Roadbed filling construction device and construction method thereof
By designing a roadbed filling construction device and using the combination of a road roller and a box, roadbed filling construction on complex terrain in high groundwater levels has been achieved, solving the problems of inconvenient transportation of filling materials and waste of materials, and improving construction efficiency and material utilization.
Patent Information
- Application Number
- CN202411976482.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-31
- Publication Date
- 2025-04-04
AI Technical Summary
When filling the roadbed in high groundwater areas, the terrain is complex and the soil is soft, and there is a difference in height between the roadbed troughs, which leads to inconvenient transportation of the filling materials and is easy to pour out of the roadbed troughs, resulting in waste of materials.
A roadbed filling construction device is designed, including a drainage and grouting mechanism in the roadbed trough, as well as a combination of a road roller and a box. The box is equipped with a temporary storage bin, a discharge bin, an anti-blocking mechanism and a dispersed discharge mechanism. The box is moved by a roller to realize automatic discharge and dispersed discharge of fill materials, reducing manpower operation and material waste.
Through the automated cutting and dispersed cutting process, the transportation efficiency of filling materials is improved, material waste is reduced, and the construction process is simplified. It is suitable for roadbed filling in complex terrain in high groundwater areas.
Smart Images

Figure CN119754115A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of roadbed filling, in particular to a roadbed filling construction device and a construction method thereof. Background Art
[0002] Roadbed filling is the process of filling the soil required for the roadbed with earth and stone and other materials during road construction to ensure the stability and bearing capacity of the road. When carrying out earth filling projects in areas with high groundwater levels, special attention should be paid to the impact of hydrological conditions on the quality and long-term stability of the fill. A high groundwater level will have a significant impact on the compactness, bearing capacity and settlement of the soil. Therefore, some special construction methods and technical means are needed in earth filling construction in such areas.
[0003] Areas with high groundwater levels usually undergo drainage to lower the groundwater level at the construction site and reduce the impact of moisture on the quality of the fill. After the moisture is drained, the soil settles and gradually forms a roadbed trench. Filling materials are laid in the roadbed trench for compaction. However, there are many troubles and inconveniences in the process of laying filling materials: areas with high groundwater levels often have complex terrain, relatively soft soil, and there are height differences in the roadbed trench. When unloading materials through the bucket of a fill transport truck, the fill transport truck needs to be moved multiple times to pour the filling materials to different locations in the roadbed trench, which is rather troublesome. In the process of unloading materials through the bucket, some of the filling materials are prone to dumping outside the roadbed trench, resulting in waste of filling materials.
[0004] To this end, the present invention provides a roadbed filling construction device and a construction method thereof. Summary of the invention
[0005] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.
[0006] The present invention provides a roadbed filling construction device and a construction method thereof, comprising a roadbed trench and a road roller, wherein a drainage mechanism and a grouting mechanism are arranged in the roadbed trench, wherein the drainage mechanism is used to drain the roadbed, and the grouting mechanism is used to grout and reinforce the roadbed, wherein a filling material is arranged in the roadbed trench, and the road roller 5 is used to compact the filling material 4; The filling material consists of a crushed stone layer, a sand-gravel mixed soil layer and an asphalt concrete layer from bottom to top; The roller side wall is fixedly connected to a box body, and the box body is used for temporarily storing and unloading filling materials. A temporary storage bin and a unloading bin are fixedly connected in the box body, and the unloading bin is located at the bottom of the temporary storage bin. The side wall of the box body is fixedly connected to a motor, and the output end of the motor is fixedly connected to a screw, and the screw is a reciprocating screw, which penetrates the side wall of the box body and extends into the interior thereof and is rotatably connected to the inner wall of the box body. A movable plate is threadedly connected to the screw, and the movable plate is arranged in contact with the bottom surface of the temporary storage bin, and the movable plate is used to control the unloading of the filling material. An anti-blocking mechanism is arranged in the temporary storage bin, and the anti-blocking mechanism is used to prevent the filling material from being blocked. A dispersing unloading mechanism is arranged in the unloading bin, and the dispersing unloading mechanism is used to disperse the unloading of the filling material; The bottom of the box body is integrally formed with a partition, and a leveling mechanism is provided at the bottom of the partition, and the leveling mechanism is used to level the filling material in the roadbed trench.
