Parapet wall anti-seepage structure and construction method thereof

By setting up a hydrophobic structure and a waterproof connection structure in the daughter wall structure, combining geosynthetic materials and waterproof coating glue, the water seepage and water leakage problems caused by cracks in the daughter wall are solved, and the stability and waterproof performance of the structure are improved.

CN119877790AActive Publication Date: 2025-04-25ZHEJIANG SHUNJIANG CONSTR GRP CO LTD
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202510289288.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-12
Publication Date
2025-04-25
Estimated Expiration
2045-03-12

AI Technical Summary

Technical Problem

Cracks are prone to the joints of the daughter wall and the roof, resulting in water seepage and leakage problems. In addition, the rigidity and integrity of the daughter wall are relatively poor, and are easily affected by the expansion thrust of the roof waterproof layer and protective layer, resulting in outward movement and low safety.

Method used

An anti-leakage design including a daughter wall structure, a top wall, a longitudinal wall and a hydrophobic structure is adopted. By setting up a first hydrophobic structure, a waterproof connection structure and a second hydrophobic structure, combining geosynthetic materials and waterproof coating glue, an effective waterproof and drainage system is formed.

Benefits of technology

Effectively prevent moisture penetration, ensure that the accumulated moisture is effectively eliminated, improve the stability and bearing capacity of the wall structure, extend the service life of the waterproof layer, reduce the chance of water seepage, and improve seismic resistance and durability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119877790A_ABST
    Figure CN119877790A_ABST
Patent Text Reader

Abstract

The invention discloses a parapet wall anti-seepage structure and a construction method thereof.The parapet wall anti-seepage structure comprises a parapet wall structure, a top wall of a building and a longitudinal wall, the parapet wall structure is arranged above the longitudinal wall, a first hydrophobic structure is arranged above the parapet wall structure, a waterproof connecting structure is arranged below the parapet wall structure, and a second hydrophobic structure is arranged on one side of the longitudinal wall; a waterproof structure is arranged on the top wall, and the waterproof structure is laid upwards on the parapet wall structure along the waterproof connecting structure and is connected with the first hydrophobic structure; the second hydrophobic structure comprises a hydrophobic area, the section of the hydrophobic area is of a triangular structure inclining outwards and downwards, a hydrophobic slope is formed on the upper surface of the hydrophobic area, a connecting face is formed on the side face of the hydrophobic area, and the connecting face is combined with the longitudinal wall. A flow guide face is formed on the lower surface of the drainage area, a sealing groove is formed below the flow guide face, and the waterproof structure extends rightwards to the drainage inclined face and then enters the sealing groove along the flow guide face. And an anti-permeation effect can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of parapet wall construction, and in particular to a parapet wall anti-leakage structure and a construction method thereof. Background Art

[0002] A parapet is a term used in architectural design to refer to the perimeter or low wall of a building's roof. It is usually used at the edge of a roof to prevent people or objects from falling from the roof, or in some cases, to beautify the building's exterior.

[0003] At present, due to the construction characteristics of the building itself, the joint between the parapet and the roof is easily affected by thermal expansion and contraction, which leads to cracks. These cracks will cause water seepage and leakage, especially after rainfall, when rainwater tends to accumulate in this area and is difficult to drain. If the accumulated water is not drained for a long time, the rainwater will soak and affect the isolation and waterproof layer of the roof, especially in an environment with wind and sun, the water will penetrate into the building through the cracks, reducing the service life of the waterproof layer.

[0004] In addition, the accumulated rainwater is often exposed to high temperatures, and the water vapor expands, further exacerbating the expansion of cracks, resulting in more cracks in the building, affecting its normal use. At the same time, due to the poor rigidity and integrity of common parapet walls, they are easily affected by the expansion thrust of the roof waterproofing layer and protective layer, causing outward movement, resulting in lower safety and easy to produce larger cracks. Under the influence of the temperature difference between day and night, the thermal expansion and contraction between the parapet wall and the roof is more obvious, which is easy to form new cracks, further exacerbating the problem of rainwater leakage.

[0005] In view of the above problems, the present invention document proposes a parapet anti-leakage structure and a construction method thereof. Summary of the invention

[0006] The purpose of the present invention is to solve the problem that rainwater is easy to accumulate and difficult to discharge after rainfall. If the accumulated water is not discharged for a long time, the rainwater will soak and affect the isolation and waterproof layer of the roof. In addition, the accumulated rainwater is often exposed to high temperature, and the water vapor expands, which further aggravates the expansion of cracks and causes more cracks in the building. At the same time, due to the poor rigidity and integrity of common parapets, they are easily affected by the expansion thrust of the roof waterproof layer and the protective layer, resulting in outward movement, resulting in lower safety and easy to produce larger cracks. Under the influence of the temperature difference between day and night, the thermal expansion and contraction between the parapet and the roof is more obvious, and new cracks are easily formed, which further aggravates the problem of rainwater leakage. A parapet anti-leakage structure and a construction method thereof are proposed.

