Infrastructure management system based on big data

By designing an infrastructure management system based on big data, the problem of coordinated drainage and subsequent drainage adjustment of multiple urban drainage outlets in the existing technology is solved, and the coordinated adjustment and fault monitoring of the drainage system are realized, which improves the stability and safety of the drainage system.

CN120087618AInactive Publication Date: 2025-06-03CHENYANG YUEZHUN TECHNOLOGY CO LTD
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202510392754.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-31
Publication Date
2025-06-03
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology is difficult to achieve coordinated drainage of multiple urban drainage outlets, and there is a lack of early adjustment of subsequent drainage conditions and monitoring methods for drainage equipment failure, resulting in poor urban drainage and may cause serious problems such as floods.

Method used

Design an infrastructure management system based on big data, including map construction module, data acquisition module, processing module, fault monitoring module and information feedback module, build a visual map through GIS technology, collect and process drainage flow rate and flow data, adjust drainage equipment, judge faults and feedback information.

Benefits of technology

Coordinated drainage and pre-regulation of urban drainage outlets has been achieved, drainage risks have been reduced, and equipment failures have been discovered in a timely manner through fault monitoring, improving the stability and safety of the drainage system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120087618A_ABST
    Figure CN120087618A_ABST
Patent Text Reader

Abstract

An infrastructure management system based on big data relates to the technical field of data processing and comprises a master control center which is in communication connection with a map construction module, a data acquisition module, a first processing module, a second processing module, a fault monitoring module and an information feedback module. The map construction module is used for constructing a visual map; the data acquisition module is used for acquiring drainage flow velocity and drainage flow; the first processing module is used for obtaining a drainage state, adjusting drainage equipment, obtaining a drainage coefficient and selecting whether collaborative drainage is carried out or not; the second processing module is used for obtaining the variation trend of a drainage coefficient and pre-adjusting drainage equipment; the fault monitoring module is used for judging whether the drainage equipment has a fault and generating equipment fault information; the information feedback module is used for feeding back equipment fault information; a targeted drainage mechanism can be formed, and the drainage equipment which breaks down can be found in time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of data processing, and in particular to an infrastructure management system based on big data. Background Art

[0002] Urban drainage outlets mainly involve facilities such as gates, drainage pumps, drainage pipes, sewage treatment plants, etc. Affected by factors such as weather, drainage volume, pipeline leakage, and upstream and downstream linkage of pumps, how to manage urban drainage well is an important livelihood project. Among many safety risks, floods are the most frequent and serious in cities. Poor urban drainage often leads to waterlogging or water gushing inside the city, causing serious impacts and losses to the surrounding environment and facilities; In the prior art, the treatment methods for urban drainage are often limited to a single drainage outlet, failing to achieve coordinated drainage of multiple drainage outlets, and are also limited to the current drainage situation, failing to achieve advance adjustment of subsequent drainage situations. Moreover, in the prior art, there is a lack of a method for fault monitoring of drainage equipment based on drainage adjustment. In view of the deficiencies of the prior art, the present invention provides an infrastructure management system based on big data. Summary of the Invention

[0003] The purpose of the present invention is to provide an infrastructure management system based on big data.

[0004] The purpose of the present invention can be achieved by the following technical solutions: An infrastructure management system based on big data, including a main control center, which is communicatively connected to a map construction module, a data acquisition module, a first processing module, a second processing module, a fault monitoring module, and an information feedback module; The map construction module is used to construct a visualization map of urban drainage outlets by using GIS technology; The data acquisition module is used to collect and store the drainage velocity and drainage flow of urban drainage outlets; The first processing module is used to obtain the drainage state of the drainage velocity and drainage flow, adjust the drainage equipment according to the obtained drainage state, and obtain the drainage coefficient of urban drainage outlets, and select whether to perform coordinated drainage according to the obtained drainage coefficient; The second processing module is used to obtain the change trend of the drainage coefficient and pre-adjust the drainage equipment according to the obtained change trend; The fault monitoring module is used to construct a digital twin model of urban drainage outlets, obtain the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage equipment, judge whether there is a fault in the drainage equipment according to the comparison result of the two change diagrams, and generate equipment fault information; The information feedback module is used to feedback the generated equipment fault information to the staff.