[0007] Preferably, the drainage mechanism includes a plurality of precipitation wells opened in the construction area, and the precipitation wells are connected with a pumping pipe, the pumping pipe is fixedly connected to a water pump and is connected to the input end of the water pump, and the output end of the water pump is fixedly connected to a drainage pipe.
[0008] Preferably, the grouting mechanism comprises a plurality of vertical shafts opened in the construction area, and steel cages are arranged in the vertical shafts, and concrete is poured into the steel cages to form pile bodies.
[0009] Preferably, the anti-blocking mechanism includes a driving wheel 1 fixedly connected to the screw, a driven shaft 1 is rotatably connected in the temporary storage bin, the driven shaft 1 passes through the side wall of the temporary storage bin and is rotatably connected to the inner wall of the box body, a driven wheel 1 is fixedly connected to the driven shaft 1, a belt is provided between the driven wheel 1 and the driving wheel 1, and the driven wheel 1 and the driving wheel 1 are connected through belt transmission, and a plurality of stirring rods are fixedly connected to the driven shaft 1.
[0010] Preferably, the dispersed material discharge mechanism includes a driving wheel 2 fixedly connected to the screw, a sealing assembly fixedly connected in the material discharge bin, the sealing assembly is hollow inside and has openings on the side and the bottom, the inner top surface of the sealing assembly is rotatably connected to a driven shaft 3, the bottom end of the driven shaft 3 is fixedly connected to a plurality of dispersion blades, a driven shaft 2 is arranged in the sealing assembly, the driven shaft 2 passes through the side wall of the material discharge bin and is rotatably connected to the inner wall of the box body, the driven shaft 2 is fixedly connected to a bevel gear 1, the driven shaft 3 is fixedly connected to a bevel gear 2, and the bevel gear 2 is meshingly connected to the bevel gear 1, the driven shaft 2 is fixedly connected to a driven wheel 2, a belt is arranged between the driven wheel 2 and the driving wheel 2, and the driven wheel 2 and the driving wheel 2 are connected by a belt drive.
[0011] Preferably, the pushing mechanism includes an extension plate fixedly connected to the side wall of the partition, a plurality of hollow tubes are fixedly connected to the bottom surface of the extension plate, a spring is fixedly connected inside the hollow tube, a movable rod is fixedly connected to the spring, and the movable rod is slidably connected to the hollow tube, and a pushing plate is fixedly connected to the bottom end of the movable rod.
[0012] Preferably, a protective assembly is provided on the top surface of the dispersion blade, and the protective assembly includes a plurality of fixed cylinders fixedly arranged on the top surface of the dispersion blade, a mounting rod is slidably connected in the fixed cylinder, and a spring is arranged in the extrusion cavity of the mounting rod and the fixed cylinder, a connecting plate is provided on the top of the mounting rod, and a plurality of the mounting rods are fixedly arranged on the connecting plate, and a rubber plate is fixedly connected to the top surface of the connecting plate.
[0013] Preferably, the lead screw is arranged on one side of the movable plate, and the other side of the movable plate is slidably connected to a limiting rod, and the limiting rod is fixed between the inner walls of the box body.
[0014] Preferably, the sealing assembly is a hollow right-angle plate structure, and a triangular block is fixedly connected to the top surface of the sealing assembly.