[0007] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: the present application provides a parapet anti-leakage structure, including a parapet structure, a top wall and a longitudinal wall of a building, the parapet structure is arranged above the longitudinal wall, a first hydrophobic structure is arranged above the parapet structure and a waterproof connecting structure is arranged below the parapet structure, and a second hydrophobic structure is arranged on one side of the longitudinal wall; a waterproof structure is arranged on the top wall, and the waterproof structure is laid upward along the waterproof connecting structure to the parapet structure and connected to the first hydrophobic structure; the second hydrophobic structure includes a hydrophobic area, the cross-section of the hydrophobic area is formed into a triangular structure inclined outward and downward, the upper surface of which forms a hydrophobic inclined surface, the side surface forms a connecting surface, and the connecting surface is combined with the longitudinal wall; the lower surface of the hydrophobic area forms a guide surface, a sealing groove is opened below the guide surface, the waterproof structure extends to the right to the hydrophobic inclined surface, and then enters the sealing groove along the guide surface.

[0008] Preferably, a laying groove is opened on the upper side of one side of the parapet structure, the upper side of the laying groove is a vertical surface, and the lower side of the laying groove is an inclined surface.

[0009] Preferably, the waterproof structure includes a second waterproof membrane, which is laid on the hydrophobic surface and laid to the right on the top wall and the hydrophobic slope, and then laid back along the inflection point of the hydrophobic slope and the guide surface into the sealing groove, forming a U-shaped structure in the sealing groove, and the height of the hydrophobic surface decreases to the right.

[0010] Preferably, a first waterproof membrane is laid on top of the second waterproof membrane, and the first waterproof membrane extends to the right edge of the longitudinal wall. The first waterproof membrane is also laid upward along the parapet structure and enters the laying groove.

[0011] Preferably, the first hydrophobic structure includes a top plate, which is shaped like a ridge, and a first waterproof adhesive layer is provided at the vertical connection between the top plate and the parapet structure. The first waterproof adhesive layer is laid downward along the parapet structure and connected to the side of the first waterproof membrane at the laying groove.

[0012] Preferably, a waterproof sealing layer is provided at the angle formed between the first waterproof adhesive layer and the top plate.

[0013] Preferably, the height of the connection point between the guide surface and the longitudinal wall is greater than the height of the connection point between the guide surface and the hydrophobic slope;

[0014] A third waterproof roll is laid above the second waterproof roll located on the hydrophobic slope, one end of the third waterproof roll is connected to the first waterproof roll by a waterproof sealant, and the third waterproof roll is laid downward along the second waterproof roll and laid back along the turning point of the second waterproof roll, while forming an adaptive U-shaped structure at the part where the second waterproof roll enters the sealing material;

[0015] A third waterproof adhesive layer is provided at the angle between the guide surface and the longitudinal wall. The third waterproof adhesive layer closes the U-shaped structure formed by the second waterproof adhesive layer and the third waterproof adhesive layer. The bottom of the third waterproof adhesive layer is an arc surface, and the right side of the third waterproof adhesive layer is a vertical surface.

[0016] Preferably, a plurality of steel cages are embedded in the longitudinal wall, and the steel cages are arranged in the parapet structure, and the top of the longitudinal wall decreases in slope from left to right.

[0017] Preferably, the waterproof connection structure includes geosynthetics and multiple waterproof coating glues, the multiple waterproof coating glues are coated on a single steel bar of the same steel cage and connected to the first waterproof membrane, the multiple waterproof coating glues are arranged in the geosynthetics, the steel cage is arranged in the geosynthetics, the geosynthetics are assembled under the parapet structure, the bottom of the geosynthetics is connected to the first waterproof membrane through a second waterproof glue layer arranged around, and one end of the first waterproof membrane is also laid upward on the side of the geosynthetics.

[0018] A construction method for a parapet wall anti-seepage structure comprises the following steps:

[0019] S1. Construction preparation

[0020] Understand the design requirements, size and material requirements of the parapet, and prepare the required construction materials and tools according to the design requirements. Secondly, determine the location of the parapet structure according to the construction drawings, and lay out the lines for positioning;

[0021] S2. Formwork erection

[0022] According to the height and shape of the parapet structure, choose the appropriate formwork material, install the formwork in place according to the design requirements, the formwork should be vertical and horizontal, and then pour concrete in the formwork, pay attention to the pouring thickness and density of the concrete, use a vibrator to vibrate and remove bubbles, and after the concrete pouring is completed, timely maintenance is carried out to ensure the strength and durability of the concrete. After the concrete reaches a certain strength, the formwork is removed;

