Road goaf filling method and system
By opening injection holes in the hole drilling area of the goaf and injecting solid filler into it, combined with the impact operation of the vibration equipment, the problems of unsolid and high cost of filling in the goaf in the prior art are solved, and efficient and dense goaf filling effect is achieved.
Patent Information
- Application Number
- CN202510039211.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-01-10
- Publication Date
- 2025-04-08
AI Technical Summary
When dealing with underground goafs, the scope of application of the grouting method is limited. The grouting method has a long construction period, high cost and inaccurate positioning of the grouting holes in large-area goafs lead to poor filling.
By determining the drilling area based on the relative positional relationship between the roadbed and the goaf, determining the position distribution of the injection holes according to the goaf depth information, opening the injection holes on the foundation and injecting solid filler into the goaf, and combining with the vibration equipment to impact the filler until the goaf is filled.
This method reduces the reinforcement area and engineering volume, saves fill materials, reduces costs, and improves the filling density of goaf, meeting the needs of roadbed construction.
Smart Images

Figure CN119777349A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of road construction methods, and in particular relates to a method and system for filling a road goaf area. Background Art
[0002] When encountering unfilled underground goafs during roadbed construction, the traditional treatment methods include plugging and filling and grouting. Among them, the plugging and filling method is mainly suitable for projects with good surrounding rock above and around the goaf, which can be excavated and exposed at low cost. It cannot be implemented in cases where the goaf is buried deep, the goaf is covered with a soil layer with poor stability, the materials and machinery are difficult to put into the goaf, the personnel have difficulty in operation, or the safety risks are high. Therefore, its scope of application is limited. The grouting method has the disadvantages of large grouting workload, long construction period, high cost, and it is impossible to ensure that the grouting hole is at the top of the goaf cavity. If the grouting hole is not positioned accurately, it is easy to form an air mass at the highest point, which cannot be filled densely. Summary of the invention
[0003] In view of the above-mentioned defects or deficiencies in the prior art, it is desired to provide a method and system for filling road goaf.
[0004] A first aspect of the present invention provides a method for filling a road goaf, comprising: Determine the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf area in the foundation; Determine the position distribution of injection holes in the perforated area according to the depth information of the goaf, and open injection holes on the foundation according to the position distribution of the injection holes, wherein the injection holes penetrate the surface area of the foundation and are connected with the goaf; Injecting solid filling material into the goaf through each of the injection holes until the solid filling material at a position corresponding to each of the injection holes reaches the top area of the goaf; Then, the solid filling material at the position corresponding to each injection hole is impacted, so that the solid filling material at the position corresponding to the injection hole is diffused toward the goaf corresponding to the position of the adjacent injection hole; The injection and impact operations of the solid filling material are repeated in sequence until the goaf is filled with the solid filling material.
[0005] In addition, the road goaf filling method of the present invention may also have the following additional technical features: In some embodiments, determining the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf in the foundation includes: Detecting the overlapping area between the roadbed area and the goaf area; If the overlapping area is located in the area where the roadbed is located, the area on the roadbed corresponding to the overlapping area is used as the punching area; If the overlapping area is partially located within the area where the roadbed is located and partially located outside the area where the roadbed is located, the area on the roadbed corresponding to the overlapping area and the area within a preset distance range outside the overlapping area is used as the drilling area, and the drilling area is located within the goaf.
[0006] In some embodiments, determining the position distribution of injection holes in the perforated area according to the depth information of the goaf includes: The injection holes are opened in the drilling area in an array distribution manner, and the distribution spacing of the injection holes corresponding to the area with high depth of the goaf is set to a first distance, and the distribution spacing of the injection holes corresponding to the area with low depth of the goaf is set to a second distance, and the first distance is smaller than the second distance.
[0007] In some embodiments, the step of opening the injection holes in the punching area in an array distribution manner includes: A plurality of rows of injection holes are arranged in the punching area along the extension direction of the roadbed at intervals, each row of injection holes includes a plurality of injection holes distributed at intervals perpendicular to the extension direction of the roadbed, and the injection holes in two adjacent rows of injection holes are staggered.
[0008] In some embodiments, a vibration device is used to impact the solid filler at a position corresponding to each injection hole, and the diameter of at least some parts of the vibration device is smaller than the diameter of the injection hole.
[0009] In some embodiments, the vibration device includes a vibration rod and a driving unit, wherein the driving unit is fixedly connected to the vibration rod, and the driving unit is used to drive the vibration rod to reciprocate in the injection hole to perform an impact operation on the solid filler.
[0010] In some embodiments, one end of the vibration rod away from the driving part has a tapered tip.
[0011] In some embodiments, the method further comprises: A detection component is set in the area of any two adjacent injection holes in the foundation, and the detection component is used to detect whether the goaf corresponding to the adjacent injection holes is filled with solid filling material. The detection component includes at least one of a photoelectric sensor, an ultrasonic sensor, a laser sensor or an infrared sensor.
