Formwork locking device and construction method of I-beam diaphragm plate

By designing the first and second locking mechanisms of the formwork locking device, the problem of concrete overflow and hardening on the locking device is solved by using the combination of concrete barriers and through holes, and the free removal of components and the improvement of construction efficiency is achieved.

CN119877392APending Publication Date: 2025-04-25珠海市立胜机械有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510124055.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-26
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

During the secondary pouring of I-beam cross-dividing plates, concrete is prone to overflow and harden on the locking device, making it difficult to remove the formwork and locking device, affecting the construction progress and quality.

Method used

A formwork locking device is designed, including a first and a second locking mechanism, each of which includes a concrete barrier and a through hole, which spills out through the through hole when the concrete overflows, avoiding continuous leakage in the direction of the steel bar extension.

Benefits of technology

It effectively avoids damage caused by the concrete cover locking device, ensures free movement and removal of components, improves construction efficiency and reduces construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119877392A_ABST
    Figure CN119877392A_ABST
Patent Text Reader

Abstract

The invention discloses a formwork locking device and a construction method of an I-beam diaphragm plate, and belongs to the technical field of I-beam diaphragm plates. The formwork locking device comprises a first locking mechanism, the first locking mechanism comprises a first concrete blocking piece, and the first concrete blocking piece is provided with a first blocking cavity; a plurality of first through holes are formed in the cavity wall of the first barrier cavity and are uniformly formed along the cavity wall of the first barrier cavity; the second locking mechanism comprises a second concrete blocking piece, the second concrete blocking piece is provided with a second blocking cavity, the volume of the first blocking cavity is larger than that of the second blocking cavity, a plurality of second through holes are formed in the cavity wall of the second blocking cavity, and the second through holes are evenly formed along the cavity wall of the second blocking cavity. According to the locking device, blocking of concrete can be achieved, free moving and dismantling of components are guaranteed, construction quality is guaranteed, meanwhile, construction efficiency is improved, and construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of I-beam cross diaphragms, and in particular to a template locking device and a construction method for an I-beam cross diaphragm. Background Art

[0002] The diaphragm plays an important role in maintaining the lateral stability of the bridge, ensuring that the main beams are connected as a whole, adjusting the uneven loads of the beams, etc. in the open cross-section beam bridges such as I-beams, and in improving the torsional rigidity of the beam. At the same time, the diaphragm can also connect the main beams as a whole in the horizontal direction to bear the horizontal load, improve the torsional stability of the beam, increase the lateral rigidity of the cross section, and limit the distortion stress. It is an important part of making the bridge an integral spatial structure.

[0003] In previous construction projects, I-beam diaphragms needed to be cast a second time. However, the secondary casting was prone to quality problems such as leakage. When concrete overflowed from the diaphragm formwork along the steel bars, the overflowed concrete would harden on the locking device, making it difficult to remove the locking device. If it was forcibly removed, it would not only damage the formwork and locking device, but would also be time-consuming and labor-intensive, delaying the construction progress. Summary of the invention

[0004] The purpose of the present invention is to solve at least one of the technical problems existing in the prior art. To this end, the present invention proposes a template locking device and an I-beam cross partition construction method, which can prevent the concrete from trapping the locking device on the template, extend the service life of the construction components, and reduce construction costs.

[0005] According to the first embodiment of the present invention, the template locking device includes a first locking mechanism, the first locking mechanism includes a first concrete barrier, the first concrete barrier has a first barrier cavity, the input end of the first barrier cavity is connected to the interior of the diaphragm template, a plurality of first through holes are opened on the cavity wall of the first barrier cavity, the plurality of first through holes are evenly arranged along the cavity wall of the first barrier cavity, when the concrete in the diaphragm template overflows to the first barrier cavity along the steel bar extension path, the concrete overflows outward from the first through holes; the second locking mechanism, the second locking mechanism includes a second concrete barrier, the second concrete barrier has a second barrier cavity, the volume of the first barrier cavity is greater than the volume of the second barrier cavity, the input end of the second barrier cavity is connected to the interior of the diaphragm template, a plurality of second through holes are opened on the cavity wall of the second barrier cavity, the plurality of second through holes are evenly arranged along the cavity wall of the second barrier cavity, when the concrete in the diaphragm template overflows to the second barrier cavity along the steel bar extension path, the concrete overflows outward from the second through holes.