[0023] S3. Waterproof construction

[0024] Before the parapet wall structure is cast, the second waterproofing membrane is laid on the drainage surface, the longitudinal wall and the drainage slope, and the second waterproofing membrane bypasses the junction between the drainage slope and the diversion surface, is laid on the diversion surface, and forms a U-shaped structure in the sealing groove;

[0025] After the parapet wall structure is formed, the third waterproof membrane is laid on the right side of the second waterproof membrane. The third waterproof membrane extends to the diversion surface and forms a U-shaped structure at the end of the second waterproof membrane. The third waterproof adhesive layer is laid at the U-shaped structure of the second waterproof membrane and the third waterproof membrane, and at the angle between the diversion surface and the longitudinal wall. The right side of the third waterproof adhesive layer is vertically processed, and the bottom is arranged in an arc shape. Then, the second waterproof adhesive layer is laid at the bottom of the geosynthetics for waterproofing.

[0026] Then lay the first waterproof membrane on the second waterproof membrane, design the size according to the needs, lay the first waterproof membrane upward along the bottom of the geosynthetics, and extend the first waterproof membrane from the parapet structure into the laying groove, finally lay the first waterproof adhesive layer downward on the side above the parapet structure, so that the first waterproof adhesive layer covers the laying groove and one side of the first waterproof membrane, and lay a waterproof sealing layer between the first waterproof adhesive layer and the top plate angle for further waterproofing.

[0027] Compared with the prior art, the present invention provides a parapet wall anti-leakage structure and a construction method thereof, which has at least one of the following beneficial effects:

[0028] 1. The parapet anti-leakage structure and the construction method thereof, by combining a plurality of steel bars to form a steel cage, the overall strength is greatly improved, and the steel cage arrangement can effectively increase the stability and bearing capacity of the parapet structure, improve the seismic performance and enhance the durability, and waterproof coating glue is arranged on each steel bar of the steel cage to increase the waterproof sealing, and secondly, geosynthetics are added between the parapet structure and the longitudinal wall, and the geosynthetics can play the role of reinforcement, reinforcement, anti-seepage, isolation, drainage, anti-filtration and protection, further maintaining the bearing capacity and stability of the parapet structure, and not easy to cause displacement, and at the same time, a second waterproof glue layer is arranged at the bottom of the geosynthetics to play an anti-seepage effect.

[0029] 2. The anti-leakage structure of the parapet and the construction method thereof can effectively block the penetration of water and play a waterproof role through the water resistance of the first waterproof membrane, the second waterproof membrane and the third waterproof membrane, and can also ensure that the accumulated water is effectively discharged. There are gaps between the multiple waterproof connection structures. At the same time, the hydrophobic surface and the longitudinal wall slope decrease to the right, thereby guiding the water to be discharged smoothly to the right, which is convenient for drainage.

[0030] 3. The parapet wall anti-leakage structure and its construction method can form a good drainage channel through the hydrophobicity of the waterproof structure, the oblique arrangement of the top wall, the longitudinal wall and the second hydrophobic structure, and the gaps between the waterproof connection structures, so that water can be discharged in time to avoid the accumulation of water, thereby reducing the probability of water seepage. In addition, the second waterproof membrane and the third waterproof membrane form a U-shaped structure in the sealing groove, which can effectively play a role in sealing and waterproofing. In combination with the sealing of the third waterproof adhesive layer, the waterproof performance is greatly improved. Secondly, the hydrophobic slope is an inclined surface, and the height of the connection point between the guide surface and the hydrophobic slope is small. At the connection height between the guide surface and the longitudinal wall, the hydrophobic slope can be drained smoothly to prevent water from passing under the guide surface, thereby improving the anti-permeability. If water leaks from under the guide surface, water molecules will accumulate on the vertical surface of the third waterproof adhesive layer. The third waterproof adhesive layer is arc-shaped below, so that water molecules can be smoothly discharged downward through the vertical surface, thereby playing a double waterproofing role. By preventing water penetration and cooperating with good hydrophobicity, water accumulation is avoided, so that the waterproof structure, the second hydrophobic structure and the waterproof connection structure can better play their performance, keep the structure dry, and further avoid water seepage. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 A three-dimensional view of a parapet anti-leakage structure proposed by the present invention;

[0032] Figure 2 A three-dimensional view of the top wall of a parapet wall anti-leakage structure proposed by the present invention;

[0033] Figure 3 For the present invention Figure 2 A magnified view of point A;

[0034] Figure 4 For the present invention Figure 2 A magnified view of point B;

[0035] Figure 5 A view showing the connection between the longitudinal wall and the hydrophobic area of ​​a parapet wall anti-leakage structure proposed by the present invention;

[0036] Figure 6 A structural view of the construction of the second waterproof membrane of a parapet wall anti-leakage structure proposed by the present invention;

[0037] Figure 7 A structural view of the parapet wall structure construction of a parapet wall anti-leakage structure proposed by the present invention;

[0038] Figure 8 A structural view of the waterproof connection structure construction of a parapet anti-leakage structure proposed by the present invention;

[0039] Fig. 9A structural view of the construction of the first waterproof membrane of a parapet wall anti-leakage structure proposed by the present invention;

[0040] Fig.10 This is a structural view of the construction of a waterproof sealing layer of a parapet anti-leakage structure proposed by the present invention.