[0005] Furthermore, the process of the map construction module constructing a visualization map of urban drainage outlets using GIS technology includes: Collect the basic information of urban drainage outlets, construct a visualization map of urban drainage outlets based on the collected basic information using GIS technology, and allow staff to view the constructed visualization map through a mobile terminal.

[0006] Furthermore, the process of the data collection module collecting and storing the drainage velocity and drainage flow of urban drainage outlets includes: The urban drainage outlets include two types of drainage devices, namely gates and drainage pumps. Set a velocity monitoring unit and a flow monitoring unit to obtain the drainage velocity and drainage flow of urban drainage outlets through the velocity monitoring unit and the flow monitoring unit respectively; Set up a database, upload the obtained drainage velocity and drainage flow to the database for storage, and upload them to the visualization map for synchronization.

[0007] Furthermore, the process of the first processing module obtaining the drainage status of the drainage velocity and drainage flow and adjusting the drainage devices according to the obtained drainage status includes: Obtain the velocity range and flow range at different times, compare the drainage velocity and drainage flow with their corresponding velocity range and flow range, and mark the drainage velocity and drainage flow as different drainage statuses according to the comparison results; There are three levels of opening degrees set inside the gate, and there are three levels of drainage powers set inside the drainage pump. Set different opening degrees and drainage powers for the drainage velocity and drainage flow in different drainage statuses, and upload the obtained drainage status and the opening degrees and drainage powers of the drainage devices to the visualization map for synchronization.

[0008] Furthermore, the process of the first processing module obtaining the drainage coefficient of urban drainage outlets and selecting whether to perform coordinated drainage according to the obtained drainage coefficient includes: Set drainage weights for the drainage velocity and drainage flow respectively, obtain the drainage coefficient of urban drainage outlets at different times, set a drainage threshold, compare the drainage coefficient with the drainage threshold, and select whether to perform coordinated drainage according to the comparison results; For urban drainage outlets that require coordinated drainage, obtain the coordinated drainage outlets of the urban drainage outlet, and increase the opening degrees of the gates and the drainage powers of the drainage pumps of all coordinated drainage outlets by one level to achieve coordinated drainage.

[0009] Furthermore, the process of the second processing module obtaining the change trend of the drainage coefficient and pre-adjusting the drainage devices according to the obtained change trend includes: Set an evaluation period, mark the drainage coefficient obtained when reaching an evaluation period as the evaluation coefficient, obtain the change coefficient of the drainage coefficient based on the evaluation coefficients in several recent evaluation periods, set a change threshold, compare the change coefficient with the change threshold, and obtain the change trend of the drainage coefficient according to the comparison result. The change trend includes a downward trend and an upward trend; For the drainage coefficient with a downward trend, reduce the opening degree of its gate and the drainage power of the drainage pump by one level. For the drainage coefficient with an upward trend, increase the opening degree of its gate and the drainage power of the drainage pump by one level. At the same time, upload the obtained drainage coefficient and change trend to the visualization map for synchronization.

[0010] Further, the process by which the fault monitoring module constructs a digital twin model of the urban drainage outlet and obtains the theoretical adjustment change diagram and actual adjustment change diagram of the drainage equipment includes: Set a model construction unit. Through the model construction unit, collect the equipment information of the drainage equipment, respectively construct the physical model and behavior model of the drainage equipment according to the equipment information, and integrate the physical model and behavior model to obtain the digital twin model of the drainage equipment; In the digital twin model, monitor the drainage flow velocity, drainage flow rate before adjustment, after adjustment, and during the adjustment process of the drainage equipment, construct the theoretical adjustment change diagram of the drainage flow velocity and drainage flow rate. In actual situations, construct the actual adjustment change diagram of the drainage flow velocity and drainage flow rate in the same way.

[0011] Further, the process by which the fault monitoring module determines whether there is a fault in the drainage equipment based on the comparison result of the two change diagrams and generates equipment fault information includes: Compare the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage flow velocity and drainage flow rate, and determine whether there is a fault in the drainage equipment based on the comparison result, and generate corresponding type I fault information, type II fault information, type III fault information, and type IV fault information.

[0012] Further, the process by which the information feedback module feeds back the generated equipment fault information to the staff includes: Feed back the generated equipment fault information to the staff, and the staff processes the drainage equipment according to the obtained equipment fault information. The equipment fault information includes type I fault information, type II fault information, type III fault information, and type IV fault information.