[0006] The template locking device according to the embodiment of the present invention has at least the following beneficial effects: when concrete overflows outward from the connection between the diaphragm template and the steel bar, the concrete flows into the first barrier cavity and the second barrier cavity along the extension direction of the steel bar, and then overflows outward through the first through hole opened on the peripheral wall of the first barrier cavity and the second through hole opened on the peripheral wall of the second barrier cavity, thereby preventing the concrete from continuing to leak out along the extension direction of the steel bar, thereby achieving concrete blocking, avoiding damage to components caused by being covered and solidified by concrete, ensuring the free movement and removal of components, and improving construction efficiency and reducing construction costs while ensuring construction quality.

[0007] According to some embodiments of the present invention, the first locking mechanism also includes a first sealing assembly and a first locking assembly. The first sealing assembly, the first concrete barrier and the first locking assembly are sequentially sleeved on the steel bars in a direction away from the diaphragm formwork. The first sealing assembly is detachably connected to the diaphragm formwork, the first concrete barrier is detachably connected to the first sealing assembly, the first locking assembly is detachably connected to the first concrete barrier, the first sealing assembly is used to seal the connection with the steel bars, and the first locking assembly is used to lock the diaphragm formwork and the steel bars.

[0008] According to some embodiments of the present invention, the second locking mechanism also includes a second sealing assembly and a second locking assembly, and the second sealing assembly, the second concrete barrier and the second locking assembly are sequentially sleeved on the steel bars in a direction away from the diaphragm formwork, the second sealing assembly is detachably connected to the diaphragm formwork, the second concrete barrier is detachably connected to the second sealing assembly, the second locking assembly is detachably connected to the second concrete barrier, the second sealing assembly is used to seal the connection with the steel bars, and the second locking assembly is used to lock the diaphragm formwork and the steel bars.

[0009] According to some embodiments of the present invention, the first sealing assembly further includes: a first pad, the first pad is connected to the diaphragm formwork, the first pad is used to seal the connection between the diaphragm formwork and the steel bar, and provide structural support for the diaphragm formwork; a first sealer, the first sealer is arranged at the other end of the first pad relative to the diaphragm formwork, the first sealer is connected to the first concrete barrier, the first pad, the first sealer and the first concrete barrier are sequentially sleeved on the steel bar in a direction away from the diaphragm formwork, and the first sealer can provide an effective seal between the first pad and the concrete barrier; the second sealing assembly further includes: a second pad, the second pad is connected to the diaphragm formwork, the second pad is used to seal the connection between the diaphragm formwork and the steel bar, and provide structural support for the diaphragm formwork; a second sealer, the second sealer is arranged at the other two ends of the second pad relative to the diaphragm formwork, the second sealer is connected to the second concrete barrier, the second pad, the second sealer and the second concrete barrier are sequentially sleeved on the steel bar in a direction away from the diaphragm formwork, and the second sealer can provide an effective seal between the second pad and the concrete barrier.

[0010] According to some embodiments of the present invention, the first locking assembly includes: a first locking nut, which is movably connected to the first concrete barrier; a first locking screw, which is inserted into the first locking nut, and a first tightening bolt is also provided on the first locking screw, and the first tightening bolt can fix the steel bar on the first locking screw; the first locking nut and the first locking screw are sequentially sleeved on the steel bar in a direction away from the first concrete barrier; the second locking assembly includes: a second locking nut, which is movably connected to the second concrete barrier; a second locking screw, which is inserted into the second locking nut, and a second tightening bolt is also provided on the second locking screw, and the second tightening bolt can fix the steel bar on the second locking screw; the second locking nut and the second locking screw are sequentially sleeved on the steel bar in a direction away from the second concrete barrier.

[0011] According to some embodiments of the present invention, the first concrete barrier is provided with a first limiting groove, the opening end of the first limiting groove is arranged toward the first locking screw, and the first limiting groove is used to limit the position of the first locking screw; the second concrete barrier is provided with a second limiting groove, the opening end of the second limiting groove is arranged toward the second locking screw, and the second limiting groove is used to limit the position of the second locking screw.

[0012] The construction method of the I-beam diaphragm according to the second embodiment of the present invention comprises:

[0013] Step 1: Tie the steel bars and install them on the I-beam;

[0014] Step 2: Assemble the diaphragm formwork;

[0015] Step 3: Use the template locking device to fix the diaphragm template and steel bars;

[0016] Step 4: pouring concrete in the diaphragm formwork;

[0017] Step 5: Remove the template locking device.

