Project management method and device of electrical equipment, equipment, medium and product
By providing project management configuration pop-up windows in electrical equipment project management, users can configure project attributes, plan information and equipment plan layout information, solving the problem of lack of reasonable project management in the existing technology, and improving project management efficiency and convenience of the production process.
Patent Information
- Application Number
- CN202411948091.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-27
- Publication Date
- 2025-04-25
AI Technical Summary
The existing technology lacks reasonable and effective project management methods, which leads to time-consuming and labor-intensive production of electrical equipment, and there is no archive or chaotic archive, making it difficult to trace the source later.
It provides a project management method for electrical equipment. By responding to the trigger of project management controls in the management interface, it displays the project management configuration pop-up window, including the project attribute information interface, the project plan information interface and the project equipment plan layout information interface. The user can generate and configure project attributes, plan information and equipment plan layout information.
The efficiency of project management has been improved, the efficiency of information search and utilization has been improved, the data distribution of production materials and project data are connected, and the accuracy, speed and convenience of design and distribution of materials have been reduced, cumbersome steps in production have been improved, and cross-departmental coordination and efficiency have been improved.
Smart Images

Figure CN119887096A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electrical equipment manufacturing, and in particular to a project management method, device, equipment, medium and product for electrical equipment. Background Art
[0002] As high and low voltage electrical equipment become increasingly mature, competition among major manufacturers becomes increasingly fierce, placing higher and higher demands on cost savings and production efficiency.
[0003] However, there is no reasonable and effective project management method at present, so many manufacturers still choose to rely on engineers for manual management, which is time-consuming and labor-intensive; and there may be no archives or chaotic archives, making it difficult to trace the source later. Summary of the invention
[0004] The present invention provides a project management method, device, equipment, medium and product for electrical equipment to solve the problem of lack of reasonable and effective project management methods in the production process of high and low voltage electrical complete sets of equipment.
[0005] According to one aspect of the present invention, there is provided a project management method for electrical equipment, comprising the following steps:
[0006] In the management interface, in response to the triggering of the project management control, a project management configuration pop-up window is displayed to the user; wherein the project management configuration pop-up window includes a project attribute information interface, a project plan information interface, and a project equipment plan arrangement information interface;
[0007] In the project attribute information interface, in response to the user's operation, attribute information of the current project is generated and displayed in the project attribute information interface, and the information in the project attribute information interface at least includes the project name;
[0008] In the project solution information interface, in response to the triggering of adding a solution control, the solution information associated with the current project is imported and displayed in sequence in the project solution information interface. The solution information associated with the current project includes at least electrical equipment 3D model data information, electrical component data information and copper busbar data information;
[0009] In the project equipment scheme arrangement information interface, the scheme information associated with the current project is imported as the preset scheme library. According to the correspondence between the electrical equipment number of the current project and the scheme information serial number, the scheme information of the electrical equipment of the current project is configured in response to the user's operation.
[0010] Optionally, the project management configuration pop-up window also includes a historical project record interface; the method also includes:
[0011] In the historical project record interface, in response to the user's filtering operation, the project name of the historical project is displayed to the user, and the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are displayed based on the project name.
[0012] Optionally, after scheduling and displaying the project attribute information, project plan information and project equipment plan arrangement information associated with the historical projects based on the project name, it also includes: in response to the user's operation, adjusting one or more of the project attribute information, project plan information or project equipment plan arrangement information associated with the historical projects, and displaying the adjusted historical projects to the user.
[0013] Optionally, after displaying the project management configuration pop-up window to the user, also include:
[0014] In response to triggering the open control, displaying the list of history items to the user;
[0015] Based on the user's selection of the project name of the historical project in the historical project list, the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are displayed based on the project name scheduling and displayed in the project management configuration pop-up window.
[0016] Optionally, after configuring the scheme information for the electrical equipment of the current project, it also includes:
[0017] In response to triggering of the save control, the current project is saved.
[0018] Optionally, after displaying the project management configuration pop-up window to the user, also include:
[0019] In the project solution information interface, in response to the triggering of the delete solution control, the solution information not associated with the current project is deleted.
[0020] Optionally, after displaying the project management configuration pop-up window to the user, also include:
[0021] In response to triggering of the delete control, the content in the project management configuration pop-up window is deleted.