[0012] In some embodiments, the method further comprises: Obtaining the water accumulation position in the goaf; If the water accumulation location is located within the drilling area, the injection hole is used to discharge the accumulated water corresponding to the water accumulation location; if the water accumulation location is located outside the drilling area, a drainage hole is opened on the foundation outside the drilling area, and the drainage hole passes through the surface area of the foundation and is connected with the goaf, and the drainage hole is used to discharge the accumulated water corresponding to the water accumulation location.
[0013] A second aspect of the present invention provides a road goaf filling system, comprising: Planning equipment, used to determine the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf area in the foundation; and used to determine the position distribution of injection holes in the drilling area according to the depth information of the goaf area; Drilling equipment, used for opening injection holes on the foundation according to the position distribution of the injection holes, wherein the injection holes penetrate the surface area of the foundation and are connected with the goaf; A filling device, used for injecting solid filling material into the goaf through each of the injection holes, until the solid filling material at the corresponding position of each of the injection holes reaches the top area of the goaf; A vibration device is used to perform an impact operation on the solid filling material at the position corresponding to each injection hole, so that the solid filling material at the position corresponding to the injection hole is diffused toward the goaf corresponding to the position of the adjacent injection hole; The filling device and the vibration device are used to repeat the injection and impact operations of the solid filling material in sequence until the goaf is filled with the solid filling material.
[0014] According to the road goaf filling method and system provided by the present invention, the road goaf filling method uses solid filling materials to fill and reinforce the corresponding goaf within the bearing range below the roadbed, thereby reducing the reinforcement area and the amount of reinforcement work, saving filling materials and reducing costs; and uses injection holes to inject solid filling materials into the goaf, and then combines the impact operation of the solid filling materials to improve the density of the goaf filling. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings: Figure 1 Fill the existing goaf with grouting method; Figure 2 A geological exploration result map of the goaf provided in the embodiment of the present application; Figure 3 A road cross-sectional view of the arrangement of injection holes provided in an embodiment of the present application; Figure 4 A longitudinal section of a road with injection holes arranged according to an embodiment of the present application; Figure 5 A top view of a road where injection holes are arranged according to an embodiment of the present application; Figure 6 A cross-sectional view of a road injected with solid filling material provided in an embodiment of the present application; Figure 7 A longitudinal section of a road injected with solid filling material provided in an embodiment of the present application; Figure 8 A top view of a road injected with solid filler provided in an embodiment of the present application; Fig. 9 A cross-sectional view of a road impacted by a solid filler provided in an embodiment of the present application; Fig.10 A longitudinal section of a road impacted by a solid filler provided in an embodiment of the present application; Fig.11 A cross-sectional view of a road with the goaf below the roadbed fully filled with the goaf provided in the embodiment of the present application; Fig.12 A longitudinal section of a road with the goaf below the roadbed fully filled with the goaf provided in the embodiment of the present application; Fig.13 An exemplary structural diagram of a vibration device provided in an embodiment of the present application.
[0016] In the above picture: 10 roadbed; 20 foundation; 201 goaf; 202 injection hole; 203 grouting hole; 30 solid filling material; 40 vibration device; 401 vibration rod; 4011 conical tip; 402 driving part; 50 air mass; 60 liquid filling material. DETAILED DESCRIPTION
[0017] The present application will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It should also be noted that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0018] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0019] The terms used in this application are only for the purpose of describing specific embodiments and are not intended to limit this application. The singular forms of "a", "said" and "the" used in this application and the appended claims are also intended to include plural forms, unless the context clearly indicates other meanings. It should also be understood that the term "and / or" used in this article refers to and includes any or all possible combinations of one or more associated listed items.
[0020] Unless the context requires otherwise, throughout the specification and claims, the term "comprising" is to be construed in an open, inclusive sense, ie, meaning "including, but not limited to."
[0021] In the description of the specification, the terms "one embodiment", "some embodiments", "exemplary embodiment", "example", "specific example" or "some examples" are intended to indicate that a specific feature, structure, material or characteristic associated with the embodiment or example is included in at least one embodiment or example of the present disclosure. The schematic representation of the above terms does not necessarily refer to the same embodiment or example. In addition, the specific features, structures, materials or characteristics may be included in any one or more embodiments or examples in any appropriate manner.
[0022] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the embodiments of the present disclosure, unless otherwise specified, "plurality" means two or more.
[0023] When encountering unfilled underground goafs during roadbed construction, the traditional treatment methods include plugging and filling and grouting. The plugging and filling method is for goaf cavities with very shallow burial depths. Excavation is used to expose the goaf, and then materials such as stone flakes, concrete, and sandbags are used to build retaining wall partitions at the edge of the roadbed structure bearing capacity. Then, the area below the roadbed with bearing capacity requirements is filled with sand, gravel, clay and other materials. This method is mainly suitable for projects with good surrounding rock above and around the goaf, which can be excavated and exposed at low cost. It cannot be implemented for situations where the goaf is buried deep, the soil cover above the goaf is unstable, the materials and machinery are difficult to put into the goaf, the personnel have difficulty in operation, or the safety risks are high. Therefore, its scope of application is limited.