[0018] According to some embodiments of the present invention, in step two, the corners of the diaphragm formwork are repaired and leveled to form a smooth transition, and sealing rubber is attached to the periphery of the diaphragm formwork to prevent leakage between two adjacent diaphragm formworks.

[0019] According to some embodiments of the present invention, in step three, the first locking mechanism and the second locking mechanism are arranged on the diaphragm template at intervals along the vertical direction.

[0020] According to some embodiments of the present invention, in step four, concrete is poured in a layered slope manner.

[0021] Additional aspects and advantages of the present invention will be given in part in the following description and in part will be obvious from the following description, or will be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The present invention is further described below in conjunction with the accompanying drawings and embodiments:

[0023] Figure 1 is a schematic structural diagram of a template locking device according to an embodiment of the first aspect of the present invention;

[0024] Figure 2 It is a structural schematic diagram of a construction method of an I-beam diaphragm according to a second aspect of an embodiment of the present invention;

[0025] Figure 3 yes Figure 1 Cross-sectional view in

[0026] Figure 4 yes Figure 3 A partial enlarged view of the middle A;

[0027] Figure 5 yes Figure 2 Schematic diagram of the process.

[0028] Reference numerals:

[0029] A first locking mechanism 100, a first concrete barrier 110, a first barrier cavity 111, a first through hole 112, a first limiting groove 113, a first sealing assembly 120, a first pad 121, a first sealing assembly 122, a first locking assembly 130, a first locking nut 131, a first locking screw 132, and a first fastening bolt 133;

[0030] The second locking mechanism 200, the second concrete barrier 210, the second barrier cavity 211, the second through hole 212, the second limiting groove 213, the second sealing assembly 220, the second pad 221, the second sealing assembly 222, the second locking assembly 230, the second locking nut 231, the second locking screw 232, and the second fastening bolt 233;

[0031] Steel bars 10, I-beams 20, and diaphragm formwork 30. DETAILED DESCRIPTION

[0032] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.

[0033] In the description of the present invention, it should be understood that descriptions involving orientations, such as up, down, front, back, left, right, etc., and orientations or positional relationships indicated are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0034] In the description of the present invention, "several" means one or more, "more" means more than two, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0035] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0036] refer to Figures 1 to 5 The template locking device and the construction method of the I-beam diaphragm according to the embodiment of the present invention are described.

[0037] like Figures 1 to 5As shown, the template locking device according to the first embodiment of the present invention includes a first locking mechanism 100, the first locking mechanism 100 includes a first concrete blocking member 110, the first concrete blocking member 110 has a first blocking cavity 111, the input end of the first blocking cavity 111 is connected to the interior of the diaphragm template 30, a plurality of first through holes 112 are opened on the cavity wall of the first blocking cavity 111, and the plurality of first through holes 112 are evenly arranged along the cavity wall of the first blocking cavity 111. When the concrete in the diaphragm template 30 overflows to the first blocking cavity 111 along the extension path of the steel bar 10, the concrete overflows outward from the first through holes 112; Second locking mechanism 200, the second locking mechanism 200 includes a second concrete barrier 210, the second concrete barrier 210 has a second barrier cavity 211, the volume of the first barrier cavity 111 is greater than the volume of the second barrier cavity 211, the input end of the second barrier cavity 211 is connected to the interior of the diaphragm template 30, a plurality of second through holes 212 are opened on the cavity wall of the second barrier cavity 211, and the plurality of second through holes 212 are evenly arranged along the cavity wall of the second barrier cavity 211. When the concrete in the diaphragm template 30 overflows to the second barrier cavity 211 along the extension path of the steel bar 10, the concrete overflows outward from the second through holes 212.