[0015] A construction method according to the above-mentioned roadbed filling construction device comprises the following steps: S1: dig several precipitation wells in the construction area, set up several water pumps in the construction area, install a pumping pipe at the input end of the water pump, install the pumping pipe into the precipitation well, install a drainage pipe at the output end of the water pump, dig a drainage ditch away from the construction area, lay the drainage pipe into the drainage ditch, the water level at the bottom of the construction area drops, the soil layer sinks and forms a roadbed groove; S2: Drill several vertical shafts on both sides of the roadbed trench by a drilling rig, put the steel cage into the vertical shaft, and then pour concrete into the steel cage to form a pile body; S3: The roller is hoisted into the roadbed trench by a crane. The roller compacts the roadbed trench first, and then delivers a number of filling materials into the box in sequence. The order of loading is crushed stone layer - gravel mixed soil layer - asphalt concrete layer. The roller unloads and compacts a number of filling materials, using layered compaction. The thickness of the filling materials is controlled between - centimeters each time.
[0016] The beneficial effects of the present invention are as follows: the roadbed filling construction device and the construction method thereof described in the present invention respectively transport several kinds of filling materials to the temporary storage bin by manpower, unload them through the unloading bin, and the box body moves in the roadbed trench as the roller moves, so that the filling materials can be moved and laid in the roadbed trench. Compared with the dump bucket unloading process of the traditional filling transport vehicle, the filling materials are laid by using the roller instead of the filling transport vehicle, and the waste rate of the filling materials is low.
[0017] The roadbed filling construction device and the construction method thereof described in the present invention can avoid clogging of the filling material in the temporary storage bin through the anti-clogging mechanism, which is beneficial to the unloading of the filling material.
[0018] The roadbed filling construction device and construction method of the present invention can utilize a plurality of rotating dispersing blades to collide or throw the filling material to the surroundings through a dispersing material discharging mechanism, thereby increasing the discharging range of the filling material and achieving the effect of dispersing material discharging. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of the drainage mechanism in the present invention; Figure 2 It is a structural schematic diagram of the grouting mechanism in the present invention; Figure 3 It is a structural schematic diagram of the road roller in the present invention; Figure 4 is a cross-sectional view of the box body of the present invention; Figure 5 It is a structural schematic diagram of the movable plate in the present invention; Figure 6 The present invention Figure 4 The enlarged view of point A in the middle; Figure 7 It is a structural schematic diagram of the sealing component in the present invention; Figure 8 The present invention Figure 4 Enlarged view of point B in the middle.
[0020] Description of reference numerals: 1. Roadbed groove; 2. Drainage mechanism; 3. Grouting mechanism; 4. Filling material; 41. Crushed stone layer; 42. Sand and gravel mixed soil layer; 43. Asphalt concrete layer; 5. Road roller; 6. Box; 7. Partition; 8. Pushing mechanism; 81. Extension plate; 82. Hollow cylinder; 83. Movable rod; 84. Pushing plate; 9. Motor; 10. Temporary storage bin; 11. Screw; 12. Movable plate; 13. Anti-blocking mechanism; 131. Driving wheel 1; 132. Driven wheel 1; 1 33. Driven shaft one; 134. Stirring rod; 14. Discharging bin; 15. Dispersing discharging mechanism; 151. Driving wheel two; 152. Driven shaft two; 153. Driven wheel two; 154. Sealing assembly; 155. Bevel gear one; 156. Driven shaft three; 157. Bevel gear two; 158. Dispersing blades; 16. Limiting rod; 17. Triangular block; 18. Protective assembly; 181. Fixing cylinder; 182. Mounting rod; 183. Connecting plate; 184. Rubber plate. DETAILED DESCRIPTION
[0021] The subject matter described herein will now be discussed with reference to example embodiments. It should be understood that the discussion of these embodiments is only to enable those skilled in the art to better understand and implement the subject matter described herein, and the functions and arrangements of the elements discussed may be changed without departing from the scope of protection of the contents of this specification. Each example may omit, replace or add various processes or components as needed. In addition, the features described relative to some examples may also be combined in other examples. Example
