Intelligent project management method based on digital twinning

Through digital twin technology analysis and optimization of historical data, combined with big data intelligent analysis and BIM technology, the traditional construction site layout method is solved, and the problems of human factors are greatly affected by human factors, information islands and insufficient visualization are achieved, and a scientific and reasonable construction site layout and a green and environmentally friendly construction environment are achieved.

CN119887083APending Publication Date: 2025-04-25CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411876848.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-19
Publication Date
2025-04-25

AI Technical Summary

Technical Problem

Traditional construction site layout methods are greatly affected by human factors, there are information islands, it is difficult to respond quickly to emergencies, and insufficient visualization, resulting in increased energy waste, time costs and costs.

Method used

Adopt the intelligent project management method based on digital twins, and by importing historical data into the digital twin platform, analyzing and optimizing the data of the built projects, we provide optimization solutions for new projects, and create new projects in real scenarios for virtual planning and layout, combining big data intelligent analysis and BIM technology to carry out scientific and reasonable construction site layout.

Benefits of technology

It has achieved rapid acquisition of scientific and reasonable construction site layout plans, reduced the influence of human factors, overcome the problems of information silos and insufficient visualization, improved the ability to respond to emergencies, reduced energy waste and cost expenditure, and created a green and environmentally friendly construction site environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119887083A_ABST
    Figure CN119887083A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of construction site arrangement, aims to solve the problems that a traditional construction site arrangement method is greatly influenced by human factors, information islands exist, the response capability to emergencies is weak, and visualization is insufficient, and provides an intelligent project management method based on digital twinning. Comprising the following steps: S1, importing historical data of all built projects into a digital twin platform, and extracting historical data of built projects around a new project according to the position of the new project; analyzing the extracted historical data of the built project, diagnosing problems and improvement space existing in the built project, and optimizing the built project to obtain an optimization scheme of the built project around the new project; s2, creating a new project in a real scene through a digital twin platform; s3, arranging an actual construction site according to the virtual new project created in the step S2 and in combination with the optimization scheme obtained in the step S1; the method is slightly influenced by human factors, is scientific and reasonable, and overcomes the problems.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of construction site layout, and in particular to a project intelligent management method based on digital twins. Background Art

[0002] With the continuous development of the times, more and more requirements are placed on the construction environment of the construction site. Not only higher requirements are put forward for the management of noise, light pollution, dust pollution, etc. at the construction site, but also requirements are put forward for the construction unit in terms of personnel, machines, materials, methods, and environment. At the same time, the construction unit also needs to minimize energy waste and cost expenditure during the construction process.

[0003] The traditional construction site layout method is as follows:

[0004] 1. Choice of temporary office and living area: mainly divided into arrangement within the red line and off-site rental. The arrangement within the red line needs to be combined with the surplus of on-site space. If the surplus is large, the implementation is more feasible, otherwise it is more difficult. Compared with the implementation within the red line, off-site rental requires additional application and increases costs, but the advantage is that it has less impact on on-site construction.

[0005] 2. Site layout of the construction site operation area: According to the building height and the key parts of material lifting, the optimal vertical transportation equipment is manually analyzed, and the material yard stacking position is considered in combination with the location of the vertical transportation equipment, and finally a plane site layout diagram is formed to guide the on-site implementation; inadequate consideration (such as the location of the tower crane and the selection of the tower crane model) will directly affect the construction period and equipment rental time, and will also lead to construction inconvenience and increase time cost and expenses;

[0006] The traditional construction site layout method has the following problems:

[0007] 1. Influence of human factors: Traditional construction site layout methods often rely on human experience, without more scientific judgment, and will not be evaluated in combination with local hydrological and meteorological factors, which may lead to energy waste (such as: the improper location of temporary office and living areas increases the use of air conditioners, thereby increasing electricity consumption). Since each project location and working conditions are different, the traditional construction site layout method cannot quickly obtain a scientific and reasonable site layout plan suitable for different projects. In the subsequent implementation process, unreasonable layouts are found and then modified, which increases time costs and expenses, and causes more energy consumption and pollution to the internal and external environments of the construction site.

[0008] 2. Information islands: Traditional construction site layout methods often lack the collection and sharing of real-time data, resulting in information opacity, affecting decision-making efficiency, and the existence of information islands.

