Hard rock TBM normal anchor rod (cable) drilling machine and construction method thereof
By designing a hard rock TBM normal anchor (cord) drilling rig, the front and rear movement tracks of the anchor/cord drilling rig, annular beam, crawling trolley and annular beam are used to realize 360° vertical hole wall setting and high prestress application, which solves the problem that anchor (cord) drilling rigs cannot vertical hole wall setting and prestress application in the prior art, and improves the support capacity and efficiency of the TBM anchor/cord drilling system.
Patent Information
- Application Number
- CN202510172156.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-02-17
- Publication Date
- 2025-04-29
AI Technical Summary
Existing anchor (cable) drilling rigs cannot be drilled and anchor (cable) vertically on the hole wall, and the installation range is limited, making it difficult to achieve high prestress application, and it is difficult for multiple drilling rigs to work independently to adapt to the convergence of surrounding rocks.
A hard rock TBM normal anchor (line) drilling rig is designed, including anchor/line drilling rig, annular beam, crawler trolley and annular beam front and rear moving tracks. Through these components, 360° vertical hole wall setting and prestressing application of drill rod, anchor and anchor cable are realized. Multiple drilling rigs can work independently in concert.
The 360° anchor/cable coverage of the hole wall is achieved, effectively responding to the large deformation and collapse of surrounding rock convergence, and improving the support capacity and efficiency of the TBM anchor/cable drilling system.
Smart Images

Figure CN119900573A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of TBM engineering machinery, and in particular to a hard rock TBM normal anchor (cable) drilling rig and a construction method thereof. Background Art
[0002] Hard rock tunnel boring machines (TBMs) are widely used in tunnel (hole) construction in transportation, water conservancy, mining and other fields due to their advantages such as fast excavation speed, high construction quality and low environmental disturbance. Hard rock TBMs can be divided into open TBMs, single shield TBMs and double shield TBMs, among which open TBMs are the most widely used in my country and even in the world. For exposed surrounding rock (or tunnel wall), open TBMs generally adopt support measures such as steel arch frames, anchor net spraying, advanced pipe sheds, and advanced grouting to deal with the risks of surrounding rock convergence and collapse. However, when TBM encounters high-stress soft surrounding rock or fault fracture zones, untimely or inappropriate support can easily cause the exposed surrounding rock to collapse and become unstable. In severe cases, it may cause damage to equipment in the L1 area, casualties, and even cause the TBM to be trapped and stuck. The use of reasonable support methods can effectively improve the construction efficiency of TBMs and ensure the safety of TBM operations. Anchor (cable) support is one of the most effective means to deal with large deformation of surrounding rock convergence and establish a bearing arch in the loose circle of surrounding rock, and is widely used in tunnel (hole) projects.
[0003] However, current anchor (cable) drilling rigs (such as Figure 1 The following defects exist when driving anchors (cables): 1) It is impossible to drill holes and anchors (cables) vertically on the cave wall, and thus it is impossible to effectively apply high prestress of the anchors (cables); 2) The drilling range of holes and anchors (cables) is limited, generally not exceeding 180° of the arch top; 3) It is difficult for multiple (generally two) anchor (cable) drilling rigs to work independently to adapt to the convergence of the surrounding rock.
[0004] Therefore, it is urgent to design a hard rock TBM normal anchor (cable) drilling rig and its system, so that it can drill holes and anchors (cables) 360° vertically on the tunnel wall and achieve high prestressing. In addition, multiple anchor (cable) drilling rigs can work relatively independently according to the convergence of the surrounding rock to improve the support capacity and efficiency. Summary of the invention
[0005] The object of the present invention is to provide a hard rock TBM normal anchor (cable) drilling rig and a construction method thereof, so as to solve the problems raised in the above-mentioned background technology.
[0006] To achieve the above object, the present invention provides the following technical solutions: In a first aspect, the present invention provides a hard rock TBM normal bolt (cable) drilling rig, the drilling rig comprising:
[0007] An anchor / cable drilling machine, comprising a rock drill, a drilling guide rail, a gasket fixing device, a grouting pipe and a drill rod; the end of the rock drill is connected to the tail end of the drill rod or anchor rod, and the rock drill moves along the drilling guide rail; the grouting pipe is used to inject grout into the gap between the anchor rod / cable and the borehole; a metal gasket is installed on the outermost anchor rod of the borehole and the end of the anchor cable, which is used to apply prestress to the anchor rod and the anchor cable, and is fixed to the hole wall by the gasket fixing device;
[0008] The ring beam includes a ring beam track and a walking mechanism. The ring beam is arranged on the TBM main beam through the ring beam forward and backward moving track and its axis is parallel to the tunnel axis.
