A temporary access road structure for a barrel-type foundation structure embankment and its implementation method
By designing the temporary walkway structure of the barrel infrastructure dike, using jacks and rubber pads to improve structural stability, and decomposing the vehicle load through vertical racks, the high cost and complex installation problems of the closing opening of the barrel infrastructure dike in the existing technology are solved, and the stability and construction efficiency are improved.
Patent Information
- Application Number
- CN202510263177.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-06
- Publication Date
- 2025-05-23
- Estimated Expiration
- 2045-03-06
AI Technical Summary
The prior art solves the problems of high cost, complex installation, poor adaptability and stability when opening the barrel infrastructure dam to traffic.
A temporary walkway structure of barrel infrastructure dam surrounding the dike was designed, including barrel infrastructure, lower frame, support frame, vertical frame, surface frame, railing, jack, rubber pad and panel. The lower frame is supported on the barrel infrastructure through jack and rubber pads, and the vertical frame is used to decompose the vehicle load and improve structural stability.
It significantly improves the stability of the structure, has a short construction period, is easy to install, and is easy to dismantle, solving the problems of high cost and complex installation in the existing technology.
Smart Images

Figure CN119754143B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of civil engineering and construction engineering, and in particular to a temporary access road structure of a barrel-type foundation embankment and an implementation method thereof. Background Art
[0002] The barrel foundation structure is a new type of foundation, usually made of precast concrete or steel structure, and shaped like a barrel or cylinder. It has the advantages of strong stability, fast construction speed, and adaptability to complex geological conditions. The closure of the dike is a key node in the construction of the dike. It is usually necessary to design temporary or permanent traffic at the closure to meet the traffic needs of construction vehicles, equipment and personnel. During the construction of the closure, how to ensure the passage of vehicles without affecting the progress and quality of the project, that is, to solve the traffic demand at the closure of the barrel foundation structure dike is an important technical problem.
[0003] At present, the commonly used methods to solve the traffic demand of the closing mouth of the barrel foundation structure embankment include: ① Designing a large-span bridge, although it can meet the traffic demand, but the construction cost is high, and as a temporary engineering facility, it needs to be dismantled after the main project is completed, and the cost of temporary measures for the main project accounts for a relatively high proportion; ② Traditional temporary bridges usually use steel trusses or Bailey bridges as temporary traffic structures, but there are problems such as complex installation and poor adaptability; ③ Floating bridges or floating platforms are suitable for areas with greater water depths, but they have poor stability and are greatly affected by wind and waves; ④ Precast concrete structures have good stability, but long construction periods, and are difficult to install and disassemble quickly; ⑤ Combined structures, combining steel structures and concrete structures, but are expensive and have high requirements for construction technology.
[0004] The above-mentioned prior art either has the problem of high cost, or has the problem of complex installation and construction, poor adaptability and stability. Based on the shortcomings of the prior art, combined with the characteristics of the barrel-type foundation structure embankment closing mouth and the barrel-type foundation structure, the present invention provides a barrel-type foundation structure embankment temporary access road structure and implementation method to solve the problem of closing mouth passage. Summary of the invention
[0005] The present invention provides a temporary access road structure for a levee with a barrel-type foundation structure, comprising a barrel-type foundation structure, a lower layer frame, a supporting frame, a vertical frame, a surface layer frame, a handrail, a jack, a rubber pad and a panel;
[0006] One end of the jack is connected to the lower frame, and the other end is connected to the rubber pad, and the other side of the rubber pad is connected to the inner side of the barrel-type foundation structure;
[0007] The supporting rack is arranged on the barrel-type foundation structure and is located on the upper part of the lower rack; the vertical rack is located on the upper part of the supporting rack, the surface rack is located on the upper part of the vertical rack, and the railing and panel are arranged on the upper part of the surface rack.
[0008] Further, the lower layer truss includes several layers to form a truss structure. Each layer is composed of columns, scissor braces, and four-side braces. The scissor braces are in a cross shape, and the four-side braces are in a "square" shape. The lower layer truss bears horizontal loads.
[0009] Further, the lower layer truss is supported on the bucket foundation structure through jacks and rubber pads. One end of the rubber pad connected to the bucket foundation structure is arc-shaped.
[0010] Further, the support truss is in a "well" shape, fixedly connected to the upper part of the lower layer truss and supported on the bucket foundation structure, and is used to transfer vertical loads to the bucket foundation structure.
[0011] Further, the vertical truss includes columns and four-side braces. The vertical truss is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
[0012] Further, the vertical truss is fixedly connected to the upper part of the support truss, and the vertical members of the vertical truss and the lower layer truss are on the same center line.
[0013] Further, the surface layer truss includes columns and a grid structure. The surface layer truss is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
[0014] Further, the railing is vertically fixed on the surface layer truss, and is used to protect vehicles and prevent personnel from falling off the temporary access road.