[0024] like Figure 1 As shown, the grouting method is to drill a small diameter grouting hole 203 on the ground, and then pour cement slurry, mortar or chemical slurry and other liquid filling materials 60 into the goaf through the grouting hole 203, so that the cavity of the goaf is completely filled. This method is suitable for the disposal of various goafs, but it also has the following shortcomings: First, when the goaf area is large, the grouting workload is large, the construction period is long, and the cost is high; second, it is difficult to accurately describe and simulate the three-dimensional space of the goaf due to the current detection technology, and it is impossible to ensure that the grouting hole 203 is at the top of the goaf cavity. If the grouting hole 203 is not positioned accurately, it is easy to form an air mass 50 at the highest point, and it is impossible to fill it densely, and the ideal foundation reinforcement effect cannot be achieved, which affects the bearing capacity of the foundation.
[0025] To solve the above problems, refer to Figures 2 to 12 According to a first aspect of an embodiment of the present application, a method for filling a road goaf is provided, comprising: S110 : Determine a drilling area on the foundation 20 according to the relative position relationship between the area where the roadbed 10 is located and the goaf 201 in the foundation 20 .
[0026] refer to Figure 2 , conduct geological survey on the goaf 201 in the foundation 20, and obtain parameter information of the goaf 201, such as the depth, area and volume of the cavity in the goaf 201, the location and amount of water accumulation, the presence or absence of filling materials, etc., especially obtain information such as the depth, area and location of water accumulation in the goaf 201 within the bearing capacity range of the roadbed 10, so as to provide a basis for the subsequent processing of the goaf 201.
[0027] For example, the boundary of the area where the roadbed 10 is located and the boundary of the goaf 201 are determined through geological survey, and whether there is an overlapping area between the area where the roadbed 10 is located and the goaf 201 is determined based on the boundary of the two, that is, the relative position relationship between the area where the roadbed 10 is located and the goaf 201 in the foundation 20 can make the overlapping area exist or not exist. If there is an overlapping area, the punching area at least covers the overlapping area to ensure that the corresponding goaf 201 within the bearing range of the roadbed 10 can be filled with solid filling material 30, and the injection workload can be minimized, shortening the construction period and saving costs.
[0028] S120: Determine the position distribution of injection holes 202 in the drilling area according to the depth information of the goaf 201, and open injection holes 202 on the foundation 20 according to the position distribution of the injection holes 202. The injection holes 202 penetrate the surface area of the foundation 20 and are connected with the goaf 201.
[0029] refer to Figures 3 to 5 , the position distribution of the injection holes 202 in the drilling area is designed in combination with the depth information of each position of the goaf 201, so that the position distribution of the injection holes 202 can meet the setting requirements of goafs 201 of different depths, and ensure that corresponding injection holes 202 can be set in goafs 201 with high depths and goafs 201 with low depths. When the solid filling material 30 is filled into the corresponding goaf 201 through the injection holes 202, each position of the goaf 201 can be filled with the solid filling material 30, thereby avoiding the problem of air mass 50 formed at the highest point due to inaccurate positioning of the injection holes 202, and improving the compactness of the filling of the goaf 201.
[0030] S130 : injecting solid filling material 30 into the goaf 201 through each of the injection holes 202 until the solid filling material 30 at the corresponding position of each of the injection holes 202 reaches the top area of the goaf 201 .
[0031] refer to Figures 6 to 8 Solid filling material 30 is injected into the goaf 201 through the injection hole 202. The solid filling material 30 includes crushed stone, sand, stone powder or other small-particle soil-rock mixture, etc. The goaf 201 is filled with the solid filling material 30 so that the goaf 201 corresponding to the roadbed 10 below the roadbed 10 reaches the bearing force range required by the roadbed 10 to meet the construction requirements of the roadbed 10.
[0032] S140 : performing an impact operation on the solid filling material 30 at the position corresponding to each of the injection holes 202 , so that the solid filling material 30 at the position corresponding to the injection hole 202 is diffused toward the goaf 201 corresponding to the position of the adjacent injection hole 202 .
[0033] When the solid filling material 30 at the corresponding position of each injection hole 202 reaches the top area of the goaf 201, the solid filling material 30 can no longer be injected, and the goaf 201 is not actually filled. Fig. 9 and Fig.10 , the solid filling material 30 at the corresponding position of each injection hole 202 is impacted so that the solid filling material 30 at the corresponding position of the injection hole 202 diffuses toward the goaf 201 corresponding to the position of the adjacent injection hole 202, which is convenient for the subsequent further injection operation of the solid filling material 30 and improves the compactness of the goaf 201.
[0034] S150 : The injection and impact operations of the solid filling material 30 are repeated in sequence until the goaf 201 is filled with the solid filling material 30 .
[0035] refer to Fig.11 and Fig.12 , repeat steps S130 and S140 in sequence, such as injection, impact, injection, impact, etc. of the solid filler 30, until the solid filler 30 diffuses to any adjacent injection holes 202 and the goaf 201 corresponding to the goaf 201 is filled with the solid filler 30, so that the foundation 20 corresponding to the goaf 201 meets the bearing range requirements of the roadbed 10, the foundation 20 is reinforced, and the construction requirements of the roadbed 10 are met.