[0009] The crawling trolley includes a driving device and a swing motor. The driving device drives the anchor / cable drill to move circumferentially on the circular beam track. The swing motor includes an encoder for accurately adjusting the drilling angle of the anchor / cable drill so that the anchor / cable is injected vertically into the hole wall.
[0010] The annular beam forward and backward moving track is arranged on the TBM main beam, and two upper and lower tracks are arranged on both sides of the TBM main beam. The annular beam can move forward and backward along the annular beam forward and backward moving track under the drive of the walking mechanism.
[0011] Furthermore, the end of the rock drill is connected to the tail end of the drill rod, and the anchor / cable drill realizes the driving, connection and withdrawal of the drill rod.
[0012] Furthermore, the rock drill end of the anchor / cable drilling machine is connected to the tail end of the anchor, and the anchor / cable drilling machine realizes the driving, connection and prestressing of the anchor.
[0013] Furthermore, the anchor cable is driven toward the drill hole under the rolling action of the roller at the end of the anchor rod / cable drilling machine guide rail, thereby achieving the driving and prestressing of the anchor cable.
[0014] Furthermore, the ring beam track of the ring beam is a ring gear, and the walking mechanism drives the ring beam to move forward and backward along the ring beam forward and backward movement track, and the moving distance is not less than the maximum stroke of the TBM propulsion cylinder;
[0015] Furthermore, the driving device of the crawling trolley is realized by hydraulically driving two small gears to rotate, so that the crawling trolley can move along the annular beam track, and the swing motor of the crawling trolley makes the anchor rod / cable drilling machine swing within the radial range of ±45° in the tunnel (hole).
[0016] Furthermore, a plurality of the anchor / cable drills may be deployed on the annular beam to improve the drilling efficiency of the anchor / cable drill system.
[0017] In a second aspect, the present invention provides an anchor / cable construction method based on a hard rock TBM normal anchor (cable) drilling rig, characterized in that it specifically includes the driving, splicing and withdrawal of the drill rod, the driving, splicing and prestressing of the anchor, and the driving and prestressing of the anchor cable;
[0018] The end of the rock drill of the anchor / rope drill is connected to the tail end of the drill rod, and the rock drill moves along the drill guide rail. The steps of setting, connecting and retracting the drill rod of the anchor / rope drill are as follows:
[0019] Step 1.1: The anchor / cable drill rig is in its original position, and the on-site worker connects the tail end of the first drill rod to the end of the rock drill;
[0020] Step 1.2: The anchor / cable drill moves to the designated position under the drive of the crawler trolley and adjusts the drilling angle of the drill rod to be perpendicular to the cave wall;
[0021] Step 1.3: The anchor / cable drill rig drives the first drill rod toward the tunnel (hole) wall. After the driving is completed, the rock drill returns along the drill rig guide rail to the bottom of the guide rail;
[0022] Step 1.4: The anchor / cable drill rig is driven back to its original position by the crawler trolley, and the on-site worker connects the tail end of the second connecting drill rod to the end of the rock drill;
[0023] Step 1.5: The anchor / cable drill rig is driven by the crawler trolley to move to the first drill rod driving position, the end of the rock drill rotates to drive the head end of the second connecting drill rod to connect with the tail end of the first drill rod, and then the rock drill moves along the drill guide rail to drive the second drill rod. After the driving is completed, the rock drill returns to the bottom of the guide rail along the drill guide rail;
[0024] Step 1.6: Repeat steps 1.4 to 1.5 until all the follow-up drill rods are driven into the hole wall and the required drilling depth is reached;
[0025] Step 1.7: The rock drill moves along the drill guide rail until its end is connected to the tail end of the last drill rod. The end of the rock drill rotates in the opposite direction so that the last drill rod is separated from the previous drill rod. The rock drill returns to the bottom of the guide rail along the drill guide rail.
[0026] Step 1.8: The anchor / cable drill returns to its original position under the drive of the crawler trolley. The on-site worker removes the last drill rod, and the anchor / cable drill returns to the drilling position under the drive of the crawler trolley.
