support column platform is provided with an auxiliary shaft rod groove, a swing support frame is installed on the auxiliary shaft rod groove, the swing support frame is provided with a slot, an inner shaft is installed on the swing support frame, an adjustable support column is nested on the inner shaft, a sleeve column tube is provided in the adjustable support column, the sleeve column tube is provided with an axis through hole, a telescopic sleeve column is nested in the sleeve column tube, the telescopic sleeve column and the sleeve column tube are provided with a plurality of groups of limit holes, one group of the limit holes is penetrated by a limit pin. The auxiliary shaft groove on the support column platform is mainly for the swing support frame to swing, so that when the frame reaches the designated construction area, the corresponding swing extension is completed, thereby compensating for the flatness of the ground and the stability of the frame docking.
[0014] The present invention is further improved, the limit pin passes through the sleeve tube and the telescopic sleeve column respectively, the bottom of the telescopic sleeve column is provided with a rubber pad, the sleeve tube is hingedly matched with the inner rotating shaft through the shaft through the shaft through-hole, the top end of the sleeve tube is engaged in the slot after the sleeve tube swings, and the support column platform is welded to the upper surface of the frame. The top of the sleeve tube is engaged in the slot to form a snap fit, and the telescopic sleeve column nested in the sleeve tube can be pulled outward accordingly to complete the length change, and complete the work of compensating for the height difference of different on-site construction equipment.
[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. The present invention coordinates the control spraying device with the on-site construction equipment, installs the spray gun between the adapter clamp and the lower connecting clamp to complete the fastening, and under the remote control of the operator, can trigger its drive motor to drive the drive transmission member to work, so that the fixed wheel frame and the slide table connected to the connecting frame move laterally with the cooperation of the slide rail, and then drive the second electric control rod installed on the slide table to perform lateral displacement, and under the jacking of the first electric control rod, can drive the nested column to complete the height adjustment, so that its height is adapted to different building volumes. Compared with the traditional handheld spraying construction, the sprayed UHPC material is more uniform and has a higher standard degree.
[0016] 2. The present invention installs the mixing agitator above the equipment box, so that when UHPC is produced, the built-in mixing impeller can cooperate with the vibrator to fully mix it to obtain high-standard UHPC, and when the feed hopper is connected, the feed hopper body can be fixed by the conveying bucket frame arranged on the mixing drum, making the connection more firm, and preventing the feed hopper from being separated from the mixing agitator during operation, resulting in spillage of raw materials.
[0017] 3. The present invention installs at least two sets of stable support platforms on the frame. When moving to on-site construction positions with different heights, the swing support frame can be swung to allow the top of the sleeve tube to be engaged in the slot and maintain a vertical state. The telescopic sleeve is then pulled out of the sleeve tube to compensate for different heights. Finally, the limit pins are inserted into the corresponding limit holes of the two to ensure that the frame is firm and stable at the construction site. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 This is a schematic structural diagram of a UHPC building material on-site construction equipment of the present invention; Figure 2 It is a rear structural schematic diagram of a UHPC building material on-site construction equipment of the present invention; Figure 3 It is a schematic diagram of the three-dimensional structure of a controlled spraying device in a UHPC building material on-site construction equipment of the present invention; Figure 4 It is a schematic diagram of the top view of the structure of a driving and lateral movement assembly in a UHPC building material on-site construction device of the present invention; Figure 5 It is a schematic diagram of a partially enlarged structure of A in a UHPC building material on-site construction equipment of the present invention; Figure 6 It is a three-dimensional structural schematic diagram of an on-site construction equipment of a UHPC building material on-site construction equipment of the present invention; Figure 7 It is a front view structural schematic diagram of an on-site construction equipment of a UHPC building material on-site construction equipment of the present invention; Figure 8 It is a schematic diagram of the top view of the structure of a mixing agitator in a UHPC building material on-site construction equipment of the present invention; Fig. 9 It is a schematic diagram of the three-dimensional structure of a stable support platform in a UHPC building material on-site construction equipment of the present invention; Fig.10 The present invention is a schematic diagram of the three-dimensional structure of an adjustable support column in a UHPC building material on-site construction device.