[0022] According to another aspect of the present invention, there is provided a project management device for electrical equipment, comprising:
[0023] A first response module is used to execute the step of displaying a project management configuration pop-up window to the user in response to the triggering of the project management control in the management interface; wherein the project management configuration pop-up window includes a project attribute information interface, a project plan information interface and a project equipment plan arrangement information interface;
[0024] A second response module is used to execute the step of generating the property information of the current project in response to the user's operation on the project property information interface and displaying it on the project property information interface, wherein the information in the project property information interface at least includes the project name;
[0025] A third response module is used to execute the steps of importing solution information associated with the current project in response to the triggering of adding a solution control on the project solution information interface, and displaying the solution information associated with the current project in sequence on the project solution information interface, wherein the solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information, and copper busbar data information;
[0026] The fourth response module is used to execute the steps of importing the scheme information associated with the current project as a preset scheme library in the project equipment scheme arrangement information interface, and configuring the scheme information for the electrical equipment of the current project according to the correspondence between the electrical equipment number of the current project and the scheme information serial number in response to the user's operation.
[0027] According to another aspect of the present invention, an electronic device is provided, the electronic device comprising:
[0028] at least one processor; and
[0029] a memory communicatively connected to at least one processor; wherein,
[0030] The memory stores a computer program that can be executed by at least one processor, and the computer program is executed by at least one processor so that the at least one processor can execute the project management method for electrical equipment described in any embodiment of the present invention.
[0031] According to another aspect of the present invention, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the project management method for electrical equipment described in any embodiment of the present invention when executed.
[0032] According to another aspect of the present invention, a computer program product is provided. The computer program product includes a computer program. When the computer program is executed by a processor, the project management method for electrical equipment described in any embodiment of the present invention is implemented.
[0033] In the embodiment of the present invention, a project management configuration pop-up window is displayed to the user in response to the triggering of the project management control in the management interface, thereby providing a first-level management page, thereby facilitating the user to select the second-level interface such as project attributes, solution information, and equipment solution arrangement information for configuration. In the project attribute information interface, in response to the user's operation, the attribute information of the current project is generated and displayed in the project attribute information interface. The information in the project attribute information interface includes at least the project name. In the project attribute information interface, the user can generate and input the attribute information of the solution according to the actual situation of the project.
[0034] In the project solution information interface, in response to the trigger of adding a solution control, the solution information associated with the current project is imported and displayed in sequence in the project solution information interface. The solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information and copper busbar data information, which optimizes solution information management and improves information search and utilization efficiency. In the project equipment solution arrangement information interface, the solution information associated with the current project is imported as a preset solution library. According to the correspondence between the electrical equipment number of the current project and the solution information sequence number, in response to the user's operation, the solution information is configured for the electrical equipment of the current project, and the configuration speed is further accelerated by setting a preset database. The embodiment of the present invention integrates multiple types of information through the management interface to facilitate staff to find historical projects, or import new projects, and configure electrical equipment solutions in the relevant information of the associated solutions in the project, thereby improving project management efficiency and quality.
[0035] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0037] Figure 1 A flowchart of a project management method for electrical equipment is provided for the first embodiment of the present invention;
[0038] Figure 2 A flowchart of a project management method for electrical equipment provided in Embodiment 2 of the present invention;
[0039] Figure 3 A flowchart of the logic of a project management method for electrical equipment provided by an embodiment of the present invention;
[0040] Figure 4 A schematic diagram of the structure of a project management device for electrical equipment provided in Embodiment 3 of the present invention;
[0041] Figure 5 A schematic diagram of the structure of an electronic device provided in Embodiment 4 of the present invention;
[0042] Figure 6 A schematic diagram of a management interface in a project management method for electrical equipment provided by an embodiment of the present invention;
[0043] Figure 7 A schematic diagram of a project information interface in a project management method for electrical equipment provided by an embodiment of the present invention;
[0044] Figure 8 A schematic diagram of an interface for selecting a solution in a project management method for electrical equipment provided by an embodiment of the present invention;
[0045] Fig. 9 for Figure 7 Schematic diagram of the project name secondary menu in the project information interface;
[0046] Fig.10 for Figure 7 Schematic diagram of the secondary menu of the solution name in the project information interface. DETAILED DESCRIPTION
[0047] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0048] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0049] Embodiment 1
[0050] Figure 1 A flowchart of a project management method for electrical equipment is provided for the first embodiment of the present invention. Figure 3 A flowchart of the logic of a project management method for electrical equipment provided by an embodiment of the present invention;
[0051] Figure 6 A schematic diagram of a management interface in a project management method for electrical equipment provided by an embodiment of the present invention, Figure 7 A schematic diagram of a project information interface in a project management method for electrical equipment provided by an embodiment of the present invention, Figure 8 A schematic diagram of an interface for selecting a solution in a project management method for electrical equipment provided by an embodiment of the present invention, Fig. 9 for Figure 7 Schematic diagram of the project name secondary menu in the project information interface. Fig.10 for Figure 7 The method can be executed by a project management device for electrical equipment, and the project management device for electrical equipment can be implemented in the form of hardware and / or software. Figure 1 As shown, the method includes:
[0052] S110. In the management interface, in response to triggering of the project management control, a project management configuration pop-up window is displayed to the user.
