Cable trench cover plate construction device

By designing a cable trench cover construction device including a support mechanism, mounting base, winding mechanism, boom and traction parts, the problem of high labor intensity for staff in traditional technology is solved, and the convenient movement of cable trench cover and the efficiency of cable maintenance is improved.

CN119976665AActive Publication Date: 2025-05-13GUANGZHOU POWER SUPPLY BUREAU GUANGDONG POWER GRID CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202510001001.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-01-02
Publication Date
2025-05-13
Estimated Expiration
2045-01-02

AI Technical Summary

Technical Problem

In traditional technology, staff need to move the cable trench cover from the trench, resulting in high labor intensity.

Method used

A cable trench cover construction device is designed, including a support mechanism, a mounting base, a winding mechanism, a boom and a traction member. Through the coordinated work of these components, the cover plate can be easily moved from above the cable trench to other areas.

Benefits of technology

This device can significantly reduce the labor intensity of staff, improve the movement efficiency of the cable trench cover, and facilitate the maintenance of the cables in the cable trench.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119976665A_ABST
    Figure CN119976665A_ABST
Patent Text Reader

Abstract

The invention relates to a cable trench cover plate construction device. A mounting base is arranged on a supporting mechanism and can reciprocate in the first direction of a cable trench; one end of the first suspension arm is arranged on one side of the mounting seat along a second direction of the cable trench, one end of the second suspension arm is arranged on the other side of the mounting seat along the second direction, the second direction is perpendicular to the first direction, one end of the first suspension arm far away from the mounting seat is provided with a first winding piece, and one end of the second suspension arm far away from the mounting seat is provided with a second winding piece; one end of the first traction piece is arranged on the winding mechanism, the other end of the first traction piece bypasses the first winding piece and is used for being connected with the cover plate, one end of the second traction piece is arranged on the winding mechanism, the other end of the second traction piece bypasses the second winding piece and is used for being connected with the cover plate, and the winding mechanism can wind or release the first traction piece and the second traction piece. Therefore, the cover plate can be lifted or dropped down. According to the cable trench cover plate construction device, a worker can conveniently overhaul the cable in the cable trench.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cable trench cover construction, and in particular to a cable trench cover construction device. Background Art

[0002] A cable trench is an underground channel used to accommodate cables. The cable trench cover is used to cover the top of the cable trench to prevent debris outside the cable trench from entering the cable trench and causing damage to the cables in the cable trench, thereby ensuring the safe operation of the cables. The cables in the cable trench need to be inspected and maintained regularly to prevent safety accidents involving the cables. The first step in cable maintenance is to remove the cover on the cable trench.

[0003] In the traditional technology, workers are required to remove the cover plate from the cable trench, which results in high labor intensity for the workers. Summary of the invention

[0004] Based on this, it is necessary to provide a cable trench cover construction device to address the problem that traditional technology requires workers to move the cover away from the cable trench, resulting in high labor intensity for the workers.

[0005] The technical solution is as follows:

[0006] One embodiment provides a cable trench cover construction device, comprising:

[0007] Support mechanism;

[0008] A mounting seat, the mounting seat is arranged on the supporting mechanism and can reciprocate along a first direction of the cable trench;

[0009] A winding mechanism, wherein the winding mechanism is arranged on the mounting seat;

[0010] A first suspension arm and a second suspension arm, wherein one end of the first suspension arm is disposed on one side of the mounting seat along a second direction of the cable trench, and one end of the second suspension arm is disposed on the other side of the mounting seat along the second direction, the second direction being perpendicular to the first direction, a first winding member is disposed on one end of the first suspension arm away from the mounting seat, and a second winding member is disposed on one end of the second suspension arm away from the mounting seat;

[0011] A first traction member and a second traction member, one end of the first traction member is arranged on the winding mechanism, the other end of the first traction member bypasses the first winding member and is used to connect with the cover plate, one end of the second traction member is arranged on the winding mechanism, the other end of the second traction member bypasses the second winding member and is used to connect with the cover plate, the winding mechanism can wind up or release the first traction member and the second traction member to lift or drop the cover plate.

[0012] When the above-mentioned cable trench cover construction device is used, the supporting mechanism is first placed on the ground and crossed over the cable trench along a first direction of the cable trench, and the end of the first traction member away from the winding mechanism and the end of the second traction member away from the winding mechanism are connected to the cable trench cover, and then the winding mechanism is controlled to wind up the first traction member and the second traction member. At this time, the end of the first traction member bypassing the first winding member away from the winding mechanism gradually approaches the first boom, and the end of the second traction member bypassing the second winding member away from the winding mechanism gradually approaches the second boom, so that the cover is lifted. Subsequently, the staff controls the mounting seat to move along the first direction on the supporting mechanism, so that the first boom and the second boom drive the cover to move, thereby driving the cover away from the area above the cable trench. Compared with traditional technology, the above-mentioned cable trench cover construction device can more conveniently move the cover from above the cable trench to other areas, so that the staff can inspect and repair the cables in the cable trench and reduce the labor intensity of the staff.