[0019] In the figure: on-site construction equipment-1, controlled spraying device-2, frame-11, shock-absorbing moving wheel-12, equipment box-13, mixing agitator-14, material conveying pipe-15, water supply pipe-16, agent supply pipe-17, mounting beam-18, spray gun-19, lower beam-21, fixed column-22, nested column-23, drive transverse movement component-24, first electric control rod-25, lifting connection block-26, fixed support block-27, stable support platform-111, agitator mounting seat-141, mixing drum-142, conveying bucket frame-143, side fixed rotary rod-144, top fixed rotary rod-145, clamping block-146, windproof and splashproof cover-147, vibrator-148, built-in mixing impeller-149, beam plate -241, through slot-242, slide rail-243, drive transmission member-244, drive motor-245, fixed wheel frame-246, second electric control rod-247, connecting frame-248, slide table-249, support column platform-1111, auxiliary shaft rod slot-1112, swing support frame-1113, card slot-1114, inner shaft-1115, adjustable support column-1116, upper connecting platform-2471, wing sleeve block-2472, spring rod-2473, adapter clamp block-2474, lower connecting clamp table-2475, alignment plug block-2476, telescopic sleeve cylinder-11161, shaft through hole-11162, limit hole-11163, nested column-11164, limit latch-11165. DETAILED DESCRIPTION
[0020] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with specific embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention, but are not used to limit the present invention.
[0021] In addition, in the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0022] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral body; it can be directly connected or indirectly connected through an intermediate medium, and it can be the internal connection of two elements or the interaction relationship between two elements. However, if it is indicated as a direct connection, it means that the two connected bodies are not connected through a transition structure, but are connected to form a whole through a connecting structure. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.
[0023] In the present invention, unless otherwise clearly specified and limited, the first feature "on" or "under" the second feature may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in an appropriate manner in any one or more embodiments or examples.
[0024] The present invention is further described below in conjunction with the accompanying drawings: Example 1
[0025] As attached Figure 1 To Attachment Figure 5 As shown: The present embodiment provides a UHPC building material on-site construction equipment, including on-site construction equipment 1, on which a controlled spraying device 2 is installed, a lower beam 21 is arranged in the controlled spraying device 2, fixed columns 22 are installed at both ends of the upper surface of the lower beam 21, nested columns 23 are nested on the fixed columns 22, a driving transverse movement assembly 24 is mounted on the top of the nested columns 23, fixed support blocks 27 are fixed to the outer walls of the fixed columns 22, lifting connection blocks 26 are fixed to the outer walls of the nested columns 23, and a first electric control rod 25 is installed between the fixed support blocks 27 and the lifting connection blocks 26; a beam plate 241 is arranged in the driving transverse movement assembly 24, a through groove 242 is opened on the beam plate 241, slide rails 243 are arranged on both sides of the through groove 242, and the beam plate 24 1 is provided with a driving transmission member 244, a driving motor 245 is fixed to the outer wall of the driving transmission member 244, a slide 249 is provided on the slide rail 243, an even number of second electric control rods 247 are provided on the slide 249, a fixed wheel frame 246 is provided above the slide 249, a connecting frame 248 is connected to the fixed wheel frame 246, an upper connecting platform 2471 is connected to the ends of the even number of second electric control rods 247, an even number of spring rods 2473 penetrate the upper connecting platform 2471, an adapting clamping block 2474 is fixed to the lower surface of the upper connecting platform 2471, wing sleeve blocks 2472 are fixed to both sides of the adapting clamping block 2474, a lower connecting clamping platform 2475 is connected to the ends of the spring rods 2473, and an even number of alignment plug blocks 2476 are fixed to the upper surface of the lower connecting clamping platform 2475.
[0026] Furthermore, the second electric control rod 247 is divided into two groups, both of which are nested and fixed on the slide 249 and pass through the slide 249. The bottom is connected to the upper connecting platform 2471 so as to complete lateral displacement when the slide 249 moves together.