[0022] like Figures 1 to 8 As shown, the roadbed filling construction device of the embodiment of the present invention, please refer to Figure 1 , Figure 2 , Figure 3 , Figure 4 , including a roadbed groove 1 and a roller 5. A drainage mechanism 2 and a grouting mechanism 3 are arranged in the roadbed groove 1. The drainage mechanism 2 is used to drain the roadbed, and the grouting mechanism 3 is used to grout and reinforce the roadbed. Filling material 4 is arranged in the roadbed groove 1, and the roller 5 is used to compact the filling material 4. The filling material 4 is composed of a crushed stone layer 41, a gravel mixed soil layer 42 and an asphalt concrete layer 43 from bottom to top. The crushed stone layer 41 is used to support the filling material 4 above and buffer the dynamic load brought by the driving of vehicles on the road. The gravel mixed soil layer 42 has good compaction, stability and water permeability. The asphalt concrete layer 43 can prevent a large amount of rainwater from dripping in and keep the filling material 4 dry. A roller 5 is arranged in the roadbed groove 1. A box 6 is fixedly connected to the side wall of the roller 5. The box 6 is used for temporary storage and unloading of the filling material 4. A temporary storage bin 10 and an unloading bin 14 are fixedly connected in the box 6, and the unloading bin 14 is located at the bottom of the temporary storage bin 10. A motor 9 is fixedly connected to the side wall of the box body 6, and a screw 11 is fixedly connected to the output end of the motor 9. The screw 11 is a reciprocating screw. The screw 11 penetrates the side wall of the box body 6 and extends into the interior thereof and is rotatably connected to the inner wall of the box body 6. A movable plate 12 is threadedly connected to the screw 11, and the movable plate 12 is arranged in contact with the bottom surface of the temporary storage bin 10. The screw 11 is arranged on one side of the movable plate 12, and the other side of the movable plate 12 is slidably connected to a limit rod 16, which is fixed between the inner walls of the box body 6. The movable plate 12 is used to control the discharge of the filling material 4. An anti-blocking mechanism 13 is arranged in the temporary storage bin 10, and the anti-blocking mechanism 13 is used to prevent the filling material 4 from blocking the material. A dispersing discharge mechanism 15 is arranged in the discharge bin 14, and the dispersing discharge mechanism 15 is used to disperse the discharge of the filling material 4. The bottom of the box body 6 is integrally formed with a partition 7, and a flattening mechanism 8 is arranged at the bottom of the partition 7. The flattening mechanism 8 is used to flatten the filling material 4 in the roadbed groove 1.
[0023] Specifically, manpower transports several kinds of filling materials 4 to the temporary storage bin 10 respectively. At this time, the movable plate 12 blocks the temporary storage bin 10, drives the motor 9, and drives the screw 11 to rotate. Since the screw 11 is a reciprocating screw, the movable plate 12 will move back and forth. The movement of the movable plate 12 can make the filling material 4 in the temporary storage bin 10 leak out and leak into the lower bin 14 for discharge. The box body 6 moves in the roadbed trench 1 with the movement of the roller 5, so that the filling material 4 can be moved and laid in the roadbed trench 1. Compared with the traditional dump bucket unloading process of the filling transport vehicle, the roller 5 is used to replace the filling transport vehicle to move and lay the filling material 4, and the waste rate of the filling material 4 is low.
[0024] Please pay attention to Figure 1 The drainage mechanism 2 includes several precipitation wells opened in the construction area, and the precipitation wells are connected with a pumping pipe, the pumping pipe is fixedly connected with a water pump and is connected with the input end of the water pump, and the output end of the water pump is fixedly connected with a drainage pipe.
[0025] Specifically, by establishing a deep well system, deep wells are drilled in areas with high groundwater levels, and then groundwater is pumped out with a pump to lower the groundwater level in the surrounding soil. The purpose of this is to reduce or control groundwater infiltration during construction, avoid the impact of rising water levels on buildings or projects, and keep the construction area dry.
[0026] Please pay attention to Figure 2 The grouting mechanism 3 includes several vertical shafts opened in the construction area, and steel cages are arranged in the vertical shafts, and concrete is poured into the steel cages to form pile bodies.
[0027] Specifically, bored cast-in-place piles can better adapt to irregular terrain and soft soil layers and have strong adaptability. Pile foundation reinforcement can not only improve the bearing capacity of the foundation, but also effectively reduce problems such as uneven settlement and ground subsidence, ensuring the safety and stability of buildings or roadbeds.