[0036] The method for filling a road goaf provided in the embodiment of the present application uses solid filling material 30 to fill and reinforce the goaf 201 corresponding to the bearing force range below the roadbed 10, thereby reducing the reinforcement area and the reinforcement engineering quantity, saving filling materials, and reducing costs; and uses the injection hole 202 to inject the solid filling material 30 into the goaf 201, and then combines the impact operation of the solid filling material 30 to improve the compactness of the filling of the goaf 201. The method is applicable to the surrounding rocks above and around the goaf 201 that are good, the goaf 201 that is buried deep, and the soil cover layer above the goaf 201 that is of poor stability.
[0037] In some embodiments, in S110, determining the drilling area on the foundation 20 according to the relative position relationship between the area where the roadbed 10 is located and the goaf 201 in the foundation 20 includes: S111: Detecting the overlapping area between the roadbed 10 and the goaf 201; If the overlapping area is located in the area where the roadbed 10 is located, the area on the roadbed 10 corresponding to the overlapping area is used as the punching area; If the overlapping area is partially located within the area where the roadbed 10 is located and partially located outside the area where the roadbed 10 is located, the area on the roadbed 10 corresponding to the overlapping area and the area within a preset distance range outside the overlapping area is used as a drilling area, and the drilling area is located within the goaf 201.
[0038] Specifically, the area where the goaf 201 is located is determined through geological survey, and based on the area where the goaf 201 is located and the area where the roadbed 10 is located, the overlapping area between the goaf 201 and the roadbed 10 is determined.
[0039] If the overlapping area is located in the area where the roadbed 10 is located, the area on the roadbed 10 corresponding to the overlapping area will be directly used as the punching area. The punching area can minimize the filling area of the goaf 201 corresponding to the bearing capacity of the roadbed 10, reduce the amount of reinforcement work, save filling materials and reduce costs, etc. The setting of the punching area can ensure that all positions of the goaf 201 can be covered, and can avoid invalid punching settings of injection holes 202 outside the overlapping area.
[0040] refer to Figures 3 to 5 If the overlapping area is partially located in the area where the roadbed 10 is located, and the remaining part is located outside the edge line on one side of the roadbed 10, the area on the foundation 20 corresponding to the overlapping area and the corresponding area extending outward to the area within a preset distance range outside the roadbed 10 is used as the punching area, that is, the punching area covers the overlapping area and the area within a preset distance range outside the edge line on one side of the roadbed 10; if the overlapping area is partially located in the area where the roadbed 10 is located, and the remaining part is located outside the edge lines on both sides of the roadbed 10, the punching area covers the overlapping area and the area within a preset distance range outside the edge lines on both sides of the roadbed 10. The setting of the punching area can ensure that the corresponding goaf 201 below the roadbed 10 is filled with solid filling material 30, and the punching area is set within the preset distance range outside the roadbed 10 to ensure that the corresponding goaf 201 outside the roadbed 10 can also be filled with solid filling material 30, so as to avoid the construction of the roadbed 10 being affected by the poor soil stability in the surrounding area outside the roadbed 10 during the construction of the roadbed 10. Among them, the preset distance range can be 1-3 meters, etc., and can also be set according to actual needs.
[0041] In this example, the drilling area at least covers the overlapping area where the roadbed 10 is located and the goaf 201, and the foundation 20 in the area where the roadbed 10 has bearing capacity requirements is precisely reinforced to reduce construction costs and safety risks and achieve the best treatment effect.
[0042] In some embodiments, in S120, determining the position distribution of the injection holes 202 in the drilling area according to the depth information of the goaf 201 includes: The injection holes 202 are opened in the drilling area in an array distribution manner, and the distribution spacing of the injection holes 202 corresponding to the area with a high depth in the goaf 201 is set to a first distance, and the distribution spacing of the injection holes 202 corresponding to the area with a low depth in the goaf 201 is set to a second distance, and the first distance is smaller than the second distance.
[0043] Specifically, the injection holes 202 are arranged in an array distribution manner in the drilling area, so that the injection holes 202 can be arranged on the foundation 20 corresponding to each depth position of the goaf 201, ensuring that each position of the goaf 201 can be filled with solid filling material 30, and the position distribution of the injection holes 202 is made to cover the deep area of the goaf 201 as much as possible to be close to the highest vertex of the goaf 201, so as to avoid the air mass 50 formed by inaccurate positioning of the injection holes 202.