[0027] Step 1.9: Repeat steps 1.7 to 1.8 until all drill rods are removed by on-site workers and the anchor / cable drill returns to its original position, completing one drilling.
[0028] Step 1.10: Repeat steps 1.1 to 1.9 until the anchor / cable drilling rig completes all drilling according to the construction requirements.
[0029] The end of the rock drill of the anchor / cable drill is connected to the tail end of the anchor, and the rock drill moves along the drill guide rail. The steps of driving the anchor / cable drill, connecting the anchor and applying prestress are as follows:
[0030] Step 2.1: The anchor / cable drilling machine is in the original position and is driven by the crawler trolley to move to the vicinity of the drill hole where the anchor is to be driven;
[0031] Step 2.2: On-site workers connect the tail end of the first anchor bolt to the end of the rock drill. The anchor bolt / cable drill is adjusted to the vertical direction of the cave wall under the action of the swing motor, and the anchor bolt is coaxial with the drill hole;
[0032] Step 2.3: The anchor / cable drill drill drives the first anchor toward the borehole, and then drives the second, third, and penultimate connecting anchors in sequence;
[0033] Step 2.4: The anchor / cable drill drill drives the last connecting anchor into the borehole. The anchor has a metal gasket to apply prestress to the anchor.
[0034] Step 2.5: The anchor / cable drilling machine injects grout into the gap between the anchor and the drill hole through the grouting pipe until the construction requirements are met;
[0035] Step 2.6: The gasket fixing device makes the metal gasket of the anchor rod close to the hole wall, and the anchor rod / cable drilling machine pulls the anchor rod outward for a certain distance until the specified prestressing level is reached;
[0036] Step 2.7: Repeat steps 2.1 to 2.6 until the anchor / cable drilling rig completes all anchor driving and prestressing as required by the construction.
[0037] The anchor cable is driven toward the borehole under the rolling action of the roller at the end of the anchor rod / cable drilling machine guide rail. The steps of driving the anchor cable and applying prestress by the anchor rod / cable drilling machine are as follows:
[0038] Step 3.1: The anchor / cable drilling machine is in the original position and is driven by the crawler trolley to move to the vicinity of the drill hole where the anchor cable is to be installed;
[0039] Step 3.2: On-site workers insert the anchor cable into the roller at the end of the anchor rod / cable drilling rig guide rail. The end of the anchor cable has a metal gasket to apply prestress to the anchor cable;
[0040] Step 3.3: The roller at the end of the anchor / cable drill guide rotates, and the anchor cable is gradually driven into the drill hole until it reaches the specified depth;
[0041] Step 3.4: The anchor / cable drilling rig grouting pipe injects grout into the gap between the anchor cable and the drill hole until the construction requirements are met;
[0042] Step 3.5: The gasket fixing device makes the anchor cable metal gasket close to the hole wall, and the roller at the end of the anchor rod / cable drilling rig guide rail is reversed to pull the anchor cable outward for a certain distance until the specified prestressing level is reached;
[0043] Step 3.6: Repeat steps 3.1 to 3.5 until the anchor / cable drilling rig completes all anchor cable installation and prestressing according to construction requirements.
[0044] The beneficial effects of the present invention are as follows:
[0045] The device described in the present invention can achieve 360° full coverage of the tunnel wall with anchors / cables, and can effectively deal with large deformation and unstable collapse of the surrounding rock at various positions around the tunnel wall; it can drill holes vertically on the tunnel wall to achieve the vertical installation of anchors / cables on the tunnel wall, thereby achieving effective application of high prestress of the anchors / cables; multiple anchor / cable drilling rigs can work in a coordinated and relatively independent manner, greatly improving the support capacity and efficiency of the hard rock TBM anchor / cable drilling rig system.
[0046] The present invention also provides a construction method of a hard rock TBM normal anchor (cable) drilling rig and a system thereof, which has simple steps, is easy to operate, and is suitable for large-scale promotion and application. BRIEF DESCRIPTION OF THE DRAWINGS
[0047] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0048] Figure 1 This is a schematic diagram of the existing anchor (cable) drilling rig installing anchor (cable).
[0049] Figure 2 This is a schematic diagram of the position and arrangement of the present invention in a hard rock TBM.