[0013] In one embodiment, the winding mechanism includes a rotating column, one end of which is disposed on the mounting seat, and one end of the first traction member and one end of the second traction member are both connected to the side wall of the rotating column.

[0014] In one embodiment, the winding mechanism further includes a first assembly rod and a first assembly portion, one end of the first assembly rod is arranged on the side wall of the rotating column, at least two first assembly portions are provided, all of the first assembly portions are arranged on the first assembly rod at intervals along the axial direction of the first assembly rod, and one end of the first traction member is used to connect with one of the first assembly portions; or / and,

[0015] The winding mechanism also includes a second assembly rod and a second assembly part, one end of the second assembly rod is arranged on the side wall of the rotating column, and at least two second assembly parts are provided, and all of the second assembly parts are arranged on the second assembly rod at intervals along the axial direction of the second assembly rod, and one end of the second traction member is used to be connected to one of the second assembly parts.

[0016] In one embodiment, the winding mechanism also includes a holding rod, the side wall of the rotating column is provided with at least two third assembly parts, all of the third assembly parts are arranged at intervals along the circumference of the rotating column, and one end of the holding rod is used to connect to one of the third assembly parts.

[0017] In one embodiment, the third assembly portion is provided with an inserting groove, and the inserting groove is used to be inserted with one end of the holding rod.

[0018] In one embodiment, the first suspension arm is provided with a positioning piece, and the positioning piece is used to position and cooperate with the holding rod.

[0019] In one embodiment, the positioning member includes a first positioning portion, a second positioning portion and a positioning pin, the first positioning portion and the second positioning portion are spaced apart along the axial direction of the rotating column, the first positioning portion, the first suspension arm and the second positioning portion are surrounded to form a positioning groove, the positioning groove is used to accommodate the holding rod, the first positioning portion is provided with a positioning through hole, the positioning pin is passed through the positioning through hole and can move back and forth along the axial direction of the positioning through hole, so that the positioning pin can open or close the notch of the positioning groove.

[0020] In one embodiment, the mounting seat is provided with a mounting channel, the inner wall of the mounting channel is provided with a guide seat, the guide seat is provided with a guide wheel, the cable trench cover construction device also includes a guide mechanism, the guide mechanism includes a guide column, the guide column is passed through the mounting channel and is provided with a guide channel, the side wall of the guide column is provided with a guide opening connected to the guide channel, the guide channel and the guide opening both extend along the first direction, the guide seat is passed through the guide opening, the guide wheel is located in the guide channel and rollingly cooperates with the side wall of the guide channel.

[0021] In one embodiment, a first roller is provided on one side of the mounting seat along the first direction, and a second roller is provided on the other side of the mounting seat along the first direction, the axis of the first roller and the axis of the second roller are both perpendicular to the second direction, and the first roller and the second roller are both rollingly engaged with the outer wall of the guide column.

[0022] In one embodiment, the cable trench cover construction device also includes a handle mechanism, which includes a mounting plate, a handle and a clamping rod, the handle is arranged on one side of the mounting plate, one end of the clamping rod is arranged at the other end of the mounting plate, the other end of the clamping rod is provided with a clamping portion, the guide column is provided with a clamping fitting portion, the clamping fitting portion extends along the axial direction of the guide column, the mounting seat is provided with a mounting through hole, the mounting through hole is connected to the mounting channel, the clamping rod is passed through the mounting through hole and can move back and forth along the axial direction of the mounting through hole, and the clamping portion can be clamped and fitted with the clamping fitting portion. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0024] Figure 1It is a schematic diagram of the overall structure of a cable trench cover construction device in one embodiment of the present application.

[0025] Figure 2 This is a schematic diagram of the working process of the cable trench cover construction device in one embodiment of the present application.

[0026] Figure 3 for Figure 1 A partial enlarged view of point A in the middle.

[0027] Figure 4 It is a cross-sectional view of a positioning member in one embodiment of the present application.

[0028] Figure 5 This is a structural schematic diagram from another angle of the cable trench cover construction device in one embodiment of the present application.

[0029] Figure 6 for Figure 5 A partial enlarged view of point B in the middle.

[0030] Figure 7 It is a side view of a cable trench cover construction device in one embodiment of the present application.

[0031] Figure 8 for Figure 7 A partial enlarged view of point C in the middle.

[0032] Fig. 9 It is a cross-sectional view of a mounting seat and a guide mechanism in one embodiment of the present application.