[0044] The distribution spacing of the injection holes 202 corresponding to the high-depth area in the goaf 201 is small, and the distribution spacing of the injection holes 202 corresponding to the low-depth area in the goaf 201 is large. The distribution positions of the injection holes 202 are determined according to the actual depth information of each position of the goaf 201, and it is ensured that the injection holes 202 can be set at the highest vertex of the goaf 201, so that the goaf 201 can be completely filled, thereby improving the compactness of the goaf 201; and the injection speed of the goaf 201 corresponding to the high-depth goaf 201 is fast, and the injection speed of the goaf 201 corresponding to the low-depth goaf 201 is slow, so that the goaf 201 corresponding to each depth position of the goaf 201 can reach the corresponding top area of the goaf 201 as much as possible at the same time, maintain the consistency of the injection, improve the injection rate of the goaf 201, and the solid filling material 30 can fill the goaf 201 after injection and impact compaction.
[0045] For further reference, Figure 5 , the step of opening the injection holes 202 in the punching area in an array distribution manner includes: A plurality of rows of injection holes 202 are arranged in the punching area along the extension direction of the roadbed 10 at intervals, each row of injection holes 202 includes a plurality of injection holes 202 distributed at intervals perpendicular to the extension direction of the roadbed 10, and the injection holes 202 in two adjacent rows of injection holes 202 are staggered.
[0046] In this example, the multiple rows of injection holes 202 are arranged at intervals along the extension direction of the roadbed 10, and the spacing between two adjacent rows of injection holes 202 can be equal or unequal, and the number of injection holes 202 included in each row of injection holes 202 can be equal or unequal. Exemplarily, the diameter of the injection hole 202 is 300~600mm. If the diameter of the injection hole 202 is less than 300mm, the injection rate of the goaf 201 is slow and it is not conducive to the injection of solid filling material 30; if the diameter of the injection hole 202 is greater than 600mm, the number of injection holes 202 distributed in the perforated area is small, which affects the injection effect of the goaf 201, and may cause the formation of air masses 50 in the goaf 201 with a high depth, which cannot be filled densely, etc. The distance between two adjacent injection holes 202 is 2 to 3 meters. A distance less than 2 meters is not conducive to the drilling operation of the injection holes 202. A distance greater than 3 meters results in a smaller number of injection holes 202 distributed in the drilling area, affecting the injection efficiency of the goaf 201.
[0047] Each injection hole 202 in two adjacent rows of injection holes 202 is staggered at right angles to the extension direction of the roadbed 10. When the injection holes 202 are performing injection and impact operations, the distribution positions of the injection holes 202 in the punching area can enable the goaf 201 corresponding to the adjacent injection holes 202 to be quickly filled, thereby improving the filling efficiency and compactness of the goaf 201.
[0048] In some embodiments, S140 : using a vibration device 40 to impact the solid filler 30 at a position corresponding to each injection hole 202 , wherein the diameter of at least some parts of the vibration device 40 is smaller than the diameter of the injection hole 202 .
[0049] Some components of the vibration equipment can extend into the injection hole 202 to impact the solid filler 30, so that the solid filler 30 in the injection hole 202 can be better diffused in the goaf 201, thereby improving the compactness of the goaf 201 and increasing the firmness of the foundation 20.
[0050] In some embodiments, reference Fig.13 The vibration device 40 includes a vibration rod 401 and a driving unit 402 . The driving unit 402 is fixedly connected to the vibration rod 401 . The driving unit 402 drives the vibration rod 401 to reciprocate in the injection hole 202 to perform an impact operation on the solid filler 30 .
[0051] The driving part 402 can be a screw motor, a servo motor, a pneumatic cylinder, a hydraulic cylinder, etc. The driving part 402 is fixedly connected to the vibration rod 401. The diameter of the vibration rod 401 is smaller than the diameter of the main material hole. The driving part 402 can drive the vibration rod 401 to reciprocate in the injection hole 202 to repeatedly impact the solid filling material 30 in the injection hole 202. Among them, the driving part 402 and the vibration rod 401 are arranged in a one-to-one correspondence, so that the solid filling material 30 in each injection hole 202 is impacted by an independent vibration device 40; or, the output end of the driving part 402 is connected to a support plate, and a plurality of vibration rods 401 are arranged on the support plate, and the same driving part 402 is used to simultaneously drive the plurality of vibration rods 401 to perform impact operations on the solid filling materials 30 in the corresponding plurality of injection holes 202, thereby improving the impact efficiency. It should be noted that each vibration rod 401 can be slidably set on the support plate. If multiple rows of slide rails are set on the support plate, the support rod is slidably connected to the slide rails and fixed by locking members, and the locking members are bolts, etc., so that the distance between two adjacent vibration rods 401 on the same row of slide rails can be adjusted to meet the impact operation requirements of the solid filling material 30 in the injection holes 202 with different spacings.
[0052] In some embodiments, reference Fig.13 The end of the vibration rod 401 away from the driving part 402 has a conical tip 4011.
[0053] Specifically, when the vibration rod 401 performs the impact operation on the solid filler 30, its conical tip 4011 makes the contact area between the vibration rod 401 and the solid filler 30 smaller. The greater the impact force on the solid filler 30, on the one hand, the solid filler 30 can be better crushed, and on the other hand, the solid filler 30 can be better diffused in the goaf 201.