[0009] 3. Weak response capability to emergencies: Traditional construction site layout methods are difficult to quickly adjust to emergencies (such as changes in Party A's needs and climate change), and the response capability is insufficient;

[0010] 4. Insufficient visualization: The traditional construction site layout method lacks three-dimensional visualization tools, resulting in an incomplete understanding of the overall situation and insufficient consideration of the construction site layout plan (such as the location of the tower crane and the selection of the tower crane model, which will directly affect the construction period and equipment rental time). It will also lead to construction inconvenience and increased time and expenses; it cannot create a comfortable and green construction site working environment, and cannot respond to the pollution generated on site in a targeted and timely manner. Summary of the invention

[0011] The present invention aims to provide an intelligent project management method based on digital twins to solve the problems that traditional construction site layout methods are greatly affected by human factors, have information islands, have weak response capabilities to emergencies, and lack visualization.

[0012] The present invention is achieved by adopting the following technical solutions:

[0013] The present invention provides a project intelligent management method based on digital twins, comprising the following steps:

[0014] S1: Import the historical data of all built projects into the digital twin platform, and extract the historical data of built projects around the new project according to the location of the new project; analyze the extracted historical data of built projects, diagnose the problems and improvement space in the built projects, optimize the built projects, and obtain the optimization plan for the built projects around the new project;

[0015] S2: Create new projects in real scenarios through the digital twin platform;

[0016] S3: Arrange the actual construction site according to the virtual new project created in step S2 and in combination with the optimization solution obtained in step S1.

[0017] As the preferred technical solution:

[0018] The method further includes S4: monitoring and providing feedback on the process of step S3, providing a basis for adjusting the layout of the new project, and providing historical data for subsequent new projects.

[0019] As the preferred technical solution:

[0020] In step S1, the sources of historical data of all built projects include:

[0021] Directly connect the original similar platform data to this digital twin platform; or deploy a sensor network on the existing projects and collect relevant data of the existing projects through the sensor network.

[0022] As the preferred technical solution:

[0023] In step S1, problems and improvement areas in the built project are diagnosed, including material loss, time loss, and human resource loss.

[0024] As the preferred technical solution:

[0025] In step S1, a spatial coordinate system is established in the digital twin platform, the distances between the components of the existing projects around the new project are calculated, the areas of various areas of the site are calculated, the volume of earthwork or other materials is estimated, the safety distance is calculated, a resource scheduling model is established, the working time is calculated, and collision detection is performed, so as to facilitate the analysis of the extracted historical data of the existing projects, facilitate the diagnosis of problems and improvement space in the existing projects, and obtain optimization plans for the existing projects around the new project.

[0026] As the preferred technical solution:

[0027] Step S2 obtains data of the real scene, including establishing a data acquisition layer, a data transmission layer, a data storage and processing layer, and a digital twin modeling layer, and establishing connections between them in sequence.

[0028] As the preferred technical solution:

[0029] Establishing the data collection layer includes deploying sensor networks and conducting drone monitoring;

[0030] Building a data transmission layer includes establishing a communication network and performing edge computing;

[0031] Establishing the data storage and processing layer includes establishing cloud storage and performing data integration;

[0032] Establishing the digital twin modeling layer includes three-dimensional modeling and physical modeling and simulation.

[0033] As the preferred technical solution:

[0034] Step S3 includes:

[0035] S3-01: Arrange office and living areas;

[0036] Step S3-01 specifically includes:

[0037] Analyze and determine the open space or non-main buildings within the red line site through big data intelligent analysis software, and then obtain various temporary construction plans for office and living areas through BIM technology in accordance with the enterprise's standardized temporary construction standards;

[0038] Combined with local hydrological and meteorological information, various temporary construction plans are analyzed for lighting, the natural lighting conditions of the room are evaluated, and the temperature changes and heat distribution in the room are predicted;

[0039] Optimize the temporary construction plan based on the temperature changes and heat distribution in the room;

[0040] Determine several optimized temporary construction plans, and simultaneously generate the plan drawings, 3D renderings, estimated construction costs, and operation and maintenance costs of the plans;

[0041] Select a temporary construction plan and export the construction drawings and material usage table;

[0042] Carry out construction according to the construction drawings.