[0015] Further, the panel is laid on the surface layer truss, and is used for vehicle passage and vehicle load transfer. The vehicle load transfer steps are as follows:
[0016] Step S01: When a vehicle passes, the panel transfers the vehicle load to the surface layer truss;
[0017] Step S02: The surface layer truss transfers the vehicle load to the vertical truss;
[0018] Step S03: The vertical truss divides the vehicle load into vertical load and horizontal load, and transfers them to the bucket foundation structure along two routes simultaneously. The transfer route of the vertical load is: the vertical truss transfers the vertical load to the support truss, and the support truss transfers it to the bucket foundation structure; the transfer route of the horizontal load is: the vertical truss transfers the horizontal load to the lower layer truss, and the lower layer truss transfers it to the bucket foundation structure through jacks and rubber pads.
[0019] An implementation method of a temporary access road structure for a dike of a bucket foundation structure includes the following steps:
[0020] Step S1: Install the bucket foundation structure;
[0021] Step S2: making a truss structure;
[0022] Step S3: using a crane ship to install the truss structure onto the barrel-type foundation structure;
[0023] Step S4: Fix the truss structure of the lower rack on the barrel-type foundation structure by means of jacks and rubber pads.
[0024] Compared with the prior art, the advantages and effects of this application are as follows:
[0025] 1. The barrel-type foundation structure embankment temporary access road structure provided by the present invention significantly improves the stability of the structure by considering multiple angles: ① The vertical gantry can decompose the vehicle load into vertical load and horizontal load and transmit them separately, thereby improving the structural stability by dispersing the vehicle load; ② The lower gantry is supported on the barrel-type foundation structure by jacks and rubber pads, further improving the stability of the structure itself.
[0026] 2. The implementation method of the temporary access road structure of the barrel-type foundation structure embankment provided by the present invention has a short construction period, is easy to install, and is easy to dismantle.
[0027] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application so that it can be implemented in accordance with the contents of the specification, and to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the following is a detailed description of the preferred embodiments of the present application in conjunction with the accompanying drawings as follows.
[0028] Based on the detailed description of the specific embodiments of the present application in combination with the accompanying drawings below, those skilled in the art will become more aware of the above and other objects, advantages and features of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are some embodiments of the present application. For ordinary technicians in this field, other drawings can also be obtained based on these drawings without creative work. In all drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, each element or part is not necessarily drawn according to the actual scale.
[0030] in:
[0031] Figure 1 It is an overall schematic diagram of a temporary access road structure of a barrel-type foundation structure embankment;
[0032] Figure 2 It is a front view of a temporary access road structure of a barrel-type foundation structure embankment;
[0033] Figure 3 It is a top view of the part above the supporting scaffolding of a temporary access road structure of a bucket-type foundation structure embankment;
[0034] Figure 4 It is a top view of the supporting frame and the parts below of the temporary access road structure of the embankment of a barrel-type foundation structure;
[0035] Among them: 1-barrel-type foundation structure; 2-lower layer frame; 3-supporting frame; 4-vertical frame; 5-surface layer frame; 6-rail; 7-jack; 8-rubber pad; 9-panel. DETAILED DESCRIPTION
[0036] To make the purpose, technical scheme and advantages of the embodiment of the present application clearer, the technical scheme in the embodiment of the present application will be clearly and completely described below in conjunction with the accompanying drawings in the embodiment of the present application. Obviously, the described embodiment is a part of the embodiment of the present application, rather than all of the embodiments. In the following description, specific details such as specific configuration and components are provided only to help fully understand the embodiments of the present application. Therefore, it should be clear to those skilled in the art that various changes and modifications can be made to the embodiments described herein without departing from the scope and spirit of the present application. In addition, for clarity and brevity, the description of known functions and structures is omitted in the embodiment.
[0037] It should be understood that the references to "one embodiment" or "this embodiment" throughout the specification mean that the specific features, structures, or characteristics associated with the embodiment are included in at least one embodiment of the present application. Therefore, the references to "one embodiment" or "this embodiment" appearing throughout the specification do not necessarily refer to the same embodiment. In addition, these specific features, structures, or characteristics may be combined in any suitable manner in one or more embodiments.
[0038] In addition, the present application may repeat reference numerals and / or letters in different examples. This repetition is for the purpose of simplicity and clarity, and does not in itself indicate the relationship between the various embodiments and / or settings discussed.
[0039] The term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, B exists alone, and A and B exist at the same time. The term " / and" in this article describes another type of association object relationship, indicating that there can be two relationships. For example, A / and B can mean: A exists alone, and A and B exist alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.
[0040] The term "at least one" in this article is merely a description of the association relationship of associated objects, indicating that there may be three relationships. For example, at least one of A and B can mean: A exists alone, A and B exist at the same time, and B exists alone.