[0041] In the figure: 100, parapet structure; 101, laying groove; 200, top wall; 201, hydrophobic surface; 300, first hydrophobic structure; 301, top plate; 302, waterproof sealing layer; 303, first waterproof adhesive layer; 400, longitudinal wall; 401, steel cage; 500, waterproof structure; 501, first waterproof membrane; 502, second waterproof membrane; 600, waterproof connection structure; 601, second waterproof adhesive layer; 602, geosynthetics; 603, waterproof coating glue; 700, second hydrophobic structure; 701, hydrophobic area; 702, third waterproof membrane; 703, sealing groove; 704, third waterproof adhesive layer; 705, hydrophobic slope; 706, diversion surface; 707, connection surface. DETAILED DESCRIPTION

[0042] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0043] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0044] Example 1: Reference Figures 1 to 3 and Figures 5 to 10 The parapet wall anti-leakage structure provided in the present application includes a parapet wall structure 100, and the parapet wall structure 100 is arranged on a longitudinal wall 400. A first hydrophobic structure 300 is arranged above the parapet wall structure 100, and a plurality of waterproof connection structures 600 are arranged below the parapet wall structure 100, and a top wall 200 and a second hydrophobic structure 700 are respectively arranged on both sides of the longitudinal wall 400.

[0045] In detail, a laying groove 101 is opened on the upper side of one side of the parapet structure 100 , the upper side of the laying groove 101 is a vertical surface, and the lower side of the laying groove 101 is an inclined surface. The first hydrophobic structure 300 includes a top plate 301, and the top plate 301 is shaped like a ridge. The ridge shape is set so that the top plate 301 can more easily guide rainwater to be discharged to both sides to avoid rainwater residue. A first waterproof adhesive layer 303 is provided at the vertical connection between the top plate 301 and the parapet structure 100, and the first waterproof adhesive layer 303 is laid downward along the parapet structure 100. The first waterproof adhesive layer 303 can seal the connection between the first waterproof membrane 501 and the laying groove 101 to improve the waterproof and anti-penetration effects. The reinforced concrete structure formed by combining steel bars and concrete has high durability and can resist erosion and damage in the natural environment. It is connected to the side of the first waterproof membrane 501 at the laying groove 101. A waterproof sealing layer 302 is provided at the angle formed between the first waterproof adhesive layer 303 and the top plate 301. The waterproof sealing layer 302 can play a waterproof sealing role between the top plate 301 and the first waterproof adhesive layer 303 to avoid water seepage. A plurality of steel cages 401 are embedded in the longitudinal wall 400, and the steel cages 401 are arranged in the parapet structure 100. The steel cages 401 play the role of a skeleton in the parapet, enhancing the wind pressure resistance and overturning resistance of the wall, and preventing the wall from collapsing or being damaged.

[0046] A hydrophobic surface 201 is provided above the top wall 200, and a waterproof structure 500 is provided on the hydrophobic surface 201. The waterproof structure 500 is laid upward along the waterproof connection structure 600 to the parapet structure 100 and is connected to the first hydrophobic structure 300. The waterproof connection structure 600 includes a geosynthetic material 602 and a plurality of waterproof coating adhesives 603. The geosynthetic material 602 can enhance the bearing capacity and shear strength of the parapet structure 100. At the same time, the geosynthetic material 602 has excellent anti-seepage, isolation and protection properties, thereby effectively improving the stability, bearing capacity and disaster resistance of the parapet structure 100. A plurality of waterproof coating adhesives 603 are coated on a single steel bar of the same steel cage 401, and the waterproof coating adhesive 603 seals the bottom of the steel cage 401 for waterproofing. Water treatment, and in conjunction with geosynthetics 602, multiple anti-seepage effects can be achieved, and it is connected to the first waterproof membrane 501, multiple waterproof coating adhesives 603 are arranged in the geosynthetics 602, and the steel cage 401 is arranged in the geosynthetics 602. The geosynthetics 602 are assembled below the parapet structure 100, and the bottom of the geosynthetics 602 is connected to the first waterproof membrane 501 through a second waterproof adhesive layer 601 arranged around it. The bottom of the geosynthetics 602 can be sealed and waterproofed through the second waterproof adhesive layer 601, thereby further improving the waterproof performance and avoiding the risk of water seepage in the gap between the geosynthetics 602 and the first waterproof membrane 501. One end of the first waterproof membrane 501 is also laid upward on the side of the geosynthetics 602.