[0027] Furthermore, the driving transmission member 244 is triggered by a driving motor 245, with a built-in belt drive, and is connected with a connecting frame 248 to form a slide 249 to complete the on-site position adjustment of the construction site.
[0028] Furthermore, at least two first electric control rods 25 are provided, which are respectively installed above the fixed support block 27, and the top is connected to the jacking connection block 26, so that jacking is formed after being triggered, driving the nested columns 23 to complete the height change, so that the driving transverse movement component 24 can complete the construction height requirements of different buildings.
[0029] The specific working principle is as follows: The present invention forms a construction equipment 1 and a controlled spraying device 2 that are displaced to a specified position, and then fixes the spray gun in the on-site construction equipment 1 on the driving transverse movement assembly 24, so that the spring rods 2473 on both sides of the upper connecting platform 2471 connected to the end of the second electric control rod 247 are pressed down, forcing the lower connecting clamping platform 2475 to move downward, and then the spray gun is passed through the adapter clamping block 2474 and the lower connecting clamping platform 2475 to complete the fastening engagement, and the alignment plug block 2476 is nested and passed through the side wing sleeve block 2472, and the lower beam 21 is fixed to the installation beam of the on-site construction equipment 1. Under the cooperation of the remote control control end, the driving motor 245 can be triggered to force the driving transmission member 244 to work, so that the connected connecting frame 2 48 pairs of fixed wheel frames 246 are linked to make the slide 249 displace laterally on the slide rail 243. During the displacement, the second electric control rod 247 moves laterally in the through groove 242 to carry out construction on the building site and complete the UHPC spraying of the building. When the length displacement is not enough, the second electric control rod 247 can be adjusted to complete the position compensation. When the height is insufficient, the first electric control rod 25 fixed on the fixed support block 27 is controlled to complete the jacking, and the jacking connection block 26 on the outside of the nested column 23 is lifted and lowered, so that the nested column 23 rises on the fixed column 22 to complete the height difference compensation. Compared with the traditional handheld construction spraying by operators, the UHPC material is sprayed more evenly, more efficiently and with higher standardization. Example 2
[0030] As attached Figure 6 To Attachment Figure 8 As shown: Among them, a frame 11 is provided in the on-site construction equipment 1, and shock-absorbing moving wheels 12 are installed at both ends of the frame 11. An equipment box 13 is provided on the upper surface of the frame 11, and a mixing agitator 14 is installed on the equipment box 13. A material conveying pipe 15 is connected below the mixing agitator 14, and a spray gun 19 is connected to the end of the material conveying pipe 15. A water supply pipe 16 is provided on the side wall of the equipment box 13, and a liquid supply pipe 17 is provided below the water supply pipe 16. A mounting beam 18 is installed at the bottom of the frame 11, and an even number of stable support platforms 111 are provided on both sides of the equipment box 13 on the upper surface of the frame 11. A mixer mounting seat 141 is provided in the mixing mixer 14, a mixing drum 142 is installed above the mixer mounting seat 141, a windproof and splashproof cover 147 is installed on the top of the mixing drum 142, a vibrator 148 is installed on the outer surface of the mixing drum 142, a conveying bucket frame 143 is installed on the mixing drum 142, an even number of top fixed rotating rods 145 are installed on both sides of the conveying bucket frame 143, a side fixed rotating rod 144 is provided above one of the top fixed rotating rods 145, a clamping block 146 is installed on the top of the side fixed rotating rod 144, and a built-in mixing impeller 149 is installed in the mixing drum 142.
[0031] Furthermore, the equipment box 13 includes a power system and a control system, and both are protected to prevent them from being affected by external factors. At the same time, it can cooperate with the mixer 14 to complete the control and complete the on-site manufacturing of the corresponding UHPC building materials.
[0032] Furthermore, a quarter semicircular ring-shaped windproof and splashproof cover 147 is fixed on the top of the mixing drum 142, and a conveying bucket frame 143 is installed directly in front of the windproof and splashproof cover 147, and the conveying bucket frame 143 is used to cooperate with the feed hopper to complete the connection and fixation.