[0043] As the preferred technical solution:

[0044] Step S3 also includes:

[0045] S3-02: Arrange the construction site;

[0046] Step S3-02 specifically includes:

[0047] First, create a project BIM model, including the project implementation model, the terrain around the site, and the building model. Then, according to the building conditions, automatically generate a variety of tower crane layout models, analyze the lifting load requirements of the tower crane model, and determine the preliminary vertical mechanical transportation plan based on the analysis data. Then, according to the site conditions, formulate a temporary construction access plan through big data intelligent analysis software, and then determine the temporary storage yard plan;

[0048] Next, the equipment rental costs for each plan are derived; the material installation costs and the maximum amount of material yard stacking for each plan are derived; and the power supply requirements for the construction site equipment for each plan are derived;

[0049] Select a plan for construction.

[0050] As the preferred technical solution:

[0051] Step S3 also includes:

[0052] S3-03: Arrange the garden-style construction site;

[0053] Step S3-03 specifically includes:

[0054] Plan and design the site appearance in the middle and late stages of the construction site, and analyze the construction site through big data intelligent analysis software, including lighting analysis and analysis of key areas of on-site noise pollution;

[0055] Designing an intelligent site system at the construction site, including burying different sensors in key areas of the construction site and processing the information collected by the sensors in a targeted manner;

[0056] Combined with the project landscape design plan, vegetation layout is interspersed in advance, combining permanent and temporary, and creating the construction site environment in advance.

[0057] As the preferred technical solution:

[0058] Step S4 includes:

[0059] Monitoring includes data collection, data transmission, real-time analysis, and visual display;

[0060] Providing feedback includes providing real-time feedback, generating reports regularly, making adjustments and optimizations, and learning and improving.

[0061] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0062] 1. The present invention extracts historical data of existing projects around the new project, analyzes the problems and improvement space of the existing projects, optimizes the existing projects, obtains optimization plans for the existing projects around the new project, and provides a reference for the new project.

[0063] 2. The present invention creates new projects in real scenarios through a digital twin platform, and creates new projects in a virtual way in advance, which can better carry out project planning, schedule scheduling, and resource management, and reduce risks and costs.

[0064] 3. The present invention arranges the actual construction site according to the created virtual new project and combines the optimization plan to provide a set of reasonable layout ideas for temporary offices and living areas. The optimization plan of the built project is used as a reference to obtain and optimize various temporary construction plans for offices and living areas. The design is scientific and reasonable, which can reduce energy consumption. Moreover, the material usage and accurate construction cost can be provided for each temporary construction plan, which is conducive to the construction unit to accurately control the construction cost; and the construction site is reasonably arranged to provide the construction unit with scientific and reasonable tower crane layout positions and machine models, provide time for installing and disassembling tower cranes, and control tower crane rental costs, which is conducive to controlling construction progress and costs and shortening construction period; arranging a garden-style construction site, controlling noise and dust at the construction site, and designing landscape vegetation at the construction site to break the "dirty", "messy" and "poor" phenomena of traditional construction sites and form a green environmental protection system.

[0065] 4. The present invention implements a monitoring mechanism and a feedback mechanism to provide a basis for adjusting the layout of new projects and to provide historical data for subsequent new projects.

[0066] 5. The method of the present invention can quickly obtain a scientific and reasonable on-site layout plan suitable for different projects. There will be no unreasonable layout in the subsequent implementation, and no additional modification is required, which avoids increasing time costs and expenses, and avoids causing more energy consumption and pollution to the internal and external environments of the construction site.

[0067] 6. The method of the present invention is less affected by human factors. By collecting and analyzing historical data and creating new projects through the digital twin platform, a more scientific and reasonable layout method can be obtained, which overcomes the problem of information islands. For emergencies, it can be quickly adjusted directly on the digital twin platform, and then the actual construction can be guided accordingly. It has strong responsiveness and overcomes the problem of insufficient visualization by virtually creating new projects in real scenes. BRIEF DESCRIPTION OF THE DRAWINGS

[0068] Figure 1 This is a flow chart of the project intelligent management method based on digital twins described in the present invention.

[0069] Figure 2 This is a flow chart of S1 according to the present invention.

[0070] Figure 3 This is the flow chart of S3-01 described in the present invention.