[0053] Among them, the project management configuration pop-up window includes the project attribute information interface, the project scheme information interface and the project equipment scheme arrangement information interface. The management interface can be understood as the interactive interface for users to perform project management operations, on which users can perform various operations related to project management, such as viewing project information, performing project configuration, etc.; the project management control can be understood as the operating element used to trigger specific project management functions on the management interface, such as buttons, menu options, etc., and the corresponding operation (such as the project management configuration pop-up window) is started by clicking or selecting the control; the project management configuration pop-up window can be understood as a pop-up window set in the management interface, which is used to display and collect configuration information related to project management to users. Through this pop-up window, users can configure and manage various attributes, schemes and equipment arrangements of the project.
[0054] Specifically, Figure 6 As shown in the figure, when the user selects the project management control (for example, clicks the "Project Management" button) in the management interface (such as electrical design software AutoCAD Electrical, EPLAN, etc.), the system detects the trigger action and, according to the pre-set program logic, calls out and displays the project management configuration pop-up window to the user. Figure 7As shown in the pop-up window, the project attribute information interface is used to allow users to view and import the basic attributes of the project (such as project name, contract number, rated voltage, etc.); the project solution information interface is used to manage the solution equipment related information in the project (such as solution equipment 3D model data, electrical component data, etc.); the project equipment solution arrangement information interface is used to arrange and manage the solution equipment in the project to make it consistent with the actual construction equipment installation arrangement. Fig.10 As shown, after the user completes each configuration in the pop-up window or drop-down menu, he can click the "Save" button to save the data to the project database to realize project data management and call.
[0055] S120. In the project attribute information interface, in response to the user's operation, attribute information of the current project is generated and displayed on the project attribute information interface. The information in the project attribute information interface includes at least the project name.
[0056] Among them, the project attribute information interface can be understood as the area in the project management configuration pop-up window used to display and edit various attribute information of the project. Users can view, enter or modify project-related attribute content in this area; the project name can be understood as the name used to identify and distinguish different projects.
[0057] Specifically, Figure 7 , Fig. 9 and Fig.10 As shown, in the project attribute information interface, the system will generate project attribute information in historical projects or new projects according to the user's operation (such as keyboard input, drop-down menu selection, button click, etc.). Project attribute information may include project name, contract number, rated voltage, etc. In the process of user input or selection of attribute information, when the user completes the setting of all necessary attribute information (when the user selects a certain project attribute information from the drop-down menu, or clicks on other items after completing the input of a certain project), the system will save the relevant information to the record location related to the current project in the project database, and display it on the project attribute information interface for the user to view and check.
[0058] Exemplarily, for the project name, the user directly enters a name that can describe the project characteristics in the designated input box, or selects from the drop-down menu of historical projects provided by the system, and saves it separately after modification based on the historical scheme. S130. In the project scheme information interface, in response to the triggering of the add scheme control, the scheme information associated with the current project is imported and displayed in sequence in the project scheme information interface. The scheme information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information, and copper busbar data information.
[0059] Among them, the project plan information interface can be understood as the area in the project management configuration pop-up window for displaying and editing project plans, and users can view, input or modify project plan information related to the project in this area; the add plan control can be understood as the operating element in the project plan information interface used to trigger the add plan operation (such as buttons, menu drop-down options, etc.); display in sequence can be understood as arranging and displaying the plan information in a certain order (such as chronological order, alphabetical order, etc.) on the project plan information interface; the three-dimensional model data information of electrical equipment can be understood as the data of the three-dimensional shape, structure, size and other characteristics of the electrical equipment; the electrical component data information can be understood as various attribute data of electrical components, such as model, specification, parameter, performance index, manufacturer, etc.; the copper busbar data information can be understood as various characteristic data related to the copper busbar, including the copper busbar's overlap method, embossing condition, silver plating status, opening information, busbar gauge (such as width, thickness and other size specifications), phase sequence, segment length, unfolded length, weight, etc.
[0060] Specifically, in the project solution information interface, when the system detects that the user triggers the add solution control (e.g. Figure 7 The "Add Scheme" button is shown in the figure), and the user is guided to import scheme information associated with the current project (such as electrical equipment 3D model data information, electrical component data information, and copper busbar data information, etc.) through user input or a pop-up file selection dialog box, and convert the above information into a data format that the system can recognize and manage. On this basis, the display sorting rules of scheme information can also be selected in the project scheme information interface (such as in the order of import time), and users can sort the schemes according to actual needs.
[0061] It should be noted that in step S130, the user can also import other files, such as processing drawings, etc., according to the project design requirements and actual conditions. For example, Figure 8 The drawing selection interface shown is used to import drawings by dragging, clicking, and selecting.