[0033] Notes on the attached drawings:

[0034] 100, support mechanism; 200, guide mechanism; 210, guide column; 211, guide channel; 212, guide port; 213, snap-fitting part; 300, mounting seat; 310, mounting channel; 320, guide seat; 330, guide wheel; 341, first roller; 342, second roller; 351, first auxiliary wheel; 352, second auxiliary wheel; 353, third auxiliary wheel; 400, winding mechanism; 410, rotating column; 420, first assembly rod; 421, first assembly part; 430, second assembly rod; 431, second assembly part; 440, holding rod; 450, third assembly part; 451, plug-in slot; 510 , the first hanging arm; 520, the second hanging arm; 530, the first winding member; 540, the second winding member; 550, the third winding member; 560, the fourth winding member; 610, the first traction member; 620, the second traction member; 700, the positioning member; 710, the first positioning portion; 711, the positioning through hole; 720, the second positioning portion; 721, the receiving groove; 730, the positioning pin; 731, the pull ring; 732, the first limiting plate; 733, the second limiting plate; 740, the positioning groove; 800, the grip mechanism; 810, the mounting plate; 820, the handle; 830, the clamping rod; 831, the clamping portion; 832, the third limiting plate; 900, the cover plate. DETAILED DESCRIPTION

[0035] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present application, so the present application is not limited by the specific embodiments disclosed below.

[0036] In the description of the present application, it should be understood that if the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential", etc. appear, the orientation or position relationship indicated by these terms is based on the orientation or position relationship shown in the accompanying drawings, which is only for the convenience of describing the present application and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application.

[0037] In addition, if the terms "first" or "second" appear, these terms are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, if the term "plurality" appears, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0038] In this application, unless otherwise clearly specified and limited, if the terms "installed", "connected", "connected", "fixed" and the like appear, these terms should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to the specific circumstances.

[0039] In the present application, unless otherwise clearly specified and limited, if there is a description that a first feature is "above" or "below" a second feature, etc., or similar descriptions appear, it may mean that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "above" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being "below", "below" and "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0040] It should be noted that if an element is referred to as being "fixed to" or "disposed on" another element, it may be directly on the other element or there may be a central element. If an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. If any, the terms "vertical", "horizontal", "upper", "lower", "left", "right" and similar expressions used in this application are for illustrative purposes only and do not represent the only implementation method.

[0041] See also Figure 1 to Figure 2An embodiment of the present application provides a cable trench cover construction device, including a support mechanism 100, a mounting seat 300, a winding mechanism 400, a first suspension arm 510, a second suspension arm 520, a first traction member 610 and a second traction member 620; the mounting seat 300 is arranged on the support mechanism 100 and can reciprocate along the first direction of the cable trench; the winding mechanism 400 is arranged on the mounting seat 300; one end of the first suspension arm 510 is arranged on one side of the mounting seat 300 along the second direction of the cable trench, and one end of the second suspension arm 520 is arranged on the other side of the mounting seat 300 along the second direction, the second direction is perpendicular to the first direction, and the first suspension arm A first winding member 530 is provided at one end of 510 away from the mounting seat 300, and a second winding member 540 is provided at one end of the second suspension arm 520 away from the mounting seat 300; one end of the first traction member 610 is provided on the winding mechanism 400, and the other end of the first traction member 610 bypasses the first winding member 530 and is used to connect with the cover plate 900; one end of the second traction member 620 is provided on the winding mechanism 400, and the other end of the second traction member 620 bypasses the second winding member 540 and is used to connect with the cover plate 900; the winding mechanism 400 can wind up or release the first traction member 610 and the second traction member 620 to lift or drop the cover plate 900.

[0042] When the cable trench cover construction device is used, the support mechanism 100 is first placed on the ground and straddles the cable trench along a first direction of the cable trench, and the end of the first traction member 610 away from the reeling mechanism 400 and the end of the second traction member 620 away from the reeling mechanism 400 are connected to the cable trench cover 900, and then the reeling mechanism 400 is controlled to reel in the first traction member 610 and the second traction member 620. At this time, the end of the first traction member 610 away from the reeling mechanism 400 that bypasses the first winding member 530 gradually approaches the first suspension arm 510, and the end of the second traction member 620 that bypasses the second winding member 540 gradually approaches the first suspension arm 510. The end of 20 away from the winding mechanism 400 gradually approaches the second boom 520 to lift the cover plate 900. Subsequently, the staff controls the mounting seat 300 to move along the first direction on the supporting mechanism 100, so that the first boom 510 and the second boom 520 drive the cover plate 900 to move, thereby driving the cover plate 900 away from the area above the cable trench. Compared with the conventional technology, the above-mentioned cable trench cover plate construction device can more conveniently move the cover plate 900 from above the cable trench to other areas, so as to facilitate the staff to inspect the cables in the cable trench and reduce the labor intensity of the staff.

[0043] For further information, see Figure 2After the cover plate 900 is moved from above the cable trench to other areas, the first traction member 610 and the second traction member 620 can be released by the reeling mechanism 400 to place the cover plate 900 on the ground, and then the cables in the cable trench can be inspected. In other embodiments, the first traction member 610 and the second traction member 620 can also be used to suspend the cover plate 900 in mid-air and inspect the cables. It can be flexibly selected according to the actual working conditions on site and is not specifically limited here.

