The invention discloses a construction method of an automatic bar penetrating device for
caisson prefabrication, and relates to the technical field of
building construction. Comprising the steps of device structure
size adjustment, hoisting platform trial hoisting, bar penetrating facility trial operation, longitudinal
steel bar paving and sorting, device first parking, first row bar penetrating, device stepping lifting, device bar penetrating and bar penetrating completion. Through
tower crane lifting displacement and
manual traction positioning, a double-strand
rope with scale marks is adopted at the front end of the lifting platform for lifting limiting, the lifting height of each step is controlled to be consistent with the rib penetrating
vertical distance, the rib penetrating position is rapidly aligned, and the rib penetrating efficiency is improved; the paving and discharging mechanism paves and sorts longitudinal steel bars in advance,
welding seam positions of adjacent steel bars are prevented from being overlapped, the
engineering quality is guaranteed, the single-time bar penetrating number arrangement and bearing requirements of the
caisson are met, and the hoisting and lifting displacement frequency is reduced. Through
remote control over transverse movement, overturning and longitudinal movement, automatic operation is achieved, and the labor intensity is greatly reduced; in the whole hoisting process, personnel do not need to enter the hoisting platform, and safe construction is guaranteed.