[0038] like Figure 1 As shown, the first concrete barrier 110 is a cylindrical structure, wherein the first concrete barrier 110 has a first barrier cavity 111, the first barrier cavity 111 is located at the rear of the first concrete barrier 110, and is connected to the interior of the diaphragm template 30, and the first barrier cavity 111 is evenly provided with a plurality of first through holes 112 along the circumferential direction. Similarly, the second concrete barrier 210 is a cylindrical structure, wherein the second concrete barrier 210 has a second barrier cavity 211, the second barrier cavity 211 is located at the rear of the second concrete barrier 210, and is connected to the interior of the diaphragm template 30, and the second barrier cavity 211 is evenly provided with a plurality of second through holes 212 along the circumferential direction. When concrete overflows from the connection between the diaphragm formwork 30 and the steel bar 10, the concrete flows into the first barrier cavity 111 and the second barrier cavity 211 along the extension direction of the steel bar 10, and then overflows through the first through hole 112 opened on the peripheral wall of the first barrier cavity 111 and the second through hole 212 opened on the peripheral wall of the second barrier cavity 211, thereby preventing the concrete from continuing to leak out along the extension direction of the steel bar 10, thereby achieving concrete blocking, avoiding damage to components caused by being covered and solidified by concrete, ensuring the free movement and removal of components, and improving construction efficiency and reducing construction costs while ensuring construction quality.

[0039] Furthermore, if Figures 2 to 4As shown, the radial cross-sectional areas of the first barrier cavity 111 and the second barrier cavity 211 are the same, but the axial length of the first barrier cavity 111 is greater than the axial length of the second barrier cavity 211. Therefore, the volume of the first barrier cavity 111 is larger than the volume of the second barrier cavity 211, that is, compared with the second concrete barrier 210, the first concrete barrier 110 can accommodate more concrete.

[0040] In some specific embodiments of the present invention, the first locking mechanism 100 also includes a first sealing assembly 120 and a first locking assembly 130. The first sealing assembly 120, the first concrete barrier 110 and the first locking assembly 130 are sequentially sleeved on the steel bar 10 in a direction away from the diaphragm formwork 30. The first sealing assembly 120 is detachably connected to the diaphragm formwork 30, the first concrete barrier 110 is detachably connected to the first sealing assembly 120, the first locking assembly 130 is detachably connected to the first concrete barrier 110, the first sealing assembly 120 is used to seal the connection with the steel bar 10, and the first locking assembly 130 is used to lock the diaphragm formwork 30 and the steel bar 10.

[0041] In some specific embodiments of the present invention, the second locking mechanism 200 also includes a second sealing assembly 220 and a second locking assembly 230. The second sealing assembly 220, the second concrete barrier 210 and the second locking assembly 230 are sequentially sleeved on the steel bar 10 in a direction away from the diaphragm formwork 30. The second sealing assembly 220 is detachably connected to the diaphragm formwork 30, the second concrete barrier 210 is detachably connected to the second sealing assembly 220, the second locking assembly 230 is detachably connected to the second concrete barrier 210, the second sealing assembly 220 is used to seal the connection with the steel bar 10, and the second locking assembly 230 is used to lock the diaphragm formwork 30 and the steel bar 10.

[0042] like Figure 1 As shown, the first sealing component 120, the first concrete barrier 110 and the first locking component 130 are sequentially sleeved on the steel bar 10 from back to front. The first sealing component 120 seals the connection between the diaphragm template 30 and the steel bar 10. When the concrete breaks through the first sealing component 120 and overflows forward, the concrete enters the first barrier cavity 111 and flows outward through each first through hole 112. Under the action of the first barrier cavity 111, the concrete is blocked in the first concrete barrier 110, and it is difficult for the concrete to invade the first locking component 130, thereby avoiding the first locking component 130 from being solidified by the concrete, ensuring the free removal of the first locking mechanism 100.

[0043] Similarly, the second sealing component 220, the second concrete barrier 210 and the second locking component 230 are sequentially mounted on the steel bar 10 from back to front. The second sealing component 220 seals the connection between the diaphragm template 30 and the steel bar 10. When the concrete breaks through the second sealing component 220 and overflows forward, the concrete enters the second barrier cavity 211 and flows outward through each second through hole 212. Under the action of the second barrier cavity 211, the concrete is blocked in the second concrete barrier 210, and it is difficult for the concrete to invade the second locking component 230, thereby avoiding the second locking component 230 from being solidified by the concrete, ensuring the free removal of the second locking mechanism 200.