[0044] Furthermore, the first suspension arm 510 and the second suspension arm 520 both extend along the second direction of the cable trench so as to more stably suspend the cover plate 900 on the cable trench.

[0045] As an explanation, in the above embodiment, the first direction of the cable trench is the width direction of the cable trench (i.e. Figure 1 The second direction of the cable trench is the length direction of the cable trench (i.e. Figure 1 E direction in the figure).

[0046] In one embodiment, the cable trench cover construction device also includes a guide mechanism 200, which is arranged on the support mechanism 100, and the mounting seat 300 is movably arranged on the guide mechanism 200. The guide mechanism 200 extends along the width direction of the cable trench so that the guide mechanism 200 can be set across the cable trench. The first suspension arm 510 and the second suspension arm 520 both extend along the length direction of the cable trench to lift the cover 900 on the cable trench more stably.

[0047] See also Figure 1 to Figure 2 In one embodiment, the support mechanism 100 includes a first support member and a second support member, and the first support member and the second support member are respectively disposed at opposite ends of the guide mechanism 200 along the first direction to stably support the guide mechanism 200.

[0048] Furthermore, the first support member and the second support member are both forked legs, and the structure is stable.

[0049] Furthermore, the first support member, the second support member and the guide mechanism 200 are all made of lightweight materials, such as aluminum alloy; without affecting the overall strength, the first support member and the second support member are provided with weight-reducing holes, thereby further reducing the overall weight of the cable trench cover construction device to facilitate carrying by staff.

[0050] In one embodiment, the guide mechanism 200 is provided with a guide rail extending along a first direction, and the mounting seat 300 cooperates with the guide rail and can reciprocate along the first direction.

[0051] Furthermore, the guide mechanism 200 is provided with a first driving member, which is drivingly connected to the mounting seat 300 and can drive the mounting seat 300 to reciprocate along the first direction.

[0052] See also Figure 1 and Figure 5 In one embodiment, the first winding member 530 includes a first winding wheel, and the second winding member 540 includes a second winding wheel, and the axial direction of the first winding wheel and the axial direction of the second winding wheel are both parallel to the first direction; in this way, when the winding mechanism 400 winds up or releases the first traction member 610 and the second traction member 620, the friction force exerted on the first traction member 610 and the second traction member 620 can be reduced, thereby increasing the service life of the first traction member 610 and the second traction member 620.

[0053] See also Figure 1 and Figure 5 In one embodiment, the first traction member 610 includes a first rope, and the second traction member 620 includes a second rope. The first rope and the second rope can be connected to the cover plate 900 through a hook, and the winding mechanism 400 can wind up or release the first rope and the second rope to lift or lower the cover plate 900.

[0054] Furthermore, a lifting hole for connecting with a lifting hook is usually reserved on the cover plate 900, so that the first rope and the second rope can lift the cover plate 900.

[0055] Optionally, the winding mechanism 400 may be a reel, a drum, etc., which is not specifically limited here.

[0056] Furthermore, the length of the first rope wound up in the winding mechanism 400 should be greater than the thickness of the cover plate 900 so that the cover plate 900 can be effectively lifted.

[0057] See also Figure 5 and Figure 6 In one embodiment, the winding mechanism 400 includes a rotating column 410 , one end of which is disposed on the mounting seat 300 , and one end of the first traction member 610 and one end of the second traction member 620 are both connected to the side wall of the rotating column 410 .

[0058] The rotating column 410 can rotate to wind the first traction member 610 and the second traction member 620 around the side wall of the rotating column 410, thereby realizing the winding and releasing of the first traction member 610 and the second traction member 620, with low implementation cost and reliable winding effect.

[0059] In one embodiment, the first boom 510 is further provided with a third winding member 550, and the fourth boom is further provided with a fourth winding member 560. The third winding member 550 is arranged at one end of the first boom 510 close to the mounting seat 300, and the first traction member 610 bypasses the first winding member 530. The fourth winding member 560 is arranged at one end of the second boom 520 close to the mounting seat 300, and the second traction member 620 bypasses the fourth winding member 560. In this way, when the rotating column 410 rotates and reels the first traction member 610 and the second traction member 620, it can prevent the first traction member 610 and the second traction member 620 from being offset and occupying a larger space, thereby improving the ease of use of the cable trench cover construction device.

[0060] Furthermore, the third winding member 550 includes a third winding wheel, and the fourth winding member 560 includes a fourth winding wheel. The axis direction of the third winding wheel and the axis direction of the fourth winding wheel are both parallel to the axis direction of the rotating column 410 .

[0061] In one embodiment, the winding mechanism 400 further includes a second driving member, which is disposed on the mounting seat 300 and is drivingly connected to the rotating column 410 , and is used to drive the rotating column 410 to rotate.