[0013] Compared with the prior art, the beneficial effects of the present invention are: 1. By collecting the drainage velocity and drainage flow rate of urban drainage outlets and obtaining their drainage states, and taking different opening degrees and drainage powers for drainage according to the drainage states, it is beneficial to form a targeted drainage mechanism; 2. By obtaining the drainage coefficient and its change trend, and carrying out coordinated drainage and pre-adjustment on urban drainage outlets, on the one hand, it can relieve the drainage pressure of a single drainage outlet, and on the other hand, it can handle the subsequent drainage situation in advance, which is beneficial to reducing potential drainage risks; 3. By obtaining the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage equipment, and judging whether there is a fault in the drainage equipment according to the comparison result of the two, it can realize the fault monitoring of the drainage equipment and timely detect the drainage equipment with faults. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is the schematic diagram of the present invention. DETAILED DESCRIPTION OF THE EMBODIMENTS

[0015] As Figure 1 shown, an infrastructure management system based on big data includes a main control center, and the main control center is communicatively connected with a map construction module, a data collection module, a first processing module, a second processing module, a fault monitoring module, and an information feedback module; The map construction module is used to construct a visual map of urban drainage outlets by using GIS technology; The data collection module is used to collect and store the drainage velocity and drainage flow rate of urban drainage outlets; The first processing module is used to obtain the drainage states of the drainage velocity and drainage flow rate, adjust the drainage equipment according to the obtained drainage states, and obtain the drainage coefficient of urban drainage outlets, and select whether to carry out coordinated drainage according to the obtained drainage coefficient; The second processing module is used to obtain the change trend of the drainage coefficient and pre-adjust the drainage equipment according to the obtained change trend; The fault monitoring module is used to construct a digital twin model of urban drainage outlets, obtain the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage equipment, judge whether there is a fault in the drainage equipment according to the comparison result of the two change diagrams, and generate equipment fault information; The information feedback module is used to feedback the generated equipment fault information to the staff.

[0016] It should be further noted that in the specific implementation process, the process of the map construction module constructing a visual map of urban drainage outlets by using GIS technology includes: Set up a map construction unit to collect the basic information of urban drainage outlets through the map construction unit. The basic information includes but is not limited to urban terrain data, rainwater drainage network data, sewer network data, building and road data; Use GIS technology to construct a visualization map of urban drainage outlets based on the collected basic information of urban drainage outlets. Staff can view the constructed visualization map through a mobile terminal. At this time, the constructed visualization map only includes the basic information of urban drainage outlets and does not include other data of urban drainage outlets.

[0017] It should be further noted that in the specific implementation process, the process of the data acquisition module collecting and storing the drainage velocity and drainage flow of urban drainage outlets includes: The urban drainage outlet needs to include at least two drainage devices, namely a gate and a drainage pump. A flow velocity monitoring unit is set at the gate to collect the drainage velocity of the urban drainage outlet through the flow velocity monitoring unit, and the collected drainage velocity is marked as S. A flow monitoring unit is set at the drainage pump to collect the drainage flow of the urban drainage outlet through the flow monitoring unit, and the collected drainage flow is marked as L; Set up a database. The main control center audits the collected drainage velocity and drainage flow, uploads the audited drainage velocity and drainage flow to the database for storage, and simultaneously uploads the stored drainage velocity and drainage flow to the visualization map for synchronization.