[0028] Please pay attention to Figure 4 , Figure 5 The anti-blocking mechanism 13 includes a driving wheel 131 fixedly connected to the screw 11, a driven shaft 133 is rotatably connected in the temporary storage bin 10, the driven shaft 133 penetrates the side wall of the temporary storage bin 10 and is rotatably connected to the inner wall of the box body 6, a driven wheel 132 is fixedly connected to the driven shaft 133, a belt is arranged between the driven wheel 132 and the driving wheel 131, and the driven wheel 132 and the driving wheel 131 are connected through belt transmission, and a plurality of stirring rods 134 are fixedly connected to the driven shaft 133.
[0029] Specifically, the rotation of the lead screw 11 drives the driving wheel 131 to rotate, and the driven wheel 132 is rotated through the belt transmission, which in turn drives the driven shaft 133 to rotate, and finally drives the stirring rod 134 to rotate. The rotation of the stirring rod 134 can stir the filling material 4 in the temporary storage bin 10 to avoid blockage, thereby facilitating the discharge of the filling material 4.
[0030] Please pay attention to Figure 4 , Figure 5 , Figure 6 , Figure 7 The dispersing unloading mechanism 15 includes a driving wheel 2 151 fixedly connected to the screw 11, a sealing assembly 154 is fixedly connected in the unloading bin 14, the sealing assembly 154 is hollow inside and has openings on the side and bottom, the inner top surface of the sealing assembly 154 is rotatably connected to a driven shaft 3 156, the bottom end of the driven shaft 3 156 is fixedly connected to a plurality of dispersing blades 158, a driven shaft 2 152 is arranged in the sealing assembly 154, the driven shaft 2 152 passes through the side wall of the unloading bin 14 and is rotatably connected to the inner wall of the box body 6, the driven shaft 2 152 is fixedly connected to a bevel gear 1 155, the driven shaft 3 156 is fixedly connected to a bevel gear 2 157, and the bevel gear 2 157 is meshed with the bevel gear 155, the driven shaft 2 152 is fixedly connected to a driven wheel 2 153, a belt is arranged between the driven wheel 2 153 and the driving wheel 2 151, and the driven wheel 2 1 53 and the driving wheel 2 151 are connected by belt drive, the sealing component 154 is a hollow right-angle plate structure, and the top surface of the sealing component 154 is fixedly connected with a triangular block 17, which can prevent the filling material 4 from stagnating on the sealing component 154, and at the same time can protect the sealing component 154 and reduce the impact of the falling impact of the filling material 4. The top surface of the dispersion blade 158 is provided with a protective component 18, and the protective component 18 includes a plurality of fixed cylinders 181 fixedly arranged on the top surface of the dispersion blade 158, and a mounting rod 182 is slidably connected in the fixed cylinder 181, and a spring is arranged in the extrusion cavity of the mounting rod 182 and the fixed cylinder 181, and a connecting plate 183 is arranged on the top of the mounting rod 182, and a plurality of mounting rods 182 are fixedly arranged with the connecting plate 183, and a rubber plate 184 is fixedly connected to the top surface of the connecting plate 183.
[0031] Specifically, the partition 7 can prevent the filling material 4 from being thrown forward, and the rotation of the lead screw 11 drives the active wheel 2 151 and the driven wheel 2 153 to rotate, thereby driving the driven shaft 2 152 and the bevel gear 1 155 to rotate, and the rotation of the bevel gear 155 drives the bevel gear 2 157 to rotate, thereby driving the driven shaft 3 156 and the dispersion blade 158 to rotate, and the filling material 4 descends and contacts with the protective component 18 on the top of the rotating dispersion blade 158, and the filling material 4 falls onto the rubber plate 184, which can make the filling material 4 rebound or throw the filling material 4 to the surroundings, increase the feeding range of the filling material 4, play a role in dispersing the feeding, and make the filling material 4 fill the inside of the roadbed groove 1, and the spring between the mounting rod 182 and the fixing tube 181 can buffer the impact of the falling of the filling material 4, and the rubber plate 184 has the advantages of good wear resistance and elasticity, which is conducive to rebounding the filling material 4 and dispersing the feeding.