[0054] In some embodiments, the method further comprises: A detection component is set in the area of any two adjacent injection holes 202 in the foundation 20, and the detection component is used to detect whether the goaf 201 corresponding to the adjacent injection holes 202 is filled with solid filling material 30. The detection component includes at least one of a photoelectric sensor, an ultrasonic sensor, a laser sensor or an infrared sensor.
[0055] Specifically, each detection component is arranged in the area of the foundation 20 between two adjacent injection holes 202 and in the top area of the goaf 201. Each detection component can be used to detect whether the goaf 201 corresponding to the adjacent injection holes 202 is filled with solid filler 30. When it is detected that it is filled, the injection and impact operations of the solid filler 30 are stopped. Otherwise, the injection and impact operations of the solid filler 30 are repeated until the goaf 201 is filled.
[0056] Among them, the photoelectric sensor can emit and receive light. When the emitted light is blocked by the solid filler 30, the light returns and is received by the photoelectric sensor. The photoelectric sensor can detect the blocking information of the solid filler 30 in the goaf 201. The time difference between the light emission time and the reception time can be used to determine whether the goaf 201 is filled with the solid filler 30. If the time difference is less than the preset time threshold, the goaf 201 is filled with the solid filler 30; otherwise, the goaf 201 is not filled with the solid filler 30. Among them, the preset time threshold can be set according to actual needs. The ultrasonic sensor can emit ultrasonic waves and receive their reflected waves. The ultrasonic sensor can detect the blocking information of the solid filler 30 in the goaf 201, and then determine whether the goaf 201 is filled with the solid filler 30. The laser ranging sensor can emit laser and receive laser, and the infrared sensor can emit and receive infrared signals. The principle of determining whether the goaf 201 is filled with solid fillers 30 is the same as that of the photoelectric sensor, and this application will not repeat it.
[0057] In some embodiments, the method further comprises: Obtaining the water accumulation position in the goaf 201; If the water accumulation location is located within the drilling area, the injection hole 202 is used to discharge the water corresponding to the water accumulation location; if the water accumulation location is located outside the drilling area, a drainage hole is opened on the foundation 20 outside the drilling area, and the drainage hole passes through the surface area of the foundation 20 and is connected with the goaf 201, and the water corresponding to the water accumulation location is discharged through the drainage hole.
[0058] The water accumulation detection sensor can be used to obtain information such as the location and amount of water accumulation in the goaf 201. If the water accumulation location is located in the drilling area, the injection hole 202 corresponding to the water accumulation location is used to drain the water. After the water accumulation at the water accumulation location is drained, the injection hole 202 corresponding to the water accumulation location is used to perform the injection operation of the solid filling material 30, so that the same injection hole 202 can be recycled, the drilling operation of the drainage hole can be reduced, and the cost can be reduced. It should be noted that when the water accumulation operation is performed at the water accumulation location, the goaf 201 corresponding to the non-water accumulation location can simultaneously perform the injection and impact operations of the solid filling material 30, thereby improving the reinforcement efficiency of the goaf 201.
[0059] If the water accumulation position is outside the drilling area, a drainage hole is opened in the area corresponding to the water accumulation position on the foundation 20 to discharge the accumulated water out of the goaf area 201 through the drainage hole to prevent the accumulated water from affecting the processing effect of the goaf area 201.
[0060] The present application also provides a road goaf filling system, including: Planning equipment, used to determine the drilling area on the foundation 20 according to the relative position relationship between the area where the roadbed 10 is located and the goaf 201 in the foundation 20; and used to determine the position distribution of the injection holes 202 in the drilling area according to the depth information of the goaf 201; Drilling equipment, used for opening injection holes 202 on the foundation 20 according to the position distribution of the injection holes 202, wherein the injection holes 202 penetrate the surface area of the foundation 20 and communicate with the goaf 201; A filling device, used for injecting solid filling material 30 into the goaf 201 through each of the injection holes 202 until the solid filling material 30 at the corresponding position of each of the injection holes 202 reaches the top area of the goaf 201; The vibration device 40 is used to perform an impact operation on the solid filling material 30 at the corresponding position of each injection hole 202, so that the solid filling material 30 at the corresponding position of the injection hole 202 is diffused toward the goaf 201 corresponding to the position of the adjacent injection hole 202; The filling device and the vibration device 40 are used to sequentially repeat the injection and impact operations of the solid filling material 30 until the goaf 201 is filled with the solid filling material 30 .
[0061] The planning equipment includes an exploration module and a processing module, wherein the exploration module includes a multifunctional exploration instrument or / and a seismic exploration equipment. The multifunctional exploration instrument reflects the change of underground resistivity by measuring the strength of the natural electromagnetic field, thereby analyzing and judging the location, size, depth and other related information of the underground goaf 201. The seismic exploration equipment arranges a series of detectors on the surface of the foundation 20 to receive the reflected wave or refracted wave signal of the artificially excited seismic wave after propagating underground. When the seismic wave encounters different stratum media (such as when propagating from the rock layer to the cavity of the goaf 201), its propagation speed, amplitude, frequency and other characteristics will change. The change is recorded by the seismograph, and after data processing and interpretation, the location and shape of the underground goaf 201 can be inferred. According to the area where the goaf 201 is located and the area where the roadbed 10 is located collected by the exploration module, the drilling area on the foundation 20 is determined.