[0033] Furthermore, a rubber block is provided on the top of the top fixing rod 145 to complete the top closing of the feed hopper, and at least two groups of top fixing rods 145 are provided, with two rods in each group, which are installed on both sides of the conveying bucket frame 143, and a clamping block 146 is installed on the top of the side fixing rod. The clamping block 146 completes the clamping and fixing of the feed hopper, thereby ensuring the firmness of the connection between the feed hopper and the mixing drum 142.
[0034] The specific working principle is as follows: The present invention drives the frame 11 to move to the designated construction area through the building moving wheel 12, and then operates the equipment box 13, connects the conveying bucket frame 143 on the mixing drum 142 of the mixing agitator 14 to the supply hopper, and completes the clamping under the rotation and top connection of the top fixing rotary rod 145, and the side fixing rotary rod 144 rotates and cooperates with the clamping block 146 to complete the clamping of the supply hopper, and then connects the supply pipe 17 and the water supply pipe 16 in turn to complete the supply of the mixing agitator 14, and the production UHPC raw materials input from the supply hopper enter the mixing drum 142, and the windproof and splashproof cover 147 is splash-proof, and mixed production is carried out under the supply of the built-in mixing impeller 149 and the supply pipe 17 and the water supply pipe 16, and the vibrator 148 generates vibration, so that the mixing drum 142 cooperates with the agitator mounting seat 141 to complete buffering, forcing the UHPC raw materials to be fully mixed, and finally under the transportation of the material conveying pipe 15, the UHPC is sprayed on the designated construction area from the spray gun 19. Example 3
[0035] As attached Fig. 9 To Attachment Fig.10 As shown: Among them, a support column platform 1111 is arranged in the stable support platform 111, an auxiliary rotating shaft rod groove 1112 is opened on the support column platform 1111, a swing support frame 1113 is installed on the auxiliary rotating shaft rod groove 1112, a card slot 1114 is opened on the swing support frame 1113, an inner rotating shaft 1115 is installed on the swing support frame 1113, an adjustable support column 1116 is nested on the inner rotating shaft 1115, a sleeve cylinder 11161 is arranged in the adjustable support column 1116, an axis through hole 11162 is opened on the sleeve cylinder 11161, a telescopic sleeve cylinder 11164 is nested in the sleeve cylinder 11161, a plurality of groups of limiting holes 11163 are opened on the telescopic sleeve cylinder 11164 and the sleeve cylinder 11161, and a limiting pin 11165 passes through one group of limiting holes 11163.
[0036] Furthermore, the auxiliary rotating rod slot 1112 provided on the support column platform 1111 is divided into two heights, mainly for the purpose of making a height difference and completing the avoidance of the swing support frame 1113, so that both of them can swing outwards and complete the compensation of the height of the frame.
[0037] Furthermore, the top of the sleeve cylinder 11161 is block-shaped, which is used to cooperate with the card slot 1114 to complete the engagement, and the sleeve cylinder 11161 is swung by the shaft through hole 11162 and the inner rotating shaft 1115, and the sleeve cylinder 11161 is supported in a vertical upright state after the swing.
[0038] Furthermore, the telescopic sleeve 11164 is nested in the sleeve tube 11161, and the two are provided with limiting holes 11163 of the same aperture. When the lengths are different, the telescopic sleeve 11164 extends outward to complete the height difference compensation, and the limiting pin 11165 is penetrated at the limiting holes 11163 of the same height.
[0039] The specific working principle is as follows: The present invention fixes the support column platform 1111 on the frame 11 and the two sides of the equipment box 13. When in use, the swing support frame 1113 installed in the auxiliary shaft rod groove 1112 is swung, thereby driving it to form a horizontal swing, and then the adjustable support column 1116 is swung down with the cooperation of the inner shaft 1115, so that the top of the sleeve tube 11161 is engaged between the slots 1114. When the height distance is different, the telescopic sleeve column 11164 is pulled outward accordingly to change its height. After the change, the limiting pin 11165 is inserted into the limiting hole 11163 flush with the sleeve tube 11161 to complete the limiting work of the telescopic sleeve column 11164, and the bottom of the telescopic sleeve column 11164 contacts the ground to complete the support of the frame 11, thereby realizing the compensation of different height differences at the construction site of the building, so that the frame 11 is in a stable and firm state to assist it in on-site construction work.