[0032] Please pay attention to Figure 3 , Figure 4 The pushing mechanism includes an extension plate 81 fixedly connected to the side wall of the partition 7, a plurality of hollow tubes 82 are fixedly connected to the bottom surface of the extension plate 81, a spring is fixedly connected inside the hollow tube 82, a movable rod 83 is fixedly connected to the spring, and the movable rod 83 is slidably connected to the hollow tube 82, a pushing plate 84 is fixedly connected to the bottom end of the movable rod 83, and a plurality of hollow tubes 82 are arranged in two groups, and the two groups of hollow tubes 82 are symmetrically distributed about the center line of the partition 7.
[0033] Specifically, the pushing plate 84 can push and level the filling material 4 in the roadbed trench 1 as the road roller 5 moves, so that the filling material 4 can be laid evenly and the compaction degree of the filling material 4 can be improved.
[0034] A construction method according to the above roadbed filling construction device comprises the following steps: S1: dig several precipitation wells in the construction area, set up several water pumps in the construction area, install a pumping pipe at the input end of the water pump, install the pumping pipe into the precipitation well, install a drainage pipe at the output end of the water pump, dig a drainage ditch away from the construction area, lay the drainage pipe into the drainage ditch, the water level at the bottom of the construction area drops, the soil layer sinks and forms a roadbed groove 1; S2: Drill several vertical shafts on both sides of the roadbed trench 1 by means of a drilling rig, place a steel cage into the vertical shaft, and then pour concrete into the steel cage to form a pile body; S3: The roller 5 is hoisted into the roadbed trench 1 by a crane. The roller 5 first compacts the roadbed trench 1, and then delivers a plurality of filling materials 4 to the box 6 in sequence. The loading sequence is crushed stone layer 41 - gravel mixed soil layer 42 - asphalt concrete layer 43. The roller 5 unloads and compacts the plurality of filling materials 4, and adopts layered compaction. The thickness of the filling material 4 is controlled between 30 and 40 cm each time.
[0035] How it works The packaging bags containing the crushed stone layer 41 are transported to both sides of the roadbed trench 1 by manpower or a small cart, and the filling material 4 inside is poured into the temporary storage bin 10. At this time, the movable plate 12 blocks the temporary storage bin 10, and the roller 5 is located at one end of the roadbed trench 1; When it is necessary to unload materials, the roller 5 is moved to the other end, and the driving motor 9 drives the screw 11 to rotate. Since the screw 11 is a reciprocating screw, the movable plate 12 on the screw 11 will reciprocate. The movement of the movable plate 12 can make the filling material 4 in the temporary storage bin 10 leak out. At this time, the rotation of the screw 11 drives the driving wheel 131 to rotate, and the driven wheel 132 is rotated through the belt transmission, thereby driving the driven shaft 133 to rotate, and finally driving the stirring rod 134 to rotate. The rotation of the stirring rod 134 can stir the filling material 4 in the temporary storage bin 10 to avoid its blockage, thereby facilitating the unloading of the filling material 4, and the filling The filling material 4 then leaks into the lower feeding bin 14. At this time, the rotation of the lead screw 11 also drives the second driving wheel 151 and the second driven wheel 153 to rotate, thereby driving the second driven shaft 152 and the first bevel gear 155 to rotate. The rotation of the first bevel gear 155 drives the second bevel gear 157 to rotate, thereby driving the third driven shaft 156 and the dispersion blade 158 to rotate. The filling material 4 falls and contacts the rubber plate 184 on the top of the rotating dispersion blade 158, which can make the filling material 4 rebound or throw the filling material 4 to the surroundings, thereby increasing the feeding range of the filling material 4 and playing the role of dispersing the feeding, so that the filling material 4 fills the inside of the roadbed groove 1. After the roller 5 moves to the other end, the pushing plate 84 can push the filling material 4 in the roadbed trench 1 flat as the roller 5 moves, so that the filling material 4 can be laid evenly and the compaction degree of the filling material 4 can be improved. The gravel layer 41 has also been laid, and local adjustments can be made manually to make the gravel layer 41 laid perfectly. Then the roller 5 is moved in the opposite direction for compaction. The laying and compaction principles of the gravel mixed soil layer 42 and the asphalt concrete layer 43 are the same, and multiple layered compaction is adopted. The thickness of the filling material 4 is controlled between 30 and 40 cm each time. After each layer of the filling material 4 is filled, it is fully compacted to ensure the stability of the soil layer and avoid settlement or displacement due to the buoyancy of groundwater.