[0062] The processing module includes a processor, etc. The processing module is used to obtain the depth information of the goaf 201 collected by the exploration module, and determine the position distribution of the injection holes 202 in the drilling area based on the depth information of the goaf 201.
[0063] The drilling equipment performs a drilling operation on the foundation 20 based on the position distribution information of the injection holes 202 in the drilling area determined by the processing module to open injection holes 202 in the surface area of the foundation 20 that are connected to the goaf 201 .
[0064] The filling equipment injects solid filling material 30 into the goaf 201 through the injection hole 202, and uses the solid filling material 30 to fill the goaf 201, so that the goaf 201 corresponding to the roadbed 10 reaches the bearing force range required by the roadbed 10, meeting the construction requirements of the roadbed 10.
[0065] When the solid filling material 30 at the corresponding position of each injection hole 202 reaches the top area of the goaf 201, the solid filling material 30 at the corresponding position of each injection hole 202 is impacted by the vibration equipment 40 to make the solid filling material 30 at the corresponding position of the injection hole 202 diffuse toward the goaf 201 corresponding to the position of the adjacent injection hole 202.
[0066] The filling equipment and the vibration equipment repeat the injection and impact operations of the solid filler 30 in sequence until the solid filler 30 diffuses to the goaf 201 corresponding to any adjacent injection holes 202 and is filled with the solid filler 30, so that the foundation 20 corresponding to the goaf 201 reaches the bearing capacity range requirement of the roadbed 10, thereby reinforcing the foundation 20 and meeting the construction requirements of the roadbed 10.
[0067] The road goaf filling system provided in the embodiments of the present application is used to execute the road goaf filling method provided in any embodiment of the present application. The specific technical features and technical effects of the filling system are consistent with the filling method, and will not be repeated in this application.
[0068] In some embodiments, the exploration module further includes: A detection unit, used to detect the overlapping area between the area where the roadbed 10 is located and the goaf 201; The processing unit is used to determine the punching area based on the relative position relationship between the overlapping area and the area where the roadbed 10 is located, as follows: If the overlapping area is located in the area where the roadbed 10 is located, the area on the roadbed 10 corresponding to the overlapping area is used as the punching area; If the overlapping area is partially located within the area where the roadbed 10 is located and partially located outside the area where the roadbed 10 is located, the area on the roadbed 10 corresponding to the overlapping area and the area within a preset distance range outside the overlapping area is used as a drilling area, and the drilling area is located within the goaf 201.
[0069] In some embodiments, the processing module is used to obtain the depth information of the goaf 201 collected by the exploration module, determine the array distribution of the injection holes 202 in the drilling area based on the depth information of the goaf 201, and set the distribution spacing of the injection holes 202 corresponding to the area with a high depth in the goaf 201 to a first distance, and set the distribution spacing of the injection holes 202 corresponding to the area with a low depth in the goaf 201 to a second distance, and the first distance is smaller than the second distance.
[0070] In some embodiments, the drilling equipment is used to open multiple rows of injection holes 202 in the drilling area along the extension direction of the roadbed 10, each row of injection holes 202 includes multiple injection holes 202 distributed at intervals along the extension direction perpendicular to the roadbed 10, and the injection holes 202 in two adjacent rows of injection holes 202 are staggered.
[0071] In some embodiments, the vibration device 40 is used to impact the solid filler 30 at the corresponding position of each injection hole 202, and the diameter of at least some parts of the vibration device 40 is smaller than the diameter of the injection hole 202. Further, the vibration device 40 includes a vibration rod 401 and a driving part 402, the driving part 402 is fixedly connected to the vibration rod 401, and the driving part 402 is used to drive the vibration rod 401 to reciprocate in the injection hole 202 to impact the solid filler 30; the end of the vibration rod 401 away from the driving part 402 has a conical tip 4011.
[0072] In some embodiments, the filling system also includes a detection device, which is arranged in the foundation 20 within the area of any two adjacent injection holes 202. The detection device is used to detect whether the goaf 201 corresponding to the adjacent injection holes 202 is filled with solid filling material 30. The detection device includes at least one of a photoelectric sensor, an ultrasonic sensor, a laser sensor or an infrared sensor.
[0073] The filling device is used to obtain the information detected by the detection member, and determine whether to start the filling device in response to the information detected by the detection member. If the detection member detects that the goaf 201 is filled with solid filling material 30, the filling device stops starting; if the detection member detects that the goaf 201 is not filled with solid filling material 30, the filling device starts and injects solid filling material 30 into the injection hole 202.