[0062] Furthermore, the second driving member is a driving motor.

[0063] See also Figure 5 and Figure 8 In one embodiment, the winding mechanism 400 also includes a first assembly rod 420 and a first assembly portion 421, one end of the first assembly rod 420 is arranged on the side wall of the rotating column 410, and at least two first assembly portions 421 are provided, and all the first assembly portions 421 are arranged on the first assembly rod 420 at intervals along the axial direction of the first assembly rod 420, and one end of the first traction member 610 is used to connect with one of the first assembly portions 421.

[0064] Since the length of the first traction member 610 is fixed, one end of the first traction member 610 is connected to different first assembly parts 421, so that the traction stroke of the first traction member 610 on the cover plate 900 can be adjusted; for example, one end of the first traction member 610 is connected to the first assembly part 421 close to the rotating column 410. At this time, the length of the portion of the first traction member 610 located between the first winding member 530 and the rotating column 410 becomes longer, and correspondingly, the length of the portion of the first traction member 610 located between the first winding member 530 and the cover plate 900 becomes shorter, thereby making the first traction member 610 on the cover plate 900 The traction stroke becomes shorter; for another example, one end of the first traction member 610 is connected to the first assembly portion 421 away from the rotating column 410. At this time, the length of the portion of the first traction member 610 located between the first winding member 530 and the rotating column 410 becomes shorter, and accordingly, the length of the portion of the first traction member 610 located between the first winding member 530 and the cover plate 900 will be lengthened, thereby increasing the length of the traction stroke of the first traction member 610 on the cover plate 900; with such a configuration, the traction stroke of the first traction member 610 on the cover plate 900 can be flexibly adjusted, so that the cable trench cover plate construction device can be suitable for more working conditions.

[0065] By way of explanation, since the cable trench is usually buried below the ground, there are differences in the distance between different cable trenches and the ground, which in turn leads to differences in the distance between the cable trench cover 900 and the first lifting arm 510 of different cable trenches; in the above embodiment, by connecting one end of the first traction member 610 to different first assembly parts 421, the traction stroke of the first traction member 610 on the cover 900 can be adjusted, so that the first traction member 610 can lift the cable trench cover 900 on different cable trenches, thereby improving the applicability of the cable trench cover 900 construction device.

[0066] See also Figure 5 and Figure 8 As an embodiment that can be implemented simultaneously with the above-mentioned embodiments, the winding mechanism 400 also includes a second assembly rod 430 and a second assembly portion 431, one end of the second assembly rod 430 is arranged on the side wall of the rotating column 410, and at least two second assembly portions 431 are provided, and all the second assembly portions 431 are arranged on the second assembly rod 430 at intervals along the axial direction of the second assembly rod 430, and one end of the second traction member 620 is used to be connected to one of the second assembly portions 431.

[0067] Similar to the first assembly rod 420 and the first assembly portion 421 , detailed description thereof will be omitted here.

[0068] Further, the first assembly rod 420 and the second assembly rod 430 are coaxially arranged.

[0069] In one embodiment, a hook is disposed at one end of the first traction member 610 and the second traction member 620 for connecting with the first assembly portion 421 and the second assembly portion 431 .

[0070] See also Figures 5 and 6 In one embodiment, the winding mechanism 400 also includes a holding rod 440, and the side wall of the rotating column 410 is provided with at least two third assembly parts 450, all of the third assembly parts 450 are arranged at intervals along the circumference of the rotating column 410, and one end of the holding rod 440 is used to connect with one of the third assembly parts 450.

[0071] The holding rod 440 can be connected to the third assembly part 450 on the side wall of the rotating column 410. In this way, the staff can rotate the rotating column 410 by holding the holding rod 440, which is a labor-saving process and has low implementation costs. At least two third assembly parts 450 are arranged at circumferential intervals along the rotating column 410. The rotation angle of the rotating column 410 is adjusted by connecting one end of the holding rod 440 to different third assembly parts 450, and then the rising height of the cable trench cover 900 is adjusted, so that the cable trench cover 900 is at a suitable height to facilitate the staff to inspect the cables in the cable trench.

[0072] According to the lever principle, the longer the gripping rod 440 is, the more labor is saved. In one embodiment, the length of the gripping rod 440 is 3.5 to 4.5 times the length of the first suspension arm 510 .

[0073] See also Figure 1 and Figure 5 In one embodiment, a gripping portion is further provided at one end of the gripping rod 440 away from the rotating column 410 for the staff to grip.

[0074] See also Figure 6 In one embodiment, the third assembly portion 450 is provided with an insertion groove 451 , and the insertion groove 451 is used to be inserted with one end of the holding rod 440 .

[0075] One end of the holding rod 440 can be plugged into the plug-in slot 451 of the third assembly portion 450 to achieve connection between the holding rod 440 and the third assembly portion 450 , and the connection effect is reliable and easy to assemble and disassemble.

