The invention provides a deep and thick backfill foundation
pile planting construction method, and belongs to the technical field of backfill foundation
pile construction, and the method comprises the following steps: S1, pre-drilling in a large-particle-size backfill layer by using a down-the-hole
pile hammering
machine, and synchronously burying a pile casing in the pre-drilling process; s2, the down-the-hole hammer construction equipment is moved away, and soil body backfilling is conducted in the pre-drilled hole; s3, a percussion drilling
machine is adopted for percussion drilling in the hole with the soil body backfill; s4, after the hole deeply penetrates through the large-particle-size backfill layer, a special drilling
machine with a grouting function is adopted to replace a percussion drilling machine to conduct drilling in a conventional soil layer in the hole; s5, after the special drilling machine drills a hole to a preset depth, the special drilling machine lifts a
drill rod from the interior of the
drill hole and injects curing
slurry for stirring at the same time; and S6, before the solidification
slurry in the hole is not solidified, the precast pile is implanted into the solidification
slurry in the hole. The method has the beneficial effects that the precast pile construction efficiency and effect are improved, the pile forming quality is guaranteed, and many defects existing in a traditional construction technology are overcome.