[0047] In this embodiment: by combining multiple steel bars to form a steel cage 401, the overall strength is greatly improved, and the setting of the steel cage 401 can effectively increase the stability and bearing capacity of the parapet structure 100, improve the seismic performance and enhance the durability, and waterproof coating glue 603 is arranged on each steel bar of the steel cage 401 to increase the waterproof sealing. Secondly, geosynthetics 602 are added between the parapet structure 100 and the longitudinal wall 400. The geosynthetics 602 can play the role of reinforcement, reinforcement, anti-seepage, isolation, drainage, anti-filtration and protection, further maintaining the bearing capacity and stability of the parapet structure 100, and is not easy to cause displacement. At the same time, a second waterproof glue layer 601 is arranged at the bottom of the geosynthetics 602 to play an anti-seepage effect.

[0048] Example 2: Reference Figure 2 and Figures 4 to 5 The parapet anti-leakage structure includes a waterproof structure 500, and the waterproof structure 500 includes a second waterproof membrane 502. The first waterproof membrane 501, the second waterproof membrane 502 and the third waterproof membrane 702 have the characteristics of blocking moisture penetration, ensuring that moisture cannot penetrate into the interior of the building structure, and also have the functions of water conduction and drainage, water resistance, good mechanical strength, good elongation, fracture resistance and erosion resistance, ensuring that the waterproof effect is optimal and the service life is improved. The second waterproof membrane 502 is laid on the hydrophobic surface 201, and the height of the hydrophobic surface 201 decreases to the right, and the slope of the hydrophobic surface 201 decreases to the right, so that the hydrophobic surface 201 can smoothly perform the hydrophobic operation and reduce moisture residue. The longitudinal wall 400 continues to decrease to the right along the slope of the hydrophobic surface 201, so that the moisture can continue to be guided to the right for discharge. The top of the longitudinal wall 400 is from the left The slope decreases to the right, and it is laid to the right on the top wall and the hydrophobic slope 705, and then laid back along the turning point of the hydrophobic slope 705 and the guide surface 706 into the sealing groove 703, forming a U-shaped structure in the sealing groove 703, and a U-shaped structure is formed in the sealing groove 703 by the second waterproof membrane 502 and the third waterproof membrane 702, so as to increase the sealing performance. At the same time, the third waterproof adhesive layer 704 can seal the ends of the second waterproof membrane 502 and the third waterproof membrane 702, so as to prevent warping. The first waterproof membrane 501 is laid above the second waterproof membrane 502, and the first waterproof membrane 501 extends to the right edge of the longitudinal wall 400. The first waterproof membrane 501 is also laid upward along the parapet structure 100 and enters the laying groove 101. A plurality of waterproof connection structures 600 are arranged below the parapet structure 100.

[0049] In this embodiment: the water resistance of the first waterproof membrane 501, the second waterproof membrane 502 and the third waterproof membrane 702 can effectively block the penetration of moisture and play a waterproof role. It can also ensure that the accumulated moisture is effectively discharged, and there are gaps between the multiple waterproof connection structures 600. At the same time, the hydrophobic surface 201 and the longitudinal wall 400 are inclined to the right in a decreasing manner, thereby guiding the moisture to be discharged smoothly to the right, which is convenient for hydrophobicity.

[0050] Example 3: Reference Figure 4 and Figure 5 The parapet anti-leakage structure includes a second hydrophobic structure 700, which includes a hydrophobic area 701. The hydrophobic area 701 includes a connecting surface 707, a flow guide surface 706 and a hydrophobic slope 705. The hydrophobic slope 705 is arranged with a slope, which can play a good hydrophobic role. The flow guide surface 706, the hydrophobic slope 705 and the connecting surface 707 are arranged on the upper and lower sides and the left side of the hydrophobic area 701, respectively. The connecting surface 707 is installed on one side of the longitudinal wall 400. A sealing groove 703 is opened below the flow guide surface 706. The waterproof structure 500 extends to the right to the hydrophobic slope 705, and then enters the sealing groove 703 along the flow guide surface 706.