[0062] Optionally, after displaying the project management configuration pop-up window to the user, also include:
[0063] In the project solution information interface, in response to the triggering of the delete solution control, the solution information not associated with the current project is deleted.
[0064] Among them, the delete plan control can be understood as an operating element (such as a button or menu option, etc.) used to trigger the deletion function in the project plan information interface. Its function is to start the action of deleting plan information that is not associated with the current project when the user operates the control; the plan information can be understood as relevant information of the plan equipment, including the three-dimensional model data of the plan equipment, electrical component data, etc.
[0065] Specifically, when the user enters the project solution information interface of the project management configuration pop-up window, by viewing historical projects, or in the current project, it is found that there is solution information that is not related to the current project (for example, by viewing the solution equipment 3D model data, electrical component data, etc., it is determined that the solution is no longer applicable to the current project or has been abandoned). Figure 7 , Fig. 9 , Fig.10 As shown, the user can click or select the delete solution button. After the system detects the trigger action, it identifies the solution information selected by the user that is not associated with the current project according to the preset program logic, and then deletes the records of these non-associated solution information from the relevant database or data structure storing the solution information, including the related information (such as equipment 3D model data, electrical component data, etc.), to ensure that the project solution information interface only displays the valid solution information that is closely related to the current project.
[0066] Therefore, in the project plan information interface, plans can be added or deleted, which is convenient for users to operate and manage.
[0067] Among them, the project can be understood as a contract for user needs, and the plan is the specific parameters such as wiring, materials, specifications, etc. of each electrical equipment in the project, that is, in the contract.
[0068] S140. In the project equipment scheme arrangement information interface, the scheme information associated with the current project is imported as a preset scheme library, and according to the correspondence between the electrical equipment number of the current project and the scheme information serial number, scheme information is configured for the electrical equipment of the current project in response to the user's operation.
[0069] Among them, the preset solution library can be understood as a collection or database composed of preset project solution information; the electrical equipment number can be understood as a code used to uniquely identify each electrical equipment; and the solution information serial number can be understood as a serial number used to correspond to the identification solution in this embodiment.
[0070] Specifically, there is a corresponding relationship between the electrical equipment number and the scheme information in the preset scheme library. In the project equipment scheme arrangement information interface, there is a corresponding electrical equipment number, and the preset scheme library is formed by step S130. Figure 3 As shown in the figure, by creating a new project in the project scheme information interface, click the "Add / Import Scheme" button, select or enter the scheme information corresponding to the list of electrical equipment involved in the current project (for example, each device displays its number), and form a preset scheme library. Then, in the project equipment scheme arrangement information interface, search for schemes in the preset scheme library (such as Fig.10 As shown), the scheme information is matched with the device number, and then the corresponding device and scheme information are configured.
[0071] Optionally, after displaying the project management configuration pop-up window to the user, also include:
[0072] In response to triggering of the delete control, the content in the project management configuration pop-up window is deleted.
[0073] Specifically, when a user triggers a delete control in a project management configuration pop-up window (e.g., clicks a "delete" button), the system detects the triggering action and deletes the selected content in the pop-up window according to the pre-set program logic. Figure 7 and Fig.10 As shown in the figure, for example, for project attribute information, the project name, contract number, rated voltage and other attribute values will be deleted; for project plan information, the plan equipment 3D model data, electrical component data and other related information will be deleted; for project equipment plan arrangement information, the set equipment arrangement plan data will be cleared. After all content is deleted, the pop-up window will be displayed as empty, and users can re-perform project management configuration operations according to actual needs, or close the pop-up window.
[0074] Optionally, after configuring the scheme information for the electrical equipment of the current project, it also includes:
[0075] In response to triggering of the save control, the current project is saved.
[0076] The save control can be understood as an operation element (such as a button, menu drop-down option, etc.) in the project plan information interface that is used to trigger the save plan operation.
[0077] Specifically, after completing the configuration of the electrical equipment scheme information of the current project in the project scheme information interface, the save control is triggered according to the preset save logic, or when the user presses the "Save" button, the system saves the data to the project database to save the project data.