[0076] See also Figure 1 In one embodiment, the first suspension arm 510 is provided with a positioning member 700 , and the positioning member 700 is used to position and cooperate with the holding rod 440 .

[0077] When the holding rod 440 rotates to the positioning member 700, the positioning member 700 can be positioned and cooperated with the holding rod 440 to limit the holding rod 440 from continuing to rotate. In this way, when the staff controls the holding rod 440 to rotate to lift the cover 900, the positioning member 700 can limit the rotation of the holding rod 440 to continue to lift the cover 900, which is convenient for driving the cover 900 to move through the mounting seat 300. The implementation process is convenient and highly safe.

[0078] See also Figure 3 to Figure 4 In one embodiment, the positioning member 700 includes a first positioning portion 710, a second positioning portion 720 and a positioning pin 730. The first positioning portion 710 and the second positioning portion 720 are spaced apart along the axial direction of the rotating column 410. The first positioning portion 710, the first suspension arm 510 and the second positioning portion 720 are surrounded to form a positioning groove 740. The positioning groove 740 is used to accommodate the holding rod 440. The first positioning portion 710 is provided with a positioning through hole 711. The positioning pin 730 is penetrated through the positioning through hole 711 and can reciprocate along the axial direction of the positioning through hole 711, so that the positioning pin 730 can open or close the notch of the positioning groove 740.

[0079] When the holding rod 440 is rotated into the positioning groove 740, the positioning pin 730 is moved and the notch of the positioning groove 740 is closed. At this time, the side wall of the positioning pin 730 abuts against the holding rod 440 in the positioning groove 740, thereby preventing the holding rod 440 from falling out of the positioning groove 740, so as to continuously lift the cover plate 900, thereby facilitating driving the cover plate 900 away from the area above the cable trench; after the cable maintenance is completed, the positioning pin 730 is moved and the notch of the positioning groove 740 is opened, and then the holding rod 440 is removed from the positioning groove 740, and the cover plate 900 is lowered to seal the cable trench; with such a configuration, the implementation cost is low and the positioning effect of the holding rod 440 is reliable.

[0080] See also Figure 3 to Figure 4 In one embodiment, the positioning pin 730 includes a pull ring 731, a first limit plate 732, a second limit plate 733 and a pin body. The first limit plate 732 and the second limit plate 733 are respectively arranged at the opposite ends of the pin body. The pull ring 731 is arranged on the first limit plate 732. The pin body is penetrated by the positioning through hole 711 and can reciprocate along the axial direction of the positioning through hole 711. The diameter of the first limit plate 732 and the diameter of the second fiberboard are both larger than the aperture of the positioning through hole 711 to prevent the positioning pin 730 from detaching.

[0081] Furthermore, the second positioning portion 720 defines a receiving groove 721 , and the receiving groove 721 is used to accommodate the second limiting plate 733 .

[0082] In addition, in other embodiments, at least two positioning members 700 are provided, wherein one positioning member 700 is provided on the first boom 510 and the other positioning member 700 is provided on the second boom 520. Thus, no matter whether the holding rod 440 is rotated clockwise or counterclockwise, it can be positioned with the positioning member 700, thereby making the operation process of the cable trench cover construction device more convenient.

[0083] See also Figures 5 to 9 In one embodiment, the mounting seat 300 is provided with a mounting channel 310, the inner wall of the mounting channel 310 is provided with a guide seat 320, the guide seat 320 is provided with a guide wheel 330, the cable trench cover construction device also includes a guide mechanism 200, the guide mechanism 200 includes a guide column 210, the guide column 210 is penetrated through the mounting channel 310 and is provided with a guide channel 211, the side wall of the guide column 210 is provided with a guide opening 212 connected to the guide channel 211, the guide channel 211 and the guide opening 212 both extend along the first direction, the guide seat 320 is penetrated through the guide opening 212, the guide wheel 330 is located in the guide channel 211 and rollingly cooperates with the side wall of the guide channel 211.

[0084] The guide column 210 is passed through the installation channel 311 of the installation seat 300, and the inner wall of the installation channel 310 is provided with a guide seat 320, and the guide seat 320 is passed through the guide opening 212 of the guide column 210, so that the guide wheel 330 on the guide seat 320 is set in the guide channel 211, and the guide wheel 330 rolls with the side wall of the guide channel 211, so that the installation seat 300 can reciprocate along the first direction on the guide column 210, and the movement process is stable and reliable.

[0085] Furthermore, by passing the guide seat 320 through the guide opening 212 and making the guide wheel 330 roll with the side wall of the guide channel 211 , the guide wheel 330 can be prevented from falling off from the guide opening 212 , thereby further improving the movement stability of the mounting seat 300 .

[0086] In one embodiment, the length of the guide column 210 is 2.2-2.5 times the width of the cover plate 900. In this way, the length of the guide column 210 can be reduced while ensuring the effective movement of the cover plate 900, thereby reducing the overall weight and facilitating carrying.