[0018] It should be further noted that in the specific implementation process, the process of the first processing module obtaining the drainage state of the drainage velocity and drainage flow and adjusting the drainage device according to the obtained drainage state includes: Obtain the drainage velocity and drainage flow of all urban drainage outlets at the same moment, mark the average value of the drainage velocity and drainage flow of all urban drainage outlets as the velocity average value and flow average value at this moment, and mark the obtained velocity average value and flow average value as S 均 and L 均 ; Taking the drainage velocity as an example, obtain the corresponding velocity range according to the obtained velocity average value, and mark the obtained velocity range as [S 均 -s, S 均 +s], where s is a preset fixed value. Compare the obtained drainage velocity with its corresponding velocity range, and mark the drainage velocity as different drainage states according to the comparison result; If S < S 均 -s, then mark it as a low velocity state. If S 均 -s ≤ S ≤ S 均 +s, then mark it as a high velocity state. If S > S均 If it is +s, it is marked as the high flow rate state; There are three levels of opening degrees set inside the gate, namely the first opening degree, the second opening degree, and the third opening degree. Among them, the first opening degree is less than the second opening degree which is less than the third opening degree. There are three levels of drainage powers set inside the drainage pump, namely the first drainage power, the second drainage power, and the third drainage power. Among them, the first drainage power is less than the second drainage power which is less than the third drainage power; Taking the drainage flow rate as an example, for the drainage flow rate in the low flow rate state, set the opening degree of its gate to the first opening degree. For the drainage flow rate in the medium flow rate state, set the opening degree of its gate to the second opening degree. For the drainage flow rate in the high flow rate state, set the opening degree of its gate to the third opening degree; And so on, use the same method to obtain the flow rate range [L 均 -l, L 均 +l], where l is a preset fixed value, and mark it as different drainage states, including the low flow state, the medium flow state, and the high flow state. Set the corresponding drainage power for the drainage flow rate in different drainage states, and at the same time upload the obtained drainage state, the opening degree of the drainage equipment, and the drainage power to the visualization map for synchronization.

[0019] It should be further noted that in the specific implementation process, the process by which the first processing module obtains the drainage coefficient of the urban drainage outlet and selects whether to perform collaborative drainage based on the obtained drainage coefficient includes: Set drainage weights for the drainage flow rate and the drainage flow volume obtained at the same moment respectively. Set the drainage weight of the drainage flow rate to Q s , and set the drainage weight of the drainage flow volume to Q l , obtain the drainage coefficient of the urban drainage outlet at this moment, and mark the obtained drainage coefficient as P;

[0020] Set the drainage threshold P 0 , compare the obtained drainage coefficient with the set drainage threshold, and select whether to perform collaborative drainage according to the comparison result. If P < P 0 , then do not perform collaborative drainage. If P ≥ P 0 , then perform collaborative drainage; For urban drainage outlets that require coordinated drainage, a circular area with a radius of a preset distance R is constructed centered on it. All other urban drainage outlets within this circular area are regarded as the coordinated drainage outlets of this urban drainage outlet. The opening degrees of the gates and the drainage powers of the drainage pumps of all coordinated drainage outlets are increased by one level to achieve coordinated drainage. After the drainage coefficient drops below the drainage threshold, it is restored to its original level.

[0021] It should be further noted that in the specific implementation process, the process of the second processing module obtaining the change trend of the drainage coefficient and pre-adjusting the drainage equipment according to the obtained change trend includes: Set an evaluation period, mark the evaluation period, denoted as k, where k = 1, 2,.... It should be further noted that in the specific implementation process, k represents the current evaluation period, and k - 1 represents the previous evaluation period; When an evaluation period is reached, record the obtained drainage coefficient, and mark the recorded drainage coefficient as the evaluation coefficient, denoted as P k , obtain the change coefficient of the drainage coefficient based on the evaluation coefficients within the most recent k evaluation periods, and denote the obtained change coefficient as B Pk ;

[0022] Set the change threshold B P0 , compare the obtained change coefficient with the set change threshold, and obtain the change trend of the drainage coefficient according to the comparison result. The change trend includes a downward trend and an upward trend; When |B Pk - B Pk-1 | ≤ B P0 , mark it as a normal change; When |B Pk - B Pk-1 | > B P0 , mark it as an abnormal change, and compare the parameter values of P k and P k-1 ; When P k < P k-1 , mark the drainage coefficient as a downward trend; When P k > P k-1 , mark the drainage coefficient as an upward trend; For the drainage coefficient with a downward trend, reduce the opening degrees of its gates and the drainage powers of its drainage pumps by one level. For the drainage coefficient with an upward trend, increase the opening degrees of its gates and the drainage powers of its drainage pumps by one level. At the same time, upload the obtained drainage coefficient and change trend to the visualization map for synchronization.