[0044] In some specific implementations of the present invention, the first sealing assembly 120 also includes: a first pad 121, the first pad 121 is connected to the diaphragm formwork 30, the first pad 121 is used to seal the connection between the diaphragm formwork 30 and the steel bar 10, and provide structural support for the diaphragm formwork 30; a first seal 122, the first seal 122 is arranged at the other end of the first pad 121 opposite to the diaphragm formwork 30, the first seal 122 is connected to the first concrete barrier 110, the first pad 121, the first seal 122 and the first concrete barrier 110 are sequentially sleeved on the steel bar 10 in a direction away from the diaphragm formwork 30, and the first seal 122 can provide a seal between the first pad 121 and the first concrete barrier 210. Provide effective sealing; the second sealing assembly 220 also includes: a second pad 221, the second pad 221 is connected to the diaphragm formwork 30, the second pad 221 is used to seal the connection between the diaphragm formwork 30 and the steel bar 10, and provide structural support for the diaphragm formwork 30; a second seal 222, the second seal 222 is arranged at the other two ends of the second pad 221 opposite to the diaphragm formwork 30, the second seal 222 is connected to the second concrete barrier 210, the second pad 221, the second seal 222 and the second concrete barrier 210 are sequentially sleeved on the steel bar 10 in the direction away from the diaphragm formwork 30, and the second seal 222 can provide effective sealing between the second pad 221 and the second concrete barrier 210.

[0045] In some specific implementations of the present invention, the first locking assembly 130 includes: a first locking nut 131, the first locking nut 131 is movably connected to the first concrete barrier 110; a first locking screw 132, the first locking screw 132 is inserted into the first locking nut 131, and the first locking screw 132 is also provided with a first fastening bolt 133, and the first fastening bolt 133 can fix the steel bar 10 on the first locking screw 132; the first locking nut 131 and the first locking screw 132 are sequentially sleeved in a direction away from the first concrete barrier 110. On the steel bar 10; the second locking assembly 230 includes: a second locking nut 231, the second locking nut 231 is movably connected to the second concrete barrier 210; a second locking screw 232, the second locking screw 232 is passed through the second locking nut 231, and the second locking screw 232 is also provided with a second tightening bolt 233, and the second tightening bolt 233 can fix the steel bar 10 on the second locking screw 232; the second locking nut 231 and the second locking screw 232 are sequentially sleeved on the steel bar 10 in a direction away from the second concrete barrier 210.

[0046] like Figure 1 As shown, the first pad 121, the first seal 122, the first concrete barrier 110, the first locking nut 131, and the first locking screw 132 are sequentially sleeved on the steel bar 10 extending from the diaphragm formwork 30 from the back to the front. When in use, the first pad 121, the first seal 122, and the first concrete barrier 110 are sequentially sleeved on the steel bar 10, the first locking nut 131 and the first fastening bolt 133 are installed on the first locking screw 132, and the first locking nut 131 is withdrawn to the front of the first locking screw 132 so that it abuts against the first fastening bolt 133, and then the first locking screw 132 is sleeved on the steel bar 10 to press the first concrete barrier 110. Tighten the first fastening bolt 133 and make it stuck in the groove surface of the steel bar 10, fix the first locking screw 132 to the steel bar 10, and finally rotate the first locking nut 131 to compress the diaphragm formwork 30 until the diaphragm formwork 30 is tightly fitted with the I-beam 20.

[0047] Similarly, the second pad 221, the second seal 222, the second concrete barrier 210, the second locking nut 231, and the second locking screw 232 are sequentially sleeved on the steel bar 10 extending from the diaphragm form 30 from the back to the front. When in use, the second pad 221, the second seal 222, and the second concrete barrier 210 are sequentially sleeved on the steel bar 10, the second locking nut 231 and the second fastening bolt 233 are installed on the second locking screw 232, and the second locking nut 231 is withdrawn to the front of the second locking screw 232 so that it abuts against the second fastening bolt 233, and then the second locking screw 232 is sleeved on the steel bar 10 to press the second concrete barrier 210. Tighten the second fastening bolt 233 and make it stuck in the groove surface of the steel bar 10, fix the second locking screw 232 to the steel bar 10, and finally rotate the second locking nut 231 to compress the diaphragm formwork 30 until the diaphragm formwork 30 is tightly fitted with the I-beam 20.

[0048] like Figure 5 As shown, the construction method of the I-beam diaphragm according to the second embodiment of the present invention includes:

[0049] Step 1: Tie the steel bars 10 and install the steel bars 10 on the I-beam;

[0050] Step 2: Assembling the diaphragm template 30;

[0051] Step 3: Use a template locking device to fix the diaphragm template 30 and the steel bar 10;

[0052] Step 4: pouring concrete in the diaphragm formwork 30;

[0053] Step 5: Remove the template locking device.