[0051] The waterproof structure 500 includes a second waterproof membrane 502, which is laid on the hydrophobic surface 201, and is laid to the right on the top wall and the hydrophobic slope 705, and then laid back along the turning point of the hydrophobic slope 705 and the guide surface 706 into the sealing groove 703, forming a U-shaped structure in the sealing groove 703. The height of the hydrophobic surface 201 decreases to the right, and the height of the connection point between the guide surface 706 and the longitudinal wall 400 is greater than the height of the connection point between the guide surface 706 and the hydrophobic slope 705. The different connection point heights at both ends of the guide surface 706 prevent water molecules from being guided to the left, so that water molecules can be smoothly discharged through the hydrophobic slope 705, avoiding subsequent damage to the wall. A third waterproof membrane 702 is laid above the second waterproof membrane 502 located on the hydrophobic slope 705, and one end of the third waterproof membrane 702 is connected to the first A waterproof roll 501 is connected by a waterproof sealant, and a third waterproof roll 702 is laid downward along the second waterproof roll 502, and laid back along the turning point of the second waterproof roll 502, and at the same time, a U-shaped structure is formed at the part where the second waterproof roll 502 enters the sealant, and a third waterproof adhesive layer 704 is provided at the angle between the guide surface 706 and the longitudinal wall 400, and the third waterproof adhesive layer 704 closes the U-shaped structure formed by the second waterproof adhesive layer 601 and the third waterproof adhesive layer 704, and the bottom of the third waterproof adhesive layer 704 is an arc surface, and the right side of the third waterproof adhesive layer 704 is a vertical surface, through which moisture can be accumulated, and at the same time, the arc surface is used to make water molecules accumulate smoothly on the vertical surface, preventing water molecules from flowing to the longitudinal wall 400, thereby achieving a secondary waterproof effect, and making the protection effect of the longitudinal wall 400 better. In one embodiment, a layered or meshed anti-sun and anti-cracking material can be provided at the third waterproof adhesive layer 704. In one example, a high-density mesh polyethylene material is provided at the U-shaped structure, and then the adhesive layer 704 is coated, which can improve the sun-proof and crack-proof performance of the third adhesive layer 704. This prevents the adhesive layer from falling off and the roll material from warping after long-term exposure to the sun and rain. The polyethylene mesh can be provided at the edge of the third waterproof adhesive layer 704, or the entire surface to be sealed.

[0052] In this embodiment: through the hydrophobicity of the waterproof structure 500, the oblique arrangement of the top wall 200, the longitudinal wall 400 and the second hydrophobic structure 700, and the gaps between the waterproof connection structures 600, a good drainage channel can be formed, and water can be discharged in time to avoid the accumulation of water, thereby reducing the probability of water seepage. In addition, the second waterproof roll 502 and the third waterproof roll 702 form a U-shaped structure in the sealing groove 703, which can effectively play a role in sealing and waterproofing. In combination with the sealing of the third waterproof adhesive layer 704, the waterproof performance is greatly improved. Secondly, the hydrophobic slope 705 is a slope, and the height of the connection point between the guide surface 706 and the hydrophobic slope 705 is less than the guide surface. The connection height between the flow surface 706 and the longitudinal wall 400 allows the hydrophobic slope 705 to drain water smoothly, preventing water from passing under the guide surface 706, thereby improving the anti-permeability. If water leaks from under the guide surface 706, water molecules will accumulate on the vertical surface of the third waterproof adhesive layer 704. The bottom of the third waterproof adhesive layer 704 is arc-shaped, so that water molecules can be smoothly discharged downward through the vertical surface, thereby achieving a double waterproof effect. By preventing water penetration and cooperating with good hydrophobicity to avoid water accumulation, the waterproof structure 500, the second hydrophobic structure 700 and the waterproof connection structure 600 can better exert their performance and keep the structure dry, thereby further avoiding water seepage.

[0053] A construction method for a parapet wall anti-seepage structure comprises the following steps:

[0054] S1. Construction preparation

[0055] Understand the design requirements, size and material requirements of the parapet, and prepare the required construction materials and tools according to the design requirements. Secondly, determine the location of the parapet structure 100 according to the construction drawings, and lay out the lines for positioning;

[0056] S2. Formwork erection

[0057] According to the height and shape of the parapet structure 100, select the appropriate formwork material, install the formwork in place according to the design requirements, the formwork should be vertical and horizontal, and then pour concrete in the formwork, pay attention to the pouring thickness and density of the concrete, use a vibrator to vibrate and remove bubbles, and after the concrete pouring is completed, perform maintenance in time to ensure the strength and durability of the concrete. After the concrete reaches a certain strength, remove the formwork;

[0058] S3. Waterproof construction

[0059] Before the parapet structure 100 is cast, the second waterproofing membrane 502 is laid on the hydrophobic surface 201, the longitudinal wall 400 and the hydrophobic slope 705, and the second waterproofing membrane 502 bypasses the junction between the hydrophobic slope 705 and the diversion surface 706, is laid on the diversion surface 706, and forms a U-shaped structure in the sealing groove 703;

[0060] After the parapet structure 100 is formed, a third waterproof roll 702 is laid on the right side of the second waterproof roll 502, and the third waterproof roll 702 extends to the guide surface 706 and forms a U-shaped structure at the end of the second waterproof roll 502. A third waterproof adhesive layer 704 is arranged at the U-shaped structure of the second waterproof roll 502 and the third waterproof roll 702, and at the angle between the guide surface 706 and the longitudinal wall 400. The right side of the third waterproof adhesive layer 704 is vertically processed, and the bottom is arranged in an arc shape. Then, a second waterproof adhesive layer 601 is arranged at the bottom of the geosynthetics 602 for waterproofing.