[0071] Figure 4 This is the flow chart of S3-02 described in the present invention. DETAILED DESCRIPTION

[0072] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0073] Example 1

[0074] like Figure 1-Figure 4 As shown, this embodiment proposes a project intelligent management method based on digital twins, including the following steps:

[0075] S1: Import the historical data of all built projects into the digital twin platform, and extract the historical data of built projects around the new project according to the location of the new project; analyze the extracted historical data of the built projects, diagnose the problems and improvement space in the built projects, optimize the built projects, and obtain the optimization plan for the built projects around the new project.

[0076] Among them, the digital twin platform can adopt Siemens MindSphere, PTC ThingWorx, Microsoft Azure Digital Twins, etc.

[0077] Historical data includes basic project information (name, number, type, etc.), cost data (material costs, labor costs, equipment costs, etc.), time data (planned construction period, actual construction period, etc.), resource usage data (human resource usage, material usage, equipment usage, etc.), and quality data (quality inspection report, rework rate, etc.).

[0078] There are two sources of historical data for all built projects:

[0079] 1. Directly connect the original similar platform data to this digital twin platform;

[0080] 2. Deploy sensor networks for existing projects and collect relevant data of existing projects through sensor networks. Sensor networks include sensors for energy monitoring, load management monitoring, air smart sensors, noise monitoring sensors, vibration sensors, temperature and humidity sensors, structural health monitoring sensors, etc.

[0081] Diagnose problems and room for improvement in existing projects, including material loss, time loss, human resource loss, etc.

[0082] A spatial coordinate system is established in the digital twin platform, the distance between the components of the existing projects around the new project is calculated, the area of ​​each area of ​​the site is calculated, the volume of earthwork or other materials is estimated, the safety distance is calculated, a resource scheduling model is established, the working time is calculated, and collision detection is performed, so as to facilitate the analysis of the extracted historical data of the existing projects, facilitate the diagnosis of problems and improvement space in the existing projects, and obtain optimization plans for the existing projects around the new project.

[0083] (1) Space coordinate system:

[0084] It is used to construct a three-dimensional coordinate system for the construction site, usually expressed as: P(x, y, z), where x, y, and z represent the position of the site in three dimensions respectively.

[0085] (2) Distance calculation:

[0086] It is often necessary to calculate the distance between various locations on a construction site. For example, the distance d between point A (x1, y1, z1) and point B (x2, y2, z2) can be calculated using the following formula:

[0087]

[0088] (3) Area calculation:

[0089] When arranging the venue, it is necessary to calculate the area of ​​different areas. For example, the area A of the rectangular area can be calculated using the following formula:

[0090] A=l×w

[0091] Where l is the length of the field and w is the width of the field.

[0092] For irregular areas, you can use the integration method or divide it into multiple regular shapes for calculation.

[0093] (4) Volume calculation:

[0094] When you need to estimate the volume of earthwork or other materials, you can use the following formula:

[0095] V=A×h

[0096] Where A is the area of ​​the cross section of the earth or other material, and h is the height of the earth or other material.

[0097] (5) Calculation of safety distance:

[0098] Construction sites often require safety distances. For example, set a safety distance between workers and machinery. s :

[0099] d s = k × D

[0100] Where k is the safety factor and D is the operating radius of the equipment or worker.

[0101] (6) Establish resource scheduling model:

[0102] In construction projects, the scheduling of resources usually follows an optimization algorithm, such as linear programming. Assuming that the total cost C needs to be minimized, it can be expressed as:

[0103]

[0104] Among them, c i is the cost of the ith resource, and x is the usage of the ith resource.

[0105] (7) Calculation of working hours:

[0106] The time forecast of the construction task can be calculated by the weighted average method:

[0107]

[0108] Among them, O is the optimistic time, M is the most likely time, and P is the pessimistic time.

[0109] (8) Perform collision detection:

[0110] Maintaining safety is critical on construction sites, and collision detection algorithms are often needed to avoid collisions between equipment and personnel.