[0050] Figure 3 It is a detailed structural schematic diagram of the normal anchor / cable drilling rig system of the present invention.
[0051] Figure 4 It is a detailed structural schematic diagram of the normal anchor / cable drilling rig of the present invention. DETAILED DESCRIPTION
[0052] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0053] Example 1
[0054] See also Figure 2-Figure 4 The present invention provides a hard rock TBM normal anchor (cable) drilling rig, comprising: an anchor / cable drilling rig, an annular beam, a crawling trolley and an annular beam forward and backward moving track.
[0055] The anchor / cable drilling machine comprises a rock drill, a drilling machine guide rail, a gasket fixing device, a grouting pipe and a drill rod. The anchor / cable drilling machine can realize the setting, connection and withdrawal of the drill rod, the setting, connection and prestressing of the anchor rod, and the setting and prestressing of the anchor cable;
[0056] The annular beam mainly includes an annular beam track and a walking mechanism. The annular beam is arranged on the TBM main beam and its axis is parallel to the tunnel axis.
[0057] The crawling trolley includes a driving device and a swing motor. The driving device can drive the anchor / cable drill to move circumferentially on the annular beam track. The swing motor includes an encoder, which can accurately adjust the drilling angle of the anchor / cable drill so that the anchor / cable is injected vertically to the cave wall.
[0058] The forward and backward moving tracks of the annular beam are arranged on the main beam, and two upper and lower tracks (four in total) are arranged on both sides of the main beam. The annular beam can move forward and backward along the tracks under the drive of the walking mechanism.
[0059] As a specific embodiment, the rock drill end of the anchor / cable drill is connected to the tail end of the drill rod, and the rock drill moves up and down along the drill guide rail to achieve the installation, connection and withdrawal of the drill rod.
[0060] As a specific embodiment, the rock drill end of the anchor / cable drilling rig is connected to the tail end of the anchor, and the rock drill moves along the drilling rig guide rail to achieve the installation, connection and prestressing of the anchor.
[0061] As a specific embodiment, the roller at the end of the anchor / cable drilling rig guide rail allows the anchor cable to pass through, and the rotation of the roller can achieve the installation and prestressing of the anchor cable.
[0062] As an improved embodiment, the annular beam mainly includes an annular beam track and a walking mechanism. The annular beam can be supported on the TBM main beam (L1 area) or the rear supporting beam (L2 area), wherein the annular beam track is a circle of gear rings, providing a walking track for the circular motion of the anchor / cable drill rig, and the walking mechanism can drive the annular beam to move forward and backward along the annular beam forward and backward track for a certain distance (not less than the distance of one TBM excavation cycle, such as about 2m).
[0063] Furthermore, the driving device of the crawling trolley is realized by hydraulically driving two small gears to rotate, so that the crawling trolley can move along the annular beam track. The swing motor of the crawling trolley can make the anchor / cable drill rig swing in the radial range of ±45° in the tunnel (hole). It connects the anchor / cable drill rig with the crawling trolley and drives the drill rig to swing in the section of the tunnel (hole), ensuring that the drilling direction of the drill rig is perpendicular to the hole wall.
[0064] Furthermore, the anchor / cable drills may be deployed in plurality on the annular beam (two anchor / cable drills are shown in this embodiment, and four or more may be deployed) to improve the drilling efficiency of the anchor / cable drill system.
[0065] Example 2
[0066] The embodiment of the present invention also provides a hard rock TBM normal anchor (cable) drilling rig construction method, including the setting, connection and withdrawal of the drill rod, the setting, connection and prestressing of the anchor rod, and the setting and prestressing of the anchor cable:
[0067] The end of the rock drill of the anchor / rope drill is connected to the tail end of the drill rod, and the rock drill moves along the drill guide rail. The steps of setting, connecting and retracting the drill rod of the anchor / rope drill are as follows:
[0068] Step 1: The anchor / rope drill is in the original position ( Figure 3 The original positions of the two anchor / cable drills are at 10 o'clock and 14 o'clock respectively. This embodiment only takes one of the anchor / cable drills as an example to illustrate its use method). The on-site worker connects the tail end of the first drill rod to the end of the rock drill;
[0069] Step 2: The anchor / cable drill moves to the designated position along the annular beam track under the drive of the crawler trolley, and the swing motor adjusts the drilling angle of the drill rod so that the drill rod is perpendicular to the hole wall;
[0070] Step 3: The anchor / cable drill rig drives the first drill rod toward the tunnel (hole) wall. After the driving is completed, the rock drill returns along the drill rig guide rail to the bottom of the guide rail;
[0071] Step 4: The anchor / cable drill rig is driven by the crawler trolley drive device to return to its original position along the circular beam track, and the on-site workers connect the tail end of the second connecting drill rod to the end of the rock drill;
[0072] Step 5: The anchor / cable drill rig is driven by the crawler trolley drive device to move along the annular beam track to the first drill rod installation position and the swing motor adjusts the angle of the second drill rod to ensure that the second drill rod is in a straight line with the first drill rod. The end of the rock drill rotates to drive the head end of the second connecting drill rod to connect with the tail end of the first drill rod. Then the rock drill moves along the drill guide rail to install the second drill rod. After installation, the rock drill returns to the bottom of the guide rail along the drill guide rail.