[0078] In the embodiment of the present invention, a project management configuration pop-up window is displayed to the user in response to the triggering of the project management control in the management interface, and a first-level management page is provided, so that the user can select the second-level interface such as project attributes, scheme information and equipment scheme arrangement information for configuration. In the project attribute information interface, in response to the user's operation, the attribute information of the current project is generated and displayed in the project attribute information interface. The information in the project attribute information interface at least includes the project name. In the project attribute information interface, the user can generate and input the attribute information of the scheme according to the actual situation of the project. In the project scheme information interface, in response to the triggering of adding a scheme control, the scheme information associated with the current project is imported and displayed in the project scheme information interface in sequence. The scheme information associated with the current project at least includes electrical equipment three-dimensional model data information, electrical component data information and copper busbar data information, optimizes scheme information management, and improves information search and utilization efficiency. In the project equipment scheme arrangement information interface, the scheme information associated with the current project is imported as a preset scheme library, and according to the corresponding relationship between the electrical equipment number of the current project and the scheme information sequence number, the scheme information configuration is performed on the electrical equipment of the current project in response to the user's operation, and the configuration speed is further accelerated by setting a preset database. The embodiment of the present invention integrates multiple types of information through a management interface to facilitate staff to find historical projects or import new projects, and configure electrical equipment solutions based on relevant information of the solutions associated with the projects, thereby improving project management efficiency and quality.
[0079] In other words, the above method can achieve the rapid call and arrangement of the same plan, as well as clear, intuitive and accurate project information, and convenient and fast project management; and this method connects the production materials distribution data, plan equipment data and project data, so as to achieve accurate, fast and convenient design and distribution of materials, and facilitate modification and management. In this way, it is more in line with the actual production situation, and production is carried out according to projects and plans, which improves cross-departmental coordination and efficiency; in the later stage, the production materials are automatically archived according to projects and plans, which can be quickly called and traced, thereby improving the controllability of the project.
[0080] Embodiment 2
[0081] Figure 2 This is a flowchart of a project management method for electrical equipment provided in the second embodiment of the present invention. Based on the above embodiment, this embodiment also includes a historical project record interface in the project management configuration pop-up window. The historical project record interface can quickly switch and display historically generated project information. In this interface, the historical project information can be corrected and edited. If the information in the new project is similar to the historical project information or the difference is small, it can be corrected and edited in this way, reducing the tedious steps of regenerating a new project.
[0082] Specifically, there are two ways to enter the historical project management interface, one is to enter through the historical project record interface, and the other is to enter through the "Open" button on the management interface.
[0083] Among them, Figure 2 As shown, the method includes:
[0084] S210, in the management interface, in response to the triggering of the project management control, displaying a project management configuration pop-up window to the user;
[0085] The project management configuration pop-up window includes a project attribute information interface, a project plan information interface, a project equipment plan arrangement information interface, and a historical project record interface. The historical project record interface can be understood as an area in the project management configuration pop-up window for displaying historical record information related to the current project or previously completed projects. Exemplarily, the historical project record interface can be a drop-down menu or a secondary interface.
[0086] After “S110, in the management interface, in response to the triggering of the project management control, a project management configuration pop-up window is displayed to the user.”, the following is also included:
[0087] In the historical project record interface, in response to the user's filtering operation, the project name of the historical project is displayed to the user, and the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are displayed based on the project name.
[0088] Or, optionally, after presenting the project management configuration pop-up window to the user, also include:
[0089] In response to triggering the open control, displaying the list of history items to the user;
[0090] Based on the user's selection of the project name of the historical project in the historical project list, the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are displayed based on the project name scheduling and displayed in the project management configuration pop-up window.
[0091] The historical project list can be understood as a collection of previously completed or ongoing project records stored in the system, presented in the form of a list. Exemplarily, the list includes key identification information of each historical project, such as the project name.
[0092] Specifically, Fig. 9As shown, when the user operates in the project management configuration pop-up window and triggers the open control (for example, clicking the "project name" button), the system retrieves all historical project information from the project database or the relevant location where the historical project records are stored according to the pre-set program, and displays the historical project list to the user in the form of a list. The user browses and selects the historical project in the historical project list (by clicking the project name and other operations). After receiving the user's selection, the system extracts the project attribute information, project plan information, and project equipment plan arrangement information associated with it from the database according to the name and corresponding number of the selected historical project. Then, the system fills the extracted information into the project attribute information interface, project plan information interface, and project equipment plan arrangement information interface in the project management configuration pop-up window for display. For example, the contract number, rated voltage and other attribute information of the historical project are displayed in the project attribute information interface; the three-dimensional model data of the plan equipment, the electrical component data, etc. are displayed in the project plan information interface; the arrangement information such as the number and position relationship of the equipment is presented in the project equipment plan arrangement information interface.
[0093] S220. In the historical project record interface, in response to the user's filtering operation, the project name of the historical project is displayed to the user, and the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are displayed based on the project name.
[0094] Among them, the filtering operation can be understood as the operation behavior performed by the user in the historical project record interface to narrow the display scope of historical projects according to specific conditions or keywords; for example, such as entering the project completion time range, searching for specific keywords, filtering by project type, etc.