[0087] See also Figure 6 and Fig. 9 In one embodiment, a first roller 341 is provided on one side of the mounting seat 300 along the first direction, and a second roller 342 is provided on the other side of the mounting seat 300 along the first direction. The axis of the first roller 341 and the axis of the second roller 342 are both perpendicular to the second direction, and the first roller 341 and the second roller 342 are both rollingly engaged with the outer wall of the guide column 210.

[0088] The first roller 341 and the second roller 342 are respectively disposed on opposite sides of the mounting base 300 along the first direction, so that the mounting base 300 can be prevented from swinging when moving on the guide column 210, making the moving stroke of the mounting base 300 on the guide column 210 more stable.

[0089] For further information, see Figure 6 , Figure 8 and Fig. 9 The guide column 210 is in the shape of a quadrangular prism, and the guide opening 212 is opened on a side wall of the guide column 210 facing the ground (hereinafter referred to as the guide side wall), and the guide seat 320 is penetrated through the guide opening 212 to set the guide wheel 330 in the guide channel 211, and the guide wheel 330 can achieve rolling cooperation with the guide side wall, thereby realizing the movement of the mounting seat 300; in addition, the first roller 341 and the second roller 342 can achieve rolling cooperation with the guide side wall, so that the guide side wall can be clamped between the guide wheel 330 and the first roller 341 and the second roller 342, thereby further improving the movement stability of the mounting seat 300.

[0090] See also Fig. 9 In one embodiment, at least two guide seats 320 are provided and are spaced apart along the first direction, and at least two guide wheels 330 are provided and are arranged one-to-one with the guide seats 320 .

[0091] See also Figure 6 and Figure 8 In one embodiment, the inner wall of the installation channel 310 is further provided with a first auxiliary wheel 351, a second auxiliary wheel 352 and a third auxiliary wheel 353. The first auxiliary wheel 351, the second auxiliary wheel 352 and the third auxiliary wheel 353 respectively roll with the three side walls of the guide column 210 except the guide side wall, thereby further improving the movement stability of the mounting base 300.

[0092] Further, at least two first auxiliary wheels 351 are provided and are spaced apart along the first direction, at least two second auxiliary wheels 352 are provided and are spaced apart along the first direction, and at least two third auxiliary wheels 353 are provided and are spaced apart along the first direction.

[0093] See also Figure 1 , Figure 8 and Fig. 9In one embodiment, the cable trench cover construction device also includes a handle mechanism 800, which includes a mounting plate 810, a handle 820 and a clamping rod 830. The handle 820 is arranged on one side of the mounting plate 810, one end of the clamping rod 830 is arranged on the other end of the mounting plate 810, and the other end of the clamping rod 830 is provided with a clamping portion 831. The guide column 210 is provided with a clamping fitting portion 213, and the clamping fitting portion 213 extends along the axial direction of the guide column 210. The mounting seat 300 is provided with a mounting through hole, which is connected to the mounting channel 310. The clamping rod 830 is penetrated through the mounting through hole and can move back and forth along the axial direction of the mounting through hole. The clamping portion 831 can be clamped and matched with the clamping fitting portion 213.

[0094] With such arrangement, the staff can not only drive the mounting seat 300 to move along the first direction by holding the handle 820, but also drive the clamping rod 830 to move back and forth along the axial direction of the mounting through hole by pulling the handle 820, so that the end of the clamping rod 830 away from the mounting plate 810 can be clamped with the clamping fitting part 213, thereby realizing the positioning of the mounting seat 300, preventing the mounting seat 300 from moving on the guide column 210 when the cable trench cover construction device lifts or lowers the cover 900, thereby improving the ease of use of the cable trench cover construction device.

[0095] See also Figure 1 and Fig. 9 In one embodiment, the snap-fitting portion 831 includes a snap-fitting protrusion, and the snap-fitting mating portion 213 includes a plurality of snap-fitting grooves spaced apart along the axial direction of the guide column 210. The staff realizes the assembly between the snap-fitting protrusion and the snap-fitting groove by lifting the handle 820, thereby realizing the positioning of the mounting seat 300.

[0096] See also Figure 1 In one embodiment, the handle 820 is made of hard plastic to reduce the overall weight, and the handle 820 is an inverted U-shaped handle 820.

[0097] See also Fig. 9 In one embodiment, a third limiting plate 832 is provided on the side wall of the clamping rod 830 , and the third limiting plate 832 can limit the clamping rod 830 from escaping from the installation channel 310 .

[0098] The technical features of the above embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0099] The above embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.