[0074] In some embodiments, the filling system further includes a water accumulation detection sensor, and the water accumulation detection sensor is used to obtain the water accumulation position in the goaf 201; The processing module is used to obtain the water accumulation position information uploaded by the water accumulation detection sensor, and determine the drainage method of the goaf 201 based on the water accumulation position information. If the water accumulation position is located in the perforated area, the injection hole 202 is used to discharge the water corresponding to the water accumulation position; if the water accumulation position is located outside the perforated area, the drainage hole outside the perforated area is used to discharge the water corresponding to the water accumulation position. The drainage hole is formed by drilling with a drilling device, and a water pump is connected to the injection hole 202 and the drainage hole corresponding to the water discharge, and the water is discharged by the water pump.
[0075] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with the technical features with similar functions disclosed in this application (but not limited to) by each other to form a technical solution.
Claims
1. A method for filling a road goaf, characterized in that: include: Determine the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf area in the foundation; Determine the position distribution of injection holes in the perforated area according to the depth information of the goaf, and open injection holes on the foundation according to the position distribution of the injection holes, wherein the injection holes penetrate the surface area of the foundation and are connected with the goaf; Injecting solid filling material into the goaf through each of the injection holes until the solid filling material at a position corresponding to each of the injection holes reaches the top area of the goaf; Then, the solid filling material at the position corresponding to each injection hole is impacted, so that the solid filling material at the position corresponding to the injection hole is diffused toward the goaf corresponding to the position of the adjacent injection hole; The injection and impact operations of the solid filling material are repeated in sequence until the goaf is filled with the solid filling material.
2. The method for filling road goaf according to claim 1, characterized in that: Determining the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf area in the foundation includes: Detecting the overlapping area between the roadbed area and the goaf area; If the overlapping area is located in the area where the roadbed is located, the area on the roadbed corresponding to the overlapping area is used as the punching area; If the overlapping area is partially located within the area where the roadbed is located and partially located outside the area where the roadbed is located, the area on the roadbed corresponding to the overlapping area and the area within a preset distance range outside the overlapping area is used as the drilling area, and the drilling area is located within the goaf.
3. The method for filling road goaf according to claim 1, characterized in that: The determining the position distribution of injection holes in the drilling area according to the depth information of the goaf includes: The injection holes are opened in the drilling area in an array distribution manner, and the distribution spacing of the injection holes corresponding to the area with high depth of the goaf is set to a first distance, and the distribution spacing of the injection holes corresponding to the area with low depth of the goaf is set to a second distance, and the first distance is smaller than the second distance.
4. The method for filling road goaf according to claim 3, characterized in that: The method of opening the injection holes in the punching area in an array distribution manner comprises: A plurality of rows of injection holes are arranged in the punching area along the extension direction of the roadbed at intervals, each row of injection holes includes a plurality of injection holes distributed at intervals perpendicular to the extension direction of the roadbed, and the injection holes in two adjacent rows of injection holes are staggered.
5. The method for filling road goaf according to claim 1, characterized in that: A vibration device is used to impact the solid filling material at the corresponding position of each injection hole, and the diameter of at least some parts of the vibration device is smaller than the diameter of the injection hole.
6. The method for filling road goaf according to claim 5, characterized in that: The vibration device comprises a vibration rod and a driving part, wherein the driving part is fixedly connected to the vibration rod, and the driving part is used to drive the vibration rod to reciprocate in the injection hole to perform an impact operation on the solid filler.
7. The method for filling road goaf according to claim 6, characterized in that: One end of the vibration rod away from the driving part has a tapered tip.
8. The method for filling road goaf according to any one of claims 1 to 7, characterized in that: The method further comprises: A detection component is set in the area of any two adjacent injection holes in the foundation, and the detection component is used to detect whether the goaf corresponding to the adjacent injection holes is filled with solid filling material. The detection component includes at least one of a photoelectric sensor, an ultrasonic sensor, a laser sensor or an infrared sensor.
9. The method for filling road goaf according to any one of claims 1 to 7, characterized in that: The method further comprises: Obtaining the water accumulation position in the goaf; If the water accumulation location is located within the drilling area, the injection hole is used to discharge the accumulated water corresponding to the water accumulation location; if the water accumulation location is located outside the drilling area, a drainage hole is opened on the foundation outside the drilling area, and the drainage hole passes through the surface area of the foundation and is connected with the goaf, and the drainage hole is used to discharge the accumulated water corresponding to the water accumulation location.
10. A road goaf filling system, characterized in that: include: Planning equipment, used to determine the drilling area on the foundation according to the relative position relationship between the roadbed area and the goaf area in the foundation; and for determining the position distribution of injection holes in the perforated area according to the depth information of the goaf; Drilling equipment, used for opening injection holes on the foundation according to the position distribution of the injection holes, wherein the injection holes penetrate the surface area of the foundation and are connected with the goaf; A filling device, used for injecting solid filling material into the goaf through each of the injection holes, until the solid filling material at the corresponding position of each of the injection holes reaches the top area of the goaf; A vibration device is used to perform an impact operation on the solid filling material at the position corresponding to each injection hole, so that the solid filling material at the position corresponding to the injection hole is diffused toward the goaf corresponding to the position of the adjacent injection hole; The filling device and the vibration device are used to repeat the injection and impact operations of the solid filling material in sequence until the goaf is filled with the solid filling material.