[0036] An example of the present specific implementation mode is described above, but the present embodiment is not limited to the above-mentioned specific implementation mode, which is merely illustrative and not restrictive. A person skilled in the art may make many forms inspired by the present embodiment, all of which are protected by the present embodiment.
Claims
1. A roadbed filling construction device, characterized in that: The invention comprises a roadbed trench (1) and a roller (5), wherein a drainage mechanism (2) and a grouting mechanism (3) are arranged in the roadbed trench (1), wherein the drainage mechanism (2) is used for draining the roadbed, and the grouting mechanism (3) is used for grouting and reinforcing the roadbed, wherein a filling material (4) is arranged in the roadbed trench (1), and the roller (5) is used for compacting the filling material (4); The filling material (4) consists of a crushed stone layer (41), a sand-gravel mixed soil layer (42) and an asphalt concrete layer (43) from bottom to top; The roller (5) is fixedly connected to a box body (6) on the side wall thereof. The box body (6) is used for temporarily storing and unloading the filling material (4). A temporary storage bin (10) and a unloading bin (14) are fixedly connected inside the box body (6), and the unloading bin (14) is located at the bottom of the temporary storage bin (10). A motor (9) is fixedly connected to the side wall of the box body (6). A lead screw (11) is fixedly connected to the output end of the motor (9). The lead screw (11) is a reciprocating lead screw. The lead screw (11) penetrates the side wall of the box body (6) and extends into the interior thereof and rotates with the inner wall of the box body (6). The movable plate (12) is connected to the lead screw (11) by a thread, and the movable plate (12) is arranged to fit the bottom surface of the temporary storage bin (10). The movable plate (12) is used to control the discharge of the filling material (4). The temporary storage bin (10) is provided with an anti-blocking mechanism (13). The anti-blocking mechanism (13) is used to prevent the filling material (4) from blocking. The discharge bin (14) is provided with a dispersing discharge mechanism (15). The dispersing discharge mechanism (15) is used to disperse the discharge of the filling material (4). The bottom of the box body (6) is integrally formed with a partition (7), and a leveling mechanism (8) is provided at the bottom of the partition (7). The leveling mechanism (8) is used to level the filling material (4) in the roadbed trench (1).
2. The roadbed filling construction device according to claim 1 is characterized in that: The drainage mechanism (2) comprises a plurality of precipitation wells opened in the construction area, and the precipitation wells are connected to a water pumping pipe, the water pumping pipe is fixedly connected to a water pump and is connected to an input end of the water pump, and the output end of the water pump is fixedly connected to a drainage pipe.
3. The roadbed filling construction device according to claim 1 is characterized in that: The grouting mechanism (3) comprises a plurality of vertical shafts opened in the construction area, and steel cages are arranged in the vertical shafts. Concrete is poured into the steel cages to form a pile body.
4. The roadbed filling construction device according to claim 1, characterized in that: The anti-blocking mechanism (13) comprises a driving wheel (131) fixedly connected to the lead screw (11); a driven shaft (133) is rotatably connected in the temporary storage bin (10); the driven shaft (133) penetrates the side wall of the temporary storage bin (10) and is rotatably connected to the inner wall of the box body (6); a driven wheel (132) is fixedly connected to the driven shaft (133); a belt is provided between the driven wheel (132) and the driving wheel (131); the driven wheel (132) and the driving wheel (131) are connected via a belt transmission; and a plurality of stirring rods (134) are fixedly connected to the driven shaft (133).