[0061] Then, the first waterproof membrane 501 is laid on the second waterproof membrane 502, and the size is designed as required, so that the first waterproof membrane 501 is laid upward along the bottom of the geosynthetics 602, and the first waterproof membrane 501 extends from the parapet structure 100 to the laying groove 101. Finally, the first waterproof adhesive layer 303 is laid downward on the side above the parapet structure 100, so that the first waterproof adhesive layer 303 covers the laying groove 101 and covers one side of the first waterproof membrane 501, and a waterproof sealing layer 302 is laid between the angle between the first waterproof adhesive layer 303 and the top plate 301 for further waterproofing.

[0062] The present invention combines a plurality of steel bars to form a steel cage, which greatly improves the overall strength. The steel cage can effectively increase the stability and bearing capacity of the parapet structure, improve the seismic performance and enhance the durability. Waterproof coating glue is arranged on each steel bar of the steel cage to increase the waterproof sealing. Secondly, geosynthetics are added between the parapet structure and the longitudinal wall. The geosynthetics can play the role of reinforcement, reinforcement, anti-seepage, isolation, drainage, anti-filtration and protection, further maintaining the bearing capacity and stability of the parapet structure, and is not easy to be displaced. At the same time, a second waterproof glue layer is arranged at the bottom of the geosynthetics to play an anti-seepage effect.

[0063] The above are only preferred specific implementation modes of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solutions and inventive concepts of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A parapet wall anti-leakage structure, comprising a parapet wall structure (100), a top wall (200) and a longitudinal wall (400) of a building, characterized in that: The parapet structure (100) is arranged above the longitudinal wall (400), a first hydrophobic structure (300) is arranged above the parapet structure (100) and a waterproof connection structure (600) is arranged below the parapet structure (100), and a second hydrophobic structure (700) is arranged on one side of the longitudinal wall (400); The top wall (200) is provided with a waterproof structure (500), and the waterproof structure (500) is laid upwards along the waterproof connection structure (600) onto the parapet structure (100), and is connected to the first hydrophobic structure (300); The second hydrophobic structure (700) includes a hydrophobic area (701), the cross section of which is formed into a triangular structure inclined outward and downward, the upper surface of which forms a hydrophobic inclined surface (705), and the side surface forms a connecting surface (707), and the connecting surface (707) is connected to the longitudinal wall (400); the lower surface of the hydrophobic area (701) forms a guide surface (706), and a sealing groove (703) is opened below the guide surface (706), and the waterproof structure (500) extends to the right to the hydrophobic inclined surface (705), and then enters the sealing groove (703) along the guide surface (706).

2. The parapet wall anti-leakage structure according to claim 1, characterized in that: A laying groove (101) is provided on the upper side of one side of the parapet structure (100), the upper side of the laying groove (101) is a vertical surface, and the lower side of the laying groove (101) is an inclined surface.

3. The parapet anti-leakage structure according to claim 2, characterized in that: The waterproof structure (500) includes a second waterproof roll (502), which is laid on the hydrophobic surface (201) on the upper surface of the top wall (200), and is laid to the right on the top wall and the hydrophobic slope (705), and then laid back along the turning point of the hydrophobic slope (705) and the guide surface (706) into the sealing groove (703), forming a U-shaped structure in the sealing groove (703).

4. The parapet wall anti-leakage structure according to claim 3, characterized in that: A first waterproof roll (501) is laid above the second waterproof roll (502), and the first waterproof roll (501) extends to the right edge of the longitudinal wall (400). The first waterproof roll (501) is also laid upward along the parapet structure (100) and enters the laying groove (101).

5. The parapet wall anti-leakage structure according to claim 4, characterized in that: The first hydrophobic structure (300) comprises a top plate (301), the top plate (301) being in the shape of a roof ridge, a first waterproof adhesive layer (303) being provided at a vertical connection between the top plate (301) and the parapet structure (100), and the first waterproof adhesive layer (303) being laid downward along the parapet structure (100) and connected to a side surface of the first waterproof membrane (501) at a laying groove (101).

6. The parapet wall anti-leakage structure according to claim 5, characterized in that: A waterproof sealing layer (302) is provided at the angle formed between the first waterproof adhesive layer (303) and the top plate (301).