[0040] It should be understood that the embodiments disclosed in the present invention are not limited to the specific processing steps or materials disclosed herein, but should be extended to equivalent substitutions of such features understood by ordinary technicians in the relevant field. It should also be understood that the terms used herein are only used for the purpose of describing specific embodiments and are not meant to be limiting.
[0041] The "embodiment" mentioned in the specification means that the specific features or characteristics described in conjunction with the embodiment are included in at least one embodiment of the present invention. Therefore, the phrases or "embodiment" appearing in various places throughout the specification do not necessarily refer to the same embodiment.
[0042] In addition, the described features or characteristics may be combined in one or more embodiments in any other suitable manner. In the above description, some specific details, such as thickness, quantity, etc., are provided to provide a comprehensive understanding of the embodiments of the present invention. However, those skilled in the relevant art will understand that the present invention can be implemented without one or more of the above specific details or can also be implemented using other methods, components, materials, etc.
Claims
1. A UHPC building material on-site construction equipment, characterized in that: The invention comprises a field construction device (1), wherein a controlled spraying device (2) is installed on the field construction device (1), a lower beam (21) is arranged inside the controlled spraying device (2), fixed columns (22) are installed at both ends of the upper surface of the lower beam (21), nested columns (23) are nested on the fixed columns (22), a driving transverse movement component (24) is mounted on the top of the nested columns (23), fixed support blocks (27) are fixed to the outer walls of the fixed columns (22), lifting connection blocks (26) are fixed to the outer walls of the nested columns (23), and a first electric control rod (25) is installed between the fixed support blocks (27) and the lifting connection blocks (26); The driving transverse shifting assembly (24) is provided with a beam plate (241), a through groove (242) is provided on the beam plate (241), slide rails (243) are provided on both sides of the through groove (242), a driving transmission member (244) is installed on the beam plate (241), a driving motor (245) is fixed to the outer wall of the driving transmission member (244), a slide table (249) is installed on the slide rail (243), an even number of second electric control rods (247) are installed on the slide table (249), a fixed wheel frame (246) is provided above the slide table (249), and a connecting frame (248) is connected to the fixed wheel frame (246).
2. The on-site construction equipment for UHPC building materials according to claim 1, characterized in that: The ends of an even number of the second electric control rods (247) are connected to an upper connecting platform (2471), an even number of spring rods (2473) penetrate the upper connecting platform (2471), an adapting clamping block (2474) is fixed to the lower surface of the upper connecting platform (2471), wing sleeve blocks (2472) are fixed to both sides of the adapting clamping block (2474), the ends of the spring rods (2473) are connected to a lower connecting clamping platform (2475), and an even number of alignment plug blocks (2476) are fixed to the upper surface of the lower connecting clamping platform (2475).
3. The on-site construction equipment for UHPC building materials according to claim 2, characterized in that: The alignment plug block (2476) is nested in the side wing sleeve block (2472), the lower connecting clamping platform (2475) cooperates with the adapting clamping block (2474) and is engaged, the top of the upper connecting platform (2471) is connected to the end of the second electric control rod (247), the lower connecting clamping platform (2475) is penetrated and fixed by the spring rod (2473), the second electric control rod (247) slides laterally between the penetration grooves (242), and the second electric control rod (247) is fixed and penetrates the slide table (249).
4. The on-site construction equipment for UHPC building materials according to claim 2, characterized in that: The connecting frame (248) is connected to the driving transmission member (244), the driving transmission member (244) cooperates with the driving motor (245), the roller on the fixed wheel frame (246) is slidably matched with the slide rail (243), the lower surfaces at both ends of the beam plate (241) are fixed to the top of the nesting column (23), and the lower beam (21) is connected to the on-site construction equipment (1).