[0073] Step 6: Repeat steps 4 to 5 until all the follow-up drill rods are driven into the hole wall (the anchor rod / cable driving depth requirement must be met);
[0074] Step 7: The rock drill moves along the drill guide rail until its end is connected to the tail end of the last drill rod. The end of the rock drill rotates in the opposite direction to separate the last drill rod from the previous drill rod. The rock drill returns to the bottom of the guide rail along the drill guide rail.
[0075] Step 8: The anchor / cable drill returns to its original position along the annular beam track under the drive of the crawler trolley drive device, and the on-site worker removes the last drill rod. The anchor / cable drill returns to the drilling position along the annular beam track under the drive of the crawler trolley drive device;
[0076] Step 9: Repeat steps 7 to 8 until all drill rods are removed by on-site workers, and the anchor / cable drill returns to its original position along the annular beam track under the drive of the crawler trolley drive device, completing a drilling operation;
[0077] Step 10: Repeat steps 1 to 9 until the anchor / cable drill rig completes drilling at all circumferential locations of the cave wall according to construction requirements.
[0078] The end of the rock drill of the anchor / cable drill is connected to the tail end of the anchor, and the rock drill moves along the drill guide rail. The steps of driving the anchor / cable drill, connecting the anchor and applying prestress are as follows:
[0079] Step 1: The anchor / cable drill is in the original position (14 o'clock position of the annular beam) and is driven by the crawler to move to the vicinity of the borehole where the anchor is to be driven (such as the 15 o'clock position of the cave wall);
[0080] Step 2: On-site workers connect the tail end of the first anchor rod to the end of the rock drill, and the anchor rod / cable drill is adjusted to the vertical direction of the cave wall (the anchor rod is coaxial with the drill hole) under the action of the swing motor;
[0081] Step 3: The anchor / cable drill drill drives the first anchor toward the borehole, and then drives the second anchor in sequence (a total of two anchors);
[0082] Step 4: The anchor / cable drill drill drives the last (second) connecting anchor into the borehole. The anchor has a metal gasket to apply prestress to the anchor.
[0083] Step 5: The anchor / cable drilling machine grouting pipe injects grout (resin, etc.) into the gap between the anchor and the drill hole to enhance the anchor fastening effect until the construction requirements are met;
[0084] Step 6: The gasket fixing device makes the anchor metal gasket close to the hole wall, and the anchor / cable drilling machine pulls the anchor out a certain distance (such as 10 cm) until the specified prestressing level is reached;
[0085] Step 7: Repeat steps 1 to 6 until the anchor / cable drilling rig completes all anchor driving and prestressing according to construction requirements.
[0086] The anchor cable is driven toward the borehole under the rolling action of the roller at the end of the anchor rod / cable drilling machine guide rail. The steps of driving the anchor cable and applying prestress by the anchor rod / cable drilling machine are as follows:
[0087] Step 1: The anchor / cable drilling machine is in the original position (14 o'clock position of the annular beam) and is driven by the crawler trolley to move to the vicinity of the drill hole where the anchor cable is to be set (such as the 15 o'clock position of the cave wall);
[0088] Step 2: On-site workers insert the anchor cable into the roller at the end of the anchor rod / cable drilling rig guide rail. The end of the anchor cable has a metal gasket to apply prestress to the anchor cable;
[0089] Step 3: The roller at the end of the anchor / cable drill guide rotates, and the anchor cable is gradually driven into the borehole until it reaches the specified depth (e.g. 8m);
[0090] Step 4: The anchor / cable drilling machine grouting pipe injects grout (such as resin, etc.) into the gap between the anchor cable and the drill hole to enhance the anchor fastening effect until the construction requirements are met;
[0091] Step 5: The gasket fixing device makes the anchor cable metal gasket close to the hole wall, and the roller at the end of the anchor rod / cable drilling rig guide rail is reversed to pull the anchor cable out a certain distance (such as 15cm) until the specified prestressing level is reached;
[0092] Step 6: Repeat steps 1 to 5 until the anchor / cable drilling rig completes all anchor cable installation and prestressing according to construction requirements.