[0095] Specifically, when the user performs a filtering operation in the historical project record interface (for example, entering the keyword "high voltage electrical" in the filtering input box to filter high voltage electrical related projects, or selecting a specific time interval "2022-2023" to view projects within this time period, etc.), the system detects the user's input of filtering conditions. The system searches and matches in the database or data structure storing historical project records according to the filtering conditions set by the user. For the filtered historical projects, the system obtains their project names and related filtering conditions, and displays these project names in a list in a specific area of the historical project record interface for user viewing and selection. When the user clicks on or selects the project name of one of the historical projects, the system uses the project name as an index to search and extract the associated project attribute information, project plan information, and project equipment plan arrangement information from the database. Finally, the system displays the various types of information extracted in the corresponding information display areas (such as the project attribute information interface, the project plan information interface, and the project equipment plan arrangement information interface).
[0096] After the management interface is presented, one or more of the project attribute information, the project equipment scheme information, and the project equipment scheme arrangement information may be adjusted as described in the first embodiment.
[0097] S230. In the project attribute information interface, in response to the user's operation, attribute information of the current project is generated and displayed on the project attribute information interface. The information in the project attribute information interface includes at least the project name.
[0098] Optionally, after scheduling and displaying the project attribute information, project plan information and project equipment plan arrangement information associated with the historical projects based on the project name, it also includes: in response to the user's operation, adjusting one or more of the project attribute information, project plan information or project equipment plan arrangement information associated with the historical projects, and displaying the adjusted historical projects to the user.
[0099] Specifically, when the user operates the displayed historical project-related information in the project management configuration pop-up window (for example, modifying the project name to a more accurate expression in the project attribute information interface, adjusting the parameter values of electrical components in the project plan information interface, or dragging the equipment icon to change its position in the project equipment plan arrangement information interface, etc.), the system updates the corresponding historical project-related information according to the type and target information of the user's operation to maintain data consistency. After completing the information adjustment, the system regenerates and displays the adjusted historical project to the user based on the updated historical project data. This includes replacing the original display content with new information content in each information interface of the project management configuration pop-up window, and displaying the adjusted project attribute information, project plan information, and project equipment plan arrangement information, so that users can check whether the adjusted results meet expectations.
[0100] S240. In the project solution information interface, in response to the triggering of adding a solution control, the solution information associated with the current project is imported and displayed in sequence in the project solution information interface. The solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information, and copper busbar data information.
[0101] S250. In the project equipment scheme arrangement information interface, the scheme information associated with the current project is imported as a preset scheme library, and according to the correspondence between the electrical equipment number of the current project and the scheme information serial number, scheme information is configured for the electrical equipment of the current project in response to the user's operation.
[0102] The embodiment of the present invention provides historical project information on the basis of the first embodiment, and displays associated project attribute information, project plan information and project equipment plan arrangement information based on historical projects, so that users can fully and deeply understand the details of historical projects or ongoing projects, which helps to accumulate and improve the project management of electrical equipment.
[0103] Combining the first and second embodiments, illustratively, in a specific embodiment, the project management method for electrical equipment includes the following steps:
[0104] Step 1. Click Figure 6 The "Project Management" button in the management interface shown below brings up the following Figure 7 "Project Information" dialog box; project information is stored in the "Project Database", which includes: project properties, solution equipment in the project, solution arrangement in the project, and historical project records.
[0105] Step 2: For newly added projects, first write the project attribute data through the project attribute list, such as Figure 7 As shown, the project attribute data includes project name, contract number, rated voltage, company code, product features, etc.;
[0106] Step 3. Click the "Add Scheme" button in the scheme list to write all scheme equipment to the project (batch addition and import are supported); the scheme equipment includes: scheme equipment 3D model data information, electrical component data information (such as intelligent drawing and opening position of copper busbar), and copper busbar data information (such as overlap, embossing, silver plating, opening, row gauge, phase sequence, segment length, unfolded length, weight and corresponding engineering drawings);
[0107] Step 4: After importing, the system reads the scheme name and storage path and writes them into the list, thereby completing the call and management of the above data information;
[0108] Step 5. Then click Figure 7 The secondary drop-down menu "Scheme Name" of the scheme name is read from the scheme list on the left. Arrange and manage the scheme equipment in the project to make it consistent with the equipment installation arrangement of the project construction;
[0109] Step 6. Click the "Save" button in the lower right corner to save the above data to the project database to realize data call and management;
[0110] Step 7: Figure 7 Select the project you want to manage and view (nearly 10) from the drop-down menu of "Project Name" shown; for more projects, you can click the "Open" button to enter the project folder, where all projects are listed by project name. Select to return to the project information interface for viewing and management;
[0111] Step 8. Use the "Delete" button to clear project data from the project database; at the same time, project management can be used to accurately and quickly query, call and modify the solution equipment in the project.