[0041] It should also be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusions.
[0042] Example 1
[0043] This embodiment introduces a temporary access road structure for a barrel-type foundation embankment. Figure 1 For its front view, please see the attached Figure 2 The structure includes a barrel-type foundation structure 1, a lower row frame 2, a supporting row frame 3, a vertical row frame 4, a surface row frame 5, a railing 6, a jack 7, a rubber pad 8 and a panel 9;
[0044] One end of the jack 7 is connected to the lower rack 2, and the other end is connected to the rubber pad 8, and the other side of the rubber pad 8 is connected to the inner side of the barrel-type foundation structure 1;
[0045] The supporting rack 3 is arranged on the barrel-type foundation structure 1 and is located on the upper part of the lower rack 2; the vertical rack 4 is located on the upper part of the supporting rack 3, the surface rack 5 is located on the upper part of the vertical rack 4, and the railing 6 and panel 9 are arranged on the upper part of the surface rack 5.
[0046] Preferably, the lower rack 2 includes several layers to form a truss structure, each layer is composed of columns, scissors braces and four-side braces, the scissors braces are cross-shaped, and the four-side braces are "mouth"-shaped; the lower rack 2 bears horizontal loads.
[0047] Preferably, the lower rack 2 is supported on the barrel-type basic structure 1 by means of a jack 7 and a rubber pad 8, and one end of the rubber pad 8 connected to the barrel-type basic structure 1 is arc-shaped.
[0048] Preferably, the supporting rack 3 is in a "well" shape, fixedly connected to the upper part of the lower rack 2 and supported on the barrel-type foundation structure 1, and is used to transfer the vertical load to the barrel-type foundation structure 1. For a top view of the upper part of the supporting rack 3, please refer to the attached Figure 3 For the top view of the following parts, please refer to the attached Figure 4 .
[0049] Preferably, the vertical rack 4 includes columns and four side braces, and the vertical rack 4 is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
[0050] Preferably, the vertical rack 4 is fixedly connected to the upper part of the supporting rack 3 , and the vertical rack 4 and the vertical rods of the lower rack 2 are on the same center line.
[0051] Preferably, the surface layer frame 5 includes columns and a grid structure, and the surface layer frame 5 is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
[0052] Preferably, the railing 6 is vertically fixed on the surface layer frame 5 to protect vehicles and prevent people from falling off the temporary walkway.
[0053] Preferably, the panel 9 is laid on the surface layer frame 5 for vehicle passage and vehicle load transfer.
[0054] The technical effect achieved by this embodiment is: this embodiment provides a temporary access road structure for a barrel-type foundation embankment, which uses jacks and rubber pads to support the lower-level scaffolding on the barrel-type foundation structure, thereby significantly improving the stability of the structure itself.
[0055] Example 2
[0056] Based on Example 1, this example introduces a method for implementing a temporary access road structure of a barrel-type foundation embankment, including the following steps:
[0057] Step S11: installing the barrel-type basic structure 1;
[0058] Step S12: making a truss structure;
[0059] Step S13: using a crane ship to install the truss structure onto the barrel-type foundation structure 1;
[0060] Step S14: fix the truss structure of the lower rack 2 on the barrel-type foundation structure 1 by means of the jack 7 and the rubber pad 8.
[0061] When a vehicle passes by, the panel 9 transfers the vehicle load to the surface frame 5, the surface frame 5 transfers the vehicle load to the vertical frame 4, the vertical frame 4 divides the vehicle load into vertical load and horizontal load, and transfers them to the barrel-type foundation structure 1 simultaneously through two routes; the transmission route of the vertical load is: the vertical frame 4 transfers the vertical load to the supporting frame 3, and the supporting frame 3 transfers it to the barrel-type foundation structure 1; the transmission route of the horizontal load is: the vertical frame 4 transfers the horizontal load to the lower frame 2, and the lower frame 2 transfers it to the barrel-type foundation structure 1 through the jack 7 and the rubber pad 8.
[0062] The technical effect achieved by this embodiment is: the implementation method of a temporary access road structure of a barrel-type foundation structure embankment provided by this embodiment has a short construction period, simple installation, and easy dismantling; when in use, the vertical frame can decompose the vehicle load into vertical load and horizontal load and transmit them separately, thereby dispersing the vehicle load and further improving stability.
[0063] Example 3
[0064] Based on the above embodiment, this embodiment introduces a temporary access road structure of a barrel-type foundation structure of a given specification. Figure 1 -Attached Figure 4 .