[0093] The above description is only a preferred specific implementation manner of the present invention, but the scope of protection of the present invention is not limited thereto. Any modifications, equivalent substitutions and improvements made by any technician familiar with the technical field within the technical scope disclosed by the present invention should be included in the scope of protection of the invention.
Claims
1. A hard rock TBM normal bolt (cable) drilling rig, characterized in that: The rig includes: An anchor / cable drilling machine, comprising a rock drill, a drilling guide rail, a gasket fixing device, a grouting pipe and a drill rod; the end of the rock drill is connected to the tail end of the drill rod or anchor rod, and the rock drill moves along the drilling guide rail; the grouting pipe is used to inject grout into the gap between the anchor rod / cable and the borehole; a metal gasket is installed on the outermost anchor rod of the borehole and the end of the anchor cable, which is used to apply prestress to the anchor rod and the anchor cable, and is fixed to the hole wall by the gasket fixing device; The ring beam includes a ring beam track and a walking mechanism. The ring beam is arranged on the TBM main beam through the ring beam forward and backward moving track and its axis is parallel to the tunnel axis. The crawling trolley includes a driving device and a swing motor. The driving device drives the anchor / cable drill to move circumferentially on the circular beam track. The swing motor includes an encoder for accurately adjusting the drilling angle of the anchor / cable drill so that the anchor / cable is injected vertically into the hole wall. The annular beam forward and backward moving track is arranged on the TBM main beam, and two upper and lower tracks are arranged on both sides of the TBM main beam. The annular beam can move forward and backward along the annular beam forward and backward moving track under the drive of the walking mechanism.
2. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The end of the rock drill is connected to the tail end of the drill rod, and the anchor / cable drill realizes the driving, connection and withdrawal of the drill rod.
3. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The rock drill end of the anchor / cable drilling machine is connected to the tail end of the anchor, and the anchor / cable drilling machine realizes the driving, connection and prestressing of the anchor.
4. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The anchor cable is driven toward the drill hole under the rolling action of the roller at the end of the anchor rod / cable drilling machine guide rail, thereby achieving the driving of the anchor cable and the application of prestress.
5. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The annular beam track of the annular beam is a circle of gear rings, and the walking mechanism drives the annular beam to move forward and backward along the annular beam forward and backward moving track, and the moving distance is not less than the maximum stroke of the TBM propulsion cylinder.
6. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The driving device of the crawling trolley is realized by hydraulically driving two small gears to rotate, so that the crawling trolley can move along the ring beam track, and the swing motor of the crawling trolley makes the anchor rod / cable drilling machine swing within the radial range of ±45° in the tunnel (hole).
7. The hard rock TBM normal bolt (cable) drilling rig according to claim 1, characterized in that: The anchor / cable drill can be deployed in plurality on the annular beam to improve the drilling efficiency of the anchor / cable drill system.