[0054] In some specific implementations of the present invention, in step 2, the corners of the diaphragm template 30 are repaired and leveled to form a smooth transition, and sealing rubber is attached to the periphery of the diaphragm template 30 to prevent leakage between two adjacent diaphragm templates 30.

[0055] In some specific implementations of the present invention, in step three, the first locking mechanism 100 and the second locking mechanism 200 are arranged on the diaphragm template 30 at intervals along the vertical direction.

[0056] In some specific implementations of the present invention, in step 4, concrete is poured in a layered slope manner.

[0057] The construction method of the I-beam diaphragm is described below with a specific embodiment:

[0058] Step 1: Clean the embedded sockets on the I-beam, install the main threaded steel with single-head teeth into the sockets and tighten them, and correct the horizontality of the steel bar 10, and tie the bent secondary threaded steel and the main threaded steel to fix them. When the steel bars 10 are tied and combined on site, all intersections of the steel bars 10 should be tied, and further, the two adjacent steel bars 10 should be spot welded to avoid displacement during concrete pouring. It should be noted that the steel bars 10 should be free of dust, rust, loose rust, paint, grease, oil or other foreign matter, and no harmful defects, and the production and installation of the steel bars 10 should be strictly carried out in accordance with the construction drawings and technical specifications to ensure the quality of welding.

[0059] Step 2: Add filling material and apply release agent to the corners of the original diaphragm template 30 to make the corners of the diaphragm template 30 have a smooth transition in an arc shape. It should be noted that the smooth transition corners can make the concrete flow more evenly during pouring, reduce the accumulation of concrete at the corners, avoid uneven stress distribution of concrete and possible crack formation, and reduce the adhesion between concrete and the template, making the template easier to disassemble after the concrete hardens, reducing the risk of template damage and improving construction efficiency. After repairing and leveling, apply sealing rubber to the outer ring of the edge of the diaphragm template 30 to prevent concrete from leaking from between two adjacent connected diaphragm templates 30. Place a jack at the bottom of the bottom plate of the diaphragm template 30 to adjust the bottom plate height, and finally fix the side template of the diaphragm template 30 to the bottom plate.

[0060] Step 3: Install the template locking device onto the corresponding steel bar 10. Specifically, first use the first locking mechanism 100 to lock the diaphragm template 30, and then use the second locking mechanism 200 to fix the diaphragm template 30. The first locking mechanism 100 and the second locking mechanism 200 are arranged at intervals in the vertical direction to prevent leakage when pouring cement. It should be noted that by arranging the first locking mechanism 100 and the second locking mechanism 200 at intervals, the diaphragm template 30 is alternately connected with the barrier chambers of different volumes to effectively control the flow rate and flow of cement. Specifically, the barrier chamber with a larger volume can accommodate more cement, so that it stays for a longer time and slows down the flow rate, while the barrier chamber with a smaller volume can allow cement to pass faster to maintain appropriate fluidity. In this way, the outflow speed of cement can be effectively controlled, making it more stable and controllable during the construction process. At the same time, by properly controlling the flow rate and flow of cement, cement waste can be reduced and the consistency of construction quality can be ensured.

[0061] Specifically, the first pad 121, the first seal 122, and the first concrete barrier 110 are sequentially sleeved on the steel bar 10, the first locking nut 131 and the first nail bolt 133 are installed on the first locking screw 132, and the first locking nut 131 is withdrawn to the front of the first locking screw 132 so that it abuts against the first nail bolt 133, and then the first locking screw 132 is sleeved on the steel bar 10 to press the first concrete barrier 110. The first nail bolt 133 is tightened and stuck in the groove surface of the steel bar 10, the first locking screw 132 is fixedly connected to the steel bar 10, and finally the first locking nut 131 is rotated to press the diaphragm formwork 30 until the diaphragm formwork 30 is tightly fitted with the I-beam 20.

[0062] Specifically, the second pad 221, the second seal 222, and the second concrete barrier 210 are sequentially sleeved on the steel bar 10, the second locking nut 231 and the second nail bolt 233 are installed on the second locking screw 232, and the second locking nut 231 is withdrawn to the front of the second locking screw 232 so that it abuts against the second nail bolt 233, and then the second locking screw 232 is sleeved on the steel bar 10 to press the second concrete barrier 210. The second nail bolt 233 is tightened and stuck in the groove surface of the steel bar 10, the second locking screw 232 is fixedly connected to the steel bar 10, and finally the second locking nut 231 is rotated to press the diaphragm formwork 30 until the diaphragm formwork 30 is tightly fitted with the I-beam 20.