5. The on-site construction equipment for UHPC building materials according to claim 1, characterized in that: The second electric control rod (247), the drive motor (245), the first electric control rod (25) and the on-site construction equipment (1) can all be remotely controlled.
6. The on-site construction equipment for UHPC building materials according to claim 4, characterized in that: The on-site construction equipment (1) is provided with a vehicle frame (11), and shock-absorbing moving wheels (12) are installed at both left and right ends of the vehicle frame (11). An equipment box (13) is provided on the upper surface of the vehicle frame (11), and a mixing agitator (14) is installed on the equipment box (13). A material conveying pipe (15) is connected below the mixing agitator (14), and a spray gun (19) is connected to the end of the material conveying pipe (15). A water supply pipe (16) is provided on the side wall of the equipment box (13), and a liquid supply pipe (17) is provided below the water supply pipe (16). A mounting beam (18) is installed at the bottom of the vehicle frame (11), and an even number of stable support platforms (111) are provided on both sides of the equipment box (13) on the upper surface of the vehicle frame (11).
7. The on-site construction equipment for UHPC building materials according to claim 6, characterized in that: The mixing agitator (14) is provided with an agitator mounting seat (141), a mixing drum (142) is installed above the agitator mounting seat (141), a windproof and splashproof cover (147) is installed on the top of the mixing drum (142), a vibrator (148) is installed on the outer surface of the mixing drum (142), a conveying bucket frame (143) is installed on the mixing drum (142), an even number of top fixed rotating rods (145) are installed on both sides of the conveying bucket frame (143), a side fixed rotating rod (144) is provided above one of the top fixed rotating rods (145), a clamping block (146) is installed on the top of the side fixed rotating rod (144), and a built-in mixing impeller (149) is installed in the mixing drum (142).
8. The on-site construction equipment for UHPC building materials according to claim 7, characterized in that: The built-in stirring impeller (149) is used to stir the UHPC raw materials in the stirring drum (142); the stirring device mounting seat (141) is installed above the equipment box (13); the stirring drum (142) is connected to the water supply pipe (16) and the agent supply pipe (17) respectively; the bottom of the stirring drum (142) is connected to the material conveying pipe (15); the spray gun (19) is engaged between the adapting clamp (2474) and the lower connecting clamping platform (2475); and the spray gun (19) is moved in cooperation with the slide platform (249).
9. The on-site construction equipment for UHPC building materials according to claim 6, characterized in that: A support column platform (1111) is arranged inside the stable support platform (111), an auxiliary shaft groove (1112) is provided on the support column platform (1111), a swing support frame (1113) is installed on the auxiliary shaft groove (1112), a clamping groove (1114) is provided on the swing support frame (1113), an inner shaft (1115) is installed on the swing support frame (1113), and an adjustable support column (1116) is nested on the inner shaft (1115). A sleeve cylinder (11161) is arranged inside the adjustable support column (1116), an axial through hole (11162) is opened on the sleeve cylinder (11161), a telescopic sleeve cylinder (11164) is nested in the sleeve cylinder (11161), and a plurality of groups of limiting holes (11163) are opened on the telescopic sleeve cylinder (11164) and the sleeve cylinder (11161), and a limiting pin (11165) passes through one group of the limiting holes (11163).
10. The on-site construction equipment for UHPC building materials according to claim 9, characterized in that: The limit pin (11165) passes through the sleeve tube (11161) and the telescopic sleeve tube (11164) respectively. The bottom of the telescopic sleeve tube (11164) is provided with a rubber pad. The sleeve tube (11161) is hingedly connected with the inner rotating shaft (1115) through the shaft through-hole (11162). After the sleeve tube (11161) swings, the top end is engaged in the slot (1114). The support column platform (1111) is welded to the upper surface of the frame (11).
Citation Information
Patent Citations
Constructional engineering concrete spraying and pouring construction method
CN113565329A
Concrete pouring device for high-rise building construction
CN119122286A
Ultra-high performance concrete spraying device
CN218437057U
Masonry device for aerated concrete thin layer made of sludge
CN219604891U
Apparatuses and systems for and methods of generating and placing zero-slump-pumpable concrete
US20190308342A1