[0023] It should be further noted that in the specific implementation process, the process by which the fault monitoring module constructs a digital twin model of the urban drainage outlet and obtains the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage equipment includes: Set up a model construction unit to collect the equipment information of the drainage equipment through the model construction unit. The equipment information includes the specification parameters, process parameters, historical data, environmental data, and maintenance data of the drainage equipment; Construct a physical model of the drainage equipment according to the obtained specification parameters and process parameters, construct a behavior model of the drainage equipment according to the obtained historical data, environmental data, and maintenance data, and integrate the constructed physical model and behavior model to obtain a digital twin model of the drainage equipment; In the digital twin model, when the drainage equipment starts to be adjusted, monitor the drainage flow rate, drainage volume before, after, and during the adjustment. Taking the drainage flow rate as an example, construct a theoretical adjustment change diagram with the horizontal coordinate being time and the vertical coordinate being the drainage flow rate according to the monitored drainage flow rate. Use the same method to monitor the drainage flow rate in the actual situation and construct the corresponding actual adjustment change diagram. Use the same method to obtain the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage volume.

[0024] It should be further noted that in the specific implementation process, the process by which the fault monitoring module determines whether there is a fault in the drainage equipment according to the comparison result of the two change diagrams and generates equipment fault information includes: Taking the drainage flow rate as an example, compare the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage flow rate. If the actual adjustment change diagram can adjust the drainage flow rate to the level of the theoretical adjustment change diagram, it is determined that the gate is free of faults. If not, it is determined that the gate has faults and generates a type I fault information. If the time required for the actual adjustment change diagram to make the adjustment is the same as that of the theoretical adjustment change diagram, it is determined that the gate is free of faults. If different, it is determined that the gate has faults and generates a type II fault information; And so on, use the same method to compare the theoretical adjustment change diagram and the actual adjustment change diagram of the drainage volume, determine whether there is a fault in the drainage pump according to the comparison result, and generate the corresponding type III fault information and type IV fault information. The type I fault information, type II fault information, type III fault information, and type IV fault information all belong to the equipment fault information.

[0025] It should be further noted that in the specific implementation process, the process by which the information feedback module feeds back the generated equipment fault information to the staff includes: Feedback the generated device fault information to the staff, and the staff will further process the drainage equipment according to the obtained device fault information. The device fault information includes the first-class fault information, second-class fault information, third-class fault information, and fourth-class fault information.

[0026] The above embodiments are only used to illustrate the technical method of the present invention and not to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those of ordinary skill in the art should understand that the technical method of the present invention can be modified or equivalently replaced without departing from the spirit and scope of the technical method of the present invention.

Claims

1. An infrastructure management system based on big data, including a main control center, characterized in that: The main control center is communicatively connected with a map construction module, a data acquisition module, a first processing module, a second processing module, a fault monitoring module, and an information feedback module; The map construction module is used to construct a visual map of urban drainage outlets using GIS technology; The data acquisition module is used to collect and store the drainage velocity and drainage flow rate of the urban drainage outlet; The first processing module is used to obtain the drainage state of the drainage velocity and drainage flow, adjust the drainage equipment according to the obtained drainage state, and obtain the drainage coefficient of the urban drainage outlet, and select whether to perform coordinated drainage according to the obtained drainage coefficient; The second processing module is used to obtain the variation trend of the drainage coefficient and pre-adjust the drainage equipment according to the obtained variation trend; The fault monitoring module is used to construct a digital twin model of the urban drainage outlet, and obtain a theoretical adjustment change diagram and an actual adjustment change diagram of the drainage equipment, judge whether the drainage equipment has a fault according to the comparison results of the two change diagrams, and generate equipment fault information; The information feedback module is used to feed back the generated equipment failure information to the staff.

2. The infrastructure management system based on big data according to claim 1, characterized in that: The process of the map construction module using GIS technology to construct a visual map of urban drainage outlets includes: The basic information of urban drainage outlets is collected, and a visual map of the urban drainage outlets is constructed based on the collected basic information using GIS technology. The staff views the constructed visual map through mobile terminals.

3. The infrastructure management system based on big data according to claim 2, characterized in that: The process of the data acquisition module collecting and storing the drainage velocity and drainage flow rate of the urban drainage outlet includes: The urban drainage outlet comprises two drainage devices, a gate and a drainage pump, and is provided with a flow rate monitoring unit and a flow rate monitoring unit, through which the drainage flow rate and drainage flow rate of the urban drainage outlet are respectively obtained; Set up a database, upload the obtained drainage velocity and drainage flow to the database for storage, and upload them to the visualization map for synchronization.