[0063] In this specific embodiment, a beam member is provided at the bottom of the diaphragm, and a second locking mechanism 200 is used to be sleeved on the steel bars 10 extending outward from the beam member, and locked with the diaphragm formwork 30 at the beam member. It should be noted that the beam member usually has a relatively dense arrangement of steel bars 10, and it is necessary to ensure that the concrete can fully wrap and fill the steel bars 10 to provide sufficient strength and rigidity. Therefore, the use of a smaller volume of the second locking mechanism 200 can control the flow rate of cement, so that it can better penetrate and fill the gaps between the steel bars 10, while avoiding poor concrete flow, reducing the formation of cavities and bubbles, avoiding reducing the density and strength of the concrete, and ensuring the quality of the concrete around the steel bars 10.

[0064] Step 4: The concrete is mixed in a mixing plant, transported by a mixer truck, and poured into the formwork by a combing trough. Among them, the pouring adopts a layered slope pouring method, and the insert vibrator is used for vibrating. When using the insert vibrator, the moving distance does not exceed 1.5 times the vibrator's action radius, and the distance from the side form is maintained at 50 to 100 mm. It must be inserted into the lower layer of concrete by 50 to 100 mm. After each vibration is completed, the vibrating rod should be slowly raised while vibrating to avoid collision with the formwork, steel bars 10 and other embedded parts, and each vibrating part must be vibrated until the concrete at that part is dense. It should be noted that the sign of density is that the concrete stops sinking, no more bubbles emerge, and the surface is flat and slurry.

[0065] Step 5: If Figure 1 As shown, by loosening the first fastening bolt 133 on the first locking screw 132 and loosening the second fastening bolt 233 on the second locking screw 232, the first locking mechanism 100 and the second locking mechanism 200 can be removed from the diaphragm template 30 as a whole.

[0066] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments, and various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A template locking device, characterized in that: include: A first locking mechanism (100), the first locking mechanism (100) comprising a first concrete barrier (110), the first concrete barrier (110) having a first barrier cavity (111), the input end of the first barrier cavity (111) being in communication with the interior of the diaphragm formwork (30), a plurality of first through holes (112) being provided on the cavity wall of the first barrier cavity (111), the plurality of first through holes (112) being evenly arranged along the cavity wall of the first barrier cavity (111), and when concrete in the diaphragm formwork (30) overflows into the first barrier cavity (111) along the extension path of the steel bars (10), the concrete overflows outward from the first through holes (112); A second locking mechanism (200), the second locking mechanism (200) comprising a second concrete barrier (210), the second concrete barrier (210) having a second barrier cavity (211), the volume of the first barrier cavity (111) being greater than the volume of the second barrier cavity (211), the input end of the second barrier cavity (211) being in communication with the interior of the diaphragm template (30), a plurality of second through holes (212) being provided on the cavity wall of the second barrier cavity (211), the plurality of second through holes (212) being evenly arranged along the cavity wall of the second barrier cavity (211), and when the concrete in the diaphragm template (30) overflows into the second barrier cavity (211) along the extension path of the steel bars (10), the concrete overflows outward from the second through holes (212).

2. The template locking device according to claim 1, characterized in that: The first locking mechanism (100) further comprises a first sealing assembly (120) and a first locking assembly (130); the first sealing assembly (120), the first concrete barrier (110) and the first locking assembly (130) are sequentially sleeved on the steel bar (10) in a direction away from the diaphragm template (30); the first sealing assembly (120) is detachably connected to the diaphragm template (30); the first concrete barrier (110) is detachably connected to the first sealing assembly (120); the first locking assembly (130) is detachably connected to the first concrete barrier (110); the first sealing assembly (120) is used for sealing the connection with the steel bar (10); and the first locking assembly (130) is used for locking the diaphragm template (30) and the steel bar (10).

3. The template locking device according to claim 2, characterized in that: The second locking mechanism (200) further comprises a second sealing assembly (220) and a second locking assembly (230); the second sealing assembly (220), the second concrete barrier (210) and the second locking assembly (230) are sequentially sleeved on the steel bar (10) in a direction away from the diaphragm formwork (30); the second sealing assembly (220) is detachably connected to the diaphragm formwork (30); the second concrete barrier (210) is detachably connected to the second sealing assembly (220); the second locking assembly (230) is detachably connected to the second concrete barrier (210); the second sealing assembly (220) is used for sealing the connection with the steel bar (10); and the second locking assembly (230) is used for locking the diaphragm formwork (30) and the steel bar (10).