[0112] Through the project management method shown in steps 1 to 8 above, the project database can be used not only to manage project information, but also to realize data call and integration of solution equipment in the project; at the same time, all data information in the project database can be integrated with processing drawings, cabinet combination, nesting, processing codes and other functions, and production materials can be managed and output according to solution information, which is more in line with actual production conditions and improves the coordination and efficiency of design, material management and production.
[0113] Embodiment 3
[0114] Figure 4 A schematic diagram of a project management device for electrical equipment provided in the third embodiment of the present invention is shown in FIG. Figure 4 As shown, the device comprises:
[0115] The first response module 21 is used to execute the step of displaying a project management configuration pop-up window to the user in the management interface in response to the triggering of the project management control; wherein the project management configuration pop-up window includes a project attribute information interface, a project plan information interface and a project equipment plan arrangement information interface.
[0116] The second response module 22 is used to execute the steps of generating the property information of the current project in response to the user's operation on the project property information interface and displaying it on the project property information interface. The information in the project property information interface at least includes the project name.
[0117] The third response module 23 is used to execute the steps of importing the solution information associated with the current project in the project solution information interface in response to the trigger of adding a solution control, and displaying it in sequence in the project solution information interface, wherein the solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information and copper busbar data information.
[0118] The fourth response module 24 is used to execute the steps of importing the scheme information associated with the current project as a preset scheme library in the project equipment scheme arrangement information interface, and configuring the scheme information for the electrical equipment of the current project according to the correspondence between the electrical equipment number of the current project and the scheme information serial number in response to the user's operation.
[0119] Optionally, the project management configuration pop-up window also includes a historical project record interface, and the device also includes a fifth response module, which is specifically used to execute in the historical project record interface, respond to the user's filtering operation, display the project name of the historical project to the user, and schedule the display of project attribute information, project plan information and project equipment plan arrangement information associated with the historical project based on the project name.
[0120] Optionally, the fifth response module is also specifically used to execute, after scheduling and displaying the project attribute information, project plan information and project equipment plan arrangement information associated with the historical projects based on the project name, in response to the user's operation, adjusting one or more of the project attribute information, project plan information or project equipment plan arrangement information associated with the historical projects, and displaying the adjusted historical projects to the user.
[0121] Optionally, the device also includes a sixth response module, which is specifically used to display a historical project list to the user in response to the triggering of an open control after displaying the project management configuration pop-up window to the user; based on the user's selection of a project name of a historical project in the historical project list, the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are scheduled and displayed based on the project name, and displayed in the project management configuration pop-up window.
[0122] Optionally, the device further comprises a seventh response module, configured to save the current project in response to triggering of the save control.
[0123] Optionally, the device also includes an eighth response module, which is specifically used to execute in the project solution information interface, in response to the triggering of the delete solution control, to delete the solution information not associated with the current project.
[0124] Optionally, the device also includes a ninth response module, which is specifically used to delete the content in the project management configuration pop-up window in response to the triggering of the deletion control.
[0125] The project management device for electrical equipment provided in the embodiment of the present invention can execute the project management method for electrical equipment provided in any embodiment of the present invention, and has the functional modules and beneficial effects corresponding to the execution method.
[0126] Embodiment 4
[0127] Figure 5 A schematic diagram of the structure of an electronic device provided in Embodiment 4 of the present invention is shown in FIG. Figure 5 As shown, the electronic device includes:
[0128] at least one processor; and
[0129] a memory communicatively connected to at least one processor; wherein,
[0130] The memory stores a computer program that can be executed by at least one processor, and the computer program is executed by at least one processor so that the at least one processor can execute the project management method for electrical equipment described in any embodiment of the present invention.
[0131] Figure 5 A schematic diagram of the structure of an electronic device 10 that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0132] like Figure 5 As shown, the electronic device 10 includes at least one processor 11, and a memory connected to the at least one processor 11, such as a read-only memory (ROM) 12, a random access memory (RAM) 13, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 11 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 12 or the computer program loaded from the storage unit 18 to the random access memory (RAM) 13. In the random access memory (RAM) 13, various programs and data required for the operation of the electronic device 10 can also be stored. The processor 11, the read-only memory (ROM) 12 and the random access memory (RAM) 13 are connected to each other through a bus 14. An input / output (I / O) interface 15 is also connected to the bus 14.
[0133] A number of components in the electronic device 10 are connected to an input / output (I / O) interface 15, including an input unit 16, such as a keyboard, a mouse, etc., an output unit 17, such as various types of displays, speakers, etc., a storage unit 18, such as a disk, an optical disk, etc., and a communication unit 19, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 19 allows the electronic device 10 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0134] The processor 11 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 11 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 11 executes the various methods and processes described above, such as a project management method for electrical equipment.