[0111] The plane can be represented as: A i *x+B i *y+C i *z+D=0, that is, N i *P+D=0, where N i =(A i ,B i ,C i ) is the normal vector of the plane, and the normal vector of the plane is defined to point to the front of the plane. P = (x, y, z) is any point in the plane, and D is the distance from the plane to the origin. When determining the positional relationship between point M and the plane, the coordinates of point M can be substituted into the calculation of N i *M+D, if N i *M+D>0, indicating that point M is in front of the plane. If N i *M+D<0, it means that point M is behind the plane. When judging the positional relationship between point M and the convex polyhedron (judging whether point M is inside the convex polyhedron), if point M has N for all faces of the convex polyhedron i *M+D<0, then a collision occurs if point M has N for at least one face of the convex polyhedron i *M+D>0, then no collision occurs.

[0112] S2: Use big data technology to create new projects in real scenarios through the digital twin platform.

[0113] Acquiring data from real scenarios includes establishing a data collection layer, a data transmission layer, a data storage and processing layer, and a digital twin modeling layer, and establishing connections between them in sequence;

[0114] Building the data collection layer includes:

[0115] Arrange sensor network: Set up various sensors, such as temperature sensors, humidity sensors, displacement sensors, cameras, etc., to collect environmental data in real time.

[0116] Conduct drone monitoring: Use drones to conduct on-site monitoring, take aerial photos of large areas, and provide high-definition images and videos.

[0117] Establishing the data transmission layer includes:

[0118] Establish a communication network: Use high-speed communication technologies such as 5G and Wi-Fi to connect the sensor network to the communication network to ensure real-time transmission of data to the cloud or local server.

[0119] Perform edge computing: Set up edge devices on site to process some data, reduce the burden on the cloud, and improve response speed.

[0120] Building the data storage and processing layer includes:

[0121] Establish cloud storage: store all collected data in the cloud platform for remote access and analysis;

[0122] Perform data integration: Use data processing techniques to integrate data from different sources, clean and pre-process data.

[0123] Building the digital twin modeling layer includes:

[0124] Conduct 3D modeling: Use BIM (Building Information Modeling) technology to build a 3D model of the construction site, including building structure, equipment, and site layout.

[0125] Conduct physical modeling and simulation: Incorporate actual site data to continuously update digital models and conduct enhanced simulation of physical properties.

[0126] S3: Arrange the actual construction site according to the virtual new project created in step S2 and in combination with the optimization solution obtained in step S1.

[0127] Step S3 specifically includes:

[0128] S3-01: Arrange office and living areas;

[0129] Analyze and determine the open space or non-main buildings within the red line site through big data intelligent analysis software (such as real-time closed area 3D modeling based on the Beidou satellite positioning system, etc.), and then obtain various temporary construction plans for office and living areas through BIM technology in accordance with the enterprise's standardized temporary construction standards;

[0130] Combined with local hydrological and meteorological information, various temporary construction plans are analyzed for lighting, the natural lighting conditions of the room are evaluated, and the temperature changes and heat distribution in the room are predicted;

[0131] According to the temperature changes and heat distribution in the room, the temporary construction plan is optimized to try to keep the temperature in the room within the suitable temperature range for human body;

[0132] Determine 3-10 optimized temporary construction plans, and simultaneously generate the plan drawings, 3D renderings, estimated construction costs, and operation and maintenance costs of the plans;

[0133] After the decision of the project leadership, a temporary construction plan is selected, and construction drawings (including plan view, axonometric view, and clear insulation and thickening areas) and material usage tables are exported;

[0134] Carry out construction according to the construction drawings, monitor the construction process, provide timely feedback, and continuously optimize and adjust the construction process.

[0135] When the off-site land leasing method is adopted, firstly, the open space close to the construction site is analyzed according to the satellite data, and then according to the optimization scheme obtained in step S1, various temporary construction schemes for office and living areas are obtained and optimized.

[0136] Among them, the non-main buildings refer to foyers, auxiliary rooms, etc.

[0137] In the process of obtaining temporary construction plans through BIM technology, standardized family library models can be used to achieve the purpose of rapid design and subsequent standardized construction.

[0138] The temporary construction plan obtained through BIM technology can directly provide the material consumption of the temporary construction plan, and provide accurate construction costs based on the operating cost situation.

[0139] Optimization of temporary construction plans includes: optimizing building structure design, building orientation, window location and size, and building materials. For example, for directions with stronger light, insulation measures can be added in that direction of the building to reduce subsequent air-conditioning energy consumption.