8. A hard rock TBM normal anchor / cable construction method based on the hard rock TBM normal anchor (cable) drilling rig according to any one of claims 1 to 7, characterized in that: Specifically, it includes the setting, splicing and withdrawal of drill rods, the setting, splicing and prestressing of anchor rods, and the setting and prestressing of anchor cables; The end of the rock drill of the anchor / rope drill is connected to the tail end of the drill rod, and the rock drill moves along the drill guide rail. The steps of setting, connecting and retracting the drill rod of the anchor / rope drill are as follows: Step 1.1: The anchor / cable drill rig is in its original position, and the on-site worker connects the tail end of the first drill rod to the end of the rock drill; Step 1.2: The anchor / cable drill moves to the designated position under the drive of the crawler trolley and adjusts the drilling angle of the drill rod to be perpendicular to the cave wall; Step 1.3: The anchor / cable drill rig drives the first drill rod toward the tunnel (hole) wall. After the driving is completed, the rock drill returns along the drill rig guide rail to the bottom of the guide rail; Step 1.4: The anchor / cable drill rig is driven back to its original position by the crawler trolley, and the on-site worker connects the tail end of the second connecting drill rod to the end of the rock drill; Step 1.5: The anchor / cable drill rig is driven by the crawler trolley to move to the first drill rod driving position, the end of the rock drill rotates to drive the head end of the second connecting drill rod to connect with the tail end of the first drill rod, and then the rock drill moves along the drill guide rail to drive the second drill rod. After the driving is completed, the rock drill returns to the bottom of the guide rail along the drill guide rail; Step 1.6: Repeat steps 1.4 to 1.5 until all the follow-up drill rods are driven into the hole wall and the required drilling depth is reached; Step 1.7: The rock drill moves along the drill guide rail until its end is connected to the tail end of the last drill rod. The end of the rock drill rotates in the opposite direction so that the last drill rod is separated from the previous drill rod. The rock drill returns to the bottom of the guide rail along the drill guide rail. Step 1.8: The anchor / cable drill returns to its original position under the drive of the crawler trolley. The on-site worker removes the last drill rod, and the anchor / cable drill returns to the drilling position under the drive of the crawler trolley. Step 1.9: Repeat steps 1.7 to 1.8 until all drill rods are removed by on-site workers and the anchor / cable drill returns to its original position, completing one drilling. Step 1.10: Repeat steps 1.1 to 1.9 until the anchor / cable drilling rig completes all drilling according to the construction requirements. The end of the rock drill of the anchor / cable drill is connected to the tail end of the anchor, and the rock drill moves along the drill guide rail. The steps of driving the anchor / cable drill, connecting the anchor and applying prestress are as follows: Step 2.1: The anchor / cable drilling machine is in the original position and is driven by the crawler trolley to move to the vicinity of the drill hole where the anchor is to be driven; Step 2.2: On-site workers connect the tail end of the first anchor bolt to the end of the rock drill. The anchor bolt / cable drill is adjusted to the vertical direction of the cave wall under the action of the swing motor, and the anchor bolt is coaxial with the drill hole; Step 2.3: The anchor / cable drill drill drives the first anchor toward the borehole, and then drives the second, third, and penultimate connecting anchors in sequence; Step 2.4: The anchor / cable drill drill drives the last connecting anchor into the borehole. The anchor has a metal gasket to apply prestress to the anchor. Step 2.5: The anchor / cable drilling machine injects grout into the gap between the anchor and the drill hole through the grouting pipe until the construction requirements are met; Step 2.6: The gasket fixing device makes the metal gasket of the anchor rod close to the hole wall, and the anchor rod / cable drilling machine pulls the anchor rod outward for a certain distance until the specified prestressing level is reached; Step 2.7: Repeat steps 2.1 to 2.6 until the anchor / cable drilling rig completes all anchor driving and prestressing as required by the construction. The anchor cable is driven toward the borehole under the rolling action of the roller at the end of the anchor rod / cable drilling machine guide rail. The steps of driving the anchor cable and applying prestress by the anchor rod / cable drilling machine are as follows: Step 3.1: The anchor / cable drilling machine is in the original position and is driven by the crawler trolley to move to the vicinity of the drill hole where the anchor cable is to be installed; Step 3.2: On-site workers insert the anchor cable into the roller at the end of the anchor rod / cable drilling rig guide rail. The end of the anchor cable has a metal gasket to apply prestress to the anchor cable; Step 3.3: The roller at the end of the anchor / cable drill guide rotates, and the anchor cable is gradually driven into the drill hole until it reaches the specified depth; Step 3.4: The anchor / cable drilling rig grouting pipe injects grout into the gap between the anchor cable and the drill hole until the construction requirements are met; Step 3.5: The gasket fixing device makes the anchor cable metal gasket close to the hole wall, and the roller at the end of the anchor rod / cable drilling rig guide rail is reversed to pull the anchor cable outward for a certain distance until the specified prestressing level is reached; Step 3.6: Repeat steps 3.1 to 3.5 until the anchor / cable drilling rig completes all anchor cable installation and prestressing according to construction requirements.