[0135] An embodiment of the present invention further provides a computer-readable storage medium, which stores computer instructions. The computer instructions are used to enable a processor to implement the project management method for electrical equipment according to any embodiment of the present invention when executed.
[0136] An embodiment of the present invention further provides a computer program product, characterized in that the computer program product includes a computer program, and when the computer program is executed by a processor, it implements the project management method for electrical equipment described in any embodiment of the present invention.
[0137] In some embodiments, the project management method for electrical equipment may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 18. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 10 via a read-only memory (ROM) 12 and / or a communication unit 19. When the computer program is loaded into a random access memory (RAM) 13 and executed by the processor 11, one or more steps of the project management method for electrical equipment described above may be performed. Alternatively, in other embodiments, the processor 11 may be configured to execute the project management method for electrical equipment in any other appropriate manner (e.g., by means of firmware).
[0138] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0139] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.
[0140] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0141] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).
[0142] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.
[0143] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.
[0144] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0145] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A project management method for electrical equipment, characterized in that: The following steps are involved: In the management interface, in response to the triggering of the project management control, a project management configuration pop-up window is displayed to the user; wherein the project management configuration pop-up window includes a project attribute information interface, a project scheme information interface and a project equipment scheme arrangement information interface; In the project attribute information interface, in response to the user's operation, attribute information of the current project is generated and displayed on the project attribute information interface, and the information in the project attribute information interface at least includes the project name; In the project solution information interface, in response to the triggering of adding a solution control, the solution information associated with the current project is imported and displayed in sequence on the project solution information interface, wherein the solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information, and copper busbar data information; In the project equipment scheme arrangement information interface, the scheme information associated with the current project is imported as a preset scheme library, and according to the correspondence between the electrical equipment number of the current project and the scheme information serial number, the scheme information of the electrical equipment of the current project is configured in response to the user's operation.
2. The method according to claim 1, characterized in that The project management configuration pop-up window also includes a historical project record interface; the method also includes: In the historical project record interface, in response to the user's filtering operation, the project name of the historical project is displayed to the user, and the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are scheduled and displayed based on the project name.
3. The method according to claim 2, characterized in that After scheduling and displaying the project attribute information, project scheme information and project equipment scheme arrangement information associated with the historical project based on the project name, the method further includes: In response to the user's operation, one or more of the project attribute information, project scheme information, or project equipment scheme arrangement information associated with the historical project is adjusted, and the adjusted historical project is displayed to the user.
4. The method according to claim 1, characterized in that: After showing the project management configuration popup to the user, also include: In response to triggering the open control, displaying the list of history items to the user; Based on the user's selection of the project name of the historical project in the historical project list, the project attribute information, project plan information and project equipment plan arrangement information associated with the historical project are scheduled and displayed based on the project name, and displayed in the project management configuration pop-up window.
5. The method according to claim 1, characterized in that After configuring the scheme information for the electrical equipment of the current project, the following steps are also included: In response to triggering of the save control, the current project is saved.
6. The method according to claim 1, characterized in that After showing the project management configuration popup to the user, also include: In the project solution information interface, in response to triggering of a delete solution control, solution information not associated with the current project is deleted.
7. The method according to claim 1, characterized in that After showing the project management configuration popup to the user, also include: In response to triggering of the delete control, the content in the project management configuration pop-up window is deleted.
8. A project management device for electrical equipment, characterized in that: include: A first response module is used to execute the step of displaying a project management configuration pop-up window to the user in response to the triggering of the project management control in the management interface; wherein the project management configuration pop-up window includes a project attribute information interface, a project scheme information interface and a project equipment scheme arrangement information interface; A second response module is used to execute the step of generating attribute information of the current project in response to the user's operation on the project attribute information interface and displaying the attribute information on the project attribute information interface, wherein the information on the project attribute information interface at least includes the project name; A third response module is used to execute the steps of importing the solution information associated with the current project in response to the triggering of adding a solution control on the project solution information interface, and displaying the solution information associated with the current project in sequence on the project solution information interface, wherein the solution information associated with the current project includes at least electrical equipment three-dimensional model data information, electrical component data information, and copper busbar data information; The fourth response module is used to execute the steps of importing the scheme information associated with the current project as a preset scheme library in the project equipment scheme arrangement information interface, and configuring the scheme information for the electrical equipment of the current project according to the correspondence between the electrical equipment number of the current project and the scheme information serial number in response to the user's operation.
9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the project management method for electrical equipment according to any one of claims 1 to 7.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the project management method for electrical equipment according to any one of claims 1 to 7 when executed.
11. A computer program product, characterized in that The computer program product comprises a computer program, which, when executed by a processor, implements the project management method for electrical equipment according to any one of claims 1 to 7.