4. The template locking device according to claim 3, characterized in that: The first sealing assembly (120) further includes: A first pad (121), the first pad (121) being connected to the diaphragm formwork (30), the first pad (121) being used to seal the connection between the diaphragm formwork (30) and the steel bars (10) and to provide structural support for the diaphragm formwork (30); a first sealing member (122), the first sealing member (122) being arranged at the other end of the first pad (121) opposite to the diaphragm formwork (30), the first sealing member (122) being connected to the first concrete barrier (110), the first pad (121), the first sealing member (122) and the first concrete barrier (110) being sequentially sleeved on the steel bar (10) in a direction away from the diaphragm formwork (30), the first sealing member (122) being able to provide an effective seal between the first pad (121) and the first concrete barrier (110); The second sealing assembly (220) further includes: A second pad (221), the second pad (221) being connected to the diaphragm formwork (30), the second pad (221) being used to seal the connection between the diaphragm formwork (30) and the steel bars (10) and to provide structural support for the diaphragm formwork (30); The second sealing member (222) is arranged at the other two ends of the second pad (221) opposite to the diaphragm formwork (30), the second sealing member (222) is connected to the second concrete barrier (210), the second pad (221), the second sealing member (222) and the second concrete barrier (210) are sequentially sleeved on the steel bar (10) in a direction away from the diaphragm formwork (30), and the second sealing member (222) can provide an effective seal between the second pad (221) and the second concrete barrier (210).

5. The template locking device according to claim 4, characterized in that: The first locking assembly (130) comprises: a first locking nut (131), wherein the first locking nut (131) is movably connected to the first concrete barrier (110); a first locking screw (132), the first locking screw (132) being inserted into the first locking nut (131), the first locking screw (132) being further provided with a first fastening bolt (133), the first fastening bolt (133) being capable of fixing the steel bar (10) on the first locking screw (132); The first locking nut (131) and the first locking screw (132) are sequentially sleeved on the steel bar (10) in a direction away from the first concrete barrier (110); The second locking assembly (230) comprises: a second locking nut (231), wherein the second locking nut (231) is movably connected to the second concrete barrier (210); a second locking screw (232), the second locking screw (232) being inserted into the second locking nut (231), the second locking screw (232) being further provided with a second fastening bolt (233), the second fastening bolt (233) being capable of fixing the steel bar (10) on the second locking screw (232); The second locking nut (231) and the second locking screw (232) are sequentially sleeved on the steel bar (10) in a direction away from the second concrete barrier (210).

6. The template locking device according to claim 5, characterized in that: The first concrete barrier (110) is provided with a first limiting groove (113), the opening end of the first limiting groove (113) is arranged toward the first locking screw (132), and the first limiting groove (113) is used to limit the position of the first locking screw (132); The second concrete barrier (210) is provided with a second limiting groove (213), the opening end of the second limiting groove (213) is arranged toward the second locking screw (232), and the second limiting groove (213) is used to limit the position of the second locking screw (232).

7. A construction method for an I-beam diaphragm, using the template locking device according to any one of claims 1 to 6, characterized in that: include: Step 1: tying the steel bars (10) and installing the steel bars (10) on the I-beam; Step 2: Assembling the diaphragm template (30); Step 3: Using a template locking device to fix the diaphragm template (30) and the steel bars (10); Step 4: pouring concrete in the diaphragm formwork (30); Step 5: Remove the template locking device.

8. The construction method of the I-beam diaphragm according to claim 7, characterized in that: In step 2, the corners of the diaphragm template (30) are repaired and leveled to form a smooth transition, and sealing rubber is attached to the periphery of the diaphragm template (30) to prevent mortar leakage between two adjacent diaphragm templates (30).

9. The construction method of the I-beam diaphragm according to claim 7, characterized in that: In step three, the first locking mechanism (100) and the second locking mechanism (200) are arranged on the diaphragm template (30) at intervals in the vertical direction.

10. The construction method of the I-beam diaphragm according to claim 7, characterized in that: In step four, concrete is poured in a layered sloped manner.