[0140] S3-02: Arrange the construction site;

[0141] First, create a project BIM model, including the project implementation model, the surrounding terrain of the site, and the building model. Then, according to the building conditions, automatically generate a variety of tower crane layout models, and analyze the domestic lifting load requirements combined with the tower crane model. The project decision-maker determines the preliminary vertical mechanical transportation plan based on the analysis data. Then, according to the site conditions, formulate a temporary construction access road plan through big data intelligent analysis software, and then determine the temporary storage yard plan.

[0142] Next, the equipment rental costs for each plan are derived, and the time for installing and dismantling the tower crane is provided to facilitate the control of the tower crane rental costs and assist in optimizing the construction schedule; the material setting costs and the maximum amount of material yard stacking for each plan are derived to provide a basis for the on-site material supply plan, and even a material delivery plan can be provided; the power supply requirements for the construction site equipment of each plan are derived, and temporary power distribution lines on the construction site are reasonably formulated to avoid energy waste.

[0143] Select a construction plan, monitor the construction process, provide timely feedback, and continuously optimize and adjust the construction process.

[0144] The access road route can be selected as a circular route or a single-line route according to the working conditions of the construction site. Among them, the single-line route requires a vehicle turning area.

[0145] S3-03: Arrange the garden-style construction site;

[0146] Plan and design the site appearance in the middle and late stages of the construction site (after the basement roof is closed), and analyze the construction site through big data intelligent analysis software, including lighting analysis, analysis of key areas of noise pollution on site, etc.; design an intelligent site system at the construction site, including burying different sensors in key areas of the construction site, such as noise sensors, dust pollution sensors, and rainwater sensors, and perform targeted processing based on the information collected by the sensors, such as controlling the noise at the construction site based on the noise information collected by the noise sensor, spraying water on the construction site based on the dust information collected by the dust pollution sensor, and adjusting the construction progress based on the rainfall information collected by the rainwater sensor; design landscape vegetation at the construction site. The barrier formed by landscape vegetation can reduce the impact of noise pollution in the site on the outside world, and use vegetation to collect dust, so as to achieve a combination of permanent and temporary, create an environment in the construction site in advance, and improve the construction completion schedule.

[0147] S4: Implement monitoring and feedback mechanisms to provide a basis for adjusting the layout of new projects and provide historical data for subsequent new projects.

[0148] Implementation monitoring mechanisms include:

[0149] To collect data:

[0150] Use various sensors (such as temperature, humidity, vibration, displacement, etc.) to monitor site conditions in real time.

[0151] Deploy drones to patrol and photograph sites, acquiring high-resolution images and videos.

[0152] For data transfer:

[0153] The collected data is transmitted to the central database in real time via wireless networks (such as 5G, Wi-Fi), ensuring the reliability and timeliness of the data for further analysis.

[0154] Perform real-time analysis:

[0155] Use data analysis algorithms to process and analyze real-time monitoring data. Automatically identify abnormal situations (such as equipment failure, personnel safety risks, etc.) and trigger alarms.

[0156] Visual display:

[0157] Use the digital twin platform to visualize real-time data so that decision makers can intuitively understand the on-site conditions.

[0158] Create dynamic dashboards that display key performance indicators (KPIs).

[0159] Implementation feedback mechanisms include:

[0160] For real-time feedback:

[0161] According to the real-time monitoring data and analysis results, relevant personnel are notified in time to respond. Information is sent directly to staff through mobile APP or system notification.

[0162] To schedule a report:

[0163] Generate project progress reports regularly to analyze key data and trends. Reports can help project managers communicate with stakeholders.

[0164] Adjust and optimize:

[0165] According to the feedback data, the construction plan and resource allocation are adjusted in real time. When problems are found, measures are taken quickly to reduce the impact on the project progress.

[0166] Learn and improve:

[0167] By recording and analyzing feedback data, we can identify long-standing problems or bottlenecks, continuously optimize construction processes and monitoring systems, and improve overall construction efficiency.

[0168] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A project intelligent management method based on digital twins, characterized by: The following steps are involved: S1: Import the historical data of all built projects into the digital twin platform, and extract the historical data of built projects around the new project according to the location of the new project; analyze the extracted historical data of built projects, diagnose the problems and improvement space in the built projects, optimize the built projects, and obtain the optimization plan for the built projects around the new project; S2: Create new projects in real scenarios through the digital twin platform; S3: Arrange the actual construction site according to the virtual new project created in step S2 and in combination with the optimization solution obtained in step S1.