Claims

1. A cable trench cover construction device, characterized in that: include: Support mechanism; A mounting seat, the mounting seat is arranged on the supporting mechanism and can reciprocate along a first direction of the cable trench; A winding mechanism, the winding mechanism being arranged on the mounting seat; A first suspension arm and a second suspension arm, wherein one end of the first suspension arm is disposed on one side of the mounting seat along a second direction of the cable trench, and one end of the second suspension arm is disposed on the other side of the mounting seat along the second direction, the second direction being perpendicular to the first direction, a first winding member is disposed on one end of the first suspension arm away from the mounting seat, and a second winding member is disposed on one end of the second suspension arm away from the mounting seat; A first traction member and a second traction member, one end of the first traction member is arranged on the winding mechanism, the other end of the first traction member bypasses the first winding member and is used to connect with the cover plate, one end of the second traction member is arranged on the winding mechanism, the other end of the second traction member bypasses the second winding member and is used to connect with the cover plate, the winding mechanism can wind up or release the first traction member and the second traction member to lift or drop the cover plate.

2. The cable trench cover construction device according to claim 1, characterized in that: The winding mechanism comprises a rotating column, one end of which is arranged on the mounting seat, and one end of the first traction member and one end of the second traction member are both connected to the side wall of the rotating column.

3. The cable trench cover construction device according to claim 2, characterized in that: The winding mechanism further comprises a first assembly rod and a first assembly portion, one end of the first assembly rod is arranged on the side wall of the rotating column, at least two first assembly portions are provided, all of the first assembly portions are arranged on the first assembly rod at intervals along the axial direction of the first assembly rod, and one end of the first traction member is used to connect with one of the first assembly portions; or / and, The winding mechanism also includes a second assembly rod and a second assembly part, one end of the second assembly rod is arranged on the side wall of the rotating column, and at least two second assembly parts are provided, and all of the second assembly parts are arranged on the second assembly rod at intervals along the axial direction of the second assembly rod, and one end of the second traction member is used to be connected to one of the second assembly parts.

4. The cable trench cover construction device according to claim 2, characterized in that: The winding mechanism also includes a holding rod, and the side wall of the rotating column is provided with at least two third assembly parts, all of which are arranged at intervals along the circumference of the rotating column, and one end of the holding rod is used to connect with one of the third assembly parts.

5. The cable trench cover construction device according to claim 4, characterized in that: The third assembly portion is provided with an inserting groove, and the inserting groove is used for inserting with one end of the holding rod.

6. The cable trench cover construction device according to claim 4, characterized in that: The first suspension arm is provided with a positioning piece, and the positioning piece is used for positioning and cooperating with the holding rod.

7. The cable trench cover construction device according to claim 6, characterized in that: The positioning member includes a first positioning portion, a second positioning portion and a positioning pin, the first positioning portion and the second positioning portion are spaced apart along the axial direction of the rotating column, the first positioning portion, the first suspension arm and the second positioning portion are surrounded to form a positioning groove, the positioning groove is used to accommodate the holding rod, the first positioning portion is provided with a positioning through hole, the positioning pin is passed through the positioning through hole and can reciprocate along the axial direction of the positioning through hole, so that the positioning pin can open or close the notch of the positioning groove.

8. The cable trench cover construction device according to claim 1, characterized in that: The mounting seat is provided with a mounting channel, the inner wall of the mounting channel is provided with a guide seat, the guide seat is provided with a guide wheel, the cable trench cover construction device also includes a guide mechanism, the guide mechanism includes a guide column, the guide column is passed through the mounting channel and is provided with a guide channel, the side wall of the guide column is provided with a guide opening connected to the guide channel, the guide channel and the guide opening both extend along the first direction, the guide seat is passed through the guide opening, the guide wheel is located in the guide channel and rollingly cooperates with the side wall of the guide channel.

9. The cable trench cover construction device according to claim 8, characterized in that: A first roller is provided on one side of the mounting seat along the first direction, and a second roller is provided on the other side of the mounting seat along the first direction. The axes of the first roller and the second roller are both perpendicular to the second direction, and the first roller and the second roller are both rollingly engaged with the outer wall of the guide column.

10. The cable trench cover construction device according to claim 8, characterized in that: The cable trench cover construction device also includes a handle mechanism, which includes a mounting plate, a handle and a clamping rod, the handle is arranged on one side of the mounting plate, one end of the clamping rod is arranged at the other end of the mounting plate, the other end of the clamping rod is provided with a clamping portion, the guide column is provided with a clamping fitting portion, the clamping fitting portion extends along the axial direction of the guide column, the mounting seat is provided with a mounting through hole, the mounting through hole is connected to the mounting channel, the clamping rod is passed through the mounting through hole and can move back and forth along the axial direction of the mounting through hole, and the clamping portion can be clamped and fitted with the clamping fitting portion.

Citation Information

Patent Citations

  • Well lid lifting device for municipal engineering construction

    CN112694017A

  • Well lid lifting-taking device for information and communication engineering construction and lifting-taking method thereof

    CN113071993A

  • Stainless steel metal part passivation equipment and application method thereof

    CN114411133A

  • Omnidirectional moving crane used for high rise building construction

    JP1998245189A