5. The roadbed filling construction device according to claim 1, characterized in that: The dispersing unloading mechanism (15) comprises a second driving wheel (151) fixedly connected to the lead screw (11); a sealing assembly (154) is fixedly connected in the unloading bin (14); the sealing assembly (154) is hollow inside and has openings on the side and the bottom; a driven shaft (156) is rotatably connected to the inner top surface of the sealing assembly (154); a plurality of dispersing blades (158) are fixedly connected to the bottom end of the driven shaft (156); a driven shaft (152) is arranged in the sealing assembly (154); the driven shaft (152) is connected to the driven shaft (152) through the driven shaft (152). The driven shaft (152) passes through the side wall of the lower silo (14) and is rotatably connected to the inner wall of the box body (6); the driven shaft (152) is fixedly connected to the bevel gear (155); the driven shaft (156) is fixedly connected to the bevel gear (157), and the bevel gear (157) is meshingly connected to the bevel gear (155); the driven shaft (152) is fixedly connected to the driven wheel (153); a belt is provided between the driven wheel (153) and the driving wheel (151), and the driven wheel (153) and the driving wheel (151) are connected through a belt transmission.
6. The roadbed filling construction device according to claim 1, characterized in that: The push-flattening mechanism comprises an extension plate (81) fixedly connected to the side wall of the partition (7); a plurality of hollow tubes (82) are fixedly connected to the bottom surface of the extension plate (81); a spring is fixedly connected inside the hollow tube (82); a movable rod (83) is fixedly connected to the spring; the movable rod (83) is slidably connected to the hollow tube (82); and a push-flat plate (84) is fixedly connected to the bottom end of the movable rod (83).
7. The roadbed filling construction device according to claim 5, characterized in that: A protective component (18) is provided on the top surface of the dispersion blade (158), and the protective component (18) comprises a plurality of fixed cylinders (181) fixedly arranged on the top surface of the dispersion blade (158), a mounting rod (182) is slidably connected in the fixing cylinder (181), and a spring is provided in the extrusion cavity between the mounting rod (182) and the fixing cylinder (181), a connecting plate (183) is provided on the top of the mounting rod (182), and a plurality of the mounting rods (182) are fixedly arranged on the connecting plate (183), and a rubber plate (184) is fixedly connected to the top surface of the connecting plate (183).
8. The roadbed filling construction device according to claim 1, characterized in that: The lead screw (11) is arranged on one side of the movable plate (12), and the other side of the movable plate (12) is slidably connected to a limit rod (16), and the limit rod (16) is fixed between the inner walls of the box body (6).
9. The roadbed filling construction device according to claim 5, characterized in that: The sealing component (154) is in the form of a hollow right-angle plate structure, and a triangular block (17) is fixedly connected to the top surface of the sealing component (154).
10. A construction method of the roadbed filling construction device according to any one of claims 1 to 9, characterized in that: The following steps are involved: S1: dig several drainage wells in the construction area, set up several water pumps in the construction area, install a pumping pipe at the input end of the water pump, install the pumping pipe into the drainage well, install a drainage pipe at the output end of the water pump, dig a drainage ditch away from the construction area, lay the drainage pipe into the drainage ditch, the water level at the bottom of the construction area drops, the soil layer sinks and forms a roadbed trench (1); S2: Drilling a number of vertical shafts on both sides of the roadbed trench (1) by means of a drilling rig, placing a steel cage into the vertical shafts, and then pouring concrete into the steel cage to form a pile body; S3: The roller (5) is hoisted into the roadbed trench (1) by a crane. The roller (5) first compacts the roadbed trench (1), and then sequentially delivers a plurality of filling materials (4) into the box (6). The loading sequence is crushed stone layer (41) - gravel mixed soil layer (42) - asphalt concrete layer (43). The roller (5) delivers and compacts the plurality of filling materials (4). Layered compaction is adopted, and the thickness of each filling material (4) is controlled to be between 30 and 40 centimeters.