7. The parapet wall anti-leakage structure according to claim 6, characterized in that: The height of the connection point between the guide surface (706) and the longitudinal wall (400) is greater than the height of the connection point between the guide surface (706) and the hydrophobic slope (705); A third waterproof roll (702) is laid above the second waterproof roll (502) located on the hydrophobic slope (705), one end of the third waterproof roll (702) is connected to the first waterproof roll (501) by a waterproof sealant, and the third waterproof roll (702) is laid downward along the second waterproof roll (502) and laid back along the turning point of the second waterproof roll (502), while forming an adaptive U-shaped structure at the part where the second waterproof roll (502) enters the sealing material; A third waterproof adhesive layer (704) is provided at the angle between the guide surface (706) and the longitudinal wall (400), and the third waterproof adhesive layer (704) closes the U-shaped structure formed by the second waterproof adhesive layer (601) and the third waterproof adhesive layer (704), and the bottom of the third waterproof adhesive layer (704) is a curved surface, and the right side of the third waterproof adhesive layer (704) is a vertical surface.

8. The parapet wall anti-leakage structure according to claim 7, characterized in that: A plurality of steel cages (401) are embedded in the longitudinal wall (400), and the steel cages (401) are arranged in the parapet structure (100). The top of the longitudinal wall (400) has a decreasing slope from left to right.

9. The parapet wall anti-leakage structure according to claim 8, characterized in that: The waterproof connection structure (600) comprises a geosynthetic material (602) and a plurality of waterproof coating adhesives (603), wherein the plurality of waterproof coating adhesives (603) are coated on a single steel bar of the same steel cage (401) and connected to the first waterproof roll (501), wherein the plurality of waterproof coating adhesives (603) are arranged in the geosynthetic material (602), wherein the steel cage (401) is arranged in the geosynthetic material (602), wherein the geosynthetic material (602) is assembled below the parapet structure (100), wherein the lower part of the geosynthetic material (602) is connected to the first waterproof roll (501) via a second waterproof adhesive layer (601) arranged around the lower part, and wherein a section of the first waterproof roll (501) is also laid upward on the side of the geosynthetic material (602).

10. The construction method of the parapet anti-leakage structure according to claim 9, characterized in that: The following steps are involved: S1. Construction preparation Understand the design requirements, dimensions and material requirements of the parapet, and prepare the required construction materials and tools according to the design requirements. Secondly, determine the location of the parapet structure (100) according to the construction drawings, and lay out the lines for positioning; S2. Formwork erection According to the height and shape of the parapet structure (100), a suitable formwork material is selected, and the formwork is installed in place according to the design requirements. The formwork should be vertical and horizontal, and then concrete is poured in the formwork. Attention is paid to the pouring thickness and density of the concrete. A vibrator is used to vibrate and remove bubbles. After the concrete pouring is completed, it is cured in time to ensure the strength and durability of the concrete. After the concrete reaches a certain strength, the formwork is removed; S3. Waterproof construction Before pouring the parapet wall structure (100), a second waterproofing membrane (502) is laid on the hydrophobic surface (201), the longitudinal wall (400) and the hydrophobic slope (705), and the second waterproofing membrane (502) bypasses the connection point between the hydrophobic slope (705) and the diversion surface (706), is laid on the diversion surface (706), and forms a U-shaped structure in the sealing groove (703); After the parapet structure (100) is formed, a third waterproof roll (702) is laid on the right side of the second waterproof roll (502), the third waterproof roll (702) extends to the diversion surface (706) and forms a U-shaped structure at the end of the second waterproof roll (502), and a third waterproof adhesive layer (704) is arranged at the U-shaped structure of the second waterproof roll (502) and the third waterproof roll (702), and at the angle between the diversion surface (706) and the longitudinal wall (400), and the right side of the third waterproof adhesive layer (704) is vertically processed, and the bottom is arranged in an arc shape, and then the second waterproof adhesive layer (601) is arranged at the bottom of the geosynthetics (602) for waterproofing; Then, the first waterproof roll (501) is laid on the second waterproof roll (502), and the size is designed as required, so that the first waterproof roll (501) is laid upward along the bottom of the geosynthetics (602), so that the first waterproof roll (501) extends from the parapet structure (100) to the laying groove (101), and finally, the first waterproof adhesive layer (303) is laid downward on the side above the parapet structure (100), so that the first waterproof adhesive layer (303) covers the laying groove (101) and covers one side of the first waterproof roll (501), and a waterproof sealing layer (302) is laid between the angle between the first waterproof adhesive layer (303) and the top plate (301) to further perform waterproofing.

Citation Information

Patent Citations

  • Parapet wall seepage-proof structure and construction method thereof

    CN109252624A

  • Anti-cracking parapet wall waterproof structure

    CN116607710A

  • Parapet anti -leakage structure

    CN207211545U

  • Overhanging sliding type cover plate structure of building roof deformation joint

    CN209742102U

  • Parapet wall water outlet building structure

    CN213897846U