2. The project intelligent management method based on digital twin according to claim 1 is characterized by: The method also includes S4: monitoring and providing feedback on the process of step S3, providing a basis for adjusting the layout of the new project, and providing historical data for subsequent new projects.

3. The project intelligent management method based on digital twin according to claim 1 is characterized by: In step S1, the sources of historical data of all built projects include: Directly connect the original similar platform data to this digital twin platform; or deploy a sensor network on the existing projects and collect relevant data of the existing projects through the sensor network.

4. The project intelligent management method based on digital twin according to claim 1 is characterized by: In step S1, problems and improvement areas in the built project are diagnosed, including material loss, time loss, and human resource loss.

5. The project intelligent management method based on digital twin according to claim 1 is characterized by: In step S1, a spatial coordinate system is established in the digital twin platform, the distances between the components of the existing projects around the new project are calculated, the areas of various areas of the site are calculated, the volume of earthwork or other materials is estimated, the safety distance is calculated, a resource scheduling model is established, the working time is calculated, and collision detection is performed, so as to facilitate the analysis of the extracted historical data of the existing projects, facilitate the diagnosis of problems and improvement space in the existing projects, and obtain optimization plans for the existing projects around the new project.

6. The project intelligent management method based on digital twin according to claim 1 is characterized by: Step S2 obtains data of the real scene, including establishing a data acquisition layer, a data transmission layer, a data storage and processing layer, and a digital twin modeling layer, and establishing connections between them in sequence.

7. The project intelligent management method based on digital twin according to claim 6 is characterized by: Establishing the data collection layer includes deploying sensor networks and conducting drone monitoring; Building a data transmission layer includes establishing a communication network and performing edge computing; Establishing the data storage and processing layer includes establishing cloud storage and performing data integration; Establishing the digital twin modeling layer includes three-dimensional modeling and physical modeling and simulation.

8. The project intelligent management method based on digital twin according to claim 1 is characterized by: Step S3 includes: S3-01: Arrange office and living areas; Step S3-01 specifically includes: Analyze and determine the open space or non-main buildings within the red line site through big data intelligent analysis software, and then obtain various temporary construction plans for office and living areas through BIM technology in accordance with the enterprise's standardized temporary construction standards; Combined with local hydrological and meteorological information, various temporary construction plans are analyzed for lighting, the natural lighting conditions of the room are evaluated, and the temperature changes and heat distribution in the room are predicted; Optimize the temporary construction plan based on the temperature changes and heat distribution in the room; Determine several optimized temporary construction plans, and simultaneously generate the plan drawings, 3D renderings, estimated construction costs, and operation and maintenance costs of the plans; Select a temporary construction plan and export the construction drawings and material usage table; Carry out construction according to the construction drawings.

9. The project intelligent management method based on digital twin according to claim 8 is characterized by: Step S3 also includes: S3-02: Arrange the construction site; Step S3-02 specifically includes: First, create a project BIM model, including the project implementation model, the terrain around the site, and the building model. Then, according to the building conditions, automatically generate a variety of tower crane layout models, analyze the lifting load requirements of the tower crane model, and determine the preliminary vertical mechanical transportation plan based on the analysis data. Then, according to the site conditions, formulate a temporary construction access plan through big data intelligent analysis software, and then determine the temporary storage yard plan; Next, the equipment rental costs for each plan are derived; the material installation costs and the maximum amount of material yard stacking for each plan are derived; and the power supply requirements for the construction site equipment for each plan are derived; Select a plan for construction.

10. The project intelligent management method based on digital twin according to claim 9 is characterized in that: Step S3 also includes: S3-03: Arrange the garden-style construction site; Step S3-03 specifically includes: Plan and design the site appearance in the middle and late stages of the construction site, and analyze the construction site through big data intelligent analysis software, including lighting analysis and analysis of key areas of on-site noise pollution; Designing an intelligent site system at the construction site, including burying different sensors in key areas of the construction site and processing the information collected by the sensors in a targeted manner; Combined with the project landscape design plan, vegetation layout is interspersed in advance, combining permanent and temporary, and creating the construction site environment in advance.