[0065] The barrel-type foundation structure 1 is 10m high, with a long axis of 36.6m and a short axis of 20m; the upper cylinder has a diameter of 8.9m and a height of 5.0m;
[0066] Lower gantry 2: 4 1.5m long 300 I-beams as columns, 2 7.5m long 300 I-beams as scissor braces, 4 3.5m long 300 I-beams as four-side braces, one layer each in the upper and lower layers to form a truss structure;
[0067] The supporting frame 3 is composed of four 8.9m long 300 I-beams in a "well" shape;
[0068] Vertical frame 4: 4 7.8m long 300 I-beams are used as columns, and 4 3.5m long 300 I-beams are used as four side braces; vertical frame 4 is divided into three layers vertically, and scissor braces are set in each layer to form a truss structure;
[0069] Surface layer frame 5: 30 1.8m long 300 I-beams are used as columns, 6 9.0m long 300 I-beams and 5 11.0m long 300 I-beams are used as grids; surface layer frame 5 is vertically divided into two layers, and scissor braces are set in each layer to form a truss structure;
[0070] Railing 6: diameter 8cm, height 1.2m, wall thickness 5mm;
[0071] Panel 9: 9.0m*11.0m steel grille, 10cm thick, surface steel plate 1cm;
[0072] Jack 7: jacking weight 20 tons, stroke 30cm;
[0073] Rubber pad 8: one end is curved, the other end is flat, 40cm long, 30cm high and 30cm thick.
[0074] The above description is only the preferred embodiment of the present invention, which does not limit the protection scope of the present invention. For those skilled in the art, the present invention can be modified and varied in various ways. Within the spirit and principle of the present invention, any change, modification, replacement, integration and parameter change of these embodiments by conventional substitution or capable of achieving the same function without departing from the principle and spirit of the present invention shall fall within the protection scope of the present invention.
Claims
1. A method for implementing a temporary access road structure of a barrel-type foundation structure embankment, characterized in that: The following steps are involved: Step S11: installing the barrel-type base structure (1); Step S12: making a truss structure; Step S13: using a crane vessel to install the truss structure onto the barrel-type foundation structure (1); Step S14: fixing the truss structure of the lower rack (2) on the barrel-type foundation structure (1) by means of a jack (7) and a rubber pad (8); The temporary access road structure of the barrel-type foundation structure embankment comprises a barrel-type foundation structure (1), a lower layer frame (2), a supporting frame (3), a vertical frame (4), a surface layer frame (5), a handrail (6), a jack (7), a rubber pad (8) and a panel (9); One end of the jack (7) is connected to the lower rack (2), and the other end is connected to the rubber pad (8); the other end of the rubber pad (8) is arc-shaped and connected to the inner side of the barrel-type foundation structure (1); The supporting row frame (3) is arranged on the barrel-type foundation structure (1) and is located on the upper part of the lower row frame (2); the vertical row frame (4) is located on the upper part of the supporting row frame (3); the surface row frame (5) is located on the upper part of the vertical row frame (4); and the railing (6) and the panel (9) are arranged on the upper part of the surface row frame (5).
2. The implementation method of a temporary access road structure of a barrel-type foundation structure embankment according to claim 1 is characterized in that: The lower layer of the gantry (2) comprises several layers to form a truss structure, each layer being composed of uprights, scissor braces and four-side braces, the scissor braces being in a cross shape, and the four-side braces being in a "mouth" shape.
3. The implementation method of a temporary access road structure of a barrel-type foundation structure embankment according to claim 2 is characterized in that: The lower rack (2) is supported on the barrel-type foundation structure (1) by means of a jack (7) and a rubber pad (8).
4. The implementation method of a temporary access road structure of a barrel-type foundation structure embankment according to claim 1 is characterized in that: The supporting rack (3) is in a "well" shape and is fixedly connected to the upper part of the lower rack (2).
5. The method for implementing a temporary access road structure of a barrel-type foundation structure embankment according to claim 1 is characterized in that: The vertical frame (4) comprises upright columns and four side braces. The vertical frame (4) is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
6. The implementation method of a temporary access road structure of a barrel-type foundation structure embankment according to claim 2 or 5 is characterized in that: The vertical rack (4) is fixedly connected to the upper part of the supporting rack (3), and the vertical rack (4) and the vertical rods of the lower rack (2) are on the same center line.
7. The method for implementing a temporary access road structure of a barrel-type foundation structure embankment according to claim 1 is characterized in that: The surface layer frame (5) comprises upright columns and a grid structure. The surface layer frame (5) is vertically divided into several layers, and scissor braces are arranged in each layer to form a truss structure.
8. The method for implementing a temporary access road structure of a barrel-type foundation structure embankment according to claim 7 is characterized in that: The handrail (6) is vertically fixed on the surface layer frame (5).
9. The method for implementing a temporary access road structure of a barrel-type foundation structure embankment according to claim 8 is characterized in that: The panel (9) is laid on the surface layer frame (5) and is used for vehicle passage and vehicle load transfer.
Citation Information
Patent Citations
Sludge ultra-soft soil in-water steel structure construction platform and construction method thereof
CN115627744A