4. The infrastructure management system based on big data according to claim 3, characterized in that: The first processing module obtains the drainage state of the drainage flow rate and the drainage flow rate, and the process of adjusting the drainage equipment according to the obtained drainage state includes: Obtaining flow velocity ranges and flow rate ranges at different times, comparing the drainage flow velocity and drainage flow rate with their corresponding flow velocity ranges and flow rate ranges, and marking the drainage flow velocity and drainage flow rate as different drainage states according to the comparison results; The gate is provided with three levels of opening and closing degrees, and the drainage pump is provided with three levels of drainage power. Different opening and closing degrees and drainage powers are set for drainage flow rates and drainage flows in different drainage states. The obtained drainage states and the opening and closing degrees and drainage powers of the drainage equipment are uploaded to the visual map for synchronization.

5. The infrastructure management system based on big data according to claim 4, characterized in that: The first processing module obtains the drainage coefficient of the urban drainage outlet, and the process of selecting whether to perform coordinated drainage according to the obtained drainage coefficient includes: Set drainage weights for drainage velocity and drainage flow respectively, obtain drainage coefficients of urban drainage outlets at different times, set drainage thresholds, compare drainage coefficients with drainage thresholds, and choose whether to perform coordinated drainage based on the comparison results; For urban drainage outlets that require coordinated drainage, the coordinated drainage outlets of the urban drainage outlets are obtained, and the opening and closing degrees of the gates of all coordinated drainage outlets and the drainage power of the drainage pumps are increased by one level to achieve coordinated drainage.

6. The infrastructure management system based on big data according to claim 4, characterized in that: The second processing module obtains the variation trend of the drainage coefficient, and the process of pre-adjusting the drainage equipment according to the obtained variation trend includes: An evaluation cycle is set, the drainage coefficient obtained when an evaluation cycle is reached is marked as the evaluation coefficient, a change coefficient of the drainage coefficient is obtained according to the evaluation coefficients in the most recent evaluation cycles, a change threshold is set, the change coefficient is compared with the change threshold, and a change trend of the drainage coefficient is obtained according to the comparison result, wherein the change trend includes a downward trend and an upward trend; For the drainage coefficient that is on a downward trend, the opening and closing degree of the gate and the drainage power of the drainage pump are reduced by one level. For the drainage coefficient that is on an upward trend, the opening and closing degree of the gate and the drainage power of the drainage pump are increased by one level. At the same time, the obtained drainage coefficient and change trend are uploaded to the visualization map for synchronization.

7. The infrastructure management system based on big data according to claim 5, characterized in that: The process of the fault monitoring module constructing a digital twin model of the urban drainage outlet and obtaining a theoretical adjustment change diagram and an actual adjustment change diagram of the drainage equipment includes: A model building unit is provided, and equipment information of the drainage equipment is collected through the model building unit, a physical model and a behavior model of the drainage equipment are respectively built according to the equipment information, and the physical model and the behavior model are integrated to obtain a digital twin model of the drainage equipment; In the digital twin model, the drainage velocity and drainage flow of the drainage equipment before, after and during adjustment are monitored to construct a theoretical adjustment change diagram of the drainage velocity and drainage flow. In actual situations, the same method is used to construct an actual adjustment change diagram of the drainage velocity and drainage flow.

8. The big data-based infrastructure management system according to claim 7, characterized in that: The process in which the fault monitoring module determines whether the drainage equipment has a fault according to the comparison results of the two change graphs and generates equipment fault information includes: The theoretical adjustment change diagram of the drainage velocity and drainage flow rate is compared with the actual adjustment change diagram, and whether the drainage equipment has a fault is determined based on the comparison result, and corresponding Class I fault information, Class II fault information, Class III fault information, and Class IV fault information are generated.

9. The infrastructure management system based on big data according to claim 8, characterized in that: The process of the information feedback module feeding back the generated equipment failure information to the staff includes: The generated equipment fault information is fed back to the staff, and the staff processes the drainage equipment according to the obtained equipment fault information. The equipment fault information includes type I fault information, type II fault information, type III fault information, and type IV fault information.

Citation Information

Patent Citations

  • City drainage integrated operation intelligent scheduling management system

    CN107516167A

  • Unattended transformer substation intelligent flood prevention system

    CN110578678A

  • Intelligent water velocity adjusting and water flow route planning system

    CN111519730A

  • Urban drainage area cooperative scheduling method

    CN111798108A

  • Urban underground pipe gallery risk prevention and control analysis system